CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 2.1.1 Regarding Chapter 7, Borden’s Testimony on Rate Design, please answer the following questions: Question 2.1.1: Referring to page DAB-3, lines 3-12: 2.1.1.1. 2.1.1.2. 2.1.1.3. Is it SDG&E intention to recover all generation-capacity-related costs in its proposed commodity demand charge? How are these costs to be recovered by season and by TOU period for all M&L C&I rate schedules? Is the proposed $/kWh charge to recover the program costs associated with CSI, SGIP, hazardous substance cleanup costs, AMI, and DR to be recovered on an equal cents per kWh basis for all M&L C&I rate schedules? Will it vary by service voltage or in any other way within the class? Will it differ from the related charge for any other class(es), and, if so, how? SDG&E Response: 2.1.1.1 SDG&E’s proposal is to recover 50% of marginal generation capacity costs in the proposed commodity demand charge. 2.1.1.2 The M&L C&I generation capacity costs are recovered according to the marginal generation capacity costs calculated for each rate schedule by seasonal period, adjusted for rate design, as set forth on Attachment JSP-2 to the testimony of SDG&E witness James Parsons. For rate design purposes, the marginal generation capacity costs (in $/kW) are decreased by 50% for each M&L C&I rate schedule with commodity demand charges. 2.1.1.3 Yes, the rate is calculated using the EPMC factors for all M&L C&I rate schedules, with the exception of Schedule S Standby. (Standby rates do not include an energy charge but since standby customers typically use energy on other applicable M&L C&I rates they contribute to cost recovery for the programs under their otherwise applicable rates.) The charge does not vary by service voltage. For each M&L C&I rate schedule the charge is an identical amount of $0.00213 /kWh (including FF&U) added to the proposed distribution energy charge. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.2: Referring to page DAB-3, lines 3-12: 2.1.2.1.Please explain the data and methodology SDG&E proposes to use to determine the contribution of each M&L C&I class to system peak. 2.1.2.2.Please explain in detail what SDG&E means when it says that it “currently does not have coincident peak billing determinants for each rate schedule and thus calculated demand charges for the rate schedules based on the available determinants.” Which data does it have and which data does it use for each schedule and how does it use these data to calculate generation demand charges? 2.1.2.3.Please explain what SDG&E means when it says “[i]n allocating capacity costs to M&L C&I, the capacity costs are allocated to each rate schedule according to the variation in coincident peak demand by time of use… and season.” What variation is being referenced and how is it calculated and applied to the allocation process? 2.1.2.4.SDG&E states that “greater than 90% of the capacity costs are covered through the summer demand charge and a small amount is recovered in a modest winter demand charge”. Is this true for each M&L C&I rate schedule? What data and concept create the basis for this 90-10 split? 2.1.2.5.SDG&E states that its proposed generation demand charges be set at 50% of their calculated cost of service. Where is the remaining generation capacity revenue recovered? How would this revenue be recovered in default CPP rates and what is the relationship between the two types of schedules in generation revenue recovery? SDG&E Response : 2.1.2.1 As discussed in the testimony of SDG&E witness James Parsons, JSP-10 through JSP-14, SDG&E uses the class contribution to system load during the top 300 hours of system demand over a three year period to determine the applicable rate schedule’s contribution to system peak. 2.1.2.2 SDG&E has monthly billing determinants for coincident peak demands for all Schedule A6-TOU customers and for customers with demands equal to or greater than 200 kW. For the overwhelming number of other M&L C&I customers with demands less than 200 kW, SDG&E’s metering equipment does not record demands in the intervals required to measure monthly coincident peak demands. For Schedule A6-TOU, SDG&E divides seasonal marginal generation capacity costs, as calculated by SDG&E witness James Parsons, by coincident peak demand determinants to arrive at the $/kW demand charge. CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Response to Question 2.1.2 (Continued) or Schedule AL-TOU, SDG&E divides seasonal marginal generation capacity costs, as calculated by SDG&E witness James Parsons, by maximum peak period demand determinants to arrive at the $/kW demand charge. For Schedule AD, SDG&E divides seasonal marginal generation capacity costs, as calculated by SDG&E witness James Parsons, by maximum peak period demand determinants to arrive at the $/kW demand charge. For Schedule PA-T-1, SDG&E uses Schedule AL-TOU demand charges, scaled to maintain existing relationships between rate options on Schedule PA-T-1 to determine the $/kW demand charges. 2.1.2.3 SDG&E means that in allocating capacity costs to the classes within M&L C&I, that it is determined by the class contribution to system peak (or coincident peak). (SDG&E is describing the methodology used primarily for Schedule AL-TOU and A6-TOU, given that these two rate schedules make up the vast majority of M&L C&I load and customers.) The reference to ”time of use and seasonal variation” is only meant to explain that the class contribution to system peak occurs over different hours and with the inclusion of October in the winter period for M&L C&I customers, also occurs over seasons. Schedule A6-TOU demand charges are based upon coincident peak demand determinants. Schedule ALTOU demand charges are based on demand determinants for the maximum monthly demands during the peak period. Schedule PA-T-1 demand charges are based upon Schedule AL-TOU demand charges scaled to maintain existing relationships between the current rate option on Schedule PA-T-1 and Schedule AL-TOU. For Schedule AD demand charges, SDG&E divides seasonal marginal generation capacity costs, as calculated by SDG&E witness James Parsons, by maximum peak period demand determinants to arrive at the $/kW demand charge. 2.1.2.4 See the marginal cost capacity amounts and resulting marginal cost revenue amounts set forth on Attachment JSP-4-3 to the testimony of SDG&E witness James Parsons, for seasonal recovery of capacity costs. Each rate schedule exceeds 90% recovery of annual capacity costs in the summer. Adjusted for rate design this still holds, with the exception of Schedule PA-T-1, which drops to about 88.2% recovery of annual capacity costs in summer. The basis for this result is the methodology, sponsored by SDG&E witness James Parsons, that is used to calculate the marginal generation capacity costs. 2.1.2.5 The remaining 50% of marginal generation capacity costs is recovered through the energy rates on an EPMC basis for each M&L C&I rate schedule. That is to say, peak, semi-peak, and off-peak energy rates by season are adjusted on an EPMC basis such that the overall M&L C&I commodity revenue requirement allocation remains unchanged. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 2.1.3.: On page DAB-6, lines 18-19, SDG&E says that the annual average marginal energy cost is scaled according to 24 hourly price shapes. Question 2.1.3.1: What is the source of these hourly price shapes and how are they applied? SDG&E Response: Please see the testimony of SDG&E witness Parsons in Chapter SDG&E-04, pages JSP16, lines 7-23, and JSP-17, lines 1-8, for a description of the rate schedule price shapes. The model “TY 08 GRC Commodity Energy Workpapers.xls” provided in witness Parsons’ workpapers for Chapter-04 provide the detailed calculations. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 2.1.4. On page DAB-7, SDG&E states that the “overall revenue impact to M&L C&I is an approximate 5% reduction in marginal generation cost recovery when compared to existing rates” due to its proposal to set generation demand charges initially at 50% of cost without ratchets. Questions 2.1.4.: 2.1.4.1. 2.1.4.2. Please provide the calculation of this reduction. Does SDG&E believe that generation demand charges should ever be ratcheted? Why or why not? How does the revenue uncertainty associated with the use of these generation demand charges compare to that associated with recovery of generation capacity cost through CPP rates? 2.1.4.3. SDG&E Response: 2.1.4.1. See attached for the present and proposed commodity revenues by rate schedule. If the present and proposed columns for M&L C&I rate schedules are summed and compared the change should be approximately a 4.8% revenue decrease. EECC.xls 2.1.4.2. SDG&E is concerned about the rate impacts to customers and in implementing this new rate it was determined that customer impacts from ratcheted commodity demand charges would be unacceptable at this time. SDG&E has not determined whether it will implement ratcheted generation demand charges in future proceedings. 2.1.4.3. SDG&E has not conducted any analysis regarding this question. In general, a rate design that includes demand charges should have less variability in revenue recovery than one relying predominantly on energy charges, all else equal. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.5: Please explain the basis for the distance adjustment in M&L C&I distribution rates. SDG&E Response: The distance adjustment fee is intended to recover distribution-related costs from customers served under the Primary and Secondary Substation Service options. The distance adjustment fee, first adopted as part of SDG&E’s Primary at Substation rate structure in D.96-06-033, allows for customers which are not located immediately adjacent to a substation to be qualified for rates based on the higher service voltage. The fee, intended to recover SDG&E’s costs of connecting the customer to the substation, is based on calculations for the cost of wire per foot adjusted for losses. The rates for overhead were established by advice letter filing in 1999. SDG&E has not updated the cost calculations and does not propose a change to these rates in this proceeding. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.6: Please explain how distribution revenue is recovered between noncoincident peak demand and maximum peak demand by season and voltage rates. SDG&E Response: Revenue recovery is based upon the EPMC allocation of distribution revenue requirement to the M&L C&I customer class. From the total M&L C&I allocation an adjustment is made to remove revenue requirement associated with CSI, SGIP and RPBA, with the remaining revenue requirement recovered from basic service fees and distribution demand charges. Schedules AL/AY-TOU, AD, and PA-T-1 current distribution demand charges are adjusted in order to maintain approximately the same revenue recovery from the schedules as under existing rates and within the constraint that the total M&L C&I customer class receives an EMPC allocation. Schedule A6-TOU non-coincident distribution demand charges equal the Schedule AL-TOU charges. The Schedule A6 current maximum peak distribution demand charges are adjusted based on the same percentage change to AL-TOU distribution demand charges. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.7: On page DAB-9, lines 11-17, SDG&E states: SDG&E proposes a monthly maximum on-peak demand charges based on $/kW to recover marginal generation capacity costs. When Schedule AL-TOU coincident peak demand determinants become available (in the future through the implementation of advanced capability meters) then the capacity costs will be recovered through a coincident peak demand charge, but until such time maximum on-peak demand are the determinations that are available.” 2.1.7.1. Does SDG&E have load research data providing coincident peak demand for some of its AL-TOU customers? Has SDG&E performed a calculation on the relationship between maximum on-peak demand and coincident on-peak demand? If so, please provide this calculation and its basis. If not, please provide such a report if the data are available. 2.1.7.2. SDG&E Response: 2.1.7.1 SDG&E has coincident peak demand determinants for Schedule AL-TOU customers with maximum demands equal to or greater than 200 kW. 2.1.7.2 SDG&E has conducted a study that is referred to as the UCAN Study, that examines the correlation between the customers’ average and peak demand during peak hours with peak and other high load hours on the system, and that is discussed in the direct testimony of SDG&E witness Leslie Willoughby. Please see LW-13, Appendix LW-A, and relevant workpapers. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.8: On page AB-10, SDG&E states that “the energy charge is the same cents per kWhs (sic) rate applicable to all M&L C&I customers and derived from the same CTC revenue requirement approved in the 2006 RDW proceeding. 2.1.8.1. Why has SDG&E not updated this rate component? 2.1.8.2. Why is this rate component the same for all M&L C&I customers? SDG&E Response: 2.1.8.1 SDG&E’s CTC revenue requirement is approved in the annual ERRA filing. At the time of filing GRC2 proposed rates, January 31, 2007, a final decision was not available regarding the 2007 ERRA and CTC revenue requirements. (A final decision was available on February 16, 2007.) In addition, CTC rate changes that implement a final decision were not contemplated to be made before June 1, 2007, with the actual CTC rate changes now pending by advice letter for July 1, 2007. 2.1.8.2 The CTC revenue requirement was re-designed for the M&L C&I class as a whole which results in the same $ per kWh charge. A single $/kWh charge is consistent with treatment of other non-bypassable charges such as those that recover Public Purpose Program, CSI, SGIP, and RPBA costs. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.9: On page DAB-11, lines 22-23, SDG&E states that it “proposes marginal capacity and energy rates for Schedule AY-TOU that are identical to the rates proposed for Schedule AL-TOU.” On pages DAB-16 and 17, SDG&E says the same thing about the commodity rates for Schedules A6-TOU and AL-TOU. Why? SDG&E Response: Regarding AL-TOU and AY-TOU, the rate schedules are combined in the calculation of marginal generation capacity costs. Rate schedules AL-TOU, AY-TOU, A6-TOU and PA-T-1 are combined in calculating marginal energy costs. Regarding A6-TOU and AL-TOU, the statement is incorrect with respect to marginal generation capacity costs and generation demand charges. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 2.1.10. On pages DAB-18 and 19, SDG&E discusses its standby rate proposals. Question 2.1.10..: 2.1.10.1: Please explain what SDG&E means that a standby customer must provide “physical assurance” to provide diversity benefits? 2.1.10.1.1. : 2.1.10.1.2.: Is this consistent with Commission decisions on standby rates in the past? Is it consistent with standby rates for PG&E and SCE? 2.1.10.2.: How does SDG&E provide for recovery of generation and transmission costs from standby customers? 2.1.10.2.1.: Please provide a detailed explanation of how these costs are recovered, in which rate components, and why. 2.1.10.2.2.: Does SDG&E’s recovery of generation and transmission costs through standby rates reflect diversity? SDG&E Response: 2.1.10.1 SDG&E uses the term physical assurance in the same manner that it is used in the attached workpaper to the testimony of SDG&E witness David A. Borden, p. 13, which states that: SDG&E is using the term “physical assurance” as the Commission defined that term in D.01-07-027 at Finding of Fact 7: “Physical assurance is the application of devices and equipment that interrupt a distributed generation customer’s normal load when distributed generation does not operate.” The rationale for requiring physical assurance is set forth on pp. 11-13 of the attached workpaper to the testimony of SDG&E witness David A. Borden. Chapter07-Workpap ersBialekTestimonyonDistCircuits.DOC 2.1.10.1.1 It is consistent with D.01-07-027. CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Response to Question 2.1.10 (Continued) 2.1.10.1.2 It appears consistent with SCE and PG&E in concept as both utilities require physical assurance for the waiver of standby reservation charges. However, both SCE and PG&E recover variable costs from standby customers, which would not be waived and SDG&E has no provision for the recovery of variable distribution costs in its standby schedule. 2.1.10.2 Generation cost recovery is not provided for under existing standby rate schedules. To the extent that a standby customer uses its otherwise applicable tariff then costs are currently recovered through energy only charges. Proposed GRC2 treatment would recover generation costs through energy and demand charges on the otherwise applicable tariff only to the extent that the customer’s own generation does not serve their designated standby load. Regarding recovery of transmission costs from Standby customers, the first step in determining retail transmission standby rates is to first determine SDG&E’s total system transmission revenue requirements (TRR). The TRR is allocated to each retail customer class using a 12-CP (coincident peak) allocation factor, which represents a 12-month average of each customer class’s contribution to SDG&E total monthly system peak. The 12-CP information used to allocate the TRR to the standby class is calculated based on estimates of the generation capacity factor for the standby customer class at time of the monthly system peaks. SDG&E utilizes recorded customer generation data to estimate this capacity factor for the standby customer class. This allocated revenue is then assigned to individual voltage levels (transmission, primary, and secondary level) in proportion to the sum of standby contract demands adjusted to the transmission level. The standby revenues at each voltage level are then divided by the sum of the applicable metered contract demands at each voltage level, which then results in the individual transmission standby rate by voltage level. 2.1.10.2.1 Please see the response to 2.1.10.2 regarding generation and transmission cost recovery. SDG&E’s proposal in GRC2 is a continuation of the existing rate design for generation costs. SDG&E’s 12 CP calculation for standby customers for transmission service is intended to estimate their contribution to coincident peak. 2.1.10.2.2 SDG&E does not have a specific generation charge for standby service and thus customers pay rates based on actual usage on their otherwise applicable tariffs in the event that their own generation does not serve all of their contracted standby level, or they contribute nothing to generation cost recovery. Transmission standby rates reflect diversity through use of the standby customers’ generation capacity factor to estimate their share of the 12 CP TRR allocation. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 2.1.11 SDG&E states on pages DAB 18 and19: “In addition to physical assurance, a Standby customer may provide diversity benefits through location, size and number such that SDG&E is able to defer distribution capacity additions. In 2001 SDG&E examined its distribution system and determined that there were no distributed generators on its distribution system that met these criteria. Based on communications with the SDG&E witness responsible for the 2001 report, I understand that the number of distributed generators has increased since 2001 but the circumstance has not changed regarding diversity benefits and that currently there are no distributed generators on the SDG&E system that have allowed SDG&E to defer distribution capacity additions.” Question 2.1.11.1: Please provide any workpapers supporting this position. SDG&E Response: Please see the attached workpaper. Chapter07-Workpap ersBialekTestimonyonDistCircuits.DOC Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.12: SDG&E states that it “believes that an 80/20 split between fixed and variable charges could be appropriate for [a] standby rate structure.” What is the basis for this assertion? SDG&E Response: The basis for this response is a discussion with the SDG&E employee who authored the SDG&E 2001 report on standby service. The 80/20 ratio was based upon a sample of distribution capacity projects that determined the component whose size and subsequent cost could be impacted by the local area load. Response Prepared By: Dave Borden CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.1.13: On page DAB-21, SDG&E states “To the extent that onsite generation is operated during a summer month or a summer peak period, the customer’s diversity in generation may allow standby customers to avoid a portion of this demand charge. SDG&E will not provide a waiver of summer peak period generation demand charges for standby customers because SDG&E does not provide advanced approval of maintenance outages in summer months.” 2.1.13.1 2.1.13.2. 2.1.13.3 Does this demand charge apply only when the standby customer is taking power from SDG&E due to a forced outage? How does the proposed demand standby demand charge compare to the standby charge for the standby customers otherwise applicable rate? Is the standby demand charge subject to a ratchet mechanism? SDG&E Response: 2.1.13.1 Yes. 2.1.13.2 They are the same. Currently SDG&E waives demand charges on the otherwise applicable tariff for approved outages. SDG&E will continue this policy and will not provide for a waiver during the summer period. 2.1.13.3 The demand charge for commodity service that standby load would pay is not subject to a ratchet. Response Prepared By: David Bordon CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.1.: Regarding Chapter 11, the Velasquez testimony: 2.2.1. On page JV-1, SDG&E notes that CPP periods can occur on Saturdays, which is not the case for current rates. However, on page JV-6, SDG&E states that its proposal to include Saturdays as days when a CPP event may be called “would not change the existing summer on-peak time periods.” Please explain the inconsistency between these statements. SDG&E Response: SDG&E’s existing summer On-Peak period is defined as 11:00a.m. – 6:00p.m., weekdays (excluding holidays). The CPP time-of-use hours on a CPP event day, including Saturdays, are the same as the summer season On-Peak time period (11:00 a.m. – 6:00 p.m.). Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.2.: 2.2.2.1 : On page JV-2, SDG&E states that its default CPP commodity rate is identical for both Large and Medium C&I customers. Why does SDG&E have different energy rates under its proposal otherwise applicable tariffs for non-CPP schedules but not for CPP schedules? SDG&E Response: SDG&E's proposed CPP energy rates differ by TOU period and voltage level. See Attachments JRM 10-1, 10-3, & 10-4 to the testimony of SDG&E witness James Magill for the CPP energy rates and the energy rates on the otherwise applicable rate schedules. Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 1.2. Question 2.2.3.: SDG&E proposes a Capacity Reservation Charge (CRC) as an optional component it’s the default CPP commodity rate. 1.3. 1.4. 2.2.3.1. Does the CRC incorporate only generation cost recovery? 1.5. 2.2.3.2. Why are customers required to choose a specific capacity level for their CRC for a twelve month-period? Are we correct in assuming that this level is the same for all 12 months? How do customers address seasonal diversity in loads if they must choose the same level for every month? 1.6. 2.2.3.3. If a customer chooses a CRC that covers its maximum monthly on-peak demand during a year, how does SDG&E treat any excess revenue that results from maximum on-peak usage below this amount in other months? 1.7. 2.2.3.4. If a customer’s maximum monthly on-peak demand is less than its CRC level, how does SDG&E treat any excess revenue that results? 1.8. 2.2.3.5. If a customer chooses a CRC that covers its maximum monthly on-peak demand during a year, how does the customer see any commodity-based pricing that provides an incentive for demand response? 1.9. SDG&E Response 2.2.3: 2.2.3.1 Yes. 2.2.3.2. As stated on page JV-2, choosing to reserve capacity is “completely optional”. The capacity reservation charge (CRC) is based on the amount of reserved capacity and is the same fixed charge for all 12 months in order to spread the costs evenly over a 12-month period, thus providing a tool for customers to achieve more predictable bills. The reserved capacity is not intended to vary monthly but rather it is intended to apply during the entire summer period (May through September) when a CPP event can occur. In electing to reserve capacity, a customer should consider the amount of load it can shed and the amount of load it wishes to be subject to the CPP rate during any potential critical peak period (i.e., May through September, 11 a.m. - 6 p.m., Monday through Saturday, excluding holidays). 2.2.3.3. Over collections associated with commodity-related revenues are captured in the Energy Resource Recovery Account (ERRA). 2.2.3.4. See response to question 2.2.3.3. CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 SDG&E Response 2.2.3-Continued: 1.10. 2.2.3.5. Customers will have the ability to reserve a level of capacity up to and including their most recent summer maximum on-peak demand that they believe best meets their operational needs. In the event a customer elects to reserve 100% of its maximum on-peak demand, it would be a clear indication that the customer has made the decision to protect its entire load from the critical peak price and has no intentions for reducing load. Response Prepared By: Joe Velasquez and James Magill CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.4.: Does Bill Protection only apply to the generation-related part of the customer’s bill? SDG&E Response: Yes. Please refer to footnote 9 on page JV-4. Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.5.: Is it correct that the M&L C&I customer’s otherwise applicable tariff (OAT) would be the tariffs proposed in Mr. Borden’s testimony and not the current OAT? Would Bill Protection be based on these newly-proposed OAT, if adopted? Would customers have had any experience with these newly-proposed OAT prior to default CPP service if default CPP rates go into effect for these customers on 1/1/2008? SDG&E Response: After receiving service for an initial 12-month period under default CPP with Bill Protection, customers will be permitted to opt-out of CPP and receive service under the otherwise applicable commodity rate schedule which is described by SDG&E Witness Borden at pp. DAB - 5 & 6. Bill Protection would be calculated based on the otherwise applicable commodity rates in effect that a customer would have been billed during its first year of service under default CPP. As indicated in Witness Borden’s prepared direct testimony at page DAB-5, SDG&E is proposing to include a generation demand charge component, which currently does not exist, in its electric commodity rates applicable to commercial and industrial customers. While a generation demand charge introduces a structural change to commodity rates, demand charges have been a component of transmission and distribution rates for over 20 years. In addition, prior to electric industry restructuring, SDG&E’s rates did include a portion of generation costs as part of its demand charge. As such, the introduction of a generation demand charge does not represent a change that customers have not previously been exposed to. Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.6.: Why is the Base Interruptible Program (aka BIP) shown in Table JV-1 as not applicable for customers on default CPP rates? What would be the case if the Commission decides not to eliminate BIP for SDG&E? SDG&E Response: Table JV-1 indicates that BIP is compatible with CPP. To the extent that BIP remains in effect, it would be available to customers receiving service under CPP Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.7.: Why is Capacity Bidding shown in Table JV-1 as incompatible with default CPP rates? SDG&E Response: While allowing customers on CPP to participate in the CBP day-of option would be consistent with SDG&E’s position related CPP compatibility with other day-of demand response programs, pursuant to SDG&E’s current and effective CPUC approved tariff, Schedule CBP, Special Condition 11, customers participating in CBP are prohibited from participating in any other utility demand response program. Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.8.: On page JV-11, SDG&E states that a voluntary CPP customer must be signed up for voluntary CPP by May 1, 2007 to be eligible for bill protection. How would customers know this when May 1 has already occurred? SDG&E Response: As part of SDG&E’s outreach efforts to recruit participants for the existing voluntary CPP program, customers have been informed about SDG&E’s bill protection eligibility proposal. Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.9.: 2.2.9.1. 2.2.9.2. On page JV-12, lines 11-12, SDG&E says it will provide bill impact information to customers about the consequences of default CPP, once such a rate has been approved by the Commission, based on “some level of assumed demand response; and capacity reservation assumptions.” What would be the basis of these assumptions? Would SDG&E use a standardized demand response assumption? If so, what would it be? SDG&E Response: 2.2.9.1 Consistent with the basis of the “Proposed Default CPP Bill Impacts” results in attachment JRM 10-2 to SDG&E Witness Magill’s testimony, the initial customer specific bill impact analyses will assume 9 CPP events, a capacity reservation equal to 50% of the customers most recent maximum summer on-peak demand and zero load reduction. As the customer education process unfolds, SDG&E will work with individual customers to assist them in developing assumptions based on their specific operational requirements. SDG&E is also developing a rate analysis tool that customers can use to analyze the impacts of CPP under various assumptions. 2.2.9.2 See response to 2.2.9.1 Response Prepared By: Joe Velasquez CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.2.10.: On page JV-13, SDG&E states that “[w]hile Small C&I customers will not default to the proposed CPP commodity rate applicable to medium and large commercial customers, SDG&E believes that small customers that desire the benefits of lower rates during non-CPP event periods and are willing t reduce either demand during CPP events should have the opportunity to take service under the default CPP commodity rate, under the same conditions that would be applicable to the medium and large customers.” 2.2.10.1 2.2.10.2. Why should Small C&I customers not default to a proposed CPP commodity rate? Is the issue the availability of meters, or that Small C&I customers should have a different CPP commodity rate, or something else. Please explain. SDG&E Response: 2.2.10.1 SDG&E Witness Fong, in chapter 9 at page EF 9, summarizes the Peak Time Rebate (PTR) program proposed by SDG&E witness Mr. Gaines1 in A.05-03-015 that would be available to small commercial customers with demands less than 20kW. The PTR would be available in combination with the three period time-ofuse rate described in the testimony of SDG&E Witness Magill beginning on page JRM-10. SDG&E believes PTR is appropriate for small C&I customers because of the simplicity of the program and the ability for all customers in the segment to benefit if they change their energy consumption behavior during CPP events. The simplicity of the program allows SDG&E to easily explain the benefits of the program to customers through mass media information channels and to easily remind customers of the opportunity to save money each time a CPP event is announced. 2.2.10.2. See response to 2.2.10.1 above. Response Prepared By: Joe Velasquez 1 See A.05-03-015, Ex. 25, Ch 5, MFG-15 CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 1.11. Question 2.2.11.: Regarding Chapter 10, the Magill testimony, please answer the following questions: 1.12. 1.13. 2.2.11.1. On page JRM-2, SDG&E states that it “has designed the proposed CPP rate based on the total greater than 20 kW class, rather than bifurcating the class since the metering limitations are no longer relevant. Please explain why SDG&E has determined that the metering limitation is determinative here. 2.2.11.2.Will all customers with demands 20 kW and above have demandmetering and demand charges? 2.2.11.3. On page JRM-3, SDG&E states that [t]he applicable CPP rate is based on the marginal capacity cost multiplied by the average load associated with the greater than 20 kW customer class during the top nine (9) CPP dates plus the summer on-peak marginal energy cost.” Would this calculation be different if there were a separate CPP rate for each schedule for customers greater than 20 kW due to different average loads? 2.2.11.4.On page JRM-6, SDG&E states that the “CPP energy rate equals the CPP marginal capacity cost revenues, minus the capacity revenues associated with the CRC, divided by forecasted billed CPP usage, plus the summer on-peak marginal energy rate.” In a footnote to this sentence, SDG&E states that [t]he CPP billing determinants are CTC revenues reflect the proposed fifty (50) percent default CPP. 1.14. 2.2.11.4.1. Please produce CPP rates based on an assumed 100 percent CRC. 2.2.11.4.2. Please produce CPP rates based on an assumed zero percent CRC. 2.2.11.4.3. Please provide forecast revenues under the 0%, 50%, and 100% CRC alternatives. 2.2.11.5. On page JRM-6, SDG&E states that it only adjusts non-CPP on-peak and semi-peak rates to achieve revenue neutrality, since a downward adjustment to off-peak rates would lead to rates below marginal cost. What is the resulting TOU energy rate ratio and how does it compare to the MEC ratio? 2.2.11.6. Referring to page JRM-9, why did SDG&E chose to use “the top forty (40) hours… to split 2008 forecast energy sales into CPP-E and on-peak, semi-peak, and off-peak energy billing determinants” as opposed to a different number of hours? 1.15. 1.16. 1.17. 1.18. 1.19. CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 1.20. Question 2.2.11.-Continued: 2.2.11.7. On page JRM-14, SDG&E indicates that on 1/1/2011 it will switch to a 6-month summer period. Has SDG&E performed any bill impact calculations on the impact of a longer summer and a shorter winter rate period? If so, please provide them. If not, will SDG&E provide such analysis prior to such a change going into effect? How will SDG&E notify its customers of this change and when? 1.21. SDG&E Response 2.2.11: 2.2.11.1 Please refer to the Prepared Direct Testimony of SDG&E Witness James Magill, page JRM-2, lines 4-11. For commodity revenue allocation purposes customers with demands greater than 20 kW (for twelve consecutive months) are treated as a single customer class. All customers with demands greater than 20 kW(for twelve consecutive months) will have interval metering once AMI is implemented and should be treated as a single rate class for CPP rates. 2.2.11.2 Customers with demands greater than 20 kW (for twelve consecutive months) currently have demand metering and demand charges. 2.2.11.3 The resulting rates would differ to the extent the individual schedules have different demand / energy ratios as compared to the total class during the top nine days. 2.2.11.4 See the attached workpapers. C:\Documents and C:\Documents and C:\Documents and Settings\jmagill\Desktop\James Settings\jmagill\Desktop\James Magill\RDW\2008 Settings\jmagill\Desktop\James GRC Magill\RDW\2008 P2\Filed 13107\CLECA GRC Magill\RDW\2008 P2\Filed 2.2.11.4.1 13107\CLECA CPP Rates GRC P2\Filed 2.2.11.4.2 (20kW -13107\C&I 9DCPP 100 Rates CRC) CPPv12 (20 Ra 2.2.11.5 See the attached workpaper. C:\Documents and Settings\jmagill\Desktop\James Magill\RDW\2008 GRC P2\Filed 13107\CLECA 2.2.11.5.xls 2.2.11.6 The top 40 hours were used as a proxy for the number program hours that could potentially occur during the year. The CPP-E rate is limited to a maximum of 40 hours in a month and 80 program hours per year. CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 SDG&E Response 2.2.11: 2.2.11.7 SDG&E has not performed any bill impact calculations. Prior to implementing the seasonal change, SDG&E will provide estimated bill impacts for various customer types. SDG&E would notify customers in any of a number of ways including direct mail, email or bill insert as well as by posting on SDG&E’s website. Response Prepared By: James Magill CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 2.3 Regarding Chapter 13, the Willoughby testimony, please answer the following questions: Question 2.3.1: On page LW-2, in describing the monthly statistics it will provide for all CPP and PTR events, SDG&E states that it will “include econometric Model estimates for peak days”. 2.3.1.1.: Won’t SDG&E have actual peak day data to be used after the date whose results are being reported? Why use model estimates? SDG&E Response: The CPUC requires monthly reporting of demand reduction estimates for all Demand Response programs (D.)01-04-006. Even though SDG&E will have peak day data to assist in providing results, there also must be an estimate of what the load would have been in absence of the rate or program. In order to estimate the impacts from CPP and PTR events in a timely manner SDG&E proposed using econometric model estimates. SDG&E currently uses econometric estimates in its Dynamic Load Profile (DLPs) process along with meter data estimates. The econometric estimates produced are not influenced by CPP or PTR events. This process would produce an estimate of the load that would have been without the CPP or PTR event. The large meter data sample can be used to calculate estimates of demand levels on CPP days. An estimate of the overall load reductions can be derived by taking the difference of the meter data estimates and econometric estimates. The purpose of this method is to aid in providing the monthly report of DR activities and is not intended to replace the official load impact estimation that will take place after the program year has ended. Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.2: On page LW-2, in describing the monthly statistics it will provide for all CPP and PTR events, SDG&E states that it will “utilize population and large meter sample for megawatt (MW) load reduction estimates compare (sic) to forecasted system load shape with no demand response”. 2.3.2.1. 2.3.2.2. 2.3.2.3. Please describe in detail how SDG&E proposes to do this analysis. What load sample will SDG&E use to estimate load reductions? Is it statistically significant? Has SDG&E ever performed such an analysis before? If so, how accurate were the results? SDG&E Response: 2.3.2.1 Please see SDG&E’s response to 2.3.1.1 2.3.2.2 SDG&E intends to use as much information as feasible to estimate load reductions. When possible all available load data will be used. This is subject to basic verification and editing. SDG&E intends to utilize samples that are statistically significant for the monthly reporting. 2.3.2.3 SDG&E currently uses a similar methodology when calculating it’s Dynamic Load Profiles (DLPs). SDG&E has using this methodology for nearly 10 years. SDG&E has no reason or cause to believe that the estimates are not accurate. Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.3: On page LW-3, SDG&E states that it has used DRA’s estimated benefits attributed to daily website access and information display technologies from A. 05-03-15. What level of benefits did the Commission adopt for this technology in that proceeding? SDG&E Response: (D.)07-04-043 adopted $19 million for Information Feedback Systems benefit. Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.4: With reference to the Peak Time Rebate (PTR), SDG&E has chosen to use the highest 3 out of the past 5 eligible days as a reference level for residential customers but the highest 3 out of the past 10 eligible days for small commercial customers. What is basis for this difference? SDG&E Response: SDG&E analyzed the accuracy of several reference levels using statistics such as total error and bias. The overall goal was a reference level with low total error, low bias, easy for customers to understand, and difficult for a customer to game. The residential high 3 of 5 day baseline performed well in all categories as did the high 3 of 10 day for the small commercial class. Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.5: On page LW-7, Table LW-1, SDG&E shows its estimate of Total Rebates Paid no DR and Total Rebates Paid with DR. Please calculate what these numbers would be if SDG&E had used a reference level of the highest 1 day in the past 5 eligible days for residential customers. Please perform a similar calculation for small commercial customers (per Table LW-3) using the highest 1 day in the past 10 eligible days for small commercial customers. SDG&E Response: Residential High 1 of 5 CRL Year 2004 2005 2006 Reference Level High 1of 5 High 1of 5 High 1 of 5 Total rebates no DR (millions) -$24 -$23 -$25 Total rebates with DR (millions) -$30 -$29 -$33 Small Commercial High 1 of 10 CRL Total Rebates No DR (millions) Total Rebate with DR (millions) Year Reference Level 2004 High1 of 10 -$3.91 -$5.05 2005 High 1 of 10 -$3.77 -$4.86 2006 High 1 of 10 -$5.52 -$6.91 Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.6: Please provide workpapers developing SDG&E’s claimed increased demand response benefits from its proposed rates in this proceeding compared to its AMI business case. SDG&E Response 2.3.6: Ch13_tbl5_DRbenefi SCh13_SDGE_Prism_ Ch13_SDGE_Prism_R ts_v2.xls Commercial_jan31.xls es_jan31.xls Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.7: On page LW-12, SDG&E states that the assumptions it uses to calculate these benefits “are consistent with the assumptions used in SDG&E’s AMI application (A).05-03-15”. Please calculate SDG&E’s proposed demand response benefits based upon the benefit figures adopted by the Commission in Decision 07-04-043. SDG&E Response: Table DR Benefits according to AMI decision Present Value of Demand Response Benefits (Millions of 2008 $) Customer Segment Residential Capacity $72.8 Energy $6.2 Total $79.0 2011 MW 109 Small C&I (<20 kW) $11.1 $0.8 $11.9 9 Medium C&I (20- 200 kW) $49.4 $2.0 $51.4 72 Large C&I (> 200 kw) Total $47.9 $181.2 $1.6 $10.5 $49.5 $191.7 66 256 Customer Class Assumptions Residential 50% Avoided Capacity Value Small Commercial Medium Commercial Large C&I years 2009-2010 Large C&I year 2011-2026 All classes Prices Dollars All classes All classes 100% of customers with thermostats 100% 5% 100% $52/kw real GRC phase II proposed rates present value 2008 Load Benefit Period All classes All classes 2005 load 2009-2026 Participation Rates Response Prepared By: Leslie Willoughby CLECA DATA REQUEST CLECA DR-02 SDG&E PHASE 2 GRC – ELECTRIC RATE DESIGN - A.07-01-047 Date Submitted: July 5, 2007 Question 2.3.8: Please explain why, on page LW-12, SDG&E says it has chosen to change the “load underlying the avoided capacity benefits ...to the annual peak day load from 11 am to 6 pm instead of the average of the top 9 days” when there is only one annual peak day and SDG&E is performing its calculations based on an assumed 9 event days SDG&E Response: SDG&E provided an example on LW12-LW13 as to why it is more appropriate to calculate the capacity benefits using the annual peak load instead of an average of the highest 9 days. SDG&E believes that if it uses the average of the nine peak days that it underestimates the load reduction and therefore underestimates the capacity benefits. The average usage for the top 9 days is still used to calculate the avoided energy benefits. Response Prepared By: Leslie Willoughby