HIGHWAY 2 TRANSIT PRIORITY MEASURES

CLASS ENVIRONMENTAL ASSESSMENT

DESIGN AND CONSTRUCTION

NOTICE OF CONSTRUCTION

WORKS DEPARTMENT Aug. 29, 2013 NEWSLETTER 5

NOTICE OF CONSTRUCTION AND PUBLIC INFORMATION CENTRE

The Regional Municipality of Durham has completed a Class Environmental Assessment (Class EA) study for roadway modifications to support the DRT Pulse Bus Rapid Transit (BRT) service on

Highway 2 (Kingston Road). The preferred design is to construct bus only lanes and on-road buffered bicycle lanes in three “bus only lane areas” in Ajax and Pickering (see map below).

Ajax

Town

Hall

Construction of these lanes is now beginning on the Harwood Avenue to Salem Road segment in the

Town of Ajax (see detail map below). The Contractor plans to start during the week of September 3 rd.

Harwood – Salem construction limits for curbside bus only lanes with on-road buffered bicycle lanes

PUBLIC INFORMATION CENTRE

A Public Information Centre (PIC) will be held on Sept.12th from 3 p.m. to 8 p.m. at the Town of Ajax

Municipal Building, to provide interested parties an opportunity to see the design drawings and ask any questions. The PIC will be an open house format with no formal presentation.

Thursday Sept. 12th

Ajax Town Hall - River Plate Room

65 Harwood Avenue South, Ajax

Drop by anytime between 3 p.m. and 8 p.m.

The Regional Municipality of Durham

605 Rossland Rd. E., Whitby, ON L1N 6A3

Telephone 905-668-7711 or 1-800-372-1102

……continued on page 2 www.durhambrt.ca www.durham.ca www.durhamregiontransit.com

HIGHWAY 2 TRANSIT PRIORITY MEASURES NEWSLETTER 5 Page 2

PROJECT SCHEDULE AND STAGING

The total value of work to be completed with the Harwood Avenue to Salem Road contract is just under $5 million. Construction will take approximately eight months; September-December 2013 and May-August 2014.

The work is staged to reduce impact to businesses, pedestrians and vehicles. Through traffic lanes will be maintained in the peak direction during peak traffic periods. Area businesses and residents will have access to their driveways. Road users should expect additional delay for the duration of the construction. Motorists are asked to exercise caution for the safety of the workers.

The Region realizes that the construction will be disruptive to you, and we sincerely appreciate your patience and understanding.

Most construction will occur in the daytime, Monday to Friday. Some road crossing construction and road resurfacing will be completed overnight. Along with the road works, the Region is replacing a 400 mm diameter watermain from the Harwood Avenue intersection westerly to the west limit of construction at the Real

Canadian Superstore. The project staging and planned schedule is:

Stage 1

(2013 – Sept. to Dec)

Roadwork and watermain construction on the north side of Highway 2

Stage 2

(2014 – May to July)

Roadwork construction on the south side of

Highway 2

QUESTIONS OR COMMENTS

Stage 3

(2014 – May to July)

Modifications to median traffic islands along

Highway 2

Stage 4

(2014 – July to Aug.)

Resurface existing traffic lanes along Highway 2

The contract for this construction work has been awarded to Miwel Construction Limited. Construction inspection and monitoring will be provided by the Region of Durham Works Department, Construction

Management Division. The following individuals are the key contact persons for the construction (Jim

Mumford and Greg Gummer) and design (David Dunn) of the Highway 2 Transit Priority Measures

DRT Pulse :

Jim Mumford

Construction Inspector

905-261-8070

Greg Gummer

Project Supervisor

Construction Management Services

The Regional Municipality of Durham

Works Department

605 Rossland Rd. E.

Whitby, ON L1N 6A3

905-668-7711 ext. 3427 or 905-261-0107 greg.gummer@durham.ca

David Dunn, CET, E.I.T.

Project Co-ordinator,

Rapid Transit Office

The Regional Municipality of

Durham Works Department

605 Rossland Road E.

Whitby, ON L1N 6A3

905-668-7711 ext. 3422 david.dunn@durham.ca

CONSTRUCTION UPDATES

The Region will be posting regular construction update newsletters at durhambrt.ca.

If this information is required in an accessible format, please contact David Dunn at 1-800-372-1102 extension 3422.

The Durham Highway 2 Bus Rapid Transit project is funded by the Province of Ontario

The Regional Municipality of Durham

605 Rossland Rd. E., Whitby, ON L1N 6A3

Telephone 905-668-7711 or 1-800-372-1102 www.durhambrt.ca www.durham.ca www.durhamregiontransit.com

Download