Material Requirement Planning Training Manual

advertisement
SPCL Confidential
Material Requirement Planning Training Document
Material Requirement Planning
Training Manual
Author: Ask SAP Expert
Version: 1.0
Prepared by: Ask SAP Experts
1
SPCL Confidential
Material Requirement Planning Training Document
Note:
This Training material has been prepared taking reference from SAP Best Practice
documentation from SAP. Some business process has been updated, modified according to SPCL
specific Requirement
Icons
Icon
Meaning
Caution
Example
Note
Recommendation
Syntax
External Process
Business Process Alternative/Decision Choice
Prepared by: Ask SAP Experts
2
SPCL Confidential
Material Requirement Planning Training Document
Contents
1
Purpose ......................................................................................................................................... 4
2
Prerequisites.................................................................................................................................. 4
3
Total Planning Run on line ............................................................................................................ 4
4
Single Item Multi Level Planning ................................................................................................... 7
5
Stock Requirement List ............................................................................................................... 10
6
MRP List Evaluation .................................................................................................................... 13
7
MRP List Evaluation .................................................................................................................... 16
8
Stock over View ........................................................................................................................... 18
Prepared by: Ask SAP Experts
3
SPCL Confidential
Material Requirement Planning Training Document
1 Purpose
The purpose of the MRP training document is to provide guide how to create totaling and single
multilevel planning and generate MRP Evaluation list as well as stock requirement list.
2 Prerequisites
The business roles have been assigned to the user who is testing these scenarios.
3 Total Planning Run on line
Functionality
Material Requirement Planning will ensure the right availability right material at right time. Once the
production plan or requirements are maintained in SAP MRP run will take place. Normally MRP run
will be done at a periodic interval say once in a week as a background Job. The same planning run
can be run at On Line also.
Demand based MRP– This MRP uses the actual requirements placed either on Demand
Management as Planned Independent Requirements or Schedules or Sales Order requirement and
create procurement proposals.
Scenario
Total On line planning is to be done for a given plan. This document explains the process of running
MRP as ONLINE processing for a plant.
Prerequisites:PP Master Data
Menu Path
Logistics → Materials Management → Material Requirements
Planning (MRP) → MRP → Planning → Total Planning → MD01 –
Online
Transaction Code
MD01
Prepared by: Ask SAP Experts
4
SPCL Confidential
Material Requirement Planning Training Document
Press Twice on MD01 – Online
Prepared by: Ask SAP Experts
5
SPCL Confidential
Material Requirement Planning Training Document
Update the following data:
Field Name
Values
Scope of Planning
BLANK
Plant
Enter value in Plant.
Processing key
Enter value in Processing key.
Create Purchase
Requisitions
Enter value in Create Purchase
Requisitions.
Schedule Lines
Enter value in Schedule Lines
Example: 3
Create MRP List
Enter value in Create MRP List
Example: 1
Planning Mode
Enter value in Planning Mode
Example: 1
Scheduling
Enter value in Scheduling
Example: 1
Select Display material list
.
This defines if an MRP list is displayed at the end of the MRP run.
Press Enter
Press Enter
twice.
.
Press Back F3
until SAP menu screen appears.
Prepared by: Ask SAP Experts
6
SPCL Confidential
Material Requirement Planning Training Document
4 Single Item Multi Level Planning
Functionality
Material Requirement Planning will ensure the right availability right material at right time. Once the
production plan or requirements are maintained in SAP MRP run will take place. Normally MRP run
will be done at a periodic interval say once in a week as a background Job. The same planning run
can be run at On Line also. If any changes are made the plan in between the MRP schedule, It is
required to run MRP to that particular material to adjust the complete planning data to its dependent
requirements.
To run MRP for a single item, by exploring its BOM is done through single item multi level MRP
process.
Demand based MRP– This MRP uses the actual requirements placed either on Demand
Management as Planned Independent Requirements or Schedules or Sales Order requirement and
create procurement proposals.
Scenario
This document explains the process of running MRP as Single item Multi level for a given item code.
Prerequisites
PP Master Data
Menu Path
Logistics → Production → MRP → MD02 - Single-Item, Multi-Level
Transaction Code
MD02
1.
Press Twice on MD02 – Single-Item, Multi-Level.
Prepared by: Ask SAP Experts
7
SPCL Confidential
2.
3.
Material Requirement Planning Training Document
Update the following data:
Field Name
Values
Material
Enter value in Material.
Plant
Enter value in Plant.
Processing key
Enter value in Processing key.
Planning mode
Enter value in Processing key.
Scheduling
Enter value in Scheduling.
Press Enter
.
Prepared by: Ask SAP Experts
8
SPCL Confidential
4.
Press Back F3
Material Requirement Planning Training Document
.
Prepared by: Ask SAP Experts
9
SPCL Confidential
Material Requirement Planning Training Document
5 Stock Requirement List
Functionality
Stock Requirement transaction will show the present status of any given material with its entire
requirements, issues along with the MRP exception messages if any. Through the stock requirement
list transaction, navigations like converting planned order or process order/production order, to
purchase requisition etc. are possible. AT any given instant through the stock requirement list,
projected stock and or present stock at any given period can be seen.
Scenario
MRP run is completed. It is required to analyze the situation through the stock requirements list. This
document will explain how to read stock requirement list for MRP run.
Prerequisites
MRP run with independent requirement
Menu Path
Logistics → Materials Management → Material Requirements
Planning (MRP) → MRP → Evaluations → MD04 - Stock/Reqmts List
Transaction Code
MD04
Prepared by: Ask SAP Experts
10
SPCL Confidential
Material Requirement Planning Training Document
5.
Press Twice MD04 - Stock/Reqmts List
6.
Update the following data:
7.
Field Name
Values
Material
Enter value in material.
Plant
Enter value in Plant.
Press Enter
.
Prepared by: Ask SAP Experts
11
SPCL Confidential
Material Requirement Planning Training Document
Note: The stock requirements screen gives you an overall picture of the status of a material with
regards to requirements and supplies. The independent requirement created by the transfer from
Schedules lines of SD scheduling agreement. MRP will plan will cover the sales requirement.
Note that when the SD order is dispatched, the sales requirement is removed leaving only the
modified independent requirement.
MRP Element – This shows you what type of request has been made on an item, this could be a SD
schedules line, production order, reservation, purchase order, purchase requisition, planned order
etc.
Required Quantity – This shows if the MRP element is putting material into stock or taking it out. If
the element is taking it out then the quantity will be a negative quantity if the element is putting
material in then it will be a positive quantity.
Available Quantity – This figure takes the physical stock and calculates the projected stock based on
the MRP element quantities in and out of stock.
The header information on the screen shows what information has been set up in the material
master. In this example you can see that MRP type “PD” has been used and all the necessary data
associated with. You can open up the Header information by Pressing on Expand header details
or close it by Pressing on Collapse header details
8.
Press Back F3
9.
Press Back
.
.
.
Prepared by: Ask SAP Experts
12
SPCL Confidential
Material Requirement Planning Training Document
6 MRP List Evaluation
Functionality
When the MRP run is completed, Procurement proposals are created for the required items.
Exception messages will be generated according to the material situation and procurement status.
These list are saved and can be viewed through MRP list at any time after MRP run. This
information will be retained till next MRP run.
MD04 – Stock requirement is the list where it will display the current status of the material. For E.g. if
any planned order is changed / deleted or any new sales order is created, it will be displayed in the
MD04 list as the current status. Where as it will not be displayed in the MD05 MRP list.
Basically MRP list will display all the details which are generated at the time of MRP run.
Scenario
This document will explain how to evaluate the MRP result using MD05 transaction.
Prerequisites
MRP Run completed.
Menu Path
Logistics → Materials Management → Material Requirements
Planning (MRP) → MRP → Evaluations → MD05 - MRP List –
Material
Transaction Code
MD05
Prepared by: Ask SAP Experts
13
SPCL Confidential
10.
Material Requirement Planning Training Document
Press Twice on MD05 - MRP List – Material
MRP List: Initial Screen
11.
12.
Update the following data:
Field Name
Values
Material
Enter value in Material.
Plant
Enter value in Plant.
Press Enter
.
Prepared by: Ask SAP Experts
14
SPCL Confidential
Material Requirement Planning Training Document
Note: This screen looks similar to the MD04 stock requirements screen but it is only a kind of
report at the time of MRP run. If changes need to be made, MD04 will have to be used to see the
changes.
13. Press Processing indicator on F9
.
Set the processing indicator to mark the material as processed. When using the collective display
you have the option to narrow down your list based upon processed or unprocessed materials.
14. Press Back F3
.
MRP List: Initial Screen
15. Press Back F3
.
Prepared by: Ask SAP Experts
15
SPCL Confidential
Material Requirement Planning Training Document
7 MRP List Evaluation
Functionality
When the MRP run is completed, Procurement proposals are created for the required items.
Exception messages will be generated according to the material situation and procurement status.
These list are saved and can be viewed through MRP list at any time after MRP run. This
information will be retained till next MRP run.
MD04 – Stock requirement is the list where it will display the current status of the material. For E.g. if
any planned order is changed / deleted or any new sales order is created, it will be displayed in the
MD04 list as the current status. Where as it will not be displayed in the MD05 MRP list.
Basically MRP list will display all the details which are generated at the time of MRP run.
Scenario
This document will explain how to evaluate the MRP result using MD05 transaction.
Prerequisites
MRP Run completed.
Menu Path
Logistics → Materials Management → Material Requirements
Planning (MRP) → MRP → Evaluations → MD05 - MRP List –
Material
Transaction Code
MD05
Prepared by: Ask SAP Experts
16
SPCL Confidential
16.
Material Requirement Planning Training Document
Press Twice on MD05 - MRP List – Material
MRP List: Initial Screen
17.
18.
Update the following data:
Field Name
Values
Material
Enter value in Material.
Plant
Enter value in Plant.
Press Enter
.
Prepared by: Ask SAP Experts
17
SPCL Confidential
Material Requirement Planning Training Document
Note: This screen looks similar to the MD04 stock requirements screen but it is only a kind of
report at the time of MRP run. If changes need to be made, MD04 will have to be used to see the
changes.
19. Press Processing indicator on F9
.
Set the processing indicator to mark the material as processed. When using the collective display
you have the option to narrow down your list based upon processed or unprocessed materials.
20. Press Back F3
.
MRP List: Initial Screen
21. Press Back F3
.
8 Stock over View
Functionality
Inventory of any item at any given instant can be seen. Inventory at company code level, Plant level,
stores level and Batch level will be displayed.
Example, there are three plants attached to one company code. A material having same code
number in all three plants and the stock of 1000 units of that material is available in all three plants.
At the above situation, stock will be displayed as below,
At company code level 3000 Units,
At plant 1 level 1000 units and its storage location
At plant 2 level 1000 units and its storage location
AT plant 3 level 1000 units and its storage location
Prepared by: Ask SAP Experts
18
SPCL Confidential
Material Requirement Planning Training Document
If a material is handled in batches, then batch information will also be displayed.
Scenario
How to know the stock of any material is explained in this manual.
Prerequisites
Stock of material must be available.
Menu Path
Logistics → Production→ Production Control → Information System
→ MMBE - Stock Overview
Transaction Code
MMBE
22.
Press Twice MMBE – Stock Overview
Prepared by: Ask SAP Experts
19
SPCL Confidential
23.
Material Requirement Planning Training Document
Update the following data:
Field Name
Values
Material
Specify material number.
Plant
Specify plant number(s) / range
of plant numbers for which
stock has to be displayed.
24.
Press Button
.
25.
Press on Plant name
26.
Select Environment→Material movements.
27.
Press Exit
.
28.
Press Exit
.
Prepared by: Ask SAP Experts
20
Download