Matt Mereness, ERCOT Compliance Director
August 2015
Anfield Summit
– ERCOT Background
– Business Case for Internal Controls
– Building a Controls Program
– Assessing Controls
– Preparing for Recent Audit
– 2015 Audit Experience
– Broader GRC Implementation and Benefits
2
2
3
ERCOT connections to other grids are limited to direct current (DC) ties (~1100 MW with
SPP and Mexico)
• Electric Reliability Council of
Texas – the ERCOT grid:
– Covers 75% of Texas land
– Serves 85% of Texas load
– More than 40,500 miles of transmission lines
– 550+ generation units (more than 84,000 MW of capacity)
– Physical assets are owned by transmission providers and generators, including
Municipal Utilities and
Cooperatives
– Peak Load was set on August
3, 2011 at 68,305 MW (today)
4
– Electrical island with several DC Ties
– Deregulated Market in 2000, Nodal 2010
– Non-Profit System Operator funded by state
– Dispatches real-time energy market every 5 minutes
– Executes energy markets and settlement
– Facilitates retail switching
5
5
Registered as BA, PC, RC, RP, TOP, TSP
• 2008 Compliance Violation Investigation 693
• 2008 Annual 693 Audit
• 2009 Annual 693 Audit
• 2009 CIP Spot Check
• 2010 Annual 693 Audit
• 2010 Annual CIP Audit
• 2011 FERC, NERC and Texas RE Investigation (Cold Weather)
• 2011 Three 693 Spot Checks (Laredo 2008, Valley 2011, 693 Clean-up)
• 2012 693 Spot Check (Cold Weather)
• 2012 Annual 693 Audit
• 2013 Annual CIP Audit
• 2015 Audit underway (note not 693 or CIP)
6
7
Internal Reasons for Change –
Scope and Lessons Learned
– Historically ERCOT managed a relatively large number of controls using manual processes to maintain alignment with changing NERC requirements.
– For audits, managing people and evidence was challenging across departments
• Multiple department silos of responsibility/processes in meeting a requirement
• Organizing and reviewing evidence/RSAW responses is tedious and manually intensive
(emails, sharepoint, meetings)
– Lack of centralization can create gaps and overlaps in data collection
– Often the quality of the audit is only as organized as the person responsible for assessing the requirements.
– Audits historically are an all-hands-on-deck exercise
– ERCOT committed to improving this manual and repeatable process
8
External Reasons for Change
-Transitioning NERC Audit Approach
• Reliability Assurance Initiative (RAI)
– A national effort between the NERC, the Regional Entities, and registered entities to implement changes that enhance the effectiveness of the Compliance Monitoring and Enforcement Program (CMEP). o It is an effort to retool and refocus compliance and enforcement o RAI processes will focus on risk to grid reliability in developing scope of audit o RAI is a customized compliance approach with individualized scoping for each registered entity o To NERC not all requirements are created equally when it comes to audit scope & monitoring. o Risk factor for NERC Requirement (Risk factor in standard) o National risk focus (published CMEP plan) o Regional risk focus (appendix of CMEP plan) o Historical findings (consider ERCOT RFIs, audit scope, self-reports)
9
Uncertainty of
Internal Controls Evaluation
(ICE) process
10
11
12
1.
Define categories of internal controls
• Preventative, Detective, Corrective
2.
Define & document internal controls with SMEs
• Procedures, Logs, Alarms
3.
Define & document process flows and responsible parties
• Tabletop walk-throughs for complicated processes (across silos)
4.
Map the controls to requirements
• Many requirements - relate - to - many controls
5.
Develop test sequences
• Agree to process to observe control and see evidence of compliance
6.
Optional- Automation and tracking for collection of evidence
• Implement system with built in business process flows and collection
13
14
• Internal Controls in AlertEnterprise system q Centralized record of NERC requirements in effect at a point in time q Inventory of controls for requirements q Mapping of requirements to controls q Programmable business process flows for running assessments and evidence
15
2Q2014 3Q2014 4Q2014
Initial NERC 693 & Protocols for System Operations and Planning Effort
1Q2015
6 week mapping effort for each business unit
NERC CIP
Requirements
Maintain update standards/protocols
Quality check
Close gaps
Complete NERC self-certification
Maintain with changes to requirements
Develop CIP v5
16
Compliance system- Requirement screenshot
17
Compliance Requirement mapped to multiple Internal Controls
18
19
• ERCOT performs periodic “assessments” to verify controls are effective.
– Assessments are performed based on risk
• ERCOT evaluates changes to requirements to ensure processes and controls are consistent with the changes.
• ERCOT’s goal is to assess all NERC–related controls at least once per year.
20
Business Analyst(s)
Reviews assessment questions and gathers evidence.
Compliance
Initiates changes and execution of assessments.
Business
Owner/Manager
Reviews and approves assessment and evidence.
Effective with
Date
Compliance
Final review, update in system as completed and effective.
21
Example- Control Assessment
The screenshots below provide assessment details including the start date and the overall status and example of test questions to help determine if control is effective.
Control/procedure is verified, evidence attached, and “passed ” 22
Example of Assessment of Control to Multiple Requirements
By testing this RUC procedure, you can assess/pass 3 requirements
23
24
Reqt
Risk
Factor
NERC
CMEP
Audit
History
Critical -
163
High - 117
Med - 257
Low - 389
Self-
Report
25
ERCOT
Compliance Risks
Subset of NERC
Requirements
Subset of
ERCOT Controls
Controls inventory to prioritize and assess
26
27
28
29
ERCOT 2015 Audit Scope
1200 Requirements à IRA 26 requirements à ICE 20 requirements
Auditors will be onsite Sep 21-25
30
January 2015- RE advised ERCOT of being scheduled for Sept audit engagement.
May 2015 RE advised ERCOT that IRA was complete and invited to engage in ICE.
• No interaction between ERCOT and RE during IRA evaluation
• Audit scope was unknown at this point, but told it would be “focused”
• ERCOT accepts voluntary ICE invitation
May 2015 ERCOT received ICE notice.
• ICE scope for 26 requirements supporting 2 risk themes (represented the current scope of the forthcoming audit)
• 2 week deadline to respond with controls (provided powerpoint overview of controls program, applicable procedures/controls for each requirement, and listing of dates controls last assessed)
June 2015 ERCOT received formal audit notice for 20 requirements
• Output (benefit) of ICE was that 6 of 26 requirements were removed from scope of audit.
• 40 days deadline to complete and file RSAWs and evidence for 20 requirements
• RSAWs filed and waiting for questions leading into the Sept tabletop and onsite audit activities.
31
Controls for ICE
• ERCOT submitted the inventory of key controls mapped to requirements.
Assessments for ICE
• In its submission package ERCOT included a summary of the assessment history for the related controls.
Overview of Internal Controls at ERCOT
• GRC System, terminology, goals
32
In summary Alert captured;
Narrative for how Reqt is met
Point-in-Time History of Requirement & Assessments
Links Requirement to Controls (Procedures, Software screens, etc)
Links to Owner(s)
Links to Evidence
33
34
Leveraging the tool to work for company
• Electronic/Query-able System of record
– Traceability for requirements, ownership in a database that can be queried
• Change control
– Provides quick summary of related/impacted changes- ripple effect
– 3 areas of change: Requirements, Staff, Controls/Procedures
• Auto-scheduling
– Calendar tripwires - Systemic reminders of Annual filings, certification, or authority sign-off
• Business owner configures frequency
– How often to be assessed for certain controls (accountability)
35
• Management reports
– Aging reports (when was this requirement last changed or assessed)
– Status of annual assessment progress
• Risk levels
– Flag a requirement as high risk can map to and identify critical controls
– Helped ERCOT prepare for 2015 audit (assess 20% instead of 100% controls)
• NERC CIP v5 readiness path
– Assessment completion creates CIPv5 RSAW and evidence finish line
36
ICMP Support/SSAE16
Management of corp controls and changes to policies
NERC 693 Support
Processes/Dependencies/
INCREASING
ERCOT Compliance
CFR/ Changes
NERC CIP Support
Processes/software/
Alert Scope of Requirements
800 SSAE/ICMP education (Cyber, Sec, IT)
1,200 NERC
3,000 Protocols
Protocol Must/Shall/Will
Support
Numerous new departments to interface with
Audit Preparation
SSAE, NERC, Protocol
Range of methods
Note- One effective access procedure/control may satisfy multiple reqts/frameworks 37
Different Compliance Monitoring methods-
• SSAE60/ CorpControls Attestation “ survey-only approach ”
• Alert-routed surveys with questions to execs where they confirm they are compliant
• Solicits changes and confirmation of compliance
• Quick execution/attestation
• Protocols Mapping/Traceability “ controls mapping approach ”
• Traceability/ownership/change management
• Connect words on rules to owner, narrative how they satisfy part of all, provide link to control
• NERC mapping and verification “ controls mapping with evidence approach ”
• Full traceability with testing, collecting evidence, and reviewing quality of results.
38
Matt.Mereness@ercot.com
39