Permitting Tips
(05/12)
This bulletin is to make you aware of issues that have been identified by the City or other
retailers and suggest Tenant’s architect and engineer pursue further as it relates to
Tenant’s contract documents.
•
For additional information regarding City websites and other permitting information
contact them directly at the following web site:
town.huntington.ny.us
http://town.huntington.ny.us/
Permit Application & other forms:
http://town.huntington.ny.us/permit_forms.cfm
Building Department Information:
http://town.huntington.ny.us/department_details.cfm?ID=44
Town of Huntington/Huntington Station, New York Contact Information:
• Building & Housing Department:
100 Main Street
Huntington, New York 11743
Phone: (631) 351-2822
Fax: (631) 351-3132
•
Fire Prevention Bureau
Phone: (631) 351-3138
•
Suffolk County Health Services
17 Union Blvd, Room 106
Bayshore, NY 11706
Phone: 631-854-0410
Email: scdhsweb@suffolkcountyny.gov
http://www.suffolkcountyny.gov/departments/healthservices.aspx
Town of Huntington/Huntington Station Permit Process:
•
Tenant/Tenant Agents are required to send the Tenant permit package to the Walt
Whitman Shops Management office for permit application signature and notarization.
•
Tenant’s plans/permit package plans must have been reviewed and approved by the
Landlord and must contain the Landlord’s stamp of approval.
Walt Whitman Shops
Huntington Station, New York
•
After the permit application is signed/notarized by the Walt Whitman Shops
Management office the package must be picked up by the Tenant/Tenant’s agent
and delivered to the Building Department for permitting.
•
The Landlord/Walt Whitman Shops Management Office are NOT responsible for the
Tenants permitting. Tenant/Tenant Agents are required to contact the Walt Whitman
Shops Management Office prior to sending the permit package to coordinate the
permit application signature/notarizing.
•
Worker’s Comp Insurance must be on file with the Town for permit to be released.
•
The permitting for this jurisdiction is many faceted and detail driven. Tenants shall
contract directly with Bohler Engineering for Permit Expediting services. Bohler
Engineering is the recognized permit expeditor for the Walt Whitman Shops.
Tenant Required Permitting Expeditor:
•
Bohler Engineering
James T. Powers, AIA
Paola Bergonzi, Permitting Manager
2002 Orville Drive North, Suite 100
Ronkonkoma, NY 11779
631-738-1200 | jpowers@bohlereng.com | www.bohlerengineering.com
Fire Sprinkler Permitting:
• Simplex-Grinnell is the required sprinkler contractor. The sprinkler permitting
process shall begin simultaneously with permit application. Fire sprinkler permitting
typically runs 6-8 weeks. Life Safety is strictly enforced by the Fire Marshal.
Certificate of Occupancy:
•
The Walt Whitman Shops Management Office is responsible for maintaining all
Tenant certificates of occupancy for all Tenant spaces in Walt Whitman Shops.
•
Contact the Mall Management Office for additional information.
•
When a new Tenant takes over an existing space with no structural changes the
current CO will remain unchanged until such structural changes take place.
UNION AFFLIATED GUIDELINES
•
Union labor registered with the Nassau Suffolk Building Trades shall be used.
•
In an effort to establish acceptable and unified construction and quality and
productivity standards, the Landlord strongly recommends that all union trades,
traditionally and customarily performing construction crafts be engaged to promote
project wide continuity.
•
This shall not serve as a limitation to a Tenant’s right to employ the most qualified
low bidder for a construction contract. However, Tenant shall take all necessary
action to avoid labor disputes and difficulties on the project and shall do all things to
Walt Whitman Shops
Huntington Station, New York
avoid work stoppage or delay on account thereof, regardless of whether the impact is
to the Tenant, Landlord or other Tenants. In an event of work stoppage, Tenant will
cooperate with Landlord to remove the source of the work stoppage at Landlord’s
sole discretion so that the project shall be completed on schedule in a cost efficient
manner as initially contemplated.
•
Landlord reserves the right to halt Tenant construction should work disputes result in
picketing or other disruption to the business of the shopping center. In the event
such a shut down is necessary, work will be permitted to begin after work dispute
has been resolved.
Walt Whitman Shops
Huntington Station, New York
Download