Observations on the Federal Circuit’s Impact on Bid Protest Litigation Since ADRA James J. McCullough* Michael J. Anstett* Brian M. Stanford* * * * TABLE OF CONTENTS I. Introduction ................................................ 3 II. The Federal Circuit’s Early Post-ADRA Protest Decisions ... 12 III.The Federal Circuit’s Record in Resolving Conflicts 17 A. Implied-in-fact Bid Protest Jurisdiction ................. 18 B. Protest Timeliness ....................................... 24 C. Scope of Record for Review ............................... 27 D. Other Open Issues ........................................ 29 IV. The Federal Circuit’s Impact on the U.S. Government Accountability Office......................................... 32 V. Conclusion ................................................ 35 2 I. Introduction The year was 1982, the United States Court of Appeals for the Federal Circuit had recently been created by the Federal Courts Improvement Act,1 and the court had just begun to exercise appellate jurisdiction over appeals from the newly constituted United States Claims Court (which would become the United States Court of Federal Claims)2 and the General Services Administration Board of Contract Appeals (GSBCA).3 Although disappointed bidders still had two other venues in which to file bid protests—the United States district courts and the United States General Accounting Office (GAO) (which would become the Government Accountability Office)4—the consolidation of the The Federal Courts Improvement Act of 1982, Pub. L. No. 97-164, 96 Stat. 25. 2 See The Federal Courts Administration Act of 1992, Pub. L. No. 102-572, § 902, 106 Stat. 4506, 4516. In addition to creating the Federal Circuit and the Claims Court, the Federal Courts Improvement Act of 1982 also abolished the United States Court of Claims, which was established in 1855. See The Federal Courts Improvement Act of 1982, Pub. L. No. 97-164. The Court of Claims judges and the commissioners appointed by the judges exercised both trial and appellate jurisdiction over claims against the United States. See generally History of the Federal Judiciary, Court of Claims, 1855-1982, THE FEDERAL JUDICIAL CENTER (July 15, 2012), http://www.fjc.gov/history/home.nsf/page/courts_special_coc.html . 3 See History of the Federal Judiciary, Lankdmark Judicial Legislation, THE FEDERAL JUDICIAL CENTER (July 15, 2012), www.fjc.gov/history/home.nsf/page/landmark_22.html. 4 See GAO Human Capital Reform Act of 2004, Pub. L. No. 108-271, § 8(a), 118 Stat. 811, 814 (2004) (“The General Accounting Office is hereby redesignated the Government Accountability Office”). 1 3 Federal Circuit’s appellate jurisdiction over appeals from the Claims Court and the GSBCA had squarely positioned the Federal Circuit to become the preeminent arbiter of bid protest issues.5 In its early years, however, the Federal Circuit issued only a handful of bid protest decisions.6 From 1983 through 1987, the Federal Circuit issued published opinions in only 11 bid protest cases (six arising out of the Claims Court).7 Yet, even as the See History of the Federal Judiciary, Court of Claims, 18551982, supra note 2. As one experienced practitioner observed in 1987, the Federal Circuit’s new status in reviewing bid protest appeals, “coupled with its widely recognized expertise in government contract matters,” gave the Federal Circuit the authority “to influence significantly the general development of bid protest law.” David R. Hazelton, The Federal Circuit’s Emerging Role in Bid Protest Cases, 36 AM. U. L. REV. 919, 922 (1987). Indeed, as Hazelton observed, the Federal Circuit’s new role offered “an unprecedented opportunity to clarify an area of the law that [was] in considerable disarray” because of the differing procedural and substantive rules applied to bid protest cases by the various tribunals—the Claims Court (and its predecessor), the district courts, the GAO, and the GSBCA— deciding those cases. Id. at 920. 6 See United States v. John C. Grimberg Co., 702 F.2d 1362 (Fed. Cir. 1983) (en banc); Coastal Corp. v. United States, 713 F.2d 728 (Fed. Cir. 1983); F. Alderete Gen. Contractors, Inc. v. United States, 715 F.2d 1476 (Fed. Cir. 1983); CACI, Inc.-Fed. v. United States, 719 F.2d 1567 (Fed. Cir. 1983); ATL, Inc. v. United States, 735 F.2d 1343 (Fed. Cir. 1984); Essex Electro Eng’rs, Inc. v. United States, 757 F.2d 247 (Fed. Cir. 1985); United States v. Amdahl Corp., 786 F.2d 387 (Fed. Cir. 1986); Elec. Data Sys. Fed. Corp. v. GSBCA, 792 F.2d 1569 (Fed. Cir. 1986); NKF Eng’g, Inc. v. United States, 805 F.2d 372 (Fed. Cir. 1986); United States v. Thorson Co., 806 F.2d 1061 (Fed. Cir. 1986); Federal Data Corp. v. SMS Data Prods. Grp., Inc., 819 F.2d 277 (Fed. Cir. 1987). 7 See John C. Grimberg Co., 702 F.2d 1362; Coastal Corp. 713 F.2d 728; F. Alderete Gen. Contractors, Inc., 715 F.2d 1476; CACI, Inc.-Fed. 719 F.2d 1567; ATL, Inc., 735 F.2d 1343; Essex Electro Eng’rs, Inc., 757 F.2d 247; Amdahl Corp., 786 F.2d 387; Elec. 5 4 court gained its sea legs, the potential for the Federal Circuit to have a profound impact on bid protest law was there.8 Much has changed since those early days of the Federal Circuit and its emerging role in bid protest jurisprudence.9 The Federal Circuit is no longer just the “principal” appellate tribunal for bid protests, it is, de facto, the appellate tribunal for all bid protest cases.10 The passage of the Administrative Dispute Resolution Act of 1996 (ADRA),11 and the expiration in 2000 of district court jurisdiction over bid protests, have left the Federal Circuit as the sole appellate court for bid protest appeals.12 If in 1987 the court was poised to have a significant influence on the development of bid protest law and to bring clarity to an area of the law that was Data Sys. Fed. Corp., 792 F.2d 1569; NKF Eng’g, Inc., 805 F.2d 372; Thorson Co., 806 F.2d 1061; Federal Data Corp., 819 F.2d 277. 8 See generally History of the Federal Judiciary, Court of Claims, 1855-1982, supra note 2. 9 See Michael J. Schaengold, Choice of Forum for Federal Government Contract Bid Protests, 18 FED. CIR. B.J., 244, 295 (2008). 10 See e.g., id. at 299. 11 The Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320, § 12(d), 110 Stat. 3870, 3875 (codified at 28 U.S.C. 1491(b)). 12 Id. (“SUNSET.— The jurisdiction of the district courts of the United States over the actions described in section 1491(b)(1) of title 28, United States Code (as amended by subsection (a) of this section) shall terminate on January 1, 2001 unless extended by Congress”). 5 in disarray, surely, in the years following ADRA, the potential for the court to influence bid protest law increased even more.13 So now, looking back on the past fifteen years since the passage of ADRA, is it worthwhile for bid protest practitioners to ask, how has the Federal Circuit influenced the development of bid protest law? The Federal Circuit unquestionably has had an impact on the development of bid protest law.14 With the issuance of more than 60 published and unpublished decisions in bid protest cases since ADRA, the Federal Circuit could not avoid shaping the development of bid protest law (even if, in the grand scheme of things, the court has authored a relatively small number of bid protest decisions compared to other areas of government contract law).15 But what has been the reach of that impact? Has the See Administrative Dispute Resolution Act of 1996, § 12(d) (“SUNSET.— The jurisdiction of the district courts of the United States over the actions described in section 1491(b)(1) of title 28, United States Code (as amended by subsection (a) of this section) shall terminate on January 1, 2001 unless extended by Congress”). 14 See Schaengold, supra note 9 at 326 (“because in most bid protests the COFC resolves the case on motions for judgment on the administrative record, the Federal Circuit reviews the bid protest decision de novo, which means that the Federal Circuit will freely review the entire opinion (without any deference to the COFC”); see also Dysart v. United States, 369 F.3d 1303, 1310 (Fed. Cir. 2004). 15 To provide some context, roughly 5% of the Federal Circuit’s caseload since 1996 has concerned various aspects of government contracting, and bid protest cases have been a sliver of that 5%. See Statistics, United States Court of Appeals for the Federal Circuit, http://www.cafc.uscourts.gov/the13 6 Federal Circuit fulfilled its role as the appellate tribunal charged with harmonizing conflicting decisions of the trial courts? Has the Federal Circuit developed a coherent body of case law that allows for efficient and meaningful judicial review of agency procurement decisions? As the de facto Supreme Court16 for bid protest cases, what has the Federal Circuit done to provide consistent guidance to federal agencies, the Court of Federal Claims, and other stakeholders in bid protest litigation? The answers to these questions are decidedly a mixed bag.17 ADRA’s jurisdictional grant provided that: the United States Court of Federal Claims . . . shall have jurisdiction to render judgment on an action by an interested party objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award or the award of a contract or any alleged violation of statute or court/statistics.html (last visited July 16, 2012). For example, based on an analysis of statistics available from the court for Government Fiscal Year 2011, the total number of cases pending before the Federal Circuit was 1,012, of which approximately 5%, or 50, cases involved government contracts. See id. In that same time period, the Federal Circuit issued only 5 decisions in bid protest cases. See id. That said, the Federal Circuit admittedly has been more active in the bid protest arena than it was before ADRA. See supra note 7 and accompanying text. 16 See Robert E. Korroch et al., 2005 Year in Review: Analysis of Significant Federal Circuit Government Contracts Decisions, 35 PUB. CONT. L.J. 581, 582 (2006) (noting the Federal Circuit is the “Supreme Court” of government contract cases). There appears to have been only one bid protest case decided by the United States Supreme Court, and that was in 1940. See Perkins v. Lukens Steel Co., 310 U.S. 113, 125 (1940). 17 7 regulation in connection with a procurement or a proposed procurement. [T]he United States Court of Federal Claims . . . shall have jurisdiction to entertain such an action without regard to whether suit is instituted before or after the contract is awarded.18 This new jurisdictional provision required sorting out in the years following its enactment, and the Federal Circuit fairly quickly provided some much needed guidance in the wake of ADRA to establish the basic ground rules for bid protest litigation in the Court of Federal Claims.19 Specifically, the Federal Circuit provided guidance concerning Court of Federal Claims jurisdiction and standing in bid protests in two early decisions, RAMCOR Services Group, Inc. v. United States,20 and American Federation of Government Employees v. United States (AFGE).21 In RAMCOR, the court broadly construed ADRA’s jurisdictional grant concerning what types of protests could be brought to the Court of Federal Claims by interpreting ADRA’s “operative phrase ‘in connection with’” to be “very sweeping in scope” and concluding that “‘procurement’ includes all stages of the process of acquiring property or services, beginning with the process for determining a need for property or services and 18 28 U.S.C. § 1491(b)(1) (emphasis added). 19 RAMCOR Services Group, Inc. v. United States, 185 F.3d 1286 (Fed. Cir. 1999). 21 American Federation of Government Employees v. United States, 258 F.3d 1294 (Fed. Cir. 2001). 20 8 ending with contract completion and closeout.”22 In AFGE, the court applied the definition of “interested party” used in the Competition in Contracting Act of 1984 (CICA)23 to define who would have standing to pursue a bid protest pursuant to ADRA to include an “actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or by failure to award the contract.”24 A third issue—the proper standard of review for bid protests—was resolved by the Federal Circuit in Impresa Construzioni Geom. Domenico Garufi v. United States,25 where the court made clear that bid protest cases were to be reviewed under the “arbitrary and capricious” standard set forth in the Administrative Procedure Act, 5 U.S.C. § 706(2)(A).26 In these early decisions, the Federal Circuit resolved several of the most pressing issues for the judges of the Court of Federal Claims: who could protest, what could they protest, and what standard of review would be applied by the courts in reviewing those protests.27 In all three instances, the Federal 185 F.3d at 1289 (borrowing from the definition of procurement in 41 U.S.C. § 403). 23 Pub. L. No. 98-369, 98 Stat. 1175 (1984). 24 258 F.3d at 1302 (quoting 31 U.S.C. § 3551(2)). 25 Impresa Construzioni Geom. Domenico Garufi v. United States, 238 F.3d 1324 (Fed. Cir. 2001). 26 238 F.3d at 1332. 22 27 9 Circuit brought harmony to conflicting decisions issued by the judges of the Court of Federal Claims.28 But that was just the beginning, and, for the Federal Circuit, there remained—and there still remain today, fifteen years out—a number of significant gaps to fill and conflicts to resolve in the area of post-ADRA bid protest litigation.29 It is a practical reality that, despite the Federal Circuit’s role as the de facto final word on bid protest law, the oracle rarely speaks on such matters.30 With so few opportunities to consider the nuances of bid protest litigation after ADRA, the Federal Circuit’s decisions have taken on an almost Delphic aura.31 And whatever the reason for the relatively few bid protest decisions issued by the Federal Circuit since 1997, the dearth of case law arising from the Federal Circuit has meant that the court has not had nearly the impact it might otherwise have had.32 28 Need Cite. In 2005, one commentator looking back at the court’s post-ADRA jurisprudence up to that point observed that the Federal Circuit had “almost completed the mile in eliminating inconsistencies within the [Court of Federal Claims] under the ADRA,” and that, “with a few more steps, the Federal Circuit will have developed a smooth, working body of law.” Jennifer Wittmeyer, Note, Conflicts in the Court of Federal Claims: The Federal Circuit’s Key Decisions and Resolutions Over Bid Protest Practice, 13 FED. CIR. B.J. 507, 540 (2005). That hope may have been overly optimistic. 29 30 31 Need cite. As another commentator has observed, if the Federal Circuit were more “actively and knowledgeably” engaged in shaping the federal procurement regime than it has been, the 32 10 Moreover, even when the court has had an opportunity to address open issues squarely—or at least provide some measure of guidance—the court has consistently declined many of those opportunities, leaving the judges of the Court of Federal Claims and the bid protest bar to speculate about what the Federal Circuit might think, without the benefit of authoritative judicial guidance from the only source that can provide it.33 Thus, it appears that, as an institution, the Federal Circuit has not lived up to its full potential as the only appellate court (at least for practical purposes) with the ability to provide guidance in bid protest matters. Perhaps the most frustrating aspect of these past fifteen years has been the Federal Circuit’s reluctance to resolve conflicts in bid protest law and the resulting significant transactional costs for both federal agencies and government contractors.34 And, although it is true that the Federal Circuit cannot reach out and decide all the issues it might want to address, that constraint in the bid protest context may be aggravated by a very stark trend in the Federal Circuit’s decisional law—protesters very rarely, if ever, prevail on appeal to the Federal Circuit. Indeed, the number of “wins” (or even partial wins) for protesters that have system likely “would move ever more rapidly towards progress.” Steven L. Schooner, A Random Walk: The Federal Circuit’s 2010 Government Contracts Decisions, AM. U. L. REV. 1067, 1084 (2011). 33 34 11 appealed to the Federal Circuit since the passage of ADRA can be counted on one hand.35 Thus, at least for protesters, the outcome of an appeal to the Federal Circuit seems almost predetermined. money after bad? For protesters, the question is: Why throw good For the Government, however, the message is quite the opposite: When the Government appeals in bid protest cases, the Government always wins.36 Since the enactment of ADRA, it appears that the Government has prevailed in every bid protest appeal it has taken to the Federal Circuit.37 In the discussion that follows, we highlight several of the ways in which the Federal Circuit has had an impact on the development of bid protest law since the enactment of ADRA. II. The Federal Circuit’s Early Post-ADRA Protest Decisions In enacting ADRA, Congress ushered in a new era of judicial review of federal agency procurement decisions by significantly 35 See Paul R. Gugliuzza, Rethinking Federal Circuit Jurisdiction, 100 GEO. L.J. 1437, 1466-67 (2012). That the Federal Circuit has proven to be a hospitable forum for the Government is not a phenomenon unique to bid protest appeals. See id. (noting that the court has been a hospitable forum to the government in many areas within the court’s jurisdiction). Indeed, some have argued that, in government contracts matters in general, the Federal Circuit has drifted away from what was the preceived traditional role of its predecessor, the Court of Claims, as the “conscience of the nation.” See W. Stanfield Johnson, The Federal Circuit’s Great Dissenter and Her “National Policy of Fairness to Contractors”, 40 PUB. CONT. L.J. 275, 346 (2011); Ralph C. Nash, Jr., The Government Contract Decisions of the Federal Circuit, 78 GEO. WASH. L. REV. 586, 587-86 (2010). 36 37 12 expanding the bid protest jurisdiction of the Court of Federal Claims and by establishing the Federal Circuit as the sole reviewing authority for bid protests once ADRA’s grant of concurrent jurisdiction over bid protests to the district courts expired in 2000.38 ADRA fully empowered the Court of Federal Claims with specific statutory jurisdiction, as well as remedial powers, over both pre-award and post-award protests.39 Thus, following the enactment of ADRA, the Federal Circuit became the de facto final forum of appellate review for all bid protests.40 In this role, the Federal Circuit generally has taken a broad view of the types of issues that can be brought to the Court of Federal Claims, while at the same time taking a more limited view of who has standing to bring those claims and, in the end, the level of scrutiny to be applied to the actions of federal agency officials.41 Thus, for example, the Federal Circuit has been relatively consistent in its view that ADRA’s jurisdictional grant over protests “objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award See 142 Cong. Rec. S11848 (daily ed. Sept.30, 1996) (statement of Sen. Cohen) (stating that the proposed amendment to ADRA would “expand the bid protest jurisdiction of the Court of Federal Claims”). 39 See American Federation of Government Employees, AFL-CIO v. U.S., 258 F.3d 1294, 1300 (C.A.Fed.,2001). 40 See Baltimore Gas and Elec. Co. v. United States, 290 F.3d 734,737 (4th Cir. 2002). 41 See infra notes 43-45, 48-55 and accompanying text. 38 13 or the award of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement” is very expansive.42 Early on, in RAMCOR, the court held that “the operative phrase ‘in connection with’ is sweeping in scope.”43 Adopting the definition of “procurement” set forth in 41 U.S.C. § 403(2), the court concluded that the phrase “in connection with a procurement or proposed procurement” covered all stages of the acquisition process, including “the process for determining a need for property or services.”44 Thus, in RAMCOR, the court held that ADRA authorized the Court of Federal Claims to hear a protest challenging the override of an automatic stay triggered by the CICA, 31 U.S.C. § 3553(c)(1).45 On the other hand, the Federal Circuit has taken a narrow view of standing under ADRA, adhering to CICA’s definition of “interested party” for GAO protests and adopting a standard that is more restrictive than the standing requirements under 28 U.S.C. § 1491(b)(1). 185 F.3d at 1289. 44 Id. 45 Need Cite. The court has placed some limits on what qualifies as being “in connection with” a procurement. Need Cite. For example, in Resource Conservation Group, LLC v. United States, the court held that a lease of government property was not a “procurement.” Resource Conservation Group, LLC v. United States, 597 F.3d 1238, 1244 (Fed. Cir. 2010). Likewise, the court in Creation Upgrades, Inc. v. United States, 417 F. App’x 957 (Fed. Cir. 2011), held that a sale of government property was not a “procurement.” Creation Upgrades, Inc. v. United States, 417 F. App’x 957 (Fed. Cir. 2011). 42 43 14 Article III.46 This more narrow view of standing in Court of Federal Claims bid protest cases is manifested in the twin requirements that the protester demonstrate that it was an actual or prospective bidder and that it was prejudiced by the challenged action.47 Thus, in AFGE, the court held that the term “interested party” in § 1491(b)(1) “is limited to actual or prospective bidders or offerors whose direct economic interest would be affected by the award of the contract or by failure to award the contract.”48 By construing the term “interested party” in accordance with the definition set out in CICA—thus requiring protesters to be “actual or prospective bidders” and to possess a “direct economic interest that would be affected by the award of the contract or by the failure to award the contract”49—the See American Federation of Govt. Employees, AFL-CIO v. United States, 258 F.3d 1294, 1302 (C.A. Fed., 2001). 47 See Id. 48 258 F.3d at 1302. 49 See American Federation of Govt. Employees, AFL-CIO v. United States, 258 F.3d 1294, 1302 (C.A. Fed., 2001). The Court of Appeals for the Fourth Circuit in Baltimore Gas & Electric Co. v. United States, 290 F.3d 734 (4th Cir. 2002), followed the Federal Circuit’s formulation in AFGE of ADRA’s standing requirement. Id. at 738. In contrast, the United States Court of Appeals for the Tenth Circuit has held that United States district courts continue to have independent Tucker Act jurisdiction (even after the sunset of district court bid protest jurisdiction under ADRA) to hear protests of federal government procurement decisions by parties whose economic interests would be affected by the procurement, but who are not actual or prospective bidders for the procurement. See City of Albuquerque v. United States Dep’t of the Interior, 379 F.3d 901, 911 (10th Cir. 2004). See also Nat’l Treasury Emp’t Union 46 15 Federal Circuit has confirmed that, in the post-award protest context, the protester needs to have, at a minimum, submitted a timely proposal in a competitive procurement.50 With respect to sole source procurements, the Federal Circuit has held that a protester must show that it was at least a minimally qualified bidder.51 Finally, in addressing the requisite degree of prejudice (which the Federal Circuit confirmed as a “necessary element of standing”),52 the court has required a threshold showing of harm by way of a protester’s “substantial chance” of receiving a contract award that was thwarted due to the Government’s alleged error.53 v. IRS, No. 04-CV-0820, 2006 WL 416161, *6 (D.D.C. Feb. 22, 2006) (following City of Albuquerque). 50 See, e.g., Rex Serv. Corp. v. United States, 448 F.3d 1305, 1308 (Fed. Cir. 2006) (holding that regardless of any illegalities by the Government in the competitive procurement process, if the protester has not bid within the bidding period, it is not an interested party). 51 See Myers Investigative & Sec. Servs., Inc. v. United States, 275 F.3d 1366, 1370-71 (Fed. Cir. 2002). The Federal Circuit recently clarified this holding in Digitalis Education Solutions v. United States, concluding that, where an agency requests statements of capability from potential sources, a protester must submit such a statement in order to be considered an interested party for purposes of standing. Digitalis Education Solutions v. United States, 664 F.3d 1380 (Fed. Cir. 2012). For pre-award bid protests, the Federal Circuit recently adopted a somewhat less rigorous standard, requiring that protesters demonstrate a “non-trivial competitive injury which can be addressed by judicial relief.” Weeks Marine, Inc. v. United States, 575 F.3d 1352, 1362 (Fed. Cir. 2009). 52 Myers, 275 F.3d at 1370. 53 See, e.g., Alfa Leval Separation, Inc. v. United States, 175 F.3d 1365, 1367 (Fed Cir. 1999). 16 The Federal Circuit has also taken a relatively narrow view of the level of scrutiny that should be applied to agency procurement actions.54 In Impresa, the court adopted the APA standard of review and held that an agency’s decision could be set aside if “(1) the procurement official’s decision lacked a rational basis” or “(2) the procurement procedure involved a violation of regulation or procedure.”55 III. The Federal Circuit’s Record in Resolving Conflicts In setting out the above parameters, the Federal Circuit established the basic ground rules for resolving most post-ADRA bid protest actions brought in the Court of Federal Claims.56 But it took the Federal Circuit many years to establish and clarify some of these rules, and, beyond these most basic ground rules, the Federal Circuit has left a number of other important questions still unsettled.57 Of course, as an appellate court, the Federal Circuit is not able to resolve issues in cases that See Impresa, 238 F.3d at 1332-33. Need Cite. Notably, the court did not adopt a standard of review that was as strict as the standard urged by the Government in that case. Need Cite. The Government argued that post-ADRA bid protests should not be set aside “absent allegations of fraud or bad faith.” Impresa, 238 F.3d at 1333. However, as discussed below, the court in Impresa took the unusual step of ordering the deposition of the Contracting Officer to document the basis for the Contracting Officer’s responsibility determination in the record so that the court below could determine whether the determination had a rational basis. Id. at 1339. 56 See supra section II. 57 See infra notes 61-110 and accompanying text. 54 55 17 the parties choose not to appeal.58 The Federal Circuit cannot reach out to decide cases that are not properly before the court.59 But, whatever the reasons (and there likely are a number of independent and related reasons), it appears that the Federal Circuit has not yet fully realized its potential to bring harmony to the law of bid protests. Indeed, the lack of uniformity in the law and the length of time it has taken for the Federal Circuit to resolve conflicting decisions among the judges of the Court of Federal Claims has resulted in significant transaction costs for the Court of Federal Claims and litigating parties.60 The following examples illustrate the point. A. Implied-in-fact Bid Protest Jurisdiction Perhaps the most prominent example of the Federal Circuit’s failure to address an open question created by ADRA has been the issue of the Court of Federal Claims’ jurisdiction to hear 58 59 60 Unified Architecture & Eng'g, Inc. v. United States, 46 Fed. Cl. 56, 60-61 (2000) aff'd, 251 F.3d 170 (Fed. Cir. 2000)(holding that implied in fact jurisdiction had survived ADRA); Block v. United States, 66 Fed. Cl. 68, 77 (Fed. Cl. 2005) (holding that implied in fact jurisdiction had not survived ADRA). However, as one commentator has noted, there are those who do not object to issues “percolating” up through the lower courts towards an ultimate, if delayed, resolution. See Paul D. Carrington & Paulina Orchard, The Federal Circuit: A Model for Reform?, 78 GEO. WASH. L. REV. 575, 583 (2010). 18 protests founded upon the theory of breach of an implied contract of fair dealing.61 Despite a number of conflicting decisions issued by Court of Federal Claims judges, the Federal Circuit in two relatively early opinions expressly declined to provide any guidance on this issue.62 In both Impresa63 and Emery Worldwide Airlines, Inc. v. United States,64 the Federal Circuit acknowledged the issue, but it would take the court nearly a decade to resolve the continuing conflict over this basic issue among the judges of the Court of Federal Claims.65 Indeed, it See 28 U.S.C. § 1491(a)(1) (premising jurisdiction on the existence and breach of an express or implied contract). 62 ; Emery Worldwide Airlines, Inc. v. United States, 264 F.3d at 1081 n.9. 63 238 F.3d at 1332 n.6 (“Although it has been argued that the implied contract theory survives the 1996 amendment [of the ADRA] . . . we need not decide this issue.” (citation omitted)). 64 264 F.3d 1071, 1081 n.9 (Fed. Cir. 2001) (“[W]e decline to address whether the implied contract theory survives the ADRA.”). 61 65 Unified Architecture & Eng'g, Inc. v. United States, 46 Fed. Cl. 56, 60-61 (2000) aff'd, 251 F.3d 170 (Fed. Cir. 2000); Resource Conservation Group, LLC v. United States, 597 F.3d 1238, 1245 (Fed. Cir. 2010); Forestry Surveys & Data v. United States, 44 Fed. Cl. 485, 491 (1999); Aero Corp. v. United States, 38 Fed. Cl. 739, 748 (1997). By the time the Federal Circuit decided Resource Conservation, the conflict among the Court of Federal Claims judges was acute. Need Cite. In the decision under consideration by the Federal Circuit in Resource Conservation, Judge Braden had adhered to an earlier ruling in which she had joined some of her colleagues in holding that implied-in-fact jurisdiction had not survived ADRA. See Res. Conservation Group, LLC v. Dep’t of Navy, 86 Fed. Cl. 475, 486 (2009) (Braden, J.); Information Scis. Corp. v. United States, 85 Fed. Cl. 195, 205 (2008) (Braden, J.); Biltmore Forest Broad. FM, Inc. v. United States, 80 Fed. Cl. 322, 334 19 was not until 2010 that the Federal Circuit concluded that the Court of Federal Claims continued to have implied-in-fact bid protest jurisdiction, at least as to protests where ADRA did not provide a remedy.66 In Resource Conservation Group, LLC v. United States,67 the Federal Circuit held that the Court of Federal Claims could continue to exercise its pre-ADRA jurisdiction under Section 1491(a)(1) over implied-in-fact contract claims.68 In so ruling, the Federal Circuit apparently sought to make clear that ADRA’s new jurisdictional grant under Section 1491(b) was limited to the procurement context but that ADRA’s new jurisdictional provision had not repealed the earlier jurisdictional grant set forth in Section 1491(a)(1) with regard to non-procurement (2008) (Merow, J.); Block v. United States, 66 Fed. Cl. 68, 77 (2005) (Firestone, J.); Lion Raisins, Inc. v. United States, 52 Fed. Cl. 115, 120 (2002) (C. Miller, J.). Several other Court of Federal Claims judges, however, had reached the opposite conclusion. See Hamilton Sundstrand Power Sys. v. United States, 75 Fed. Cl. 512, 516 (2007) (Bruggink, J.); L-3 Commc’ns Integrated Sys., L.P. v. United States, 79 Fed. Cl. at 453, 461-62 (2007) (Williams, J.); Hunt Bldg. Co. v. United States, 61 Fed. Cl. 243, 273 (2004) (Williams, J.); Phoenix Air Grp. v. United States, 46 Fed. Cl. 90, 100 (2000) (Horn, J.); Unified Architecture & Eng’g, Inc. v. United States, 46 Fed. Cl. 56, 60-61 (2000) (Tidwell III, J.); Forestry Surveys & Data v. United States, 44 Fed. Cl 485, 491 (1999) (Gibson, J.); Aero Corp. v. United States, 38 Fed. Cl. 739, 748 (1997) (Futey, J.). 66 Resource Conservation Group, LLC v. United States, 597 F.3d 1238, 1245 (Fed. Cir. 2010). 67 597 F.3d at 1245. 68 20 solicitations.69 In the non-procurement context, the court held, the implied-in-fact contract jurisdiction survived ADRA’s passage and could be exercised by the Court of Federal Claims or the United States district courts.70 Curiously, in resolving this important jurisdictional question that had remained open since the enactment of ADRA, the Federal Circuit did not even acknowledge that it was resolving such a long-standing conflict among the judges of the Court of Federal Claims.71 Rather, the opinion merely noted that it was addressing an issue that the court had left open since its 2001 decisions in Impresa and Emery Worldwide.72 Reading the decision in Resource Conservation, one would have no inkling that the judges of the Court of Federal Claims had been so divided for so long on this issue.73 Id. at 1246 (quoting H.R. No. 104-841, which stated that ADRA was not intended to affect existing jurisdiction applied by the Court of Federal Claims in any other context). 70 Need Cite. The Federal Circuit acknowledged that its ruling would allow both the Court of Federal Claims and United States district courts to exercise jurisdiction over implied-in-fact contract cases, which arguably could lead to the same dualjurisdiction problems that had prompted the passage of ADRA and the consolidation of procurement bid protest jurisdiction in one court. Need Cite. Nevertheless, the Federal Circuit explained, it was for Congress to address that potential problem in the statutory scheme, and not the court. See Res. Conservation Grp., 597 F.3d at 1246. 69 71 72 73 21 Although the decision in Resource Conservation at first blush may appear to have finally provided closure on the question of implied-in-fact contract jurisdiction in the Court of Federal Claims, the Federal Circuit’s decision, in fact, has spawned yet more conflicts among the judges of the Court of Federal Claims.74 As Judge Lettow wryly observed after the Resource Conservation decision, the Federal Circuit’s decision “has been applied in varying ways.”75 Some judges have held that, pursuant to Resource Conservation, the Court of Federal Claims has no jurisdiction to hear an implied covenant of good faith and fair dealing claim in a bid protest action.76 Other judges have held that the Court of Federal Claims continues to have jurisdiction to hear impliedin-fact contract claims in bid protests under Section 1491(a)’s Castle-Rose, Inc. v. United States, 99 Fed. Cl. 517, 530-31 (2011). 74 Castle-Rose, Inc. v. United States, 99 Fed. Cl. 517, 530-31 (2011). 75 76 See Linc Gov’t Servs., LLC v. United States, 96 Fed. Cl. 672, 693 (2010) (“[T]he ADRA added subsection [] 1491(b)(1) . . . displacing the implied contract theory with an explicit statutory grant of jurisdiction to adjudicate bid protest actions.”) ; Metro. Van & Storage v. United States, 92 Fed. Cl. 232, 249-50 n.7 (2010) (concluding that, because the case involved a bid protest of a procurement, the implied-in-fact contract theory was precluded by Section 1491(b)). 22 jurisdictional grant.77 And still other judges have applied Resource Conservation in a third way, concluding that “the Federal Circuit [in Resource Conservation] did not determine that the ADRA precludes a protester from alleging a breach of an implied contract of fair dealing in a procurement case brought pursuant to [S]ection 1491(b). . . . [A] protester may challenge arbitrary and capricious conduct based upon an implied-in-fact contract to consider bids fairly theory as part of a procurement protest in which Tucker Act jurisdiction is based upon 28 U.S.C. § 1491(b)(1).”78 And in attempting to close the door on this basic question about whether the Court of Federal Claims could hear protests based on an implied in-fact contract theory, the Federal Circuit also appears to have raised yet another question: What is the See L-3 Commc’ns Integrated Sys., L.P. v. United States, 94 Fed. Cl. 394, 398 (2010) (“[A]n implicit repeal of [Section] 1491(a)’s procurement jurisdiction would run counter to the longstanding principle of statutory construction which recognizes a strong presumption against an implied repeal of a jurisdictional statute. . . . Without an express repeal . . ., the common law developed under [Section] 1491(a) permitting bid protests of procurements and [the] ADRA should be interpreted ‘in a manner which gives harmonious operation and effect to both.’”). 77 78 Bilfinger Berger AG Sede Secondaria Italiana v. United States, 97 Fed. Cl. 96, 151-52 (2010). . Accord Castle-Rose, Inc. v. United States, 99 Fed. Cl. at 530-31 (concluding that, “[w]hether or not this court has jurisdiction to hear an implied-contract claim under Section 1491(a) in a bid protest action, the court agrees with Bilfinger Berger that it surely has jurisdiction to hear such a claim under Section 1491(b) as added by the ADRA”). 23 standard by which the Court of Federal Claims should review a non-procurement action that is subject to an implied-in-fact contract breach action?79 Despite the existence of this open question, the Federal Circuit in Creation Upgrades, Inc. v. United States80 instead avoided the question in an unpublished decision, even though the case provided the court with an opportunity to address the issue.81 Although the court appeared to apply an “arbitrary and capricious” APA standard of review in that case, the panel issued the opinion as non-precedential, and the question remains open.82 B. Protest Timeliness Protests filed with the Court of Federal Claims under the court’s Tucker Act jurisdiction do not have the express 79 417 F. App’x 957, 960 (Fed. Cir. 2011) (stating that, in order to maintain a claim for breach of an implied-in-fact contract of fair dealing, the plaintiff must provide prima facie evidence of an arbitrary and capricious action on the part of the Government). 80 81 Need Cite. See also Order Requiring Further Briefing on Proper Procedural Vehicle for Resolving Bid Protest, Commc’n Constr. Servs., Inc. v. United States, No. 10-878C, Order at 3-4 (Fed. Cl. Mar. 13, 2012) (Coster Williams, J.). (ordering parties to file supplemental briefs to address the proper procedural vehicle—whether cross—motions for summary judgment or cross—motions for judgment on the Administrative Record—for resolving a bid protest brought under 28 U.S.C. § 1491(a) under a breach of the implied contract of fair dealing theory). 82 24 timeliness rules that are present in GAO bid protests.83 Thus, except in rare cases, the Federal Circuit has generally avoided imposing strict timeliness requirements on protesters.84 The only substantial limitation the Federal Circuit has ever placed upon the timeliness of protests concerns the Court’s establishment of a “waiver rule” under Blue & Gold Fleet, L.P. v. United States.85 Under the standard announced in Blue & Gold, See Griffy's Landscape Maint. LLC v. United States, 46 Fed. Cl. 257, 257-58 (2000) (sustaining protest where GAO had previously dismissed the protest as untimely); Heritage of Am., LLC v. United States, 77 Fed. Cl. 66, 72 (2007) (and cases cited therein) (rejecting Government's argument that the court should dismiss the plaintiff's protest as untimely, noting that the timeliness requirement was based on GAO rules, not on the COFC's jurisdictional statues or rules); Software Testing Solutions, Inc. v. United States, 58 Fed. Cl. 533, 535-36 (Fed. Cl. 2003) (holding that the Court of Federal Claims is not subject to GAO's timeliness rules and should look for unreasonable and unexcused delay by the claimant, and prejudice to the other party.); CW Gov't Travel, Inc. v. United States, 61 Fed. Cl. 559, 568 (Fed. Cl. 2004) aff'd, 163 F. App'x 853 (Fed. Cir. 2005) and aff'd, 163 F. App'x 853 (Fed. Cir. 2005).. 84 Heritage of Am., LLC v. United States, 77 Fed. Cl. 66, 72 (2007) (and cases cited therein) (rejecting Government's argument that the court should dismiss the plaintiff's protest as untimely, noting that the timeliness requirement was based on GAO rules, not on the COFC's jurisdictional statues or rules); Software Testing Solutions, Inc. v. United States, 58 Fed. Cl. 533, 535-36 (Fed. Cl. 2003) (holding that the Court of Federal Claims is not subject to GAO's timeliness rules and should look for unreasonable and unexcused delay by the claimant, and prejudice to the other party.) 83 85 Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313-14 (Fed. Cir. 2007). . The Blue & Gold decision confirmed an earlier line of Federal Circuit decisions applying the doctrine of patent ambiguity— imposing on bidders the obligation to seek clarification from the Government of patently ambiguious solicitation provisions 25 if a protester has an opportunity to object to the terms of a solicitation which contains a patent error, the protester must bring that protest before the close of the bidding process or otherwise face dismissal.86 In so ruling, the Federal Circuit brought the timeliness rule for Court of Federal Claims protests (at least with regard to challenges to solicitations) in line with the GAO’s regulations and protest decisions.87 The Federal Circuit issued the Blue & Gold decision in 2007, nearly ten years after ADRA became effective.88 In the decade preceding Blue & Gold, however, the judges of the Court of Federal Claims had struggled to apply a consistent rule and rationale to the timeliness of pre-award bid protests.89 It was lest they waive the right to have their interpretation of the solicitation be accepted in a subsequent bid protest challenging an award to another bidder. See id. at 1313 (citing Stratos Mobile Networks USA, LLC v.United States, 213 F.3d 1375, 1381 (Fed. Cir. 2000), and Statistica, Inc. v. Christopher, 102 F.3d 1577, 1582 (Fed. Cir. 1996)). 86 Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 131314 (Fed. Cir. 2007). 87 See 4 C.F.R. § 21.2(a)(1) (2012) (requiring that “protests based upon alleged improprieties in a solicitation which are apparent prior to bid opening or the time set for receipt of initial proposals shall be filed prior to bid opening or the time set for receipt of initial proposals”). 88 Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 131314 (Fed. Cir. 2007). Compare ABF Freight Sys., Inc. v. United States, 55 Fed.Cl. 392, 399-400 (Fed. Cl. 2003) (applying the GAO’s timeliness rule). ; 89 26 not until the Federal Circuit finally announced the rule in Blue & Gold that a coherent rule with regard to timeliness for Court of Federal Claims pre-award protests came into being.90 C. Scope of Record for Review The Federal Circuit’s post-ADRA jurisprudence has attempted to ensure that an adequate record of an agency’s procurement decision is available at the Court of Federal Claims in order to facilitate meaningful judicial review of the agency’s rationale for its decision.91 In Impresa, the Federal Circuit set the standard for the sufficiency of an agency’s record justifying its procurement decision.92 The court clarified that procurement decisions, which are not formal adjudications or rulemakings, N.C. Div. of Servs.s For Blind v. United States, 53 Fed. Cl. 147, 165-66 (Fed. Cl. 2002) aff'd sub nom. N. C. Div. of Servs. for the Blind v. United States, 60 F. App'x 826 (Fed. Cir. 2003) (same). , with Argencord Mach. & Equip., Inc. v. United States, 68 Fed. Cl. 167, 175 n. 14 (Fed. Cl. 2005). (declining to apply the GAO’s timeliness rule); CW Gov't Travel, Inc. v. United States, 61 Fed. Cl. 559, 568 (Fed. Cl. 2004) aff'd, 163 F. App'x 853 (Fed. Cir. 2005) and aff'd, 163 F. App'x 853 (Fed. Cir. 2005)(same);EDP Enters., Inc. v. United States, 56 Fed. Cl. 498 (2003) (same); MVM, Inc. v. United States, 46 Fed. Cl. 126 (2000) (same). 90 Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 131314 (Fed. Cir. 2007). 91Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 1379-83 (Fed. Cir. 2009); Impresa Construzioni Geom. Domenico Garufi v. United States, 238 F.3d 1324, 1337-41 (Fed. Cir. 2001). 92 27 are subject to less stringent documentation requirements on the part of the agency.93 Nevertheless, because a Contracting Officer’s discretion in reaching procurement decisions is not absolute, the Federal Circuit confirmed the Court of Federal Claims’ authority to compel the agency to explain its rationale in cases where evidence rebuts the presumption of the “regularity” of the agency’s decision.94 In what the court itself described as a “rare case,” the court concluded that the lack of explanation on the part of the Contracting Officer in reaching a responsibility determination constituted a “rare case” in which the Contracting Officer’s rationale was not apparent from the record.95 The Court concluded that additional testimony from the Contracting Officer would be required in order to establish the basis for his decision.96 However, the Federal Circuit more recently reiterated its view that the Court of Federal Claims should only review the administrative record before the agency in considering protests of agency procurement decisions and that supplementation of the record with extra-record evidence should be avoided.97 In Axiom 93 94 95 96 Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 137983 (Fed. Cir. 2009). 97 28 Resource Management, Inc. v. United States,98 the Court concluded that the Court of Federal Claims had abused its discretion by allowing extensive supplementation of the administrative record without first determining whether the record before the court was sufficient to allow for a meaningful judicial review.99 The Federal Circuit reiterated that inclusion of extra-record evidence in the administrative record is only proper in cases where the record, without the additional evidence, was so inadequate as to preclude meaningful review.100 D. Other Open Issues An emerging protest issue that requires resolution is in the area of so-called “insourcing” (where a federal agency uses federal employees in lieu of private contractors to meet the agency’s needs).101 There are two conflicting lines of decisions in the Court of Federal Claims concerning whether the court has jurisdiction over a protest involving an insourcing decision.102 One judge concluded that, because the agency’s insourcing 98 99 Id.. Id. 100 Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 1379-83 (Fed. Cir. 2009). See also Levine v. United States, 453 F.3d 1348, 1350 (Fed. Cir. 2006). . 101 Santa Barbara Applied Research, Inc. v. United States, 98 Fed. Cl. 536, 542-43 (2011) (Firestone, J.). 102 Hallmark-Phoenix 3, LLC v. United States, 99 Fed. Cl. 65, 68 (2011) (Allegra, J.). 29 decision was made “in connection with a procurement or proposed procurement,” the court did have jurisdiction over the protest.103 In the other case, the Court of Federal Claims judge dismissed the protest of an agency’s insourcing decision, holding that the protester lacked “prudential” standing to challenge decisions related to the agency’s insourcing statutory protocol.104 It appears that neither of these decisions was appealed to the Federal Circuit, so the Federal Circuit has not yet had an opportunity to resolve this conflict.105 It should be noted, however, that two of the circuit courts of appeals have Santa Barbara Applied Research, Inc. v. United States, 98 Fed. Cl. 536, 542-43 (2011) (Firestone, J.). 104 Hallmark-Phoenix 3, LLC v. United States, 99 Fed. Cl. 65, 68 (2011) (Allegra, J.) (reasoning that Congress did not enact the Department of Defense’s in-sourcing statutes (10 U.S.C. §§ 129a and 2463) for the benefit of dissatisfied contractors). See also Triad Logistics Servs. Corp. v. United States, No. 11-43C, slip op. at *33 (Fed. Cl. Apr. 16, 2012) (Horn, J.) (concluding that the protester lacked a direct economic interest in the procurement at issue because the protester had waited for its contract to expire before challenging the agency’s decision to in-source future contract tasks but leaving open the question of whether an insourcing decision could be the subject of a proper protest). 105 Compare Santa Barbara Applied Research, Inc., 98 Fed. Cl. at 542-43 with Hallmark-Phoenix 3, LLC, 99 Fed. Cl. at 68. In yet another decision, Judge Bruggink sided with Judge Firestone and held that the court had jurisdiction to hear a protest regarding an in-sourcing decision. See Elemendorf Support Servs. Joint Venture v. United States, No. 12-346C, slip op. *10 (Fed. Cl. June 22, 2012). 103 30 held that the district courts do not have jurisdiction to hear challenges to agency insourcing decisions.106 In yet another area of conflicting decisions, judges of the Court of Federal Claims had held in the initial years after the enactment of ADRA that, because of the Suits in Admiralty Act,107 which placed jurisdiction over maritime contracts in the district courts, the proper venue for maritime bid protests was the district court, regardless of the Court of Federal Claims’ ADRA or preexisting Tucker Act jurisdiction.108 In 2009, however, one of those same judges reversed course and held that the Court of Federal Claims did indeed have jurisdiction over a bid protest, even though the underlying contract was a maritime contract.109 Congress recently resolved this open issue See Rothe Dev., Inc. v. United States Dep’t of Defense, 666 F.3d 336, 339 (5th Cir. 2011); Vero Tech. Support v. United States Dep’t of Defense, 437 F. App’x 766, 771 (11th Cir. 2011). In both decisions, the courts determined that challenges to insourcing decisions fell within the Court of Federal Claims’ exclusive jurisdiction under ADRA. 666 F.3d at 339; 437 F. App’x at 771. 107 46 U.S.C. §§ 30901-30918 (2006). 108 See Bayship Mgmt., Inc. v. United States, 43 Fed. Cl. 535, 537 (1999) (Futey, J.) (concluding that regardless of the Court of Federal Claims’ jurisdictional basis, because the subject matter of the underlying contract at issue was maritime, the court lacked jurisdiction due to the Suits in Admiralty Act); accord Asta Eng’g, Inc. v. United States, 46 Fed. Cl. 674, 67677 (2000) (Merow, J.). 109 Red River Holdings, LLC v. United States, 87 Fed. Cl. 768, 797 (2009) (Merow, J.) (concluding that Astia Engineering had been wrongly decided and the bid protest at issue was “preliminary to a possible contract and lacks a maritime nature or purpose”). 106 31 regarding the proper venue for bid protests relating to maritime contracts by vesting exclusive jurisdiction over maritime bid protests in the Court of Federal Claims.110 IV. The Federal Circuit’s Impact on the U.S. Government Accountability Office Although the other principal forum for bid protests, the GAO, is not bound by the precedent of the Federal Circuit in deciding bid protests, that does not mean the Federal Circuit’s decisions have not influenced the GAO in its decision making.111 Sometimes the Federal Circuit and the GAO arrive at the same conclusion on their own.112 And, in other instances, the GAO has expressly acknowledged that a ruling from the Federal Circuit on an issue that GAO has previously addressed could well cause the GAO to reconsider its approach and follow the Federal Circuit’s approach if it differs.113 And, for second-bite-at-the-apple See 2012 National Defense Authorization Act § 861, 28 U.S.C. § 1491(b)(6). 111 See DGR Assoc., Inc., B-402494, May 14, 2010, 2010 CPD ¶ 115 at *3. 112 Cf. Performance Evacuators, Inc., B-291771, Mar. 17, 2003, 2003 CPD ¶ 63 at 3 (citing Emery Worldwide Airlines, Inc. v. United States, 264 F.3d 1071, 1079 n.7 (Fed. Cir. 2001), and noting that the Federal Circuit, on its own, had recently reached the same conclusion as the GAO with regard to United States Postal Service procurements being exempt from the GAO’s bid protest jurisdiction). 113 See DGR Assoc., Inc., B-402494, May 14, 2010, 2010 CPD ¶ 115 (discussing the split between GAO and the Executive Branch agencies regarding an interpretation of the Small Business Act’s provisions and Small Business Administration regulations on HUBZone set-aside procurements and stating that it would continue to decide protests in accordance with its established 110 32 protests, the Federal Circuit has been the last word for bid protests that began at the GAO.114 The Federal Circuit’s decisions have clearly informed the GAO’s bid protest jurisprudence in numerous areas, and the GAO has borrowed extensively from the Federal Circuit’s decisions in the years following the passage of ADRA.115 Perhaps the most recent example of this phenomenon has been the Federal Circuit’s articulation of the appropriate standard for review of alleged organizational conflicts of interests (OCIs) in federal procurement.116 The Federal Circuit’s 2010 decision in Axiom reaffirmed the application of the APA’s “arbitrary and capricious” standard of review to Contracting Officers’ interpretation until the Federal Circuit issued a contrary decision on the matter). Indeed, in response to the Federal Circuit’s decision in Impresa, which held that the Court of Federal Claims could enterain a protest concerning a contracting officer’s responsibility determination, the GAO revised its rules to allow the GAO to consider challenges to affirmative responsibility determinations. See Final Rule, 67 Fed. Reg. 79,833, 79,836 (Dec. 31, 2002) (revising 4 C.F.R. § 21.5 to allow for GAO bid protests “that allege that definitive responsibility criteria in the solicitation were not met and those that identify evidence raising serious concerns that, in reaching a particular responsibility determination, the contracting officer unreasonably failed to consider available relevant information or otherwise violated statute or regulation”). 114 See e.g., DGR Assoc., Inc., B-402494, May 14, 2010, 2010 CPD ¶ 115. 115FN Manufacturing, Inc., B-297172; Dec. 1, 2005, at 8-9. 116 Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 137983 (Fed. Cir. 2009). 33 decisions regarding OCIs.117 Thereafter, the GAO expressly adopted this standard, characterizing the Axiom decision as a “mandate” from the Federal Circuit to do so.118 The following year, in a protest that had started at the GAO before moving to the Court of Federal Claims, the Federal Circuit rejected the GAO’s reasoning for sustaining the protest based upon the potential existence of OCIs.119 In that decision, the Federal Circuit found that the GAO’s decision itself lacked a rational basis and that the GAO had improperly substituted its judgment for that of the agency Contracting Officer.120 Moreover, the See Id. at 1386 (noting that a Contracting Officer’s review of alleged OCIs and efforts to mitigate such OCIs are accorded considerable discretion). 118 See, e.g., TriCenturion, Inc.; SafeGuard Servs., LLC, B-406032 et al., Jan. 25, 2012, 2012 CPD ¶ 52 at *22-23. 119 Turner Constr. Co. v. United States, 614 F.3d 1377, 1385 (Fed. Cir. 2010). 120 614 F.3d at 1385. The Federal Circuit’s decision in Turner Construction, where the court rejected as arbitrary and capricious the GAO’s recommendation, is one example of the Federal Circuit specifically rejecting the reasoning of the GAO. Id. The Federal Circuit’s treatment of the GAO’s analysis in the Turner Construction decision may end up driving a wedge between the GAO and the courts by increasing those instances where agencies decline to follow GAO recommendations, thus driving up the transaction cost for all stakeholders in bid protest litigation. See Federal Circuit Holds That Agency Was Arbitrary and Capricious in Following A Government Accountability Office Recommendation, 125 HARV. L. REV. 1266, 1272 (2012) (observing that Turner Construction’s “likely effect will be to increase the number of GAO recommendations that are not followed by agencies” and noting that, from this, one of the transaction costs likely will be that “the average cost of a GAO decision to sustain a bid protest will increase, as the GAO will more likely be obliged to report to Congress” that its recommendation was not followed). The Turner Construction case 117 34 Federal Circuit confirmed that a protester must identify “hard facts” that tend to indicate the existence or potential existence of a conflict and that mere “suspicion and innuendo” is not enough to establish the existence of an OCI.121 As a result, the GAO’s subsequent decisions have referenced and applied the “hard facts” standard established by the Federal Circuit in Axiom and Turner.122 V. Conclusion ADRA ushered in a new era in bid protest litigation in many ways, not the least of which was the consolidation of appellate review of bid protest decisions in one forum—the Federal Circuit.123 Following ADRA, the Federal Circuit became the one tribunal with the power and, more importantly, the ability to bring uniformity to the law of bid protests.124 Although the court has provided answers to some of the most pressing questions regarding bid protest litigation after ADRA, the full is also notable for being one of several bid protest cases decided in 2008 in which the Court of Federal Claims reached a different result from the GAO. See Richard J. Webber, Bid Protests: Different Outcomes in the Court of Federal Claims and the Government Accountability Office in 2008, 44 THE PROCUREMENT LAWYER 13 (2009) (discussing cases from 2008 in which the GAO and the Court of Federal Claims reached differing results but ostensibly applied the same legal standard). 121 Id. at 1385. 122 See, e.g., McTech Corp., B-406100 et al., Feb. 8, 2012, 2012 CPD ¶ 97, at *6. 123 Protests and appeals, 1 West's Fed. Admin. Prac. § 664 (4th ed. 2012). 124 35 promise of ADRA and the Federal Circuit still has not been met.125 Perhaps the realization of that promise has been hampered by the reality that few bid protest decisions are appealed to the Federal Circuit.126 If that is the case, and more appeals of Court of Federal Claims bid protest decisions will be needed to smooth out the post-ADRA bid protest law, the next fifteen years may prove to be very interesting, and the Federal Circuit’s impact greater than it has been thus far. Only time and many more appeals will tell. 125 126 36