Memo GROSSMONT HEALTHCARE DISTRICT To: GO Bond Committee Via: Program Director Thomas Fakner, Program Director From: Program Management Team Tim Meehan, Senior Program Manager Dan McDaniel, Senior Program Manager Cc: Barry M. Jantz, CEO Jeff Scott, District Counsel Tom Saiz, CFO Date: June 30, 2011 SUBJ: Board Memo #143 - Consideration of Master Program Budget Revisions July 5, 2011 RECOMMENDATION of the PROGRAM MANAGEMENT TEAM: Adopt the revisions incorporated in the July 5, 2011Master Program Budget Update. ASSIGNMENT: Not Applicable PURPOSE/JUSTIFICATION OF RECOMMENDED ACTIONS: Reason for Change: The Early Utilities Package and Interim Dietary Loading Dock projects (Make Ready – Early Utilities & North Dock) were recently bid to pre-qualified bidders. The low bid amount exceeded the previously approved construction cost estimate for these projects. The Early Utilities Package project also included work to install a new IS Data Backbone (estimated at $800,000) which will be funded by Sharp Healthcare during the construction phase. Funds for the IS Data Backbone are budgeted by Sharp Healthcare as part of their Capital Program Budgets. Description of Change: Revise the Master Program Budgets to transfer funds from the Additional Contingency line item to the Early Utilities Package and Interim Dietary Loading Dock projects Construction Cost line item and to revise the H&V Center Budget to reflect the most recent construction cost estimate. FISCAL IMPACT/FUNDING: Approval of this budget will have a net positive impact of $1,111,961 on the previously approved Master Program Budget Total. FACTS AND PROVISIONS/LEGAL REQUIREMENTS: The stated goal of the Prop G Program is “To improve life-saving emergency care in East County, reduce emergency room overcrowding and improve medical facility access following earthquakes, wildfires or other #143 Memo to Board -Master Program Budget Revisions July 5, 2011.doc disasters, issue $247,000,000 of bonds to complete Grossmont Hospital’s Emergency and Critical Care Center, expand cardiac care, acquire, construct, repair and improve medical facilities, add patient beds, modernize medical technology, and improve seismic safety, with independent citizens’ oversight and with all funds used locally to improve medical facilities in East County.” IMPLEMENTATION OF MASTER PLAN GOALS: Not Applicable. ENVIRONMENTAL DOCUMENTATION: Not Applicable. IMPACT ON CURRENT SERVICES (OR PROJECTS): This action does not impact other Prop G projects. IMPACT ON SCHEDULE: The overall Master Program Schedule completion date is not extended due to this change. Approving this change will allow the Early Utilities Package and Interim Dietary Loading Dock projects to begin as scheduled. CONTRACTING PROCESS: Not Applicable. Page 2 Grossmont Healthcare District Prop G All Projects Variance Report 7/5/2011 Opinion of Probable Cost Project EDU/CCU East Tower Central Energy Plant Make Ready- Early Utilities & North Dock Make Ready- South Dock/Level B Seismic H&V Center Level 1 Buildout (Base Option only) Subtotal HOTC Bond Issuance Costs Subtotal Add'l Contingency Total Approved Budget 2/14/11 $41,093,543 $44,448,508 $50,478,045 $7,820,620 $6,518,673 $60,895,300 $27,503,996 $238,758,685 $7,500,000 $3,811,093 $250,069,778 $2,150,000 $252,219,778 Re-Baseline Budget $40,823,543 $44,448,508 $50,478,045 $10,445,318 $6,518,673 $59,578,642 $27,503,996 $239,796,724 $7,500,000 $3,811,093 $251,107,817 $0 $251,107,817 Remaining Variance from Prop G Funds Conceptual Budget ($247,000,000) Notes: 1) includes allowance for headwall units as fixed equipment 2) includes $2M in above ceiling unidentified scope 3) includes APSI estimate 1-10-2009, Cumming Estimate (1-31-2011) & Moving Budget ($500,000) 4) based on 90% CD Construction Estimate dated 4-21-2011 5) based on most current Stantec/Cumming estimate dated 12-7-2010 6) includes allowance for HOK fees (negotiated) 7) based on bid results 8) includes 20% construction cost contingency on all projects 9) includes contract closeout adjustment 10) Contingency moved to Make ready - Early Utilities & North Dock Construction Cost Master Budget Update 110705.xls 6/28/2011 Variance Notes 9 $270,000 ($0) 1,2,5 ($0) ($2,624,698) 7 ($0) 3 $1,316,658 4 $0 6 ($1,038,039) 8 $0 $0 ($1,038,039) $2,150,000 10 $1,111,961 ($4,107,817) Grossmont Healthcare District 2-4-5 Build Out Opinion of Probable Cost 12/21/2007 Complete Current 2-4-5 Metrics Metrics d.) Renovation Sq. Ft. e.) Renovation Cost per Sq. Ft. f.) New Construction Sq. Ft. Finished g.) New Construction Cost per Sq. Ft. Finished h.) Shelled Space Sq. Ft. i.) Shelled Space Cost/Sq.Ft. j.) Total Construction Cost/Sq.Ft. k.) Total Project Cost/Sq. Ft. l.) Total Project Sq. Ft. $0.00 68,386 $399.94 $0.00 $484.31 $600.91 68,386 OPC Factor Construction a. New Construction Finished $/Sq.Ft. b. New Construction Shelled $/Sq.Ft. c. Renovation $/Sq.Ft. d. Commissioning e. Contract Close Out Adjustment f. Hazerdous Material Abatement Total Direct Construction and Site Cost Escalation & Design Contingency included Above Construction Contingency $273.33 $3.72 $ 0.00% 20.00% Construction Cost $ $0 $27,350,000 $0 $0 $250,000 -$270,000 $0 27,330,000 incl $5,520,000 32,850,000 Equipment a. Medical Equipment -Heraeus Arms b Furniture, b. Furniture Fixtures and EquipmentEquipment Sharp Expenditures c. Graphic Signage d. Telecommunications/Information Systems New e. Telecommunications/Information Systems Devices/Instruments/Cabling f. Nursecall System g. Security/Paging/PA/Specialty h. Food Service Subtotal for Equipment Budget Equipment Contingency $/sq.ft. $/sq.ft. $/sq.ft. $/bed $/sq.ft. $1,143,000 $0 $125,000 $273,544 $188,062 $0 $350,000 $0 $2,079,605 $103,980 $1.83 $4.00 $2.75 $0.00 $5.12 5.00% Equipment Cost $ 2,183,585 Design and Consultant Fees a. Preconstruction Services Fees b. Architect and Engineers (includes: MEP, Structural, Civil, ID, & LS) c. Equipment Planning /Other Consultant Fees. d. Food Service e. Security Consultant Subtotal for Design and Consultant Fees Design and Consultant Contingency $0 $1,831,605 $0 $0 $25,000 $1,856,605 $92,830 6.64% LS 5.00% Design and Consultants Cost $ 1,949,435 Administrative Costs a. Permit Fees b. Permit Fees Local c. Site Survey, Testing, Boring, and Reports d. Testing Services e. Inspector of Record f. Legal Fees/ Insurance g. Move-in - Start-up Costs h. Project Management Internal i. Other Administrative Costs (Recoverable Costs) Subtotal for Administrative Costs Administrative Contingency 1.65% $546,480 $0 $50,000 $275,000 $250,000 $50,000 $0 $1,656,000 $937,738 $3,765,218 $75,305 Allowance Allowance Allowance Allowance 5.00% 2.00% Administrative Cost Total Construction, Equipment, Consultant and Administratve Costs $ 3,840,523 $ 40,823,543 $0 Total Project Contingencies Included Above Financing Costs $0 $0 0.00% TOTAL PROJECT Opinion of Probable Cost $ Page 1 40,823,543 Master Budget Update 110705.xls Grossmont Healthcare District Make Ready- Early Utilities & North Dock Opinion of Probable Cost 7/5/2011 Bid Results Total Utility Master Plan Metrics Metrics a.) Renovation Sq. Ft. b.) Renovation Cost per Sq. Ft. c.) New Construction Sq. Ft. Finished d.) New Construction Cost per Sq. Ft. Finished e.) Shelled Space Sq. Ft. f.) Shelled Space Cost/Sq.Ft. g.) Total Construction Cost/Sq.Ft. h.) Total Project Cost/Sq. Ft. i.) Total Project Sq. Ft. Factor OPC Construction a. New Construction $/Sq.Ft. a. New Construction Shelled $/Sq.Ft. c. Renovation $/Sq.Ft. d. Commissioning e. Elevators f. Hazerdous Material Abatement Total Direct Construction and Site Cost g. GC Fee h. General Conditions i. Bonding j. Insurance k. Sales Tax Total Indirect Construction Costs * * * * 0.00% 0.00% 0.75% 0.00% 0.00% 0.00% $ $ $ $ $ $ $ $7,508,775 $0 $0 $0 $0 $0 7,508,775 - $7,508,775 Subtotal for Construction Contract Escalation & Design Contingency included Above Construction Contingency 0.00% 20.00% incl $1,501,755 Construction Cost $9,010,530 a. Medical Equipment -Fixed b. Furniture, Fixtures and Equipment- Sharp Expenditures c. Graphic Signage including all exterior and interior / Artwork & Plants d. Telecommunications/Information Systems New e. Telecommunications/Information Systems Devices/Instruments/Cabling f. Nursecall System g. Security/Paging/PA/Specialty h. Allowance for Installation of Equipment Subtotal for Equipment Budget Equipment Contingency* $0 $0 $0 $0 $0 $0 $0 $0 $0 Equipment $/sq.ft. $/sq.ft. $/sq.ft. $/sq.ft. $ Equipment Cost $0 Design and Consultant Fees a. Preconstruction Services b. Architect and Engineers (includes: MEP, Structural, Civil, ID, & LS) c. Equipment Planning & Other Consultant Fees. d. Food Service e. Security Consultant Subtotal for Design and Consultant Fees Design and Consultant Contingency $0 $369,714 $80,000 $0 $0 $449,714 $22,485 4.10% 0.89% 5.00% Design and Consultants Cost $472,199 Administrative Costs a. Permit Fees b. Permit Fees Local d. Site Survey, Testing, Boring, and Reports e. Testing Services f Inspector of Record f. f. Legal Fees / Insurance g. Move-in - Start-up Costs h. Project Management Internal I. Other Administrative Costs (Recoverable Costs) Subtotal for Administrative Costs Administrative Contingency 1.65% $148,674 $0 $30,000 $50,000 $158 840 $158,840 $10,000 $50,000 $469,237 $0 $916,751 $45,838 Allowance Allowance Allowance Allowance Allowance 5.21% 5.00% Administrative Cost $962,588 Total Construction, Equipment, Consultant and Administratve Costs Total Project Contingencies Included Above $ $1,570,078 $0 15.03% TOTAL PROJECT Opinion of Probable Cost $ Page 1 10,445,318 10,445,318 Master Budget Update 110705.xls Grossmont Healthcare District Heart and Vascular Center Building Opinion of Probable Cost 7/5/2011 @90% CD Phase D&T Inc 1, 2 &3 Metrics Metrics 3,324 $1,339.04 50,703 $507.93 20,319 $166.06 $568.41 $801.37 74,346 OPC a.) Renovation Sq. Ft. b.) Renovation Cost per Sq. Ft. c.) New Construction Sq. Ft. Finished d.) New Construction Cost per Sq. Ft. Finished e.) Shelled Space Sq. Ft. f.) Shelled Space Cost/Sq.Ft. g.) Total Construction Cost/Sq.Ft. h.) Total Project Cost/Sq. Ft. i.) Total Project Sq. Ft. Factor Construction a. New Construction Finished $/Sq.Ft. a. New Construction Shelled $/Sq.Ft. c. Renovation $/Sq.Ft. d. Commissioning e. Pneumatic Tube Upgrades f. Hazerdous Material Abatement Total Direct Construction and Site Cost Escalation & Design Contingency included Above Construction Contingency $507.93 $166.06 $1,339.04 $10.06 $ 0.00% 20.00% Construction Cost $25,753,622 $3,374,280 $4,450,969 $547,921 $800,000 $288,800 35,215,592 incl $7,043,118 $42,258,710 Equipment a. Medical Equipment -Fixed b. Furniture, Fixtures and Equipment- Sharp Expenditures c. Graphic Signage including all exterior and interior / Artwork & Plants d. Telecommunications/Information Systems New e. Telecommunications/Information Systems Devices/Instruments/Cabling f. Nursecall System g. Security/Paging/PA/Specialty h. Allowance for Installation of Equipment Subtotal for Equipment Budget Equipment Contingency* 3.05% $/sq.ft. $/sq.ft. $/sq.ft. $1.65 $4.53 $3.65 $/sq.ft. $5.79 $ 5.00% Equipment Cost $53,915 $0 $122,859 $229,456 $184,841 $0 $293,704 $25,000 909,775 $45,489 $955,264 Design and Consultant Fees a. Preconstruction Services b. Architect and Engineers (includes: MEP, Structural, Civil, ID, & LS) c. Equipment Planning & Other Consultant Fees. d. Food Service e. Security Consultant Subtotal for Design and Consultant Fees Design and Consultant Contingency 0.00% 22.46% 1.18% $0 $9,489,559 $500,000 $0 $0 $9,989,559 $499,478 5.00% Design and Consultants Cost $10,489,037 Administrative Costs a. Permit Fees b. Permit Fees Local d. Site Survey, Testing, Boring, and Reports e. Testing Services f. Inspector of Record f. Legal Fees / Insurance g. Move-in - Start-up Costs h. Project Management Internal I. I Other Administrative Costs (Recoverable Costs) Subtotal for Administrative Costs Administrative Contingency 1.65% $697,269 $0 $250,000 $400,000 $405,840 $150,000 $0 $3,692,729 $0 $5,595,838 $279,792 Allowance Allowance Allowance Allowance Allowance 6.20% 5.00% Administrative Cost $5,875,629 Total Construction, Equipment, Consultant and Administratve Costs $ 59,578,641 * Equipment Contingency includes $1,500,000 outlined in Board Memo #92 Total Project Contingencies Included Above Additional Contingency- None $7,867,877 $0 13.21% TOTAL PROJECT Opinion of Probable Cost Page 1 $ 59,578,642 Master Budget Update 110705.xls