1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 DALAM MAHKAMAH TINGGI MALAYA DI JOHOR BAHRU DALAM NEGERI JOHOR, MALAYSIA GUAMAN SIVIL NO. : 22-834-2003 BETWEEN CRESCENT CONCRETE SDN BHD … PLAINTIFF AND (1) SULONG ENGINEERING SDN BHD … 1ST DEFENDANT (2) DATO’ HAJI SULONG BIN HAJI MAMAT … 2ND DEFENDANT GROUNDS OF DECISION Introduction [1] The proceeding in this case arose from the claim of the plaintiff for the balance of the price of goods sold and delivered to the 1st defendant whereby the 2nd defendant was the guarantor. At the conclusion of the trial, I allowed the claim in part against the 2nd defendant but dismissed the claim against the 1st defendant. I now give my reasons. The Facts [2] The 1st defendant was the main contractor in a building project at Bandar Uda Utama, Pulai, Johor. On 18.4.2001, it engaged Lotus Quest Sdn Bhd as its total subcontractor to carry out the works of the project, which also entailed purchasing concrete from 3rd parties. Sometime in April of 2001, PW1, a director and sales manager of the plaintiff company, found out that Lotus Quest wanted to buy concrete from the plaintiff. He therefore went to an office in Larkin Perdana, Johor Bahru that had a signboard carrying the name “Sulong Engineering”. At that office, he met one Encik Zainuddin that held himself out to be a representative of Lotus Quest Sdn 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Bhd. Zainuddin had even given PW1 his business card, which indicated he was from Lotus Quest. There was no one else present at that meeting. [3] PW1 said he handed to Zainuddin a quotation dated 24.4.2001 (at pages 1-2 of Agreed Bundle D (Part B)) setting out the terms of supply of the concrete. He said it was Zainuddin that had furnished him with the details of the address and contact persons stated on the quotation. The following details on the quotation are material : (i) it was addressed to “Sulong Engineering Sdn Bhd/Lotus Quest Sdn Bhd”; (ii) the trading address of “Sulong Engineering Sdn Bhd/Lotus Quest Sdn Bhd” was stated as “15, Susur Perdana 1, Larkin Perdana, Johor Bahru”; (iii) the telephone number stated below the trading address was 072340745 and the fax number as 07-2386021; and (iv) the quotation was made to the attention of En. Zulkifli Ismail and En. Abd Aziz Khan Alior Khan. PW1 admitted in court that these 2 persons were representatives of Lotus Quest. [4] According to PW1, Zainuddin took the quotation back. Subsequently, the quotation was returned to him acknowledged and signed. The acknowledgment chop at the last page of the quotation (p.2 of Bundle D) was in the name of Sulong Engineering Sdn Bhd. However, as will be seen later, it bore the trading address of Lotus Quest as well as their telephone and fax numbers. [5] The plaintiff commenced supply of concrete to the project site on 31.5.2001. Lotus Quest received the first delivery of 350m³ and the relevant delivery orders were duly chopped and signed by them. According to PW1, when he found out that Lotus Quest received the first 350m³ and that the recipient chops were that of Lotus Quest, he stopped delivering the concrete. He then requested Lotus Quest to change the recipient’s chop to that of the 1st defendant before he would resume supply. Obviously, Lotus Quest complied because deliveries had resumed on 14.6.2001 as could be seen from the delivery order at page 36 of Bundle E, which appears to be the first to bear the chop of Sulong Engineering as recipient. Thereafter nearly all the delivery orders bore the chop of Sulong Engineering as recipient. According to PW1, the plaintiff continued to deliver the concrete until 31.7.2001 when he ceased because the plaintiff was not getting any payment from the 1st defendant despite the accumulated debt at RM 472, 804.00. 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 [6] In July of 2001, DW2, in his capacity as the project coordinator of the 1st defendant, visited the project site. He discovered there was delay in construction and a shortage of ready-mixed concrete. He informed DW1 who was the 2nd defendant and the managing director of the 1st defendant company. On 1.8.2001 DW1, DW2 and DW3, the 1st defendant’s project supervisor, met with Encik Zainuddin of Lotus Quest at the project site. Zainuddin told them that the delay was due to shortage of supply of concrete from the plaintiff. DW1 then requested Zainuddin to arrange a meeting with the plaintiff. [7] A meeting was arranged the same day at the site and attended by DW1, DW2, DW3, PW1 and Zainuddin. At the meeting, PW1 said that the stoppage of supply of concrete was due to the failure of Lotus Quest paying for the earlier deliveries because it had not received payment from the 1st defendant. DW1 stated in response that the 1st defendant had never defaulted in any payment to Lotus Quest. DW1 then offered to take over the purchase of concrete from Lotus Quest and deal directly with the plaintiff from then on, that is to say from 1 August 2001. He as well agreed to execute a personal guarantee for the supply of concrete from the plaintiff from August 2001. PW1 then handed a personal guarantee form and an application for credit facilities to DW1 for him to sign. DW1 did not sign the guarantee and application form immediately as he wanted to consult his lawyers. Further, DW1 wanted a letter of undertaking from Lotus Quest that they would settle the debts for concrete supplied to Lotus Quest prior to August 2001. He made this known at the meeting. [8] The personal guarantee (at pp 39-42 Agreed Bundle B(Part B)) and the application for credit facilities (at Bundle B pp 34-37) were signed by DW1 on 13.8.2001 and returned to the plaintiff vide letter dated 13.8.2001 (at Bundle B p 38). In the letter, DW1 stated that the guarantee was to take effect from July 13, 2001 and for deliveries made on and/or after that date. PW1 accepted the terms of the letter by signing at the portion below. In the meantime, Lotus Quest had issued a letter of 4.8.2001 (at Bundle D p.9) to the 1st defendant undertaking it would settle all amounts outstanding for the amount of concrete already ordered for the project. [9] By a letter of 22.1.2002 (at Bundle B p. 44) the 1st defendant wrote to the plaintiff to inform that there had been a mistake to the letter of 13.8.2001 in that the date the guarantee was to commence was mistakenly 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 stated as 13.7.2001 when instead it should have been 13.8.2001. PW1 testified he responded with his letter of 24.1.2002 (at p.5 Bundle D) wherein he stated his disagreement to the 1st defendant changing the commencement date and insisting instead that the date 13.7.2001 should be maintained. [10] The plaintiff resumed delivery of concrete to the project site from August 2001. Although the 1st defendant had taken over the purchase of the concrete from August 2001, Lotus Quest was still the subcontractor responsible to place orders, receive the concrete at site and collate the delivery orders for the 1st defendant to make payment. In November 2001, the 1st defendant terminated Lotus Quest as the subcontractor and thereafter, the 1st defendant was directly involved in ordering and receiving the concrete from the plaintiff. [11] It was not in dispute that the 1st defendant had paid in full to the plaintiff for all deliveries made from August 2001 onwards. The Plaintiff’s Claim [12] The plaintiff’s claim against the 1st and the 2nd defendants was for the sum of RM343, 306.32 as at 21.3.2002. It was the case for the plaintiff that this was the balance of the sum due and owing for the concrete sold and delivered by them to the 1st defendant. At the trial, it was not in dispute between the parties that the plaintiff’s claim in reality was for invoices issued for deliveries of concrete made prior to August 2001. The 2nd defendant was sued on the personal guarantee of 13.8.2001 wherein he had guaranteed payment for concrete supplied on and after 13.7.2001. The Defence and Counterclaim [13] The defendants pleaded that the 1st defendant did not have any contractual relationship with the plaintiff prior to August 2001 and was therefore not liable to pay for any concrete delivered before that date. The defendants admitted that the 2nd defendant issued the personal guarantee of 13.8.2001. They however averred that it was only to guarantee payment of all future supply of concrete by the plaintiff, that is to say, for deliveries made after August 2001. Further, the value of the concrete supplied by the plaintiff from 1.8.2001 amounted to RM 814, 287.00 and the 1st defendant had paid the plaintiff RM 841, 123.00 resulting in an overpayment of 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 RM 26, 835.50. Thus, rather then there being any sum due to the plaintiff, there instead was overpayment of RM 26, 835.50 that the 1st defendant wished to counterclaim. However, at the trial, learned counsel for the defendants withdrew the counterclaim and the court accordingly had it dismissed. Issues for Trial [14] The parties by their Statement of Issues to be Tried dated 26.11.2009 (Bundle H) confined the issues for trial to the following : (i) whether the 1st defendant was indebted to the plaintiff in the sum of RM343,306.32 as at 21.3.2002; (ii) whether the 2nd defendant was liable under the guarantee given on 13.8.2001 to pay the plaintiff the said sum of RM342,306.32; and (iii) whether the 1st defendant had overpaid the plaintiff by RM26,835.50. Given that the defendants had withdrawn the counterclaim, issue (iii) above was no longer in contention. Was the 1st defendant indebted to the plaintiff in the sum of RM343, 306.32 as at 21.3.2002? [15] As stated earlier, it was not in dispute that the claim of the plaintiff in reality was for the balance of payment on invoices issued for deliveries of concrete made before August 2001. It was the case for the plaintiff that the 1st defendant was liable to pay because the supply agreement i.e. the quotation dated 24.4.2001 (at Bundle D pp 1-2) and some of the delivery orders issued prior to August 2001 (in Bundle E) bore the company chop of the 1st defendant which proved that the agreement was between the plaintiff and the 1st defendant and the concrete delivered to the 1st defendant. I found that the plaintiff had not on balance of probabilities proved its case against the 1st defendant for the following reasons. [16] In Artic Building and Civil Engineering Sdn Bhd v Ahmad Zaki Sdn Bhd & Ors [2009] 9 MLJ 328 it was held that a subcontractor is independent from a main contractor. Further, the subcontractor’s acts or representations vis-à-vis a 3rd party supplier would not bind the main contractor so as to give an obligation by the main contractor to the 3 rd party 5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 supplier. In the present case, the acts and representations of Encik Zainuddin of Lotus Quest could not bind the 1st defendant to pay for concrete delivered prior to August 2001. Zainuddin was neither a representative nor agent of the 1st defendant and was never authorized by the 1st defendant to enter into any agreement on its behalf with the plaintiff let alone the supply agreement. [17] There was evidence from DW1 supported by DW2 that Lotus Quest had before August 2001, misused the 1st defendant’s corporate name by using the 1st defendant’s company chop and affixing it to the plaintiff’s quotation and delivery orders without the defendant’s permission and knowledge. Another misuse was falsely opening an office at No. 15, Susur Larkin Perdana 1, Larkin Perdana, Johor Bahru under the 1st defendant’s name. I believed and accepted the evidence for the 1st defendant on this because it was supported by the act of DW1 in lodging the police report of 28.11.2001 (at Bundle D pp 6-8) against Lotus Quest. This report was lodged after the 1st defendant took over the works from Lotus Quest in November and the full extent of the misuse came to light. Moreover, there was corroboration of the evidence of DW1 from PW1 himself who under cross-examination admitted that before August 2001 the 1st and 2nd defendants had no dealings at all with the plaintiff. In my judgment, if the plaintiff and the defendants had no such dealings, there was no reason for the company chop of the 1st defendant to have appeared on the quotation and delivery orders that were issued before August 2001. There must have been a misuse of it as was the assertion of the defendants. [18] In any event, the evidence in my view clearly showed that PW1 was actually aware that the supply agreement was with Lotus Quest and not with the 1st defendant. During cross-examination, PW1 let on that when he learned in early April of 2001 that someone was interested in purchasing concrete from the plaintiff, the information he received was that the party interested was Lotus Quest. Nothing was mentioned of Sulong Engineering, the 1st defendant. Thus, when he went over to the office at Larkin Perdana it was to seek out Lotus Quest and not Sulong Engineering. PW1 admitted further under cross-examination that when he met Zainuddin at the office, he knew that the latter was a representative of Lotus Quest and not acting on behalf of the 1st defendant. As he said, Zainuddin had even given him a business card that indicated he was from Lotus Quest. 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 [19] Moreover, PW1 admitted it was Zainuddin that had furnished him with the details of the address and contact persons stated on the quotation. The trading address given was “No. 15, Susur Perdana 1, Larkin Perdana, Johor Bahru”. It is noteworthy that address was actually the trading address of Lotus Quest as confirmed by the SSM search (at p.2 of Agreed Bundle B (Part A)). The telephone number stated below the trading address was 07-2340745 and the fax number 07-2386021. Both these numbers belong to Lotus Quest as can be seen on the letterhead of Lotus Quest found at p.9 of Agreed Bundle D (Part B). What was more, the quotation was made to the attention of En. Zulkifli Ismail and En. Abd Aziz Khan Alior Khan. PW1 admitted in court that these 2 persons were representatives of Lotus Quest. In my judgment, the reasonable inference was that PW1 very well knew that the supply agreement was with Lotus Quest and not with Sulong Engineering. [20] Even if for argument’s sake, Zainuddin were a representative or agent of the 1st defendant, his acts and representation, would still not bind the 1st defendant. This is because neither the 1st defendant nor Zainuddin himself had represented to the plaintiff that he had the authority to enter into any agreement on behalf of the 1st defendant. In Freeman & Lockyer (A Firm) v Buckhurst Park Properties (Mangal) Ltd and Another [1964] 2 QB 480 it was held that for an agent to have apparent authority to bind the principal, one of the conditions is that there must be a representation by the principal that the agent has the authority to enter into a contract on behalf of the principal. In Chew Hock San & Ors v Connaught Housing Development Sdn Bhd [1985] 1 MLJ 350 our Federal Court held on the facts of that case that a clerk of the respondent did not have the authority to bind the respondent as the clerk had acted without the knowledge and consent of the respondent. [21] The plaintiff in addition had a duty to take reasonable steps to ascertain and confirm with the 1st defendant that they would be the purchaser of the concrete considering the fact that: (i) Lotus Quest and the 1st defendant are separate entities; (ii) the 1st defendant was a company based in Terengganu; (iii) PW1 was aware that he was only dealing with Zainuddin as a representative of Lotus Quest; and (iv) PW1 was aware he was not dealing with any of the 1st defendant’s representatives. Under cross-examination, PW1 admitted that he should have taken steps to verify and confirm with the 1st defendant that they would be the purchaser of the concrete but he failed to do so. In Armagas Ltd v Mundogas SA; The 7 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Ocean Frost [1985] 3 All ER 795 it was held that the representee cannot assume, based simply on the agent’s representation, that the agent had authority to enter into a contract on behalf of the principal. Stephenson LJ remarked at p. 830 : “Knowing that it should have referred to Mundogas’s top management for confirmation of Magelssen’s representation that he had their authority and should not have relied on his representation (or on its agent Johannesen, who transmitted it to it), Armagas took the risk of Magelssen’s representation of authority being untrue and cannot hold Mundogas responsible for his fraudulent misrepresentation either in contract or in tort.” [22] Furthermore, PW1 admitted during cross-examination that he was the one who before August 2001 requested Lotus Quest to change the acknowledgement chop on the delivery orders from that of Lotus Quest to Sulong Engineering otherwise he would not resume supplying the concrete to the project site. That being the case, when the chop was suddenly changed from that of Lotus Quest to Sulong Engineering, PW1 in my view, should have verified and confirm with the 1st defendant that they were the purchasers of the concrete. This was the more so because PW1 knew right from the start that he was dealing with Zainuddin who was not a representative of Sulong Engineering but of Lotus Quest. Neither Zainuddin nor Sulong Engineering had ever represented to him that Zainuddin could enter into any agreement on behalf of Sulong Engineering. And presently, we had PW1 asking Lotus Quest to change the chop to that of Sulong Engineering. When the chop was suddenly changed to that of Sulong Engineering, surely PW1 should have been put on guard and should have verified with Sulong Engineering. Without verifying or confirming with Sulong Engineering, PW1 took the risk of the chop having been misused or forged as indeed it was. [23] Fourthly, I was of the view that the events that transpired at the meeting of 1.8.2001 and subsequent to that were further proof that the supply agreement prior to August 2001 could not have been with the 1 st defendant. All 3 witnesses for the defendants testified that at the meeting PW1 informed them that the stoppage of supply of concrete was due to the failure of Lotus Quest paying for the earlier deliveries because it had not received payment from the 1st defendant. DW1 asserted that he corrected PW1 by stating that Sulong Engineering had never defaulted on payments to Lotus Quest. He said he had even gone on to require from Lotus Quest a 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 letter of undertaking that they would settle the debts for concrete supplied to Lotus Quest prior to August 2001. [24] I found the evidence of the 3 witnesses for the defendants on this to be credible despite PW1’s denial of it in court. Rather, I thought it was PW1 that had not been forthright on the events that transpired at that meeting. He never mentioned the meeting in evidence-in-chief, which I found rather odd considering, as PW1 himself admitted in court, that would have been the first time representatives of the plaintiff and the 1st defendant had met. I observed too that PW1, under cross-examination, suddenly switched to the “I can’t recall” mode of answering questions when grilled on what DW1 had said in response. I was convinced he was just being evasive and not wanting to tell the truth. The evidence of DW1, DW2 and DW3 was the more cogent because in the end we had in evidence that Lotus Quest issued the letter of undertaking of 4.8.2001 (at p.9 Bundle D). This was consistent and tied in with the evidence of DW1 that he made the request of Lotus Quest at the meeting. I therefore believed and accepted the evidence of the 3 witnesses for the defendants that PW1 had at the meeting of 1.8.2001 informed all that the supply of concrete was stopped because Lotus Quest failed to pay for earlier deliveries. By saying this, PW1 had acknowledged that it was Lotus Quest and not Sulong Engineering that was liable to pay for the deliveries before August 2001. [25] Yet another matter of significance that transpired at the meeting of 1.8.2001 was that the plaintiff during the meeting requested DW1 to sign the personal guarantee (at Bundle B pp 39-42) and to make an application for credit facilities (Bundle B pp 34-37). If indeed, there had been a supply agreement in place between the plaintiff and the 1st defendant since April 2001, it did not make sense for the plaintiff to be asking the 1st defendant to make the application subsequently in August. Looking at the payment terms of 30 days and interest of 1.5% per month stated in the application for credit facilities, it is similar to the payment terms of 30 days and interest of 1% per month applicable to the earlier deliveries of concrete as shown in term 3 of the quotation of 24.4.2001 (at Bundle D p.2). The reasonable inference was that the payment term in the quotation of 24.4.2001 was applicable to Lotus Quest, which was why the plaintiff in August 2001 wanted the 1st defendant to sign the application for credit facilities to also accept similar terms of payment. 9 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 [26] It was the plaintiff that wished the court to believe that the supply and delivery of the concrete to the project site made prior to August 2001 was at the request of the 1st defendant. It was also the plaintiff that wished the court to believe that the supply agreement of 24.4.2001 i.e. the quotation, was entered into between the plaintiff and the 1st defendant. The burden therefore was on the plaintiff, by virtue of section 103 of the Evidence Act 1950, to prove the existence of these facts. For the reasons given, I found that the plaintiff had not so proved on balance of probabilities. It was for that reason that I did not find the 1st defendant liable to pay for the deliveries of concrete made before August 2001 and the claim against it accordingly dismissed. Was the 2nd defendant liable under the guarantee of 13.8.2001 to pay the plaintiff RM 342, 306.32? [27] I have earlier described the circumstances of the making of the guarantee of 13.8.2001 (at Bundle B pp 39-42). In my opinion and this was not a matter of any dispute at the trial, it was a personal guarantee signed by DW1. In his letter of 13.8.2001 (at p.38 Bundle B), DW1 had as well described the guarantee as such when he stated in paragraph 2 of the letter thus, “serta jaminan Dato’ Haji Sulong Engineering bin Haji Mamat”. By this letter, DW1 stated that the guarantee was to take effect from July 13, 2001 and for deliveries made on or after that date. His precise words were “Jaminan ini berkuat kuasa daripada 13hb Julai 2001 dan untuk bekalan yang dihantar pada dan/atau selepas daripada tarikh ini.” Ergo, we had DW1 by his letter of 13.8.2001 agreeing to be liable to pay for all deliveries that were made on or after 13.8.2001. [28] DW1 had also by the last paragraph of the letter required the plaintiff to sign at the bottom portion of the letter if the latter agreed to the terms of the letter. The exact words used by DW1 were, “Sekiranya pihak tuan bersetuju, sila tandatangani salinan surat ini dan kembalikan kepada kami untuk simpanan.” As testified by PW1, and this was not disputed by the defendants, PW1 accepted the terms of the letter and signed and affixed the plaintiff’s chop at the bottom right on 5.9.2001. In my opinion, once PW1 had accepted the terms proposed by DW1, a contract was concluded the terms of which DW1 was to abide. [29] The terms of the personal guarantee meant that the 2nd defendant was liable to pay for concrete supplied on and/or after 13.7.2001. PW1 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 himself during cross-examination, admitted that by the wordings of this letter, the 1st and the 2nd defendants were liable to pay for concrete supplied on or after 13.7.2001 and not for those supplied before that date. [30] In trying to get out of the terms of the guarantee, the 2nd defendant raised one sole defence. It was that there was a typographical error in the date stated in the letter of 13.8.2001. The 2nd defendant said that the letter wrongly stated the commencement date of the guarantee to be 13.7.2001 when it should have been 13.8.2001. He said that the error was a typing error made by his clerk. Moreover, the 2nd defendant, after realizing the typographical error, had issued the letter of 22.1.2002 (at p.44 of Bundle B) to the plaintiff to point out the error and make corrections. [31] The 2nd defendant wanted the court to believe that there was a typographical error, as such, the burden of proof was on him. I found that he had not so proved on balance of probabilities. [32] In the first place, the evidence was clear that DW1 had carefully considered the terms of the guarantee before he signed it and that negates any suggestion of a mistake. It was the evidence of DW1 that he did not sign the personal guarantee there and then on 1.8.2001 because he wanted to get advice from his lawyers. It meant that DW1 had taken time to consider the terms of the guarantee and had received legal advice on it. It is to be noted that the parties at the meeting of 1.8.2001 did not discuss or agree on the date of commencement of the guarantee. It was therefore up to the defendants to propose the date of commencement and the plaintiff to decide whether to accept the date or not. The 2nd defendant proposed the date 13.7.2001 in the letter of 13.8.2001. Considerable thought must therefore have been given to the date proposed. [33] Secondly, there was nothing illogical about the 2nd defendant agreeing to be liable from 13.7.2001 since by end of June 2001, and this is in the evidence and not disputed, the outstanding sum was only RM179.00. [34] Thirdly, under cross-examination, DW1 admitted that before the letter of 13.8.2001 was sent, his employee Mohd Azmi had shown it to him and asked for permission to send it. He admitted that he had specifically authorized Mohd Azmi to sign the letter on his behalf. DW1 went on to admit that he saw the letter again after the plaintiff had accepted it and sent it back. He said that was how he knew that the plaintiff had agreed to and 11 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 accepted the terms of the letter on 5.9.2001. It did not make sense, in my judgment that DW1 had not spotted or realized there was a typing error. Since DW1 had carefully considered the terms of the guarantee, proposed the date of commencement, seen the letter of 13.8.2001 before it was sent and again saw it after it was accepted and returned by the plaintiff, it was highly improbable in my opinion, that there had been a typographical error. The letter of correction of 22.1.2002 (at p.44 Bundle B) in my view was an afterthought. [35] Fourthly, DW1 in his evidence asserted that the clerk in the office made the typing error in the letter of 13.8.2001. He as well spoke of Mohd Azmi having shown him the letter and asking permission to send it. In my view, truly the clerk and Mohd Azmi were material witnesses who could have provided the best evidence on whether there was a typing error and therefore could clear all doubts. Although that was the case, the defendants did not call either one of them to testify. Not only that, the defendants did not explain why they could not be available. In the circumstances, I did not hesitate to make an adverse inference, as was done in Chan Yoke Lain (administrator of the estate of Chong Yoke Fah, deceased) v Pacific Orient Insurance Co Sdn Bhd [1999] 1 MLJ 303, against the defendants pursuant to section 114(g) of the Evidence Act 1950. The inference here being that if the clerk and Mohd Azmi were called they would deny there was a typographical error. For that reason, the case for the defendants that there was a typographical error was completely debunked. [36] In any case, even if there had been a typographical error in the letter of 13.8.2001 leading to an error in the date of commencement of the guarantee stated therein, it was, in my view, a unilateral mistake on the part of the defendants. The law is clear that unilateral mistake on the part of a contracting party will not invalidate the contract made. [37] Section 23 Contracts Act 1950 is applicable and it reads thus : “A contract is not voidable merely because it was caused by one of the parties to it being under a mistake as to a matter of fact.” [38] In his book, The Law of Contract in Malaysia and Singapore: Cases and Commentary, Prof. Madya Visu Sinnadurai writes at p.269 : 12 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 “…section 23 provides that a contract is not voidable merely because it was caused by one of the parties to it being under a mistake as to a matter of fact. The use of words ‘not voidable’ is not a happy one. It is not clear whether such an agreement is valid or void. However, the better view seems to be that such an agreement is valid. … It should be pointed out that if a mistake made by one of the parties to an agreement does not invalidate the agreement, then an anomaly is created: s.10 of the Contracts Act provides that all agreements are contracts if they are made by the free consent of the parties. Section 14 then spells out the circumstances under which a contract is said to be free: without coercion, undue influence, fraud, misrepresentation or mistake. Except in the case of mistake, the effect of any such agreement which is entered into without the free consent of the parties is that such an agreement is voidable. If the mistake is made by both the parties, then the agreement is void. If, however, the mistake is made by only one of the parties, then such an agreement is valid even though there is no free consent. In such a case the party is left without any remedy.” (underlined mine) [39] In Tham Kong v Oh Hiam & Ors [1968] 1 MLJ 44 Ong Hock Thye FJ elaborates (at p. 48) : “Before passing to the question of mutual mistake, I would first say a few words on the plea of unilateral mistake. The law covering the circumstances of this case is thus set out in 26 Halsbury (3rd Ed.) p. 898, citing Tamplin v James : “When the contract is clear the mistake of one party only will not, as a general rule, prevent the formation of a contract and consequent liability in damages being incurred for non-performance, for, if a man will not take reasonable care to ascertain what he is contracting about, he must take the consequences. Even if the mistake is such as a reasonably diligent man might fall into, a party cannot successfully resist an action for damages, nor, as a rule, specific performance, by a simple statement that he has made a mistake where there has been no misrepresentation and where there is no ambiguity in the terms of the contract.” According to the evidence and the relevant findings, there can be no doubt that, howsoever the mistake arose on the part of the vendor, it did so for reasons entirely unconnected with the appellant and for which he was in no way responsible. In a recent East African case, Hasham v Zenab [1960] 2 W.L.R. 374, 381 which shows several points of resemblance to 13 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 the present appeal, Lord Tucker, delivering the judgment of the Privy Council, said : “… This is a plea of mistake common to both parties which was not the case made by the defendant. Treating it, however, as a plea of unilateral mistake it could, in the absence of fraud, only afford ground for rescission if the mistake was induced by some innocent misrepresentation made by or on behalf of the plaintiff or by some misleading conduct on his part.” In the absence of any proof of fraud or misrepresentation, neither of which was pleaded or disclosed in the evidence, the respondents, therefore must fail, had they relied on unilateral mistake.” [40] In the present case, there was no evidence that the plaintiff on its part had made a mistake as to the date the guarantee was to take effect. There also was no evidence of fraud or misrepresentation on the part of the plaintiff. In any case, the defendants had not pleaded mutual mistake, fraud or misrepresentation in their defence. PW1 testified he accepted the term proposed by the 2nd defendant that the guarantee was to commence from 13.7.2001 and as such, signed the letter on 5.9.2001. DW1 testified to the same effect. Quite clearly, if there was a typographical error, it was a unilateral mistake on the part of the defendants which was entirely unconnected with the plaintiff and for which the latter was in no way responsible. The agreement therefore was valid leaving the defendants without any remedy. [41] The defendants suggested that the plaintiff had agreed to the date of commencement of the guarantee being varied. For this, they relied on the statement by Mohd Azmi in the so-called letter of correction of 22.1.2002 that he had had spoken by phone to PW1 on 15.11.2001 and the latter had agreed that the guarantee was to commence from 13.8.2001. The defendants contended that PW1 in his reply letter of 24.1.2002 (at p. 5 of Bundle D) did not specifically dispute this telephone conversation with Mohd Azmi. [42] In my opinion, although PW1 in his reply letter might not have made specific reference to the alleged telephone conversation with Mohd Azmy, there was no denying that he stated his disagreement to the defendants’ proposal to change the date from 13.7.2001 to 13.8.2001. In any case, whatever Mohd Azmy said in his letter of correction concerning the 14 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 telephone conversation was all hearsay and he was not in court to testify on it whereas PW1 was in court to deny and rebut the allegation that it was ever made. Mohd Azmi was the maker of the correction letter and was the best person to explain the letter. As such, he was a material witness but not called by the defendants. The irresistible inference pursuant to section 114 (g) Evidence Act 1950 was that, if called, he would testify that no such telephone conversation with PW1 ever took place. That being the case, there was no evidence at all that the plaintiff had agreed to the variation of the date of commencement of the guarantee. It is well settled that there can be no unilateral variation of an agreed term of a contract (see Paul Murugesu s/o Ponnusamy (as representative of Nalamah d/o Sangapillay (deceased) v Cheok Toh Gong & Ors [1996] 1 MLJ 843 and Sumeria Enterprise Sdn Bhd v Seberai Majuharta Sdn Bhd [1995] 4 MLJ 542). [43] In my view, the terms of the agreement between the parties as stated in the letter of 13.8.2001 (at p.38 Bundle B) were all too clear. By paragraph a, the parties had contracted that the personal guarantee signed by Dato’ Haji Sulong, the 2nd defendant, was to commence from 13.7.2001. The defendants did not prove on balance that there was either a typographical error or agreement to a variation. In any case, even if there was a mistake, it was unilateral on the part of the defendants and could not render the agreement invalid. The 2nd defendant was bound by the terms of the agreement and therefore liable to pay the plaintiff for deliveries of concrete made on and/or after 13.7.2001. What was the quantum of the liability of the 2nd Defendant ? [44] It was not in dispute that the defendants have paid for deliveries made after 1.8.2001. Therefore, we were concerned only with deliveries made from the 13th to the end of July 2001 for which the 2nd defendant was liable to pay pursuant to the terms of the guarantee and letter of 13.8.2001. By paragraph 1 of the Statement of Claim, the plaintiff has set out the particulars of the claim for invoices issued in the month of July 2001. The delivery orders from 28.5.2001 until 31.7.2001 are produced at pp 2-351 of Bundle E (Agreed Bundle (Part B)). As well, every one of the invoices for the month of July 2001 as set out in paragraph 1 of the Statement of Claim are produced in Bundle E (Agreed Bundle (Part B)). The invoices, the date, the corresponding page number in Bundle E and the amount of the invoices are as follows : 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Date Invoice Number Amount (RM) 15.7.2001 15.7.2001 31.7.2001 31.7.2001 00000984 GP 00243 00001008 GP00257 Total 96022.00 36198.00 125575.00 58830.00 316625.00 Corresponding page number In Bundle E Page 228 Page 233 Page 352 Page 355 It can be seen from the above that for the whole month of July 2001, there were deliveries to the value of RM 316, 625.00. [45] At the trial, the defendants did not dispute that the plaintiff had made deliveries of concrete to the project site prior to August 2001 or that the corresponding invoices were issued. In fact, it was never the case for the defendants that the plaintiff had not delivered concrete before August 2001 or that the plaintiff had not issued the corresponding invoices. That is why we had learned counsel for the defendants, after the conclusion of trial, stating in his submission that “Encik Mutalif for the Plaintiff agrees that the Plaintiff’s claim is in reality for invoices issued prior to August 2001.” A little further down learned counsel submits thus: “It is not disputed that the concrete delivered by the Plaintiff were to be used in a project in Bandar Uda Utama, Mukim Pulai, Johor … where the 1st Defendant was the main contractor and a company known as Lotus Quest Sdn Bhd … was the total sub-contractor engaged by the 1st Defendant.” These statements from learned counsel for the defendants are admissions that the plaintiff made deliveries of concrete and invoices were issued for those made prior to August 2001. [46] As well, the defendants at the trial had never disputed the contents of the invoices issued for the delivery of concrete in the month of July 2001. I say so because PW1 was never cross-examined on the truth of the content of these invoices (tabled above). In addition, the defendants had never put it to PW1 that the contents of these invoices were inaccurate or false. This was not surprising because the case for the defendants had never been that the concrete was not delivered or that the amount and pricing was wrong. What was in dispute was the liability of the defendants to pay for the deliveries made. 16 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 [47] There being no dispute, I found it proved on balance that for the month of July 2001, the plaintiff had made deliveries of concrete to the amount of RM 316, 625.00. Conclusion [48] As stated earlier and for the reasons given, the 2nd defendant was liable only for the deliveries made from the 13th to the end of July 2001. However, as pointed out by learned counsel for the plaintiff, the invoices issued on 15 July 2001 included deliveries made before 13.7.2001 i.e. from 2.7.2001 to 12.7.2001. The relevant delivery orders are at pages 138, 151, 165, 181 and 196 of Bundle E and amounted to RM 65, 734.00. This sum being the price of concrete delivered before 13.7.2001 had to be deducted from the total amount of RM 316, 625.00. This leaves us with the balance of RM 250, 891.00. That is the reason I entered judgment for the plaintiff against the 2nd defendant for the price of the goods sold and delivered between 13.7.2001 and 31.7.2001 in the sum of RM 250, 891 with interest at 12% per annum from the date of the last delivery to date of payment. The parties had agreed for costs of the action and counterclaim for the plaintiff at RM 8,000.00. SUPANG LIAN Judicial Commissioner High Court Malaya Johor Bahru Dated : 16 October 2010 Counsels Mr. Ng Chew Hor of Messrs Ng Fan & Associates for the plaintiff Mr. Yasin Aminuddin Anwar and Mr. K S Lee of Messrs Y. A. Anwar & Co. for the 1st and 2nd defendants 17