Status

What is the TXDOT Environmental Management System Verification Audit?

Short Course 2012

3

WHAT IS THE EMS VERIFICATION?

 A systematic and documented process for objectively obtaining and evaluating evidence to determine the following:

Does implementation of the TxDOT EMS conform to the TxDOT EMS criteria?

 Are EMS results communicated to management and acted upon appropriately?

Say what you do/Do what you say

TxDOT Management System Elements

1. EMS Policy

2. Roles and Responsibilities

3. Environmental Requirements

4. Assessment, Prevention and Control

5. Training Awareness and Competence

6. Records and Documentation

EMS

WHAT IS THE TXDOT EMS VERIFICATION AUDIT ? 4

01M042012D

EMS VERIFICATION OBJECTIVES

TxDOT Management

System Elements:

1.

EMS Policy

2.

Roles and

Responsibilities

3.

Environmental

Requirements

4.

Assessment, Prevention and Control

5.

Training Awareness and

Competence

6.

Records and

Documentation

 Independently evaluate the adequacy and effectiveness of the TxDOT EMS implementation from top management down and throughout each district based on a representative sample.

 Provide a independent assessment as to whether the

TxDOT EMS has been implemented in such a manner as to facilitate understanding, by appropriate TxDOT employees and contractors, of the following:

• the environmental aspects and impacts of road construction

• the environmental controls, monitoring and measurement procedures or processes contained within the TxDOT EMS to address the aspects and impacts of road construction

• individual environmental responsibilities related to the aspects and impacts of road construction as stipulated within the TxDOT EMS

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 5

01M042012D

EMS VERIFICATION APPROACH

HQ Audit

West North South East

2 Districts

TBD

2 Districts

TBD

2 Districts

TBD

2 Districts

TBD

District Selection Criteria

Geographical Coverage

Construction Activity

Large/Small Geographical Area

Rural/Urban

Active Road

Construction Sites

Active Road

Construction Sites

Active Road

Construction Sites

Active Road

Construction Sites

01M042012D

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 6

EMS VERIFICATION APPROACH - HQ

Design Division Administration Division

Headquarters

Environmental Affairs

Division

Maintenance Division

Two (2) person Team

Three (3) Day Verification

Five Divisions

Construction Division

TxDOT EMS Elements

•Policy Statement

•Roles/Responsibilities

•Environmental Requirements

•Assessment, Prevention and Control

•Training, Awareness and Competence

•Records and Documentation

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 7

01M042012D

EMS VERIFICATION APPROACH - Districts

Project

Development/Environmental

EMS Element

Preliminary Design

EMS Element

Design

EMS Element

TxDOT EMS Elements

•Policy Statement

•Roles/Responsibilities

•Environmental Requirements

•Assessment, Prevention and

Control

•Training, Awareness and

Competence

•Maintenance of Records and

Documentation

District Engineer

DISTRICT

Construction Phase

2-3 Construction

Projects/District

Construction

Inspector

2.5 day verification

2 person teams

Contractor/Subcontractor

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 8

01M042012D

EMS VERIFICATION APPROACH

Planning

 Verification Plan Developed and Approved by USEPA

 Master Audit Schedule

 District Projects Selected Fit the EMS Road Construction Definition

 Projects Selected From October 2012 Letting

 Coordinate with Districts Regarding Visit Logistics

 Identify Personnel to be Interviewed

WHAT IS THE TXDOT EMS VERIFICATION AUDIT ?

01M042012D

9

EMS VERIFICATION APPROACH

Verification (2.5 days)

 Opening Meeting

• Introductions/Process Overview

• Safety Requirements etc.

 Records Review

 Personnel Interviews

• District Employees/Contractors

 Physical inspections

2-3 Active Road Construction Projects

Closing Meeting

AM Meeting

Review of Findings

Discussion of Corrective Actions

Q&A

01M042012D

Day 1

Day 2

Day 3

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 10

EMS VERIFICATION APPROACH

Reporting and Follow Up

 Findings Report

• Submit to HQ within seven (7) business days

• Summarize Verification Activities

• Provide Detailed Verification Findings + Corrective Actions

 Periodic Requests for Corrective Action Updates

• E-Mails from Shaw to EMS Coordinator and District Contact

• Requesting Updates Regarding Corrective Action

• Track Closure of Verification Findings

• Closure Progress Reported to HQ On Recurring Basis

WHAT IS THE TXDOT EMS VERIFICATION AUDIT?

01M042012D

11

EMS VERIFICATION PROCESS - General

Say what you do/Do what you say

 Are EMS procedures/processes adequately inclusive of road construction environmental impacts?

 Do the TxDOT EMS procedures/processes describe what’s actually happening?

• Review of job site for environmental requirements, implementation of procedures.

 Is there objective evidence that EMS procedures/processes are being followed?

• Review of District and Project EMS Records

 Is EMS documentation controlled?

• Current versions or forms, procedures etc. used?

 Are related documents and records referenced?

• SOPs

• Environmental Scoping

EPIC Sheet

Pre-Construction Conference

Construction State Gate Checklist

• Storm Water Inspection Checklist

EMS

01M042012D

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 12

EMS VERIFICATION PROCESS

TxDOT EMS Elements:

1.

EMS Policy

2.

Roles and

Responsibilities

3.

Environmental

Requirements

4.

Assessment,

Prevention and

Control

5.

Training Awareness and Competence

6.

Records and

Documentation

EXAMPLE PERSONNEL INTERVIEW QUESTIONS

 How did you become aware of the TxDOT Environmental

Policy?

 What is your understanding of the EMS Policy and how does it apply to your day-to-day work?

What are your responsibilities within the TxDOT EMS?

What environmental impacts are associated with your work?

What EMS procedures or processes do you follow when conducting your work?

How does your work vary from the procedures?

What kind of EMS or environmental training have you received?

How do you escalate environmental concerns to management?

WHAT IS THE TXDOT EMS VERIFICATION AUDIT? 13

01M042012D

EMS VERIFICATION SCHEDULE

Project Tasks

Develop Verification Plan content outline

Define corrective action and follow-up methodology

Draft Verification Plan to meet CAFO requirements

Coordinate with TxDOT for Verification Plan Development

Provide draft Verification Plan to TxDOT

Incorporate TxDOT comments into Plan

Submit final Verification Plan to EPA as directed by

TxDOT

Incorporate EPA comments into Plan (30 days of receipt)

Obtain EPA approval of final Verification Plan

Finalize site visits and interview schedules

Conduct Austin, TX Headquarters Audit

Conduct Audits – TxDOT Southern Region

Conduct Audits – TxDOT Eastern Region

Conduct Audits – TxDOT Northern Region

Conduct Audits – TxDOT Western Region

Develop Verification Report Content Outline

Coordinate with TxDOT for Report development

Provide draft Verification Report to TxDOT for review

Incorporate TxDOT comments into final Report

Submit final Verification Report to EPA

S O N D J

September 2012 – January 2014

F M A M J J A S O N D J

WHAT IS THE TXDOT EMS VERIFICATION AUDIT?

01M042012D

14

QUESTIONS?

01M042012D

15

"This project was undertaken in connection with the settlement of an enforcement action taken by the U.S. Environmental Protection

Agency for alleged violations of Clean Water

Act provisions.“ (CAFO 27)

01M042012D

16

Back-Up Slides

01M042012D

EMS

TOOLS

01M042012D

EMS Road Construction Definition with

Guidance

Road Construction Project - Road construction operation that includes any of the following associated activities: earth work, concrete work, asphalt work, steel work, masonry work, demolition work, excavation work, fill work, land clearing, painting, soil stabilization, equipment operation, de-watering activities, material storage, waste management, waste disposal, and waste recycling activities. Under this definition, construction also includes project specific locations (PSLs), such as concrete and asphalt batch plants, within the Right-of-Way. The term construction does not include routine or preventative roadway maintenance activities.

– Types of projects include new location, existing pavement rehabilitations/widening, culvert work, bridge rehabilitation/replacement.

– Typical projects not requiring the Stage Gate Checklist (SGC) to be completed would be signal installation, crack sealing, retrace striping, seal coating, bridge joint repair.

– Districts should determine whether the SGC should be completed on minimal soil disturbance Construction or Maintenance contracts such as any MBGF upgrade, landscaping, ACP overlays.

01M042012D

EMS TOOLS

01M042012D

01M042012D

Download