International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 The Nigerian Power System Till Date: A Review. Folorunso Oladipo1, Olowu Temitayo O2 Department Of Electrical/Electronic Afe Babalola University, Ado-Ekiti1, Obafemi Awolowo Univeristy, Ile-Ife2, Nigeria ABSTRACT The fundamental ingredient for the growth of any country is how effective their power sector is. Power system holds the key to the development of the world. Consequently, this paper looks into how power system of Nigeria has contributed to the development of the nation. It takes a critical survey of the past and present condition of the sector. The paper also looks into what were the challenges of the sector, and possible solutions. Index Terms : National Electric Power Authority (NEPA), Niger Dams Authority (NDA), Power Holding Companies of Nigeria (PHCN), Independent Power Producers (IPPs), Transmission Company of Nigeria (TCN), Power Station (P.S). I. INTRODUCTION The present population of Nigeria is over 170 million, at a growth rate of 6% per annum. Nigeria is of no doubt the biggest country in Africa continent with a total 356, 667 sq miles (923, 768 sq km), of which 351, 649 sq miles (910, 771 sq km or 98.6% of total area) is land. The nation is made of six Geo-Political Zones subdivided into 36 states and the Federal Capital Territory (FCT). For a country of such bogus population to thrive, its power sector must be strong. The major aim of this paper is to x-ray the beginning and the present state of the Nigerian Power Sector (NPS). Therefore a history of the sector is very vital and it cannot be over emphasized. Electricity produce in Nigeria has it date back to 1896 when two (2) small generating sets were installed to serve the then Colony of Lagos. The total capacity of the generator used then was 60kW. The maximum demand was even lesser than the 60kW generated. It was fifteen years after England has been experience power supply this occurrence happened in Nigeria [1]. In 1946, the Nigerian government electricity undertaking was established under the jurisdiction of Public Works Department (PWD) to take over the responsibility of electricity supply in Lagos State [3]. By an Act of Parliament in 1951, the Electricity Corporation of Nigeria (ECN) was established, and in 1962, the Niger Dams Authority (NDA) was also established for the development of Hydro Electric Power. However, a merger of the two (2) was made in 1972 to form the National Electric power Authority (NEPA). Since ECN was mainly responsible for distribution and sales and NDA was created to build and run generating stations and transmission lines, the primary reasons for the merging the organizations were [2]-[1]. For over twenty years prior to 1999, the power sector did not witness substantial investment in infrastructural development. During that period, new plants were not constructed and the existing ones were not properly maintained, bringing the power sector to a deplorable state. In 2001, generation went down from the installed capacity of about 5,600MW to an average of about 1,750MW, as compared to a load demand of 6,000MW. Also, only nineteen out of the seventy-nine installed generating units were in operation [5]. 20 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 The National Electric Power Authority was a vertical-integrated utility responsible for the power sector in Nigeria. And between 1970s and 1980s, NEPA developed new generating capacity in both hydro and thermal power. NEPA was solely responsible for the generation, transmission and distribution of electricity until year 2005 the unbundling and the power reform took place under the administration of President Olusegun Obasanjo whereby the organization name was changed to Power Holding Company of Nigerian (PHCN). In March 2005, when President Olusegun Obasanjo signed the Power Sector Reform Bill into law, private companies were given opportunities to participate in electricity generation, transmission and distribution. The deregulation of PHCN was to consists eleven distribution companies (DISCOS), six generating companies (GENCOS), and one transmission company (TRANSCOS) [4]. TRANSCO was to be under the control of the Federal Government. It is to be noted that the establishment of PHCN was to cater for the lack of inefficiency of NEPA, and to improve power system in Nigeria. On August 8, 2005, the peak generation was 3774 MW out of the available generation of 4000MW. This improvement was said to be as a result of the participation of the private investors and rehabilitation of generating plants. By 2010, however, five years into the latest reform, very little restructuring had been undertaken, and available generation capacity was less than 4,000 MW (a figure largely unchanged since the 2005 reforms), for a population of over 150 million, the largest on the African continent [6]. Due to emergency power situation of the country, and the opportunity for private investors to participate in the sector, the genealogy of Independent Power Producers (IPPs) started from these scenarios. The first Nigeria’s IPP was established in 1999 by the Lagos State Government, the Federal Ministry of Power & Steel and NEPA. As of 2012, three large-scale IPPs produce approximately 25 percent of Nigeria’s electric power, with the balance provided by the Power Holding Company of Nigeria (PHCN) and State governments, viz. about 1,000 MW (IPPs) and 3,000 MW (non-IPP), respectively.8 9 The introduction of IPPs has been gradual (dating to 1999), but according to the ‘Road Map’, the private power component will more than double in less than five years, including via the country’s sale of its generating assets [7b]. Given the significant imminent change, a clear understanding of past experience with IPPs is paramount. It was initially stated that the PHCN is unbundled into eighteen successor companies. Strategically, the objectives of the reform include (i) the transfer of management and financing of successor companies operations to the organized private sector; (ii) the establishment of an independent and effective regulatory commission to oversee and monitor the industry; and (iii) focusing the FGN on policy formulation and long-term development of the industry. This will lead to (i) increased access to electricity services; (ii) improved efficiency, affordability, reliability and quality of services; and (iii) greater investment into the sector to stimulate economic growth. However, the unbundling leaves the Federal Government with three hydro and seven thermal generating stations with a total installed capacity of about 6,852MW, with available capacity of 3,542MW (as of 31st July 2010). Each entity had been incorporated as a single-asset generating company; a radial transmission grid (330kv and 132kv), owned and managed by the Transmission Company of Nigeria (TCN), with the responsibility of undertaking the system operation and market settlement functions, respectively as well as eleven distribution companies (33kv and below) that undertake the wires, sales, billing, collection and customer care functions within their area of geographical monopoly. 21 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 A competitive tender was thereafter carried out to receive bids from core investor groups (inclusive of competent generation asset owner/operators) for a minimum of 51% of equity in the following successor thermal generating companies including • Afam Power Plc; • Sapele Power Plc; • Ughelli Power Plc; • Geregu Power Plc As well as a separate concessioning process for successor hydro generating companies including • Shiroro Hydro Power Plc; • Kainji Hydro Power (note: that Jebba power station is part of Kainji Hydro Power Plc). A similar competitive tender was carried out to receive bids from core investor groups (inclusive of competent distribution asset owner/operators). They are • Abuja Electricity Distribution Plc; • Benin Electricity Distribution Plc; • Eko Electricity Distribution Plc; • Enugu Electricity Distribution Plc; • Ibadan Electricity Distribution Plc; • Ikeja Electricity Distribution Plc; • Jos Electricity Distribution Plc; • Kaduna Electricity Distribution Plc; • Kano Electricity Distribution Plc; • Port Harcourt Electricity Distribution Plc and • Yola Electricity Distribution Plc. As at September 2014, • Available Generation Capacity is 6,662MW • Generation Capacity is 5,228MW • Peak Generation is 4,420MW • Expected Generation from NIPP is 5,453MW and • On-going Hydro Projects is 4,234MW Power Industry projected to have available 10,000MW in 2015 and 20,000MW 2020 [8]. II. NIGERIA’S GENERATION COMPANIES 1) Afam Power Plc Afam Power Station has an installed capacity of 776MW, The plant was commissioned in phases. During the Initial phase, 1962-1963, gas turbine units 1- 4 were commissioned. During the second phase, 1976 to 1978, gas turbine units 5 to 12 were commissioned. Gas turbine units 13 to 18 were commissioned in 1982. Two gas turbine units were added in 2001 during the final phase of the Afam Power Station extension. 2) Shiroro Hydro Power Plc (concession) Shiroro Power Plant was commissioned in 1990; it has an installed capacity of 600 MW, It currently runs at full capacity, generating 2, 100 GWh of electricity annually. As Nigeria’s newest hydroelectric plant, Shiroro hosts Nigeria’s SCADA-operated national control centre. Shiroro is also equipped with switch yard facilities that include a technical “step down” function for enhanced distribution into the national 22 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 grid, an advanced control room and modern training facilities. The plant is situated in the Shiroro Gorge on the Kaduna River, approximately 60 km from Minna, capital of Niger State, in close proximity to .Abuja, Nigeria’s federal capital 3) Ughelli Power Plc Ughelli Power Plc operates a gas-fired thermal plant located in the Niger Delta region. Ughelli Power is one of the largest thermal generating power stations in Nigeria. The plant has a peak capacity of 972 MW; it can generate 2500 GWh of electricity annually. The plant meets current world specifications for plants of its type, and includes an updated control room, a switchgear room, a staff training school and recreational facilities. Ughelli began operations in 1966. 4) Kainji/Jebba Hydro Electric Pic (Concession) Kainji/Jebba Power operates as two hydro generation plants, each drawing water from the River Niger. The combined installed capacity of the two plants is 1330 MW, with Kainji generating 760 MW and Jebba 570 MW Effectively, the plants operate at full capacity. Kainji began operation as Nigeria’s first hydro power plant in 1968 while the Jebba plant was commissioned in 1985. Jebba is the smallest ofthe three operating hydro Power plants in Nigeria. In addition to generation facilities, the hydro plants have on-site Medical facilities a staff school, a recreation centre, and a training school. The two plants are in very good condition. 5) Sapele Power Plant Sapele Power Plant is a Thermal generating station located in Nigeria’s gas- rich Delta State. Sapele has an installed capacity of 1020 MW Sapele Power’s six 120 MW steam turbines generate a daily average of 86.72 MWI.j/H or approximately 2,500GW/H annually Sapele. Power currently operates at a peak capacity of 972 MW Sapele Power is strategically located in the Niger Delta region, close to sources of both natural gas feedstock and a river for cooling its steam turbine generators Sapele Power Includes an updated control room, a switchgear room, a Staff training school, and medical recreational facilities. Sapele Power began operations in 1978. 6) Calabar Thermal Power Station Calabar Power Station has an installed capacity of 6.6 MW derived from three units of 2.2 MW each. Currently, it supplje 4.4 MW to the national grid and Primarily serves as a booster station to the Afam and Oji River power stations The Calabar Power Station was built in 1934. 7) Oji River Power Station Oji River Thermal Power Station was originally built to take advantage of plentiful nearby deposits of high-gra5 coal. Oji generates io MW of power from five coal-fired boilers and four steam turbines originally installed in 1955. The plant is the only coal-fired steam Power Station in Nigeria. Water from the nearly Oji River is used to feed the steam turbines and also for cooling purposes 8) Ijora Thermal Power Station 23 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 Ijora Power Plant was commissioned in 1956 with coal-fired boilers which are no longer operational The plant has a 1 32/33i transmission station that is in good condition, but its 33/11KV transformers need replacement Although the plant is currently nonoperational, current demand for power the availability of natural gas, and the governmen.5 programmed for gas utilization give Ijora Power a competitive advantage. The location of the plant makes it ideal for an Independent Power Plant project. Table 1: List of all Generating Stations in Nigeria as at 2014 (Source: http://www.nercng.org/index.php/industry-operators/licensing-procedures/licencees?start=20 ) Name AES Nigeria Barge Limited Afam Power Plc African Oxygen & Industrial Gases Limited Agbara Shoreline Power Limited Akute Power Limited Alaoji Generation Co. Ltd (NIPP) Anita Energy Limited Azura Power West AFrica Limited Benin Generation Company Limited Calabar Generation Company Limited Century Power Generation Limited CET Power Projects (Ewekoro) CET Power Projects Ltd. CET Power Projects Ltd. CET Power Projects(Sagamu) ContourGlobal Solutions (Nig) Ltd ContourGlobal Solutions (Nig) Ltd ContourGlobal Solutions (Nig) Ltd Coronation Power and Gas Limited Delta Electric Power Limited DIL Power Limited DIL Power Plc Egbema Generation Company Limited Egbin Power Plc Eleme Petrochemical Company Limited License Type Generation on-grid Generation On-grid Afam, Rivers State Capacity 270 MW 987.2MW Generation Off-grid Ikorodu, Lagos State 19MW Generation on-grid Generation Off-Grid Generation on-grid Generation on-grid Agbara, Ogun Lagos Water Corporation Alaoji,Abia State Agbara, Lagos State 100MW 13MW 1074MW 90MW Generation on-grid Ihovbor Benin,Edo State 450MW Generation On-grid Ihonvbor, Edo State 450MW Generation On-grid Calabar, Cross Rivers State 561MW Generation On-grid Okija, Anambra State 495MW Generation off-grid Generation off-grid 6MW 20MW Generation off-grid Wapco Ewekoro,Ogun State Tinapa, Cross River State Nigerian Breweries Limited, Iganmu, Lagos WAPCO Sagamu,Ogun State Generation Off-Grid NBC Bottling Plant,Ikeja 10MW Generation Off-Grid NBC Bottling plant,Apapa 4MW NBC Bottling Plant,Benin 7MW Generation off-grid Sango Otta 20MW Generation on-grid Generation Off-grid Generation on-grid Oghareki,Etiope West LGA Cement factory, Ogun State Obajana, Kogi State 116MW 114MW 135MW Generation On-grid Egbema Imo State 338MW Generation On-grid Egbin, Lagos State 1320MW Generation On-grid Eleme Complex,P.H Rivers 135MW Generation off-grid 24 | © 2014, IJAFRSE All Rights Reserved Site Location 5MW 7MW www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 Energy Company of Nigeria (NEGRIS) Energy Company of Nigeria Limited Enersys Nigeria Limited Ethiope Energy Limited Ewekoro Power Ltd Farm Electric Supply Ltd First Independent Power Co. Ltd First Independent Power Co. Ltd First Independent Power Co. Ltd Fortune Electric Power Co. Ltd Gbarain Generation Company Limited Geometric Power Ltd Geregu Generation Company Limited Geregu Power Plc (BPE) Hudson Power Limited Ibafo Power Station Limited Ibom Power Ltd ICS Power Ltd Ikorodu Industrial Power Ltd Ikorodu Industrial Power Ltd Ilupeju Power Limited Income Electrix Limited Island Power LImited Isolo Power Generation Limited JBS Wind Power Limited Kaduna Power Supply Company Limited Kainji Hydro Electric Plc (Jebba Station) Kainji Hydro Electric Plc (Kainji Station) Knox J&L Energy Solutions Limited Lotus & Bresson Nigeria Limited Mabon Ltd MBH Power Limited Minaj Holdings Ltd Generation on-grid Ikorodu, Lagos State 140MW Generation off-grid Nestle,Agbara,Ogun State 3MW Generation On-grid Generation on-grid Generation off-grid Generation on-grid Generation on-grid Generation on-grid Generation on-grid Generation On-grid Ado-Ekiti, Ekiti State Ogorode, Sapele, Delta State Ewekoro, Ogun State Ota, Ogun State Omoku, Rivers State Trans-Amadi, Rivers State Eleme, Rivers State Odukpani, Cross River State 10MW 2800MW 12.5MW 150MW 150MW 136MW 95MW 500MW Generation On-grid Gbarain, Bayelsa State 225MW Generation on-grid Aba, Abia State 140MW Generation On-grid Geregu II, Kogi State 434MW Generation On-grid Generation on-grid Generation on-grid Generation on-grid Generation on-grid Distribution for Ewekoro Cement Embedded Generation Generation off-grid Generation off-grid Embedded generation Generation On-grid Geregu, Kogi State Warawa, Ogun State Ibafo, Ogun State Ikot Abasi, Akwa Ibom State. Alaoji, Abia State 414MW 150MW 200MW 190MW 624MW Generation On-grid Embedded Generation Ikorodu, Lagos State Ikorodu, Lagos State 39MW Academy Press,Ilupeju NPA,PH,Rivers State 2MW 6MW Marina,Lagos State 10MW Isolo Lagos State Maranban Pushit, Mangu, Plateau State 20MW Kudenda Ind.Area,Kaduna 100MW 84MW Generation On-grid Jebba, Niger State 570MW Generation On-grid kainji, Niger State 760MW Generation on-grid Generation on-grid Generation Generation on-grid Ajaokuta,Kogi State Magboro, Ogun State Dadinkowa, Gombe State Ikorodu,Lagos State Agu-Amorji Nike, Enugu East LGA, Enugu State 1000MW 60MW 39MW 300MW Generation on-grid 25 | © 2014, IJAFRSE All Rights Reserved 115MW www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 Nigerian Agip Oil Co. Ltd Nigerian Electricity Supply Corporation (Nigeria) Limited (NESCO) Notore Power Ltd Ogorode Generation Co. Ltd (NIPP) Olorunshogo Generation Co. Ltd (NIPP) Olorunsogo Power Plc (BPE) Omoku Generation Company Limited Omotosho Generation Company Limited Omotosho Power Plc (BPE) Paras Energy & Natural Resources Development Limited Generation on-grid Okpai, Delta State 480MW Generation on-grid Generation on-grid Bukuru, Plateau State Onne, Rivers State 30MW 50MW Generation on-grid Ogorode, Delta State 450MW Generation on-grid Generation On-grid Oluronshogo,Ogun State Olorunsogo, Ogun State 750MW 335MW Generation On-grid Omoku, Rivers State 250MW Generation On-grid Generation On-grid Omotosho II, Ondo State Omotosho, Ogun State 500MW 335MW Generation On-Grid 96MW PZ Power Company Limited Sapele Power Plc Shell Petroleum Dev. Co. Ltd Shiroro Hydro Electricity Plc Shoreline Power Company Limited Supertek Electric Limited Supertek Nig. Ltd Tower Power Abeokuta Limited Generation Off-grid Generation On-grid Generation on-grid Generation on-grid Ogijo,Ogun State PZ Cussons Aba Factory, Abia State Sapele, Delta State Afam VI, Shiroro, Niger State Tower Power Utility Limited Ughelli Power Plc Unipower Agbara Limited Wedotebary Nigeria Limited Westcom Technologies & Energy Services Ltd. Zuma Energy Nigeria Ltd (Gas Plant) Zuma Energy Nigeria Ltd(Coal Plant) Generation Off-grid Genration On-grid Generation on-grid Generation off-grid 4MW 1020MW 642MW 600MW 9MW 500MW 1,000MW 20MW Generation off-grid Generation On-grid Generation off-grid Generation off-grid Lafarge Wapco,Sagamu,Ogun Ajaokuta, Kogi State Akwete, Abia State Abeokuta,Ogun State Ota Industrial Estate, Ota, Ogun State Ughelli, Delta State Unilever, Agbara,Ogun St. Kuru, Jos Generation on-grid Sagamu, Ogun State 1000MW Generation on-grid Ohaji Egbema,Owerri,Imo 400MW Generation on-grid Itobe,Kogi State 1200MW 20MW 942MW 6MW 5MW III. THE CHALLENGES OF NIGERIAN POWER SECTOR Electric utility industry is the largest utility and complex industry in the whole world. Consequently, it is prone to different challenges. These challenges differ from country to country based on how technological inform and how effective their government is. Nigerian Power Sector hitherto is still battling with various challenges which sometimes seem unexplainable. These challenges range from technical to government inability to handle to industry well. 26 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 According to a study carried out by Onohaebi O.S, [10], in the year 2009, some causes and effects of power outages in the Nigerian Transmission Network were itemized. This is presented in table 2. These outages occurred in transmission network for 2004 and 2005. The problems were grouped into transmission lines constraints, shunt reactor problems, overloading of transformers and vandalization of the lines. Table 2: Summary of transmission network faults, causes and effects [10]. LINE FAULTS EFFECTS ON THE NETWORK Ikorodu-Ayede-Oshogbo Frequent Circuit was Frequent and prolonged 132kV conductor/jumper constructed in 1964 outages on the circuit. cut along entire and is aging length Akangb-Ojo 132kV Frequent earth fault Reduction of overhead Frequent forced outages on clearance refused the circuits. burning due to proliferation of houses and stations. Industrial pollution of lines and insulators due to heavy refuse dumps and heavy industrial built up reported since 1983 Gombe-Maiduguri 132kV Large voltage drops Line is single circuit Gombe 132kV bus has to circuit of 20-40kV between and is too long run as high as 140-145 kV enable acceptable Gombe and (310km) conductor to Maiduguri size is also small voltage levels at Maiduguri Gombe 132kV has to be 150mm2 run split. New-Haven-OturkpoAbout 20kV voltage Single line New Haven 132kV bus Yander drop between New configuration using voltage had to run high Haven and Yander 150mm2 and line is voltage 330km long Benin-Onitsha-Alaoji Constant tripping of Limited by single line Frequent shutdown of 330kV Benin-Onitsha-Alaoji contingency voltage Afam Power station due to line control problems transmission line faults thus stressing the Afam P.S. units. Restoration of Electricity supply prolonged due to voltage control problems. About 11 states capitals and environs experienced prolonged blackouts. 27 | © 2014, IJAFRSE All Rights Reserved CAUSES www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 Aba-Itu 132kV line Delta-Benin 132kV DC Delta/Sapele/Aladja Frequency of tripping Breakdown of only 1 of line circuit breaker on the line with no provision for by-pass facilities and is limited by single line contingency Several spans of Poor Maintenance and collapsed towers aging Poor configuration leading to poor maintenance and operation of Aladja Steel switch gear by PHCN Reactors: Onitsha 9 Rs- Reactor out of circuit 30 MX Oshogbo 4R1-75 MX Birnin-Kebbi MX Reactor out of Service 19R1-30 Reactor out of Service Prolonged blackout of Itu, Eket and Calabar complex serving the majority of cross River and Akwa Ibom State. No output for Delta O.S generation through the inter-bus transformer to Benin Transmission Station on 132kV The arrangement is Fault tracing/clearing is defective since power very precise and energy flows from metering is difficult Sapele/Delta Steel Power Station through Aladja Delta Steel Company Low resistance causes High voltages experienced the reactor to be out of at Onitsha and New Haven Circuit substations respectively. When Afam Power Station generation is separated, it took long time to synchronize the station to the grid because of high voltage difference, resulting in many areas thrown into darkness Faulty winding Excessive high voltage at Oshogbo Burnt underground High voltages at Birnin cable Kebbi above limits Sambo, A.S, 2005, [11] also presented a paper which noted the causes of inefficient and unreliable energy supply system in Nigeria. In electric energy supply efficiencies of existing thermal plants are low. They are as low as 12% whereas efficiencies of up to 40% are attainable with modern technologies. Also substantial electricity is lost during transmission and distribution. These losses are sometimes more than 30% of the total electricity generated. Apart from these inefficiencies the reliability and availability of existing installed electric generation system is low. There is the serious problem of power unreliability over the years such that most industrial establishments and upper income households install very expensive generating sets amounting to over half of the total installed grid capacity. This constitutes huge economic losses to the Nigerian economy. According to [11], the major factors contributing to the above unreliability and inefficiency in the power sector are: (a) Frequent breakdown of generating plants and equipment due to inadequate repairs and maintenance; www.ijafrse.org` 28 | © 2014, IJAFRSE All Rights Reserved International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 (b) Lack of foreign exchange to purchase needed spare parts on time (c) Obsolete transmission and distribution equipment which frequently breakdown (d) Lack of skilled manpower; as well as (e) Inadequacy of basic industries to service the power sector. According to [12], the challenges include the following: • • • • • • • • Radial Lines with no redundancies Obsolete Substation Equipment Overloaded transmission lines and Substations Inadequate Coverage of Infrastructure Limited Funds for Development projects High Technical and Non-Technical loss Limited training opportunities Community issues during project execution Idigbe and Igbinovia, 2010, [13], posited the following as the challenges facing power sector in Nigeria. • • • • • • The long period of reliance on hydro-stations, as primary sources of generating electric power. The industry had ample time to supplement power generation through alternative sources – thermal, coal, wind, etc., but wasted all the years through failed policies on dams. Poor policies on natural gas - its effective development. Natural gas has always been looked at, as a nuisance from crude oil production until lately, when the Federal Government suddenly realizes that it can be used for power generation. The so-called gas master plan is not an effective policy for the proper development of our vast resources of natural gas. Poor pricing of electricity, Obsolete facilities: Many of the gas plants are not working, and are old. Pipelines are constantly under threats of being compromised. When they are working, maintenance of the facilities are not carried out as and when due. Funding, and Social factors Discussion of results of Onohaebi and Lawal, 2010, [14] concluded on the poor state of maintenance of the power stations could be attributed to the Nigerians’ attitude towards maintenance, poor funding, unskilled manpower, lack of adequate training, over-aged and obsolete equipments. These Infact would contribute to the poor state of Nigerian Power Sector. Figure 1: Nigeria Annual Fund released to the Power Sector 1974 – 2003[14]. 29 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 Figure 2: Age range of generation plants. IV. CASES OF SYSTEM COLLAPSE System collapse’ is the term used to describe the situation when all the power generating stations connected to the grid shut down at the same time or immediately one after the other, leaving the entire area supplied by the grid (the whole country, in the case of the Nigerian grid) in blackout. Generating plants may shut down as a result of human deliberate control action as part of normal operational scheduling, or automatically as a result of self-protective action. An interview conducted by This Day Live and reported by Foluseke A. Somolu on the 25th August, 2013 gave clear explanation on the causes of system collapse in the country. This report is given as it were below: Self-protective shutdown of generators may be initiated by protective relays installed on the generating plant reacting to any one or combination of potentially harmful operational development within the power station or individual generator. It may, on the other hand be as a result of happenings on the grid, external to the generating plant, but which have the potential to impose operational duties on the generator beyond its capability. One of such is when the system operating frequency falls outside the allowable deviation from the nominal level stipulated for the generating plant. The system nominal frequency applicable to all generating plant and electrical appliances in Nigeria and many other countries is 50Hz (50 cycles per second). (The exceptions are in the Americas, north and south, where it is 60Hz). Thermal stations (i.e. those burning some form of fuel, especially the steam stations), due to their many pumps and motors controlling critical functions, are more sensitive to low frequency than hydro stations. But all of them, whether hydro or thermal, will eventually shut down when the frequency falls low enough, and then a system collapse results. We may ask what causes the system frequency to fall. A load demand imposed on the grid greater than the combined capacity of all the connected generating stations will cause the system frequency to fall. With our low generating capacity (4000MW) in comparison to our country’s actual demand, it is obvious we will always be operating in the vicinity of low system frequency. When the increase in load demand is due to consumers, the rate of fall in the system frequency is gradual and the speed governors of each generator can take some corrective action automatically by boosting the fuel input to the generator to increase its speed, and hence the frequency, provided the generator had not been fully loaded up to that point. This is similar to when, upon approaching a hill, the driver of a truck changes gear and presses down harder on the accelerator pedal of the truck. Good system operating practice requires that one or more generators in the grid are deliberately only partially loaded so there is ample and readily available spare capacity, called “spinning reserve”, to absorb unplanned sudden load demand placed on the grid 30 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 such as when a huge industrial consumer comes on line, or a generating plant is shut down by its own self-protective action thereby placing a heavy load demand on the remaining generating stations. When these automatic actions, i.e. the combination of the speed governors and the spinning reserve, fail to arrest the frequency drop, the system operators at the National Control Centre who are monitoring the state of the power system and noticing the dropping system frequency, can intervene ‘manually’ and instruct one or more power stations to start and bring up additional generating plant. They can in addition instruct a substation to disconnect some consumers to reduce the system load demand. Nowadays the system operators are not able to establish communication with stations quickly enough to arrest the impending collapse. This is because the SCADA (i.e. Supervisory Control and Data Acquisition) that enables the system operator monitor happenings at all grid stations, as well as the special “no fail” communications facilities built for instant linkup between the control centre and all stations when the grid was being developed in 1960s -1980s and which were still functioning up to the mid 1990s, are all now virtually broken down or not even there anymore. The voice communications have been largely replaced with GSM phones but their ‘network problems’ and ‘subscriber not available’ messages, and other interruptions obviously make the use of GSM completely unsuitable for this function. Another scenario in which the system frequency falls is when the system overload is caused by a fault (i.e. a short-circuit) on any one of the many transmission lines that make up the grid. Since many thousands of kilometers of our transmission lines pass through heavy forests, the possibility of vegetation fouling the lines and causing faults is ever present, except the line trace is cleared of all vegetation up to 15metres on either side of the line for the whole length of the line, which is easier said than done, especially because of the heavy costs and logistics involved. These line faults represent very heavy load demands that require every generating plant on the grid to contribute multiples of its capacity, which of course, is impossible. Here we have a “double jeopardy” situation. Apart from the overload placed on each generator, which is harmful on its own, the system frequency also drops very sharply and beyond allowable thresholds. The system protective relays should normally remove the faulted line from service promptly before the generators’ self-protection relays react. But they can only do so, if they act in a coordinated manner, i.e. if they are properly calibrated and their settings coordinated with each other, and also provided the communications links between them are functioning. Again it is doubtful if this is still so nowadays. Protection engineers, specialists in their own right, whose function it is to calibrate and ensure proper coordination of these relays are an endangered species in the power industry nowadays. Also, as has been mentioned earlier, most teleprotection communication channels in the power system are no more functioning as they used to. Line faults are therefore usually removed too slowly. The ‘last ditch’ provision to save the system from collapse in this situation then is the underfrequency emergency load-shedding arrangement. But it is not always very effective because the consumers on the feeders it removes from service may not have their total load anywhere close to the demand imposed on the system by the fault, and a system collapse still occurs. Now why blackouts due to system do collapses last so long? The major problem encountered during restoration following a system collapse is the time required to restart the generating plants. The thermal stations pose the biggest challenge. They cannot remain spinning when they have no load connected to them and usually shut down when system collapses occur. And when they shut down, they eject their steam they have built up and depend upon to operate. This is in order to avoid dangerous steam pressure buildup. It takes about six to ten hours to raise new steam and start operation again. And when they are restarted, they have to be loaded in small increments, allowing them to stabilize at each load level before 31 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org` International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 taking on additional consumers. Sometimes the anxiety to load the generators quickly and shorten the system blackout may lead to taking on too much load at a time and cause a generator to shut down again and return the operators to the beginning all over again. All this while, the national control centre (NCC) is abuzz with activities, talking to and passing instructions to all the power stations and grid-connected substations across the country, coordinating the restoration efforts. Even as simply as one has tried to describe it, the foregoing should have shown that maintaining the integrity of the grid consists of a series of many and painstaking activities, many of them highly specialized. It also requires the continuous availability of many facilities for the operators of the grid, as has been mentioned earlier, over and above simply building of power stations and substations in various parts of the country, and transmission lines to link them to each other. These facilities include but are not limited to the Supervisory Control and Data Acquisition (SCADA) and no-fail voice communications that must work even in the face of national power blackout. And having made this point, one should also add that while it may not be possible to totally avoid system collapses, their frequency can definitely be drastically reduced. In fact in 1992 the country recorded zero system collapses. In the few years preceding that year (1992), through the determined efforts of the staff and the cooperation of Management (through the provision of funds), the coordination of the protective schemes in the grid was highly improved, most of the inconsistencies in the relay settings having been ‘debugged’; the SCADA having just been commissioned and put to use in the country’s power system for the first time, and the power system communications facilities being maintained in correct working order. Staffs at that time were also very well trained to have been able to do the operation and maintenance work required at the highest standards. So if we really want to reduce or eliminate system collapses, government needs to look into all these[14]. Table 3: System collapses for the period of 2000-2003 [15]. Year Partial Collapse Total Collapse Total System Collapse 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 6 5 5 14 32 9 39 14 30 22 15 21 10 21 8 18 16 26 20 19 11 19 41 53 52 36 31 26 42 39 2010 2011 2012 2013 42 19 24 OVER 15 V. CONCLUSION From the review of the Nigerian Power Sector hitherto, it can be concluded that to have a way out of the problems and challenges facing the sector, the following points must be adhere to. • Replacement of old and obsolete power system equipments; • Establishment of more generating stations; • Embarking on ring transmission network; • Incorporating FACTS device for loss compensation; • Strong protection system; • Proper maintenance culture; and • Adequate funding of the sector. VI. REFERENCE [1] Niger Power Review: Development of the Electricity Industry in Nigeria (1960-1985) , 1985, pp. 1-6. www.ijafrse.org` 32 | © 2014, IJAFRSE All Rights Reserved International Journal of Advance Foundation and Research in Science & Engineering (IJAFRSE) Volume 1, Issue 5, October 2014. Impact Factor: 1.036, Science Central Value: 10.33 [2] A. S. Sambo, B. Garba, I. H. Zarma and M. M. Gaji, “ Electricity Generation and the Present Challenges in the Nigerian, Power Sector”, Energy Commission of Nigeria, Abuja-Nigeria. [3] O I Okoro, E Chikuni, “Power sector reforms in Nigeria: opportunities and challenges”, Journal of Energy in Southern Africa • Vol 18 No 3 • August 2007. [4] James k, and Okafor F.N, “Automatic Generation Control Performance of the Nigerian Power System After Deregulation. [5] A. S. Sambo, “Matching Electricity Supply with Demand in Nigeria”, Fourth Quarter 2008. [6] Mohiuddin, Arif (2011). “The Privatization Transaction Process and the Opportunities for Investments in the Nigerian Power Sector.” Electric Power Sector Reform Workshop, Abuja, May 25. [7] Presidential Task Force on Power (2011a).www.nigeriapowerreform.org/index.php/refrm institutions/overview . Accessed on September 30, 2011. —. (2011b). “Nigeria's Power Crisis: Light at the End of the Tunnel.” Abuja: Federal Government of Nigeria. [8] Engr. Oladele Amoda, “Lingering Issues In The Nigeria Power Market”, Eko Electricity Distribution Company Lagos, Nigeria Seminar On Dividends Of Privatization Of Power Sector, September, 2014. [9] http://www.nercng.org/index.php/industry-operators/licensing procedures/licencees?start=20 [10] Onohaebi O.S, “Power Outages in the Nigeria Transmission Grid”, Research Journal of Applied Sciences 4(1): 1-9, 2009. [11] Sambo A.S, “Renewable Energy For Rural Development : The Nigerian Perspective”, ISECO Science and Technology Vision, Vol 1 – May 2005 (12-22). [12] Labo H.S., “Current Status and Future of the Transmission Network”, Investors’ forum for the Privatisation of PHCN successor companies, 2010. [13] K.I. Idigbe, S.O. Igbinovia, “ASSESSING THE SUSTAINABILITY OF ELECTRIC POWER IN NIGERIA: A CASE STUDY OF THE IPPs”, Journal of Economics and Engineering, ISSN: 2078-0346, February, 2010. [14] O.S. Onohaebi And Y.O. Lawal, “Poor Maintenance Culture; The Bane To Electric Power Generation In Nigeria”, Journal Of Economics And Engineering, ISSN: 2078-0346, May, 2010. [15] http://www.thisdaylive.com/articles/why-we-ve-power-system-collapses-and-why-they-last-solong/157212/ Energy Mix Report, “Power Transmission: Over 139 system collapses recorded in five years”, Jan 14, 2014. [16] 33 | © 2014, IJAFRSE All Rights Reserved www.ijafrse.org`