Short Description - Kaiser Bolted Bracket: The Kaiser Bolted Bracket is a special moment frame for steel construction. It is a simple, but unique approach because it consists of a steel haunch casting which is installed through bolting. In the retrofit version, the part is drilled and bolted in place without any welding. In the new construction version, a heavy fillet weld is done in the shop and then the beam is fully bolted in the field. Lab reports and certifications: The Bolted Bracket has been extensively tested and the full lab reports are available on request. It has been installed in 29 buildings to date including three LAX airport terminals, hospitals in Los Angelas and projects in Washington, Oregon and Utah. The Kaiser Bolted Bracket is just completing the process of becoming pre-qualified per ANSI/AISC 358-05 for the AISC Seismic Provisions. Design Specifications: Size calculations for retrofits will require an engineer to review the existing beam / column connection. In both versions, the connection stiffness remains unchanged from a pre-Northridge connection, making the calculation process very simple. In new construction, the AISC latest seismic provisions guidelines should be followed and when properly applied, continuity and doubler plates can be eliminated. This can lead to considerable savings. When these guidelines for seismic applications using a strong column, weak beam environment are followed, the quick-chart of beam sizes can serve as a guide. There are only a few bracket casting sizes and each bracket covers a range of beams. Follow the ANSI/AISC 358-05 Prequalification guidelines and our spreadsheet for detailed size calculations. Design Fees: The Kaiser Bolted Bracket is a pre-engineered steel casting hardware approach to moment frame installation. It does require designing to a strong column / weak beam condition which is not unique to the Bracket, but a common standard requirement. For this reason there is no special engineering involved and the EOR can do the calculations. We do provide technical support as needed and check that the criteria have been satisfied for the installation. Although the bracket is patented, we charge simply for the part purchase and do not charge any engineering or license fees. Savings Advantages: Retrofits are drilled and bolted in place and require no welding. New construction installations need a heavy shop fillet weld, no doubler plates or continuity plates and require smaller beam sizes than the RBS connection. Erection involves bolting the beam in place through shear tabs and then proceeding with other operations such as deck installation concurrently with installing the bolts in the Bracket. Initial frame construction is greatly accelerated through this approach. Slotted and tapered holes make bolt fit-up simple and eliminate alignment problems. Cost Information (New Construction): Each bracket kit includes one casting and the bolts required for the size. These are normally A490 1-3/8” or 1-1/2” Bolts. The price list on the CD or printouts may change slightly as supply costs change, but these should be minor and can be confirmed as needed. A typical connection requires a bracket set for each of the top and bottom connections. Castings are FOB Seattle with the bolts FOB Saint Louis. The information on our recent cost study, along with all of the details on installation should be helpful in doing your own cost analysis for weld and installation calculations. We typically find that the installed cost runs around 30% under the RBS connection without including the additional time savings for the erection schedule. In addition, the process is so simple, that it does not require any significant design or procedural training. William Gibb bill@steelcastconnections.com (206) 250-7035 Steel Moment Connnection Cost Comparisons Location: Building Size: Floor Plate: Stories: # Connections: Typical Steel Beam Typical Steel Column Typical Beam Span Typical Flr-to-Flr Material Costs1,2: Erection Costs1,3: Field Welded Connections1,13: Weld Special Inspection14: Los Angeles, CA 280,000 18,667 15 342 W27x84 W14x233 24 15 $2,338 $908 $300 $80 ft2 ft2 ft. ft. per ton per ton per ton per ton Bolted BracketTM Reduced Beam Section, RBS Side Plate Sure FrameTM SSDA Slotted WebTM Material Costs1,2: Beam4 Column5 Side Plates6 Kaiser Brackets7 RBS Cutout8 Beam Slots9 Total Material Costs $2,357 $4,086 $0 $1,256 $0 $0 $7,699 $2,592 $4,086 $0 $0 $400 $0 $7,078 $2,121 $3,677 $1,298 $0 $0 $0 $7,096 $2,357 $4,086 $0 $0 $0 $280 $6,722 Installation Costs1,3: Beam4 Column5 Field Welds10,13 Weld Special Inspection10,14 Total Installation Costs $915 $1,587 $0 $0 $2,502 $1,007 $1,587 $857 $229 $3,679 $824 $1,428 $744 $198 $3,194 $915 $1,587 $827 $220 $3,549 Cost/Connection: Proprietary Licensing Fee11 $10,201 $0 $10,757 $0 $10,290 $168,000 $10,271 $40,000 $556 $189,975 $581 $198,418 $277 $68,145 Item Bracket Savings/Connection12 Total Savings 1 Source: RS Means, Building Construction Cost Data, 63rd Annual Ed., Reed Construction Data, 2005 2 Materials include: steel base price, extras and delivery to ship, drafting, shop fabrication & warehouse retarding, shop coat paint, trucking to job site 3 Installation includes: Unload and shake out, erect and plumb, field bolt, crane & minor erection equipment 4 RBS beam cost is 10% higher to account for stiffness loss at the weakened sections; Side Plate beam cost is 10% lower to account for side plate effect of increased beam stiffness 5 Side Plate column cost is 10% lower to account for deeper column sections 6 Side Plates weight: 1.2 psf per SidePlate.com web site 7 Kaiser Bracket costs includes (4) N2.0 brackets, shop welding 8 RBS includes (4) flange radius cuts per beam, and weld access holes; Source: Camron 9 SSDA slotted web includes (4) web cuts, and weld access holes 10 Full penetration welding and ultra-sonic testing included 11 Source: SSDA web site (www.ssda.net); Side Plate System ($.60/s.f. licencising fee) 12 Kaiser Bracket reduces erection time by up to two times than that of other connection types, allowing a compressed construction schedule and reduced interest paid on construction loans. Unfortunately, interest savings cannot be reflected on this table 13 Source: The Erection Company (10 hours per beam at $80/manhour plus $16.5/hour weld machine, wire, etc.) 14 Source: Construction Testing & Engineering, CTE (3 hrs per beam at $80/manhour plus $15/hour testing machine, etc.)