Improving Preventive Maintenance Using Performance Based Data Peghi Webb, Process Analyst Bart Lewis, Logistics Specialist Aera Energy LLC Supported by: Produced by: Overview About Aera Energy LLC How to set-up SAP® for performance based PMs How performance based PMs are used at Aera Benefits from using performance based PMs Key points to take home Questions About Aera Energy LLC • Oil and gas exploration and production company with onshore operations in California Began operating on June 1, 1997 o 1200 Employees o Produce 143,000 barrels of oil per day and 40 million cubic feet of natural gas per day o • Jointly owned by affiliates of Shell and ExxonMobil • SAP® went into production in 1999 o Upgraded to ECC 6.0 in 2006 • North American Maintenance Excellence (NAME) award winner in 2002 and 2004 Where Aera Operates Coalinga San Ardo Bakersfield Headquarters Belridge Lost Hills Cymric/McKittrick Coles Levee Ecosystem Preserve Midway Sunset Ventura Huntington Beach When To Use Performance Based PMs • Equipment is run on an irregular schedule • Multiple equipment is alternated when needed as a • Slide 5 back-up Performance data is available or can be collected for the equipment SAP® Set-up for Performance Based PMs • Create measuring point o Can be attached to equipment or functional location • Create initial measurement document o If needed, set-up process for automated creation of measurement documents • Create maintenance plan Can be strategy, single cycle or multiple counter plan o If using a strategy plan, create a task list using the same strategy o • Schedule maintenance plan Slide 6 Measuring Point • Use counter checkbox o Indicates that measurements are cumulative values • Provide counter over reading o Sets value for when counter goes back to zero • Provide annual estimate o Slide 7 Used to project maintenance plan call date Measurement Document • Measurement readings can be entered as counter reading or the difference from the last reading Slide 8 Connecting SAP® to Field Data • Map SAP® measuring point to identifier for the field data This is a custom table with a custom transaction to maintain the data o Used by the program that creates measurement documents each night from field data o Slide 9 Flow of Equipment Performance Data PLC Pump Field Data System Corporate Data Warehouse SAP Measurement Documents • Measurement documents are automatically created daily o Slide 11 A reversal indicator can be set if a measurement document with a “bad” reading is created Maintenance Plan • Set the counter to the desired • measuring point Offset is used to define initial counter reading for the cycle o Slide 12 Also used to reset when maintenance is performed off schedule Maintenance Plan • Lead float is used to set the call date and the basic start date on the called order o Slide 13 The basic finish date on the order is set to the plan date for performance based maintenance plans Maintenance Plan Schedule • Cycle data shows latest counter reading and projected plan date based upon annual estimate from the measuring point o Plan date calculation (46776 – 45953) * 365 / 8400 = 36 days 01/03/2012 + 36 days = 02/08/2012 Slide 14 Utilizing SAP® Performance Based PMs • Two of the highest performing pumps west of the Mississippi High pressure water injection pumps in service since 1973 o Pump performance o o 45000 bbl/day @ 4000 psi Motor performance 4500 HP 4160 VAC Slide 15 Utilizing SAP® Performance Based PMs • Manufacturers generally recommend that preventive maintenance be performed on run hours or usage rather than on calendar days (hard time) Slide 16 UNITS OF HOURS Utilizing SAP® Performance Based PMs • Runtime is seldom spread • equally between primary and secondary equipment Time based (hard time) preventive maintenance requires monitoring and manual adjustments to be effective when equipment is actually due o Slide 17 This is people dependant Utilizing SAP® Performance Based PMs • Equipment preventive maintenance previously based on “hard time” led to waste 3 orders called while equipment was down for overhaul o Orders frequently called for idle equipment o Material requisitions fulfilled and not utilized o Slide 18 Utilizing SAP® Performance Based PMs • Equipment preventive maintenance is currently based on runtime Orders generate when equipment is due o Material requisitions fulfilled and utilized (no waste) o • 8 runtime based versus 16 calendar based orders in 2 years Slide 19 Utilizing SAP® Performance Based PMs • Removes the question “Is it really due?” • Provides more effective scheduling • Eliminates need to adjust maintenance plans to stay in • • • • compliance and possibly miss needed maintenance Eliminates unnecessary requisitions (materials) Can be used as a trigger to rotate equipment Reduces costs Reduces the possibility of human error Key Points To Take Home • Performance based maintenance plans use standard • SAP® EAM functionality Maintenance is scheduled at the right time based upon equipment usage Works best for equipment run on irregular schedules o Eliminates waste o Questions Peghi Webb Aera Energy LLC mawebb@aeraenergy.com Bart Lewis Aera Energy LLC gblewis@aeraenergy.com Supported by: Produced by: