KNPC NEW REFINERY PROJECT

advertisement
CLEAN FUELS PROJECT (CFP)
PREQUALIFICATION QUESTIONNAIRE
FOR
ENGINEERING, PROCUREMENT
AND CONSTRUCTION (EPC)
BIDDERS
Rev.
Date
00
01
Description
Issued for PQ
20-MAY-2012
Revised pages 70&71 (Exhibit A & Exhibit B)
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Table of Contents
Description
Page No.
1.0
Introduction
2
2.0
3.0
5
4.0
Overview
Engineering, Procurement and Construction (“CONTRACTOR”)
Responsibilities
Pre-Requisite for Prequalification
29
5.0
Instructions to Companies Registering for Qualified Bidders List
30
26
Documents Required:
CONTRACTOR Declaration
34
FACT SHEET
36
Attachment No. 1 Contractor Information
38
Attachment No. 2 Experience
42
Attachment No. 3 Establishment
43
Attachment No. 4 Financial
46
Attachment No. 5 Project Execution
48
Attachment No. 6 Quality Management
50
Attachment No. 7 Health, Safety and Environmental
51
Attachment No. 8 Construction and Procurement Strategy
52
Attachment No. 9 Litigation / Arbitration / Disputes
55
Attachment No. 10 IT Support System
56
Forms, Tables and Exhibits
Form-1 : Experience World-Wide
57
Form-1.1 : Experience World-Wide Summary
60
Form-2 : Contractor Reference Inquiry
61
Form-3 : Contractor Safety Performance
63
Table-1 : Contractor’s Interest
69
Exhibit A : Minimum PQ requirement for Bidder
70
Exhibit B : Minimum PQ requirements for JV Leader
71
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 2
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
1.0
INTRODUCTION
This prequalification procedure and attached documents are presented by Kuwait
National Petroleum Company (“KNPC” or “Owner”), for the purpose of establishing a
list (“Qualified Bidders List” or “QBL”) of qualified Engineering, Procurement and
Construction Contractors (“CONTRACTOR”) for the KNPC Clean Fuels Project
(“Project”) to be constructed in the State of Kuwait.
The objective of the Project is to safely and economically build new units,
modify/revamp existing units in two existing refinery complexes and retire one
complete refinery complex, all work
designed, procured, constructed and
commissioned in accordance with Owner requirements utilizing world class execution
standards and procedures. The project will be divided in three (3) EPC packages.
Submission of the required prequalification information by the CONTRACTOR shall in
no way bind the Owner to invite any of the CONTRACTOR submitting qualifications to
enter into any contract and shall also not bind the Owner to make any financial
commitment in connection with any individual projects within the overall Project.
The information contained in this document and attachments is strictly confidential
and all companies submitting for qualification are required NOT to divulge the
contents to any third party.
The Owner, likewise, shall treat information submitted by the CONTRACTOR as
strictly confidential and will not make it available to any third party except to its
Partners and/or Consultants where the Owner deems it appropriate and applicable.
The selection of companies to be compiled on the QBL shall be based on specific
selection criteria which is solely determined by Owner and shall be applied equally to
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 3
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
all CONTRACTORs responding to this letter. Final selection of companies to be on
the QBL will be approved by Owner and shall be solely at Owners discretion.
Bid Basis: The EPC Package(s) will be tendered on Lump Sum Turnkey basis and
will be issued by the Kuwait Central Tendering Committee (CTC). It is currently
anticipated that the tenders for the Project will be issued in the last quarter of calendar
year 2012 and an expected award in the last quarter of calendar year 2013.
.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 4
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
2.0
OVERVIEW
KNPC currently owns and operates three refineries in the State of Kuwait; Mina Al
Ahmadi (MAA), Mina Abdullah (MAB), and Shuaiba (SHU) Refineries, all located
along the coastal zone south of Kuwait City, and within approximately 10 Kilometers
distance apart overall. As part of the Clean Fuels Project, KNPC plans the retirement
of the processing facilities at Shuaiba Refinery, and a major upgrade/expansion of the
MAA and MAB refineries to integrate KNPC’s Refining System into one Refining
Complex with Full Conversion operation with highest Light Ends Products Yields and
nil Fuel Oil production. These CFP Project objectives will be to:
-
Meet year 2020 market demands and specifications for transport fuels
-
Increase processing capacity at MAA/MAB to 800,000 BPSD from
736,000 BPSD (after SHU Retirement)
-
Integrate operating capability of the MAA/MAB with optimum utilization
of the existing Infrastructure.
The retirement of SHU will include potential integration of some offsites facilities
(storage, blending and shipping/logistics facilities) with MAA/MAB Operations.
KNPC had engaged the services of Fluor Limited as the Project Management Consultant
during the Front End Engineering Design (FEED) stage.
A brief description of the scope for CFP packages is provided below. The scope described
herein covers only the important units and is intended to provide a general idea to the
Contractors. The EPC works will be contracted on a competitively bid Lump Sum basis and
will be executed using three EPC Contracts for the main units.
BRIEF DESCRIPTION OF MAA EPC PACKAGE - SCOPE OF WORK
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 5
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Refinery
MAA EPC PACKAGE
Refinery
Unit No.
Unit Name
MAA
135
DCU-NHTU
MAA
137
DIP (Deisopentanizer)
MAA
138
MAA
Capacity
Status
Licensor
8,400
BPSD
New
Haldor Topsoe
42,000
BPSD
New
Open Art - Fluor
IC5 Merox Unit
8,000
BPSD
New
UOP
146
DIB (Deisobutanizer)
6,800
BPSD
New
Open Art - Fluor
MAA
141
ARDS
50,000
BPSD
New
CLG
MAA
183
VRU
72,000
BPSD
New
Open Art - Fluor
MAA
136
DCU
37,000
BPSD
New
ABB Lummus
MAA
283
HOC
39,000
BPSD
New
Open Art - Fluor
MAA
163
Waste Water Treatment
m3/h
New
Open Art - Fluor
MAA
148
HPU
MMSCFD
MAA
156
SWT
330
60
2 X 110
New
Haldor Topsoe
3
New
Open Art - Fluor
3
SM /H
MAA
150
HSR
2x250
SM /H
New
Open Art - Fluor
MAA
151/152
SRU
2x200
MTPD
New
Shell Global Sol.
MAA
39
Eocene Topping Unit
24,000
BPSD
Revamp
MAA
144
GOD
45,000
BPSD
New
Shell Global Sol.
MAA
186
FCC-NHTU
26,000
BPSD
New
Axens
New
Open Art - Fluor
Revamp
Open Art - Fluor
BPSD
Revamp
Open Art - Fluor
MAA
195
FCC Sour Water Treating
MAA
56
Sour Water Stripper -- 1
MAA
83
VRU
MAA
25/26
MAA
107
Isomerization Unit (New)
MAA
125
LPG Treating Unit
MAA
153
HSR (New)
MAA
46
Alkylation
MAA
86
FCC
MAA
178-B-02
MAA
178
46
3
SM /H
2 X 385
77000
CCR Pre-Fac & NHT
2X
33,000
30,000
BPSD
Revamp
UOP
BPSD
New
Axens or UOP
2,264
BPSD
New
UOP
SM3/H
New
Shell Global Sol.
6,400
BPSD
Revamp
DuPont
42,500
BPSD
Revamp
UOP
New
Open Art - Fluor
140
CCR Building
--
--
Buildings
--
--
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 6
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 135 – Coker Naphtha Hydrotreater (DCU-NHTU) Unit
The new Coker Naphtha Hydrotreater Unit (NHTU-135) is designed to process 8,400 BPSD of
unstabilized full range naphtha into a product of petrochemical grade naphtha (PCN). The PCN
will meet KNPC specifications including 500 ppmw max. sulfur, 1 vol% max. olefins and 10
ppmw max. diolefins; as well as other critical specifications. NHTU-135 is designed by the
Licensor, Haldor Topsoe.
MAA Unit 136 – Delayed Coker Unit (DCU)
The new Delayed Coker Unit (DCU-136) is designed to process 37,000 BPSD of hydrotreated
vacuum residuum from the existing Vacuum Unit (VR-83) and the new Vacuum Rerun Unit
(VR-183) into the following products of fuel gas, naphtha, kerosene, diesel, heavy coker gas oil,
and anode grade coke. DCU-136 is designed by the Licensor, CBI Lummus (formerly ABB
Lummus Global).
MAA Unit 137 – Deisopentanizer (DIP)
The new Deisopentanizer Unit (DIP-137) is to be provided near the existing Unit 31/32/33
Gas Plant area. The objective of DIP-137 is to separate isopentane from the Kuwait Natural
Gasoline (KNG) stream via a fractionation column and to provide sufficient isopentane to
meet the Mogas blending requirements.
MAA Unit 138 - IC5 Merox Unit
The new IC5 Merox Unit (Unit 138) is designed to remove mercaptans from the isopentane
stream to meet the CFP sulfur specification of 10 ppmw before being sent to Mogas blending.
The unit is designed by the Licensor UOP to handle 8,000 BPSD of isopentane feed using
UOP’s Extractor Plus and Merox process technologies.
MAA Unit 141 – Atmospheric Residue Desulphurization (ARDS) Unit
The new ARDS (Unit 141) at the MAA Refinery is designed to process 100% High Sulfur
Atmospheric Residuum (HSAR) from the existing Crude Distillation Units (CDU Unit 40 and
80) and the existing Eocene Unit 39. Unit 141 is designed by the Licensor, Chevron Lummus
Global (CLG), to treat the atmospheric residue in order to produce Low Sulfur AR (LSAR).
Naphtha and distillate are also produced in the ARDS. The conversion of Atmospheric
Residuum to distillate is maximized in this new unit.
The new ARDS unit consists of major processing sections such as Make-up Hydrogen
Section, Feed Section, Reactor Section, High Pressure Separation Section, Low Pressure
Separation Section, Fractionation Section
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 7
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 146 – Deisobutanizer (DIB)
The new Deisobutanizer Unit (DIB-146) is designed to process 6,800 BPSD of field butane
feed to produce 1,650 BPSD of isobutane. The objective of DIB-146 is to provide incremental
isobutane required for the Unit 46 Alky revamp for a higher capacity.
MAA Unit 01/11/36/57/97/160 / 161 – Interconnecting Pipeways
The Interconnecting Piperack includes associated piping required to supply and/or transfer raw
materials, products, and utilities to/from various units within the CFP Complex and to the
existing refinery units.
MAA Unit 162 – Hydrocarbon Flare
The Hydrocarbon Flare collects vent and relief hydrocarbon streams from new process units
located in CFP block and safely directs them to disposal via combustion in the associated
Elevated Flare.
MAA Unit 163 – Wastewater Treatment (WWT) System
Wastewater to be treated includes process related water, fire fighting water and all rainwater
runoff collected from paved and curbed process areas.
MAA Unit 178 – Buildings
This system required modifications to accommodate the new and revamped units within the
plant. The following is a list of the permanent new buildings planned at the MAA Refinery:
•
MOB #1, 2, 3, 4, 5
•
CCR Building
•
Operator/Maintenance /Smoking Shelter &Toilets (2 nos.)
•
Chlorine Storage Enclosure (2 nos.)
•
Maintenance Workshop Complex
•
MAA Laboratory Extension Building
•
Emergency Coke Storage Building
•
HSE Building
•
Visitors Entrance Building
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 8
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 179 – Underground Piping
The OSBL underground piping for cooling water, firewater, accidentally oil contaminated (AOC)
sewer, dry slops (DS) sewer, Oil Drips System (ODS) sewer, etc. is included in Unit 179.
MAA Unit 183 – Vacuum Rerun (VR) Unit
The new open art Vacuum Rerun (VR) Unit is designed to process 72,000 BPSD of Low
Sulfur Atmospheric Residuum (LSAR) from the new ARDS Unit 141 and from the existing
ARDS Units 41/42 and 81/82.
The VR Unit includes Feed System, Vacuum Column, Vacuum Ejector and Condensate
Collection System, Offgas Compression and Scrubbing System
MAA Unit 187 - Coke Handling Facility
A new Coke Handling System to transfer coke to the existing main coke storage building
located just west of the SHU Refinery solids pier in the Shuaiba Area Authority (SAA) for
shipment to purchasers. The feedstock for this system is the green coke cut from the coke
drums in the new MAA Refinery Delayed Coking Unit (DCU, Unit 136) and drained during
cyclic operation. Green coke typically contains moisture (from the DCU decoking operation),
carbon, volatile material, sulfur and trace metals.
MAA Unit 283 – Heavy Oil Cooling
The Heavy Oil Cooling, HOC Unit-283 is designed to cool Vacuum Gas Oil (VGO), Trim Gas
Oil (TGO) and Vacuum Residue from Unit 183 before being sent to storage.
MAA Unit 144 – Gas Oil Desulphurization (GOD) Unit
The new GOD Unit 144 is designed by the Licensor, Shell Global Solutions, to produce ultra
low sulfur diesel (ULSD) with a maximum sulfur specification of 7 ppmw for export. The unit
processes 45,000 BPSD of light straight run (SR) diesel from the existing Crude Distillation
Units (CDU 4 and CDU 5) as well as diesel from the new Delayed Coker Unit (DCU 136), the
existing Atmospheric Residue Desulfurization (ARDS) units (ARDS 41, 42, 81, 82), and the
new ARDS 141 unit.
The new GOD unit consists of the processing sections such as Feed Section, Reactor,
Section, High Pressure Separation Section, Product Stripper Section, Drier Section
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 9
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 148 – Hydrogen Production Unit (HPU)
The new HPU-148 provides hydrogen required for the new hydroprocessing units in the MAA
refinery. The new units include the DCU-NHT, Unit 135, the ARDS, Unit 141, GOD, Unit 144,
ISOM , Unit 107, FCC-NHT, Unit 186, The LPG Treating, Unit 125, and SRU’s, Units
151/152. HPU-148, designed by the Licensor, Haldor Topsoe, has a hydrogen production
capacity of 67,100 Nm³/h (60 MMSCFD). The new HPU utilizes steam reforming to generate
hydrogen at a minimum purity of 99.8 volume%.
The unit contains the sections: such as Gas Preparation Section, Compression Section, Feed
Desulphurization Section, Pre-reforming, Reformer Section, CO Conversion Section, Syngas
cooling, Pressure Swing Adsorption (PSA), Condensate and Steam Section, Common
Facilities
MAA Unit 150 – New Hydrogen Sulfide Recovery (HSR) Unit
The primary objective of the Hydrogen Sulfide Removal Unit (HSR) is to remove hydrogen
sulfide (H 2 S) from the rich amine stream, and to return the lean amine to the users. HSR-150
unit consists of two-60% trains, each with a design capacity of 250 Sm3/h of rich amine. Each
train is designed with the provision of lean amine recirculation when turndown capacity is below
50% of the design feed rate. During normal operation each regenerator train will operate at
about 87% of design rate.
MAA Unit 151 and 152 – New Sulfur Recovery Unit (SRU)
There are two-200 MT/D SRU/TGTU plants namely Unit 151 and MAA Unit 152. The two
plants are identical, except that Unit 151 is also equipped with a common solvent storage tank
and the associated solvent pumps.
MAA Unit 25 – CCR 1 / Unit 26 – CCR 2 (NHT/CCR)
The NHT section in each unit will be revamped to process 35,000 BPSD of naphtha feed, and
to produce 15,000 BPSD of light naphtha to be used as feedstock to the new C5/C6
Isomerization unit (Unit 107). Heavy naphtha production rate remains the same as the original
design. Therefore, the CCR section doesn’t require a revamp.
The PDP package has prepared by the Licensor UOP.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 10
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 25/26 - CCR/Isomerization Flare System
Two new process units would be added - Isomerization Unit 107 and LPG Treating Unit 125. In
addition, the NHTs in the CCR 1 / 2 (CCR/NHT) Unit 25 and Unit 26 will be revamped, causing
the relief loads to increase. The relief loads from these new and revamped units would be
routed to the CCR Flare System. However, the capacity of the existing CCR Flare System is at
its limit. As part of the project, the existing CCR Flare System will be demolished and replaced
with the new CCR/Isomerization Flare System Unit 25/26. The new system will have two 100%
trains designed to handle the existing and new relief loads produced from either the Total
Power Failure scenario (890,000 kg/hr); or, the Partial Power Failure scenario (830,000 kg/hr).
The new CCR/Isomerization Flare stack will be located southwest of the current location.
MAA Unit 46 – Revamped Alkylation Unit and Deisobutanizer (DIB)
The purpose of the DIB is to produce adequate quantities of Isobutane make-up required for
Alkylate production.
Unit 86 FCC is being revamped as part of the Project to handle a revised (heavier) feed slate
which involves upgrade of its reactor section and necessary modifications in the Main
Fractionator and Gas Concentration section. The FCC Revamp will produce a larger total
flow rate of butylene product.
The Alky Unit will be revamped to a nominal capacity of 6,400 BPSD total alkylate in order to
process increased butylene feed due to FCC Revamp, and to support the increased alkylate
requirement for Mogas blending. A Revamp Process Design Package was prepared by the
Licensor DuPont STRATCO to define the revamp scope.
MAA Unit 74 – Fuel Gas System
This revamp of the Fuel Gas System (Unit 74) is associated with the addition of new CFP
process units in, or adjacent to existing processing areas (MAFP, FUP, RMP, & Gas Plant) in
the MAA Refinery. The revamp scope of work will include new piping tie-ins and/or
control/instrumentation from/to the new fuel gas supply for the CFP units that will be located
near the MAFP area (FCC-NHT Unit 186 and SWT Unit 195), in the RMP and Old refinery
areas (HSR Unit 153 and C5/C6 Isomerization Unit 107/LPG Treating Unit 125/GOD Unit 144,
respectively), and near the Gas Plant area (DIP Unit 137, IC5 Merox Unit 138, and DIB Unit
146).
MAA Unit 83 – Revamped Vacuum Rerun (VR) Unit
The existing Unit 83 will be revamped to improve product quality while retaining its current
design capacity of 77,000 BPSD.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 11
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 86 – New Fluid Catalytic Cracking (FCC) Unit
The Unit 86 Fluid Catalytic Cracking (FCC) in MAA was designed by UOP in 1984 for a feed
rate of 30,000 BPSD of hydrotreated VGO. The unit was started up in 1987. The Unit was
revamped in 1997 to a capacity of 40,000 BPSD, with the capability of processing heavy
vacuum gas oil and coker gas oil. The FCC 86 current capacity is about 43,000 BPSD, and it
has operated at up to about 46,000 BPSD.
FCC 86 will be revamped to handle a revised and heavier feed blend that contains TGO,
CGO, and UCO from several new and existing process units in the MAA and MAB refineries.
The FCC Revamp capacity was set at 42,500 BPSD. In addition to handling more difficult
feed at the revamp capacity, the objectives of revamp also extend to upgrading reactor
technology in order to improve yields and to increase operation reliability. The revamped unit
is to be operated to produce maximum LPG plus gasoline, without ZSM-5 catalyst additive;
and, with a target propylene production of 100,000 MT/y from the downstream propanepropylene splitter.
MAA Unit 186 – New FCC Naphtha Hydrotreater (NHT) Unit
The MAA refinery CFP will include the addition of a new FCC Naphtha Hydrotreater (Unit 186)
for processing of light and heavy naphtha streams produced in the FCC Unit (Unit 86). The
selected licensor for FCC NHTU-186 is Axens and their process is based on Prime G+
technology.
The new FCC-NHTU will be designed to treat 18,800 BPSD of FCC light naphtha and 7,200
BPSD of FCC heavy naphtha, to produce treated light and heavy naphtha streams with
maximum 10 ppmw sulfur in each of the two treated product streams.
A dedicated amine regeneration unit (ARU) will be provided within the FCC-NHTU to supply
lean amine to the HDS recycle gas amine scrubber; and, to continuously regenerate the
resulting rich amine from the scrubber.
MAA Unit 195 – FCC Sour Water Treating
A new SWT-195 with a design capacity of 203 GPM will be provided to handle the phenolic
sour water from the revamped FCC Unit 86.
SWT-195 is designed to produce stripped water with H 2 S and NH 3 at or below 20 ppmw and
50 ppmw, respectively. The H 2 S and NH 3 rich acid gas is sent to the sulfur recovery units
(SRU-51/52/91/92).
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 12
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAA Unit 107 – C5 / C6 Isomerization Unit
A new 30,000 BPSD C5 / C6 Isomerization Unit is required to meet CFP gasoline standards,
including an overall aromatic content of 35 vol% maximum. The Isomerization Unit will produce
87.5 RON Isomerate for the gasoline pool.
The C5/C6 Isomerization Unit 107 is a UOP licensed Penex-DIH Unit. The C5/C6 Isomerization
Unit consists of the Isomerization Section and Deisohexanizer (DIH) Section
MAA Unit 125 – LPG Treating
The MAA Refinery will include the addition of a new LPG Treating Unit (Unit 125) for removal
of chlorides and hydrogen saturation of olefins in the combined LPG stream from the
Debutanizer of the Platforming unit of the existing Unit 25 CCR and Unit 26 CCR. The unit
has been licensed by UOP and their process is called the UOP-Fuels Complete Saturation
Process (CSP). The design capacity of the LPG Treating Unit will be 2,264 BPSD and is
based on the combined LPG production from CCR Units 25/26.
MAA Unit 159-01 - Integrated Control and Safety Systems (ICSS)
Unit 159-01 includes all equipment and wiring for the Integrated Control and Safety Systems
(ICSS). The components of the ICSS include; Distributed Control System (DCS),
Instrumented Protective System (IPS), Fire and Gas System (FGS) and Packaged
Equipment Controls.
MAA Unit 159-02 EICS
Unit 159-02 includes all equipment and wiring for the EICS within the units assigned. Included
are the Outside Plant Cabling (OSP), Structured Cabling System (SCS, building inside cabling),
Local Area Network (LAN), Wireless Local Area Network (WLAN), Wide Area Network (WAN),
Circuit Switched Telephony System, Security System / Personnel Access, Plant
Communication System (PCS), Plant Emergency Alert System (PEAS) and Process CCTV
System.
BRIEF DESCRIPTION OF MAB EPC PACKAGE # 1 - SCOPE OF WORK
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 13
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB Refinery
MAB EPC PACKAGE # 1
Refinery
Unit No.
Unit Name
MAB
115
KHT
39,000
MAB
117
NHT
23,500
MAB
127
CCR
18,000
BPSD
New
Axens
MAB
116
DHT
73,000
BPSD
New
Shell Global Sol.
MAB
214
HCR (Hydrocracker)
50,000
BPSD
New
UOP
MAB
216
DHT
73,000
BPSD
New
Shell Global Sol.
MAB
114
HCR (Hydrocracker)
70,000
BPSD
New
UOP
MAB
212
ARDS
50,000
BPSD
New
CLG
MAB
111
CDU
264,000
BPSD
New
Open Art - Fluor
MAB
112
ARDS
100,000
BPSD
New
CLG
MAB
113
HOC
121,300
BPSD
New
Open Art - Fluor
MAB
213
VRU
50,000
BPSD
New
Open Art - Fluor
MAB
179
Underground Piping
--
--
Revamp
Open Art - Fluor
MAB
249
DHT Flare
--
--
New
Open Art - Fluor
MAB
314
HCR Flare
--
--
New
Open Art - Fluor
MAB
165
Buildings
--
--
New
SHU
53
Inter Refinery Transfer Lines
--
--
Revamp
Open Art - Fluor
Open Art - Fluor
SHU
30
Local Ship Pumps
--
--
Revamp
Open Art - Fluor
SHU
32
Marine Shipping Pumps
--
--
Revamp
Open Art - Fluor
SHU
33
Shuaiba Harbour
--
--
Revamp
Open Art - Fluor
SHU
34
Transfer Pumps
--
--
Revamp
Open Art - Fluor
SHU
38
Shuaiba Oil Pier
--
--
Revamp
Open Art - Fluor
SHU
129
Air System
--
--
New
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Capacity
Page 14
Status
Licensor
BPSD
New
Haldor Topsoe
BPSD
New
Haldor Topsoe
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB Unit 111 – Crude Distillation Unit
The new open art Crude Distillation Unit is designed to process 264,000 BPSD of Kuwait
Export Crude (KEC). The Crude Unit fractionates KEC Crude into the following products:
petrochemical grade naphtha, kerosene (fed hot to existing KHT 15 and new KHT 115, or
cold to storage), light diesel (fed hot to new DHT 116/216, or cold to storage), heavy diesel
(fed hot to new Hydrocracker HCR 214), and atmospheric residue (fed hot to ARDS 112/212
with excess to HOC 113 for cooling). Sour LP and MP offgas and sour LPG are sent to SGP
129 for H 2 S removal. The units consists of Feed System, Atmospheric Column & Side
Strippers, Crude Distillation Tower Overhead System, Offgas Compression and Naphtha
Stabilizer System
MAB Units 112/212 (Includes Soda Ash, DMDS, and Flushing Tank) Atmospheric Residue
Desulphurization (ARDS) units.
There are two new ARDS Units (112/212) at the MAB Refinery. Both Units are designed to
process 100% High Sulfur Atmospheric Residuum (HSAR) from the existing Crude Distillation
Units (CDU 11) and the new CDU 111. Units 112/212 are designed by the Licensor, Chevron
Lummus Global (CLG), to treat the atmospheric residue in order to produce Low Sulfur AR
(LSAR). Naphtha and distillate are also produced in the ARDS. The conversion of
Atmospheric Residuum to distillate is maximized in these new units.
Each new ARDS unit consists of the major processing sections such as Unit 112 Feed
Section, Unit 212 Feed Section, Reactor Section, High Pressure Separation Section, Low
Pressure Separation Section and Fractionation Section
MAB Unit 113 – Heavy Oil Cooling (HOC)
The new open art HOC Unit 113 is designed to cool the heavy oils from MAB processing
units to 82°C for three distinct objectives. The first objective to cool High Sulfur Atmosphere
Residue (HSAR) from CDU 111; Low Sulfur Atmosphere Residue (LSAR) from ARDS
112/212; and Vacuum Residue (VR), Trim Gas Oil (TGO) and Vacuum Gas Oil (VGO) from
VR 213 to a safe storage temperature during scheduled and unscheduled shutdowns of
individual units. The second objective is to cool LSAR during normal operations for
processing in VR 13. The third objective is to cool crude for recirculation back to CDU 111
during CDU startup. The HOC 113 design capacity is based on the highest LASR flow of
121,300 BPSD from ARDS-112/212 during scheduled shutdown of VR-213 and one DCU-20
train.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 15
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB Unit 114 – Hydrocracker Unit (HCR)
The new HCR 114 is designed by the Licensor, UOP, to process 70,000 BPSD of a
combination of the various feeds.
The new HCR Unit produces sour LPG, light naphtha, heavy naphtha, kerosene, diesel
(when operating in Distillate mode), and a small amount of unconverted oil (UCO). Kerosene,
however, is the hydrocracker’s primary intended product.
This unit consists of two reactor stages with a common fractionation system for product
separation. The unit consists of systems such as First Stage Feed System, First Stage
Reactor Section, Second Stage Feed System, Second Stage Reactor section, Common
Separation Section, Fractionation Section,
MAB Unit 115 – Kero Hydrotreating Unit (KHT)
The new KHT is designed by the Licensor, Haldor Topsoe, to process 39,000 BPSD of
straight run (SR) kerosene from the MAB Refinery’s existing and new Crude Distillation Units
(CDU 111 and /or CDU 11, respectively) and coker kerosene from the new MAA Refinery
Coker (DCU 136) and existing MAB Refinery Coker (DCU 20).
The new KHT consists of four process sections: a Feed Section, a Reactor Section, a
Recycle Gas Section and a Stripper Section.
MAB Unit 116 – Diesel Hydrotreating (DHT) Unit
The new DHT Unit 116 is designed by the Licensor, Shell Global Solutions, to produce ultra
low sulfur diesel (ULSD) with a maximum sulfur specification of 7 ppmw for export. The unit
processes 73,000 BPSD of light straight run (SR) diesel produced from CDU-11 and CDU111, diesel from ARDS-12 and ARDS-112/212, and coker diesel from DCU-20.
The new DHT unit consists of the processing sections namely Feed Section, Reactor
Section, High Pressure Separation Section, Product Stripper Section and Drier Section.
MAB Units 117 – Naphtha Hydrotreating (NHT) Units
The new NHT produces hydrotreated / desulfurized full range Naphtha that meets both
quantity and quality feed specifications for the new downstream CCR (Unit 127). The NHT
was designed by the Licensor, Haldor Topsoe, to process a flow rate of approximately 23,500
BPSD.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 16
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB Unit 127 – Continuous Catalytic Reformer (CCR)
The Continuous Catalytic Reformer (CCR 127) is a licensed unit designed by Axens for
inclusion within the KNPC MAB Refinery. Axens has employed its registered Octanizing ®
process in the design of the unit. The purpose of the CCR unit is to process 18,000 BPSD of
heavy naphtha from an upstream Naphtha Splitter to produce a high octane reformate, which
is a main component of the gasoline pool, and a hydrogen rich gas. Feed to the naphtha
splitter is provided by the Naphtha Hydrotreater (NHT 117) unit in the refinery.
There are three (3) main processing sections in the CCR facility: Naphtha Splitter Section,
Reaction Section and Catalyst Regeneration / Circulation Section
MAA Unit 156 – New Sour Water Treatment (SWT) Unit
The new open art SWT-156 consists of two identical trains, each designed for 60 percent of the
expected sour water rate. Each train has a design capacity of 110 Sm3/h. This provides
sufficient margin to handle peak sour water loads from DCU-136 during blowdown operation;
and covers upsets in other process units. During normal operation, both trains will operate in
parallel at about 80% of the design rate.
SWT-156 has a 3-phase separator vessel to remove gas, light hydrocarbons, and oil emulsions
from the sour water feed before steam stripping. H 2 S and NH 3 rich acid gas from the SWT-156
is sent to the Sulfur Recovery Unit (SRU-151/152). Sour water may also contain phenols,
cyanides, chlorides and carbon dioxide. SWT-156 is designed to handle maximum 100 ppmw
of phenol, 20 ppmw of cyanide, and 25 ppmw of mercaptans.
MAB Unit 165 – Buildings
The scope includes permanent new buildings MOB #1, 2 , 4 and 5.
MAB Unit 166 – Site Preparation/Roads/Paving/Fencing/Temporary Facilities
This unit includes final grading and drainage, trenches, roads, pavement and parking lots,
fencing, concrete pavement with or without curbs and walkways, dikes and retaining walls,
pits, sumps, catch basins, manholes, culverts and Temporary Facilities and electrical. All
design and installation is included.
MAB Unit 179 – Underground Piping
The OSBL underground piping for cooling water, firewater, accidentally oil contaminated (AOC)
sewer, dry slops (DS) sewer, Oil Drips System (ODS) sewer, etc. is included in Unit 179.
MAB Unit 213 – Vacuum Rerun (VR) Unit
The new open art Vacuum Rerun (VR) Unit is designed as a stand alone unit for all heat
integration is internal to the unit. The new VR Unit is designed to process 50,000 BPSD of
Low Sulfur Atmospheric Residuum (LSAR) from the new ARDS Units 112 & 212.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 17
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB Unit 214 – Hydrocracker Unit (HCR)
A second hydrocracker, HCR 214, is required in MAB to process available feed material.
Unit 214 is largely identical to Unit 114, except that it isdesigned for 50,000 BPSD.
The HCR 214 product slate is very similar to that of HCR 114. HCR 214, however, is also
designed to produce 10,000 BPSD of UCO (unconverted oil) for lube oil base stock. The unit
is licensed by UOP.
MAB Unit 216 – Diesel Hydrotreating Unit (DHT)
The new DHT Unit 216 is designed by the Licensor, Shell Global Solutions, to produce ultra
low sulfur diesel (ULSD) with a maximum sulfur specification of 7 ppmw for export. The unit
processes 73,000 BPSD of light straight run (SR) diesel produced from CDU-11 and CDU111, diesel from ARDS-12 and ARDS-112/212, and coker diesel from DCU-20.
The new DHT unit consists of the processing sections - Feed Section, Reactor Section, High
Pressure Separation Section, Product Stripper Section, Drier Section, Amine Section
MAB Unit 249 – DHT Flare
The DHT Flare collects vent and relief hydrocarbon streams from within the new CFP DHT
Unit 216 and safely directs them to disposal via combustion in the associated elevated flare.
MAB Unit 314 – HCR Flare
The HCR Flare System collects HP and LP vent and relief hydrocarbon streams from within
the new CFP HCR Units 114 and 214 and safely directs them to disposal via combustion in
the associated elevated flare. whichever is the higher.
Shuaiba (SHU) Refinery
Shuaiba Refinery process units will be retired, but the offsites, such as tankage, associated
pumps, ship loading facilities, and IRT pipeline will be maintained.
(1)
SHU Unit 129 - Utility Area
A new air compression and dehydration system is provided to meet the plant air and
instrument air requirements. Nitrogen and steam will be brought in by pipeline. Steam
requirement for Shuaiba will be met by importing LP Steam from the neighboring
Equate complex.
(2)
SHU Units 30/32/33/34/38/65 – Existing Tankage, Interconnecting Piping and
Shipping
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 18
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
New equipment and major modification to the existing equipment at Shuaiba Refinery
that comprises the Work includes various Pumps, Custody Transfer Meter/ Prover
Skids and Shuaiba Pier Modifications, Tank Modifications and Other Equipment.
(3)
MAB Unit 53 – Inter Refinery Transfer Pipelines
Inter Refinery Transfer (IRT) lines are provided by CFP, transferring intermediate
streams and finished products between refineries, to support normal operation, as
well as to manage intermediate product.
BRIEF DESCRIPTION OF MAB EPC PACKAGE # 2 - SCOPE OF WORK
MAB EPC PACKAGE # 2
47000
13,000
5 x 155,000
MAB
129
SGP
MAB
131
Steam System
MAB
132
Cooling Water Systems
495,000
MAB
134
Nitrogen / Air Systems
26,600
MAB
137
Water systems
MAB
156
Wastewater Treatment systems
MAB
118
HPU
MAB
123
SRU
MAB
MAB
125
126
ARU
128-01
MAB
119
MAB
128-02
MAB
133
Fuel System
MAB
13
VRU
MAB
21
Merox Unit
MAB
11
CDU
MAB
48, 148,150
MAB
50,51,52
MAB
Open Art - Fluor
New
Open Art - Fluor
New
Open Art - Fluor
Nm3/h
New
Open Art - Fluor
1,450
m3/h
New
Open Art - Fluor
455
m3/h
New
Open Art - Fluor
3 X 185
MMSCFD
New
Haldor Topsoe
3 X 450
MTPD
New
Shell Global Sol.
3
New
Open Art - Fluor
3
SM /H
New
Open Art - Fluor
280
MMSCFD
New
Open Art - Fluor
127
MMSCFD
New
Non-Licensed
811
MMSCFD
New
Non-Licensed
2 X 325
HPU Feed Treating &
Compression
H2 Recovery
MAB
New
kW
2 X 1,100
SWS
3
NM /H
BPSD(LPG)
kg/h
H2 Compression
SM /H
2,660,376
Sm3/d
New
Open Art - Fluor
2 X 64,000
BPSD
Revamp
Open Art - Fluor
Revamp
190,000
BPSD
Revamp
--
--
--
--
179
Interconnecting Pipeways
Tank Farm, Product Pumping &
Blending
Underground Piping
--
--
New/Revamp
Open Art – Fluor
MAB
165
Central Control Room
--
--
Open Art – Fluor
MAB
136
Electrical
--
--
Revamp
New/Revamp
MAB
154
Fire Water
--
--
New/Revamp
Open Art – Fluor
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 19
New/Revamp
New/Revamp
Open Art - Fluor
Open Art – Fluor
Open Art – Fluor
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB
159
ICSS / EICS
--
--
New/Revamp
Open Art – Fluor
MAB
149
Flare System
Site Preparation/Roads/Pavings
etc.
Acid Gas Flare
--
--
New/Revamp
Open Art – Fluor
--
--
New/Revamp
Open Art – Fluor
--
--
New/Revamp
Open Art – Fluor
Buildings
--
--
New
Open Art – Fluor
MAB
166
MAB
146
MAB
132/156/165
MAB Unit 06 – Utilities & Offsites
The existing utility system will supply utilities to new Units; Wastewater Treating Unit 156-02,
Diesel Hydrotreating Unit 216, and Flare Unit 249. Due to the retirement of Crude Unit 01,
RCD Unibon Unit 02, Hydrogen Unit 03, and Diesel Hydrotreating Unit 16, sufficient utility
capacity exists for the new units without modification to the existing utility systems.
MAB Unit 11 – Revamped Crude Distillation Unit (CDU)
The MAB refinery will be operated at a design feed rate of 454,000 BPSD of Kuwait Export
Crude (KEC). CDU 11 will process 190,000 BPSD of the KEC crude feed, while the
remaining crude is fed to new Crude Distillation Unit, CDU 111. The original design capacity
of CDU 11 is 156,000 BPSD.
CDU 11 unit operation will be reconfigured and impacted equipment services upgraded to
produce a light diesel cut only, ASTM T95 at 653°F (345°C), from the existing Diesel Stripper
T-11-103. This will meet the KNPC CFP Marketing Parameter for ultra-low sulfur diesel
(ULSD); i.e., the heavy diesel cut will go down with the Atmospheric Residue from the bottom
of the Crude Fractionator T-11-101.
ISBL (Non-Revamp) Tie-Ins
MAB Units 12, 14, 15, 18 and 20 include tie-ins inside the ISBL battery limits for the
installation of control valves and addition of new lines to/ or from new CFP units and/or
existing units for routing feed stocks and hydrogen.
MAB Unit 13 – Existing Vacuum Rerun (VR) Unit
Scope involves piping and controls systems modifications to the units. Each train will
process 64,000 BPSD of Low Sulfur Atmospheric Residuum (LSAR) supplied from both the
new and existing ARDS Units 112/212 and 12, respectively.
MAB Unit 21 – Merox Unit
New Merox ATK Product Pumps will be installed for blending U 21 ATK product with ATK
produced from existing refinery and new CFP process units.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 20
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
MAB Unit 48 Interconnecting Pipeways
New piping and tie-ins will be provide on the existing refinery main interconnecting piperack,
U-48, to route feed / and product streams from /to from existing refinery process unit s and
new units in CFP block.
MAB Unit 50/51/52 – Existing Tank Farm/Product Pumping and Shipping/Pre-RMP Tank
Farm
The existing Tank Farm at the MAB Refinery receives, stores, blends and transfers feed,
intermediate product and finished product streams from source units and sends them to the
process units, ship loading facilities or to other refineries through inter refinery pipelines. For
CFP, existing tankage has been reallocated and five additional tanks and associated pumps
are installed to meet storage requirements for post CFP operations. The scope includes new
equipment
MAB Unit 118 – Hydrogen Production Unit (HPU)
The new HPU 118 provides hydrogen required for the new hydroprocessing units in the MAB
refinery. The new units include the ARDS (Units 112 and 212), HCR (Units 114 and 214),
KHT (Unit 115), DHT (Units 116 and 216), and NHT (Unit 117).
HPU 118 designed by the Licensor, Haldor Topsoe, consists of three hydrogen production
trains, each with 206,900 Nm³/h (185 MMSCFD) hydrogen production capacity. The plant
total installed hydrogen production capacity is 620,700 Nm3/hr (555 MMSCFD).
The unit comprises of Feed Desulphurization Section, Pre-reformer Section, Reformer
Section, CO Conversion Section, Syngas cooling Section, Pressure Swing Adsorption (PSA)
Section, Condensate and Steam Section, Common Facilities.
MAB Unit 119 – Hydrogen Recovery (HR) Unit
The purpose of the new open art Hydrogen Recovery (HR) Unit is to recover hydrogen from
the ARDS cold low pressure separator off-gas, Hydrocracker cold flash drum off-gas, ARDS
membrane tail gas, and CCR Unit rich gas. The PSA unit hydrogen recovery is 87%,
minimum. The PSA unit will produce 99.9 vol. % purity hydrogen.
MAB Unit 123 – Sulfur Recovery Unit (SRU)
The CFP scope for the MAB Refinery consists of three-450 MT/D SRU/TGTU plants, each
operating at 33.3% of total required capacity.
•
•
•
•
•
The SRU/TGTU plant includes the following components:
Feed Acid Gas KO Drums (Amine and SWS acid gas)
Claus Thermal Stage
Claus Catalytic Stage(s)
Tail Gas Hydrogenation Section
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 21
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
•
•
•
Tail Gas Amine Section
Tail Gas Incinerator and Stack
Sulfur degassing
In addition, there will be two common liquid sulfur storage tanks and associated pumps.
MAB Unit 125 – Amine Regeneration Unit (ARU)
The Amine Regeneration Unit (ARU) has two 75% trains, each with a design capacity of
1,100 Sm3/h of rich amine. CO 2 -free train ARU is expected to operate at 65 % of the design
capacity; and the CO 2 -bearing train ARU is expected to operate at 70% of the design
capacity.
MAB Unit 126 – Sour Water Stripping (SWS) Unit
The Sour Water Stripping Unit is designed to separate non-aqueous gas, light hydrocarbons,
and oil emulsions from the sour water feed before steam stripping to remove the bulk of the
H 2 S and NH 3 .
The Sour Water Stripping Unit consists of two trains. Each train is designed for 75% of the
expected sour water rate. Design capacity of each train is 325 Sm3/hr. During normal
operation each train will be operating at around 68% of design rate.
MAB Unit 128-1 – HPU Feed Treatment and Compression (HPU Feed) Unit
The new open art HPU Feed Treatment and Compression (HPU Feed) Unit compresses this
blended feed gas to a pressure suitable for feeding the HPU.
MAB Unit 128-2 – Hydrogen Compression (HC) Unit
The new open art Hydrogen Compression (HC) Unit is a centralized facility serving the
ARDS, DHTU, HCRU, and KHTU hydrogen demands by compressing high purity hydrogen
streams originating from the HPU, ARDS membrane, HRU, and NHTU. The compression
facility is configured to supply nominal 100 barg hydrogen to the KHTU and DHTU and
nominal 200 barg hydrogen to the ARDS and HCRU. The facility is nominally designed to
accommodate the full hydrogen production from the three HPU trains.
MAB Unit 129 – Saturated Gas Plant (SGP)
SGP Unit 129 is designed to remove H 2 S from refinery offgas and LPG streams produced in
various new process units in the CFP Block. SGP 129 consists of two distinct sections. One
section treats sour refinery offgas, and the other section treats sour LPG.
The first section treats sour refinery offgas and has a nominal design capacity of 47,000
Nm3/hr.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 22
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
The second section treats sour LPG for removal of H 2 S and has a nominal design capacity of
13,000 BPSD.
MAB Unit 131 - Steam Generation Unit
The CFP requires steam for turbine drive pumps and compressors and for process heating
and process feed. The steam requirements for the CFP include essential and non-essential
High Pressure (SH), Medium Pressure (SM), Intermediate Pressure (SI), and Low Pressure
(SL) steam. This steam is generated from a combination of utility boilers and process steam
generation. The unit includes Deaerators, Boiler Feed Water (BFW) and Boilers
MAB Unit 132 - Cooling Water System
The Cooling Water System is a closed-circuit, Fresh Water System designed to maintain the
cooling water circulation rate and temperature that is necessary in order to remove heat from
the process and utility units in CFP. The major equipment consists of a cooling tower, cooling
tower concrete basin, chemical feed systems and cooling water pumps with steam turbine
drivers. An electric motor-driven pump is also being provided for standby and startup
operation.
MAB Unit 133 - Fuel Systems
The Fuel System distributes fuel gas from the Refinery Off-gas Treatment Unit to the various
fired heaters and steam generators throughout the CFP facilities. Fuel oil is provided as a
backup fuel to the Crude Distillation Unit Heater, ARDS Fractionator Heaters, and to the
Utility Boilers via an existing distribution pipeline from the tank farm which is extended to the
new CFP area. The major components are the distribution header and pressure and flow
control stations.
MAB Unit 134 – Nitrogen / Air Systems
CFP provides a new Nitrogen / Air System in order to supply sufficient compressed air to
meet the demands of Instrument Air (compressed , dried air), Plant Air (compressed wet air
for utility and other intermittent usage), and Nitrogen (99.5% purity nitrogen for refinery
needs).
Captive Nitrogen generation (PSA) is supplied to meet normal system requirements such as
dry gas seals where identified for various Licensor and open arts units.
Pipeline nitrogen, supplied by local manufacturers, and nitrogen from tube trailers is
available.
MAB Unit 136 – Electrical
The electrical system for the facilities consists of new 132kV supply from MEW substation
MARF – W to MDSs (Main Distribution Substations). At the MDSs, the voltage is
transformed to 11kV for distribution to new unit substations throughout the plant.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 23
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
An Electrical Network Monitoring and Control (ENMC) system is included in the new electrical
system.
MAB Unit 137 - Water Systems
The Water Systems include Makeup Desalinated Water Treating, Condensate Collection and
Treating, Boiler Water Polisher, and Potable Water Conditioning and Distribution. The Water
Systems planned for the CFP include Polished Water, Potable Water, Condensate,
Desalinated Water, Acid and Caustic System, MAB Unit 146 - Acid Gas Flare.
MAB Unit 148/150- Interconnecting Piperack
Interconnecting Piperack includes associated piping required to supply feed stocks, utilities and
route products to/from various process units and utilities systems located within the CFP
Complex and the existing MAB refinery.
MAB Unit 149 - Flare
The Hydrocarbon Flare System (HFS) collects HP and LP vent and relief hydrocarbon streams
from within the new CFP process units and safely directs them to disposal via combustion in
the associated elevated flare. The major components of the HFS are HP & LP Flare KO Drums,
Flare KO Pumps, Flare Water Seals, Flare Fuel Gas KO Drums, HP Flare (one operating, one
spare), LP Flare (one operating, one spare), Flare Gas Recovery Unit (future), and Flare KO
Drum Liquid Coolers.
MAB Unit 154 – Fire Fighting Facilities
Treated effluent waste water is stored as the primary supply of firewater to the CFP firefighting
system. The firewater is supplied to a plant-wide underground ring main system through
firewater pumps during a significant fire event. Electric motor-driven jockey pumps will be
provided for general maintenance of system pressure.
The capacity of the firewater system is designed to handle the largest single fire contingency
for the CFP Facility. Fire protection in the plant is provided by a combination of hydrants,
hoses, monitors, and tank foam systems.
Two firewater tanks are sized based on the Shell DEPs, in conjunction with NFPA
requirements.
MAB Unit 156-01/156-02 - Wastewater Treating
Wastewater to be treated includes process related water, fire fighting water as well as all
rainwater runoff collected from paved areas and curbed process areas. It includes the following
systems :
•
Surplus Stripped Sour Water and Desalter Water
•
AOC Drain System
•
ODS Drain System
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 24
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
•
Dry Slops (DS) System
•
Amine Drain (AD) System
MAA Unit 159-01 - Integrated Control and Safety Systems (ICSS)
Unit 159-01 includes all equipment and wiring for the Integrated Control and Safety Systems
(ICSS). The components of the ICSS include; Distributed Control System (DCS),
Instrumented Protective System (IPS), Fire and Gas System (FGS) and Packaged
Equipment Controls.
MAA Unit 159-02 – EICS
Unit 159-02 includes all equipment and wiring for the EICS within the units assigned. Included
are the Outside Plant Cabling (OSP), Structured Cabling System (SCS, building inside cabling),
Local Area Network (LAN), Wireless Local Area Network (WLAN), Wide Area Network (WAN),
Circuit Switched Telephony System, Security System / Personnel Access, Plant
Communication System (PCS), Plant Emergency Alert System (PEAS) and Process CCTV
System.
MAB Unit 165 – Buildings
The following is a list of the permanent new buildings planned for CFP at the MAB Refinery:
•
Technical Office Building
•
Chlorine system enclosure
•
CCR Building (revamp of existing to house new CFP consoles)
•
MOB #3, 6 and 7
•
Chemical Warehouse Building
•
Catalyst Storage Facility
•
Parts Warehouse Building
•
Laboratory Building
•
Maintenance Workshop Building- Area 1
•
Mechanical Garage- Area 1
•
Diesel Filling Station- Area 2
•
Sling Wire Shop- Area 2
•
Workshop Site Office – Area 2
The following is a list of the temporary buildings planned for CFP at the MAB Refinery:
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 25
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
•
HSE Building
•
Central Training Center
•
Visitor’s Entrance Building
•
Laboratory Annex
•
Operations Building
MAB Unit 166 – Site Preparation/Roads/Paving/Fencing/Temporary Facilities
This unit includes final grading and drainage, trenches, roads, pavement and parking lots,
fencing, concrete pavement with or without curbs and walkways, dikes and retaining walls,
pits, sumps, catch basins, manholes, culverts and Temporary Facilities and electrical. All
design and installation is included
MAB Unit 179 – Underground Piping
The OSBL underground piping for cooling water, firewater, accidentally oil contaminated (AOC)
sewer, dry slops (DS) sewer, Oil Drips System (ODS) sewer, etc. is included in Unit 179.
3.0
ENGINEERING, PROCUREMENT
RESPONSIBILITIES
AND CONSTRUCTION (“CONTRACTOR”)
The CONTRACTOR’s scope of work for the Project shall be clearly stipulated in the
Tender documents.
However, in general the scope of work for CONTRACTOR shall include, but shall not
be limited to the following:
• Detailed engineering for the various process units and facility segments as
listed above.
• Prepare and issue Issued For Construction (IFC) drawings to site along with
illustrating all tie-ins to the existing utility and offsites facilities as required.
• Engineering, procurement, inspection, supply, transportation, unloading at the
Project site, installation and testing of all new equipment, machinery and
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 26
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
materials including proprietary equipment and long lead equipment in
accordance with the contract documents and requirements.
• Engineering, procurement, inspection, supply, transportation to the Project
site, unloading at site, installation and testing of all field instrumentation,
Control Systems, ESD and Electrical equipment.
• Procurement, inspection, supply, transportation to the Project site, unloading
of capital, operational and startup spares (to include the supply of spares and
special tools for the construction, pre-commissioning and commissioning
activities).
• Liason with KNPC and Kuwait statutory authorities regarding obtaining any
and all permits required in the execution of the Project.
• Demolition of facilities including disposal of all debris and unusable materials
• Full and complete erection / construction, testing / inspection, and mechanical
completion of the plant.
• Tie Ins to existing facilities, where required.
• Preparation of the required detailed operating / technical manuals.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 27
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
• Supply and loading of first charge of calibration gases, oils, chemicals,
adsorbents, molecular sieves and catalyst.
• Implement a quality management program to provide procedures for
engineering, procurement, construction and commissioning which meet the
Project and ISO 9000 quality system requirements.
• Provide an inspection and quality management program which shall ensure
that all equipment and materials meet the requirements of the project and that
all construction activities are inspected and tested as required by the quality
management program.
• Implement and comply with all local regulations on health, safety and
environment in the design and the execution of the works and maintain an
effective safety plan on site during
construction,
precommissioning,
commissioning and start-up of the projects.
• Conduct HAZOP and other similar studies for the projects in association with
the chosen Licensors and Owner.
• Implement and maintain an effective, well established and approved planning
system for the control and scheduling of all activities and development of
reports to Owner in accordance with the requirements of the Project.
• Provide assistance and coordinate with Owner, Licensors, and Vendors during
commissioning, start-up and performance testing of plant.
• Provide required services of vendor representatives and specialists for critical or
specialized activities during construction, precommissioning and commissioning
as deemed necessary by Owner.
• Carry out any warranty or guarantee obligations during the maintenance
guarantee and / or warranty periods.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 28
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
• Provide Owner with all electronic files (computer files) of drawings and
documents of the plant.
• Supply and erect materials or equipment and perform any engineering work
which is deemed necessary to fulfill any process and safety requirements or
environmental and governmental regulations.
4.0
PRE-REQUISITE FOR PRE-QUALIFICATION
4.1
Only those contracting companies that have successfully executed Major
Refinery, Petrochemical and Oil & Gas New/Upgrade/Revamp Projects
worldwide over the past fifteen (15) years shall be considered.
4.2
Any contracting company, Joint Venture (JV) or Consortium wishing to be
included on the QBL must be an established EPC CONTRACTOR/s with the
relevant experience and capability to execute the work in which interest is
indicated. Although it is intended to pre-qualify Contractors for all packages and
not separately for each package, Contractor is requested to fill Table-1
indicating his interest of participation in bidding. Specific qualification
requirements for Joint Ventures and for Lead JV partner capabilities and
experience are described in Exhibits A and B.
4.3
If CONTRACTORs are registering for prequalification for this project in the form
of a consortium or joint venture, each party must define generally what scope of
work each will execute in such an arrangement and demonstrate herein that
each party is capable of performing that scope of work. Each party shall answer
all questions herein and designate each parties’ response. Each party shall
sign the prequalification documents. In such a case, proof of a Joint Venture /
Consortium must be submitted in the form of a draft agreement.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 29
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
4.4
All Joint Venture / Consortium documentation shall be subject to KNPC
approval and conditional to submittal of a legalized Joint Venture / Consortium
agreement (notarized copy) for KNPC review before final approval is granted to
bid.
4.5
Joint Venture / Consortium documentation shall be evaluated on a single entity
basis against capabilities and previous project experience. Preference shall be
given to Joint Venture / Consortium(s) with prior working experience. Newly
established or specially formed Joint Venture / Consortium(s) for this Project
will be subject to additional reviews and bidder is advised to submit written
justification why Owner should consider such a proposed new entity.
4.6
In addition to evaluating the JV or Consortium as a single entity, the Lead
Partner will be evaluated individually to determine if it has the systems,
processes, engineering and project management capabilities to complete the
work even if a junior partner needs to be replaced.
4.7
Joint Ventures shall be formed during the prequalification stage. If a company is
not qualified individually or as a lead JV partner, that company will not be
allowed to attempt to qualify at a later time.
4.8
Please note, it is the Owner’s sole decision to determine whether or not the
prequalification information submitted by CONTRACTOR is acceptable.
Furthermore, it is the Owner’s sole decision as to whether or not a
CONTRACTOR submitting interest and information as specified in this
document will be placed on the QBL.
5.0
INSTRUCTIONS TO COMPANIES REGISTERING FOR QUALIFIED BIDDERS LIST
5.1
All documents, lists, certificates and information required from the company
must be in the English language.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 30
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
5.2
All prequalification documents shall be treated with strict confidence by the
Owner in assessing the suitability of CONTRACTOR for the above mentioned
work. Any prequalification documents submitted after the closing date shall be
disregarded.
5.3
It is important that all information requested be presented in an orderly and
sequential manner using the formats and tables attached to this inquiry
document wherever and whenever provided.
5.4
CONTRACTOR agrees that the Owner shall have the right to contact any
reference given by the CONTRACTOR in support of answers to this
questionnaire.
5.5
CONTRACTOR
shall
complete
the
“Fact
Sheet”
and
submit
with
questionnaire. The Fact Sheet, although it contains some repetitive information,
is a required document for the screening process and shall be completed in its
entirety.
The Fact Sheet shall be submitted by the CONTTRACTOR if qualifying alone
or by lead JV partner if qualifying as a JV.
5.6
CONTRACTOR must complete and answer each and every question, in full
clarity, in the same sequence as presented in the pre-qualification document. A
company’s request for inclusion onto to the Qualified Bidders List will be subject
to disqualification if the documentation and information requested by Owner is
not submitted as stipulated, is not fully answered, or if any section is
inappropriately left blank in the forms or tables. Disqualification may also occur
if, for any reason, cross references given in these forms or tables are missing
or incomplete, information or documents requested documentation are shared,
copied, compared, or discussed in any way with other companies.
5.7
In the event prequalification information is not submitted in full clarity, Owner is
under no obligation to proceed with clarifications with the CONTRACTOR.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 31
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
5.8
CONTRACTOR is requested to electronically complete the forms and tables
included or attached to these documents while maintaining the same format.
5.9
All information submitted by the CONTRACTOR must be accurate, clear and
within the context of the form submitted. Any information found to be misleading
or ambiguous shall be considered as void. Owner reserves the right to discard
any unclear information provided by the CONTRACTOR if found in doubt.
5.10
Responses and queries if any, regarding the Project or other information given
herein, shall be addressed to:
Chairman, PQ Committee
Mina Abdullah Admin Building
3rd Floor, Room 313
P.O. Box 69, Safat
Kuwait 13001
Email: cfp.contractor.pq@knpc.com
5.11
Not Used
5.12
Owner will require that twenty percent (20%) of the work (E, P or C) be
awarded to the local Kuwaiti contracting and/or supplier sector.
CONTRACTORs shall take this into account during the prequalification
documentation preparation.
5.13
CONTRACTOR shall understand the Project descriptions and relevant contract
conditions are exclusively for prequalification purposes only. The
prequalification documents are not and should not be construed as an Invitation
to Tender. Replies to the prequalification questionnaire are deemed to be
without obligation whatsoever on the part of the Owner.
5.14
The Owner is under no obligation to prequalify any CONTRACTOR or to give
reasons for either prequalifying or disqualifying any CONTRACTOR.
The
Owner is also under no obligation to proceed with the contract or invite a
prequalified CONTRACTOR to submit a subsequent bid or to enter into any
correspondence to this effect.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 32
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
5.15
Responses to the prequalification questionnaire shall be submitted in two (2)
original, single bound documents completed in all respects and duly signed and
stamped by the CONTRACTOR’s authorized person only . These must be
returned in sealed envelopes, marked “PREQUALIFICATION DOCUMENTS –
KNPC CFP” and addressed and sent to :
ITC Reception Desk
Room # 1A-046,
1st Floor, KNPC H.O.,
Ahmadi - Kuwait
Fax: 00965 23986262 (ITC, Secretary)
5.16
In addition to the above submitted bound copies and included in the same
sealed envelopes shall be a CD / DVD that contains the files in a logical
sequence of ALL submittal documents. These electronic files shall be in either
MS Office Program(s) format (e.g. MS Word / Excel) or as a “PDF” file
accessible by Adobe Reader 6.0.
5.17
CONTRACTOR
to
complete,
sign
and
submit
the
“CONTRACTOR
Declaration” on the following page.
5.18
CONTRACTOR to complete multiple questionnaires if submitting as a Joint
Venture or Consortium. One questionnaire to be completed for the combined
JV and one questionnaire to be completed for each individual company
participating as JV/Consortium Partner.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 33
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Pre-Qualification Questionnaire for CONTRACTOR
CONTRACTOR DECLARATION
TO:
Chairman, Prequalification Committee
KNPC Clean Fuels Project
Full Name of Company:_______________________________________________
We, the undersigned wish to participate in prequalification for CONTRACTOR for the
Project to be established in the State of Kuwait and we warrant our competence to
execute the entire work to the highest levels of professional standards.
We also warrant that our presented answers are complete to the best of our knowledge
and that the details submitted by us in these prequalification documents and all attached
documents are true and accurate in every respect.
We acknowledge that Owner has the discretion in selecting the qualified CONTRACTOR
for its services, and shall not be required under any circumstances to assign or give
reason(s) for disqualifying us, and that Owner decision in this regard is final and not
subject to appeal and that we shall not enter with Owner or others into any
correspondences or debates concerning this selection.
We authorize Owner to investigate or verify any statement or information given in our
prequalification document and that it is free to contact any person or any of our clients,
banks, auditors, etc. to obtain any clarification related to the information given in this
document.
We declare that in case of award of contract to us, we shall fully comply with all rules,
regulation and Health, Safety and Environment guidelines set forth by Owner or any other
Government body in the State of Kuwait.
We declare that we or any of our subcontractor or personnel required to work on this
project, shall have no objection in signing secrecy agreement with Owner, if so requested
after award of work.
We declare that, if we are qualified (Short Listed) by Owner for its project we shall be
committed to present our bid in reply to Owner’s Invitation to Bid procedure of this project.
We understand that Owner will not be responsible for payment of any expense which we
may incur in the preparation and submission of the prequalification documents.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 34
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Name :
Signature and stamp:
Address :
Tele. No.:
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 35
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Fact Sheet
Notes:
1. Response to each question is mandatory.
2. Fact Sheet to be filled up by single contractor if qualifying alone or by lead JV
partner if qualifying as JV.
A. Your willingness and ability, if you are selected to be a bidder, to submit a
competitive proposal for this project in accordance with the bid basis set out above.
Answer
Check
one
Not willing and/or not able
Willing and able
B. Your willingness and ability to submit a proposal within the period discussed above for
bidding.
Answer
Check
one
Not willing and/or not able
Willing and able
C. Your experience during the past five years with KNPC or affiliates. Please list the
affiliate names and the scope of work performed.
D. Do you have experience in executing large jobs (greater than $ 300 MM) outside your
home country during the past 15 years.
Answer
Yes
No
Check one
Please list the 3 largest contracts you have performed as a prime contractor in an
EPC capacity, including the contract amount.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 36
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
E. Your bonding ability. Please state the bonding capacity of your company.
Answer
Below $100 million
$100 million and above
Check one
F. Indicate the maximum value, in US Dollars, of an EPC contract outside your home
country that you are capable of executing, both alone and as a Joint Venture /
Consortium.
Answer
$ 300 MM to $ 600 MM
$ 600 MM to $ 1 Billion
Over $ 1 Billion
Check one
G. Construction Safety Record - Specify your Lost Time Accident Frequency for the
projects that Applicant has implemented over the last five (5) years, including the
number of fatalities and the cause of death.
Answer
LTA rate of higher than 1.0
LTA rate of 1.0 or less
Check one
H. Your willingness to execute a Confidentiality Agreement regarding this work.
Answer
No
Yes
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Check one
Page 37
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 1
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
1.0
CONTRACTOR Information
1.1
Is CONTRACTOR company the Lead JV / Consortium partner ?
Yes ________
1.2
No _________
Postal Information for any future Correspondence
1.2.1
Legal Name of CONTRACTOR (Company):
1.2.2
Country of origin:
1.2.3
Postal Address:
1.2.4
Telephone Number:
(Incl. Area Code)
1.3
1.2.5
Fax Number:
1.2.6
Visiting Address (If different than postal address)
Contact Personnel information for any future Correspondence
1.3.1
Name in Full:
1.3.2
Title:
1.3.3
E-mail Address:
1.3.4
Fax Number:
1.3.5
Telephone Number:
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 38
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
1.4
Date of Business (Company) Establishment
Day
1.5
Month
Year
Type of Business
1.5.1 Public, Private, Partnership, Limited Liability, Un-Limited Liability, etc.
(Give Details)
1.6
1.5.2
Fields of Business Activities (Give Details)
1.5.3
Country of registration / Registration Number:
Affiliates / Associates / Subsidiary Companies
1.6.1
Name:
1.6.2
Address:
1.6.3
Name:
1.6.4
Address:
1.6.5
Name:
1.6.6
Address:
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 39
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
1.7
Other Offices Worldwide
1.7.1
Legal Company Name:
1.7.2
Country:
1.7.3
Postal Address
1.7.4
Telephone Number:
(Incl. Area Code)
1.7.5
Fax Number:
1.7.6
Contact Person Name and E-mail Address:
(Repeat as required if more offices)
1.8
CONTRACTOR Profile
1.8.1
Provide the CONTRACTOR’s Organization Chart from the upper
hierarchy level to Managers level. Indicate Group or Division who will
be responsible for execution of the EPC work and its management
team.
If Joint Venture, provide these organization charts for each JV
participant.
1.8.2
Parent Company; state legal name and country of residence of direct
parent company and the ultimate holding company, if any.
1.8.3
Change of Ownership; has there been any major change of Ownership
of the establishment over the past five (5) years. If so, kindly provide
details and if not, please affirm by “NONE”.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 40
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
1.8.4
Affiliates / Associates / Subsidiary Companies; provide details in the
form of a graphic representation to clearly identify each of the
CONTRACTOR’s Affiliates / Associates / Subsidiary Companies and
their interrelation to one another.
1.8.5
Stock Exchange; state on which stock exchange the CONTRACTOR
shares and/or the shares of the parent and/or holding company are
traded. If this is not applicable, please affirm by “NO SHARES ON
STOCK EXCHANGE”.
1.8.6
Internet Website (if applicable)
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 41
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 2
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
2.0
Experience
2.1
Has the CONTRACTOR carried out full EPC scope contracts with a value over
$400 million for Refinery, Petrochemical or Oil & Gas Projects worldwide (other
than the Contractor’s home country) during the past the last fifteen (15) years
that have been successfully commissioned or are expected to be
commissioned during 2012.
If the answer to the above is positive, give reference of these Plants as per
details given in Form (1). CONTRCATOR is requested to fill a separate form
for each project. Furthermore, CONTRACTOR is requested to summarize all
its experience data provided in Form (1) in Form (1.1).
2.2
Client References – CONTRACTOR shall submit Form 2, Contractor
Reference Inquiry, for five of CONTRACTOR’S most recent, relevant projects.
Have them completed and signed by a client representative.
Client
representatives should keep the reference confidential and send them directly
to KNPC at the address shown on the form.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 42
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 3
Pre-Qualification Questionnaire for CONTRACTOR
For CFP
3.0
Establishment
3.1
What is the total permanent manpower available within the CONTRACTOR’s
organization for each of the following categories:
Category
Permanently Employed
With CONTRACTOR Having
Experience
20
10-20
< 10
Years Years
Years
CORPORATE
Management
Administrative
Financial
Sales
PROJECT
Engineering
- Process
- Mechanical
- Instrument
- Electrical
- Civil
Project Control
(Planning, Costing,
Contracting,
Procurement)
CONSTRUCTION
Constr. Manager
Quality Control
Quality Assurance
Safety
Administrative
Field Engineering
Field Procurement
Constr. Supv.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 43
Contracted
Manpower
TOTAL
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Totals
Note: Engineering and Construction personnel shall not be duplicated.
3.2
Does the CONTRACTOR have any established relationships or affiliations
with specialist consultants and/or licensors of technology relevant to the
proposed projects subject of this pre-qualification? If the answer is “yes”,
kindly provide details and if not, please affirm by “NONE”.
3.3
CONTRACTOR is requested to provide information of EPC’s worldwide
offices, indicating the activities and functions of each of these offices:
No
Country
Location
(Province)
Sales
Eng.
Procur. Constr. Others
1
2
3
4
5
6
3.4
CONTRACTOR is requested to provide its typical Organization Chart for full
EPC type projects, having the same order of extent, including positions,
disciplines and responsibility relationships. CONTRACTOR is also requested
to clearly identify the project connected to the Corporation’s Organization
Chart.
3.5
CONTRACTOR is requested to provide in the table below the details /
histogram of the number of engagements that it is currently committed to
and/or bidding for as of the year 2011 projected through year 2016 showing
available manpower versus committed and projected.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 44
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Current Engagements (Manpower Availability)
No.
Project
Name/Location
1
2
3
4
5
6
7
TOTAL
:
2011 2012 2013 2014 2015
Committed
Available
Committed
Available
Committed
Available
Committed
Available
Committed
Available
Committed
Available
Committed
Available
Committed
Available
In addition, Contractor is requested to provide the following information:
No
Project Name, Location
and Category
CONTRACTOR’s
Role (E/P/C)
1
2
3
4
5
6
7
8
9
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 45
Number of Personnel
Assigned
2016
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 4
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
4.0
Financial
4.1
CONTRACTOR is requested to provide audited copies of its annual reports for
the last three years, including balance sheets of profit and loss accounts after
final auditing.
4.2
CONTRACTOR is to indicate if there have been any significant changes in its
balance sheet for this current year with reference to last year’s audited
balance sheet.
4.3
CONTRACTOR is requested to provide copies of any financial statements
released to its shareholders or to the public subsequent to the publication of
the latest audited accounts.
4.4
CONTRACTOR is requested to provide the following financial information for
the past three (3) years in the table below. (All Values to be given in US. $)
No
1
2
3
4
5
6
7
8
9
7
Description
Borrowed Capital
Net-Worth
Current Assets
Total Assets
Current Liabilities
Turn Over
Turn Over (Refining /
Petrochemical/Oil &
Gas)
Turnover Engineering
Design
Turnover Engg.
Design (Refining /
Petrochemical, Oil &
Gas)
Gross Profits before
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 46
2009(*)
2010(*)
2011(*)
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
8
9
taxes
Gross Profits after
taxes
Net profits
Note (*):
4.5
CONTRACTOR must indicate the end of financial year (If not
March ending) as appropriate.
CONTRACTOR is requested to provide the name(s) and address(es) of its
bank(s) and other information as requested below;
Bank Name:
Bank Address:
Telephone No.:
Fax. No.:
Manager’s Name:
(Repeat as required in case of additional banks)
4.6
CONTRACTOR is requested to specify the amount(s) (in US. $) of Tender and
Performance Bond(s) of its current undertaken projects. (Do not include any
contract with a value less than US $ 500 million)
Project Name
Tender (Bid)
Bond USD $
Performance
Bond USD $
Contract Value in
USD $
4.7
CONTRACTOR to provide current bonding capacity.
4.8
CONTRACTOR is requested to provide the name and address of its external
auditors used by it during the past five (5) years.
Auditors Name:
Address:
Telephone No.:
Fax. No.:
Contact Name:
(Repeat as required in case of additional auditors)
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 47
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 5
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
5.0
Project Execution
5.1
CONTRACTOR is requested to submit a summary of its proposed project
execution plan which shall include amongst others, overall execution strategy,
project management & organization plan, handling of critical execution issues,
project administration plan, project control plans, engineering plan,
procurement and material management plan, quality assurance & quality
control plan, construction plan, pre-commissioning, commissioning and startup plan.
5.2
What are the types of work that the CONTRACTOR shall carry out
independently for the Project without subcontracting to others:
Category
Project Management
Engineering
Procurement
Construction
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Activity
All
Process
Mechanical
Civil
Instrument
Electrical
Safety
QA /QC
All
Site Preparation
Civil / Structure
Mechanical
Electrical
Instrument
Inspection
Safety
Commissioning
Page 48
By
CONTRACTOR
By
Others
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
5.3
Where shall the CONTRACTOR typically carry out or cause to carry out the
following project functions:
Category
Project Management
Engineering
Procurement
5.4
Activity
Main
Office
Regional
Office
Other
Location
All
Process
Mechanical
Civil
Instrument
Electrical
Safety
Drafting
All
CONTRACTOR is requested to provide a summary of its subcontracting
practices and procedures indicating the methodology for selecting, awarding
and administering subcontracts.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 49
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 6
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
6.0
Quality Management
6.1
CONTRACTOR is requested to state which Quality Management system the
CONTRACTOR is accredited to and provide certified copy of such
accreditation. CONTRACTOR is also requested to submit a summary (Table of
Contents) of its latest quality plan implemented for a similar CONTRACTOR
Refinery or Petrochemical or Oil and Gas EPC project.
6.2
Does your quality management system accredited by international agencies
also cover Project Management, Engineering, Procurement and Project
Execution? Submit proof of the same along with the procedures and
methodologies used.
6.3
CONTRACTOR is requested to state when their last audit was done and to
submit a copy of the audit report of the quality assurance system carried out by
third party.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 50
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 7
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
7.0
Health Safety and Environment
7.1
CONTRACTOR is requested to submit details of their health, safety and
environment performance by completing the attached Form 3, CONTRACTOR
Safety Performance.
7.2
CONTRACTOR is requested to provide a summary of it’s safety program
including details of its safety training program for its employees and workers
assigned to work sites and describe how the requirements of its policy are
published and communicated to inform its personnel on health and safety
matters.
7.3
CONTRACTOR is requested to elaborate on what type of first-aid and other
facilities are offered by the CONTRACTOR to its employees and workers on a
working site.
7.4
CONTRACTOR is requested to elaborate on whether it carried out HAZOP
Studies, Environmental Practices and Environmental Program Involvement in
the past on any Petrochemical, Refinery Projects or Oil & Gas Projects, and if
so, provide details and copy of such studies and the procedures being
followed by the CONTRACTOR for such studies and the methodology
(arrangement) between the CONTRACTOR, Technology Licensor and Owner.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 51
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 8
8.0
Pre-Qualification Questionnaire for CONTRACTOR
For Clean Fuels Project
Construction and Procurement Strategies
8.1
Procurement / Expediting Strategy and Organization
8.2
i)
CONTRACTOR is requested to describe its strategy for the procurement,
transportation to jobsite and subsequent erection of the main columns, vessels
and other major equipment items.
ii)
CONTRACTOR is requested to describe the organization responsible for
procurement and expediting and the strength of the organization and its
location along with a brief description of the procurement methodology and the
strategy for inspection and expediting.
iii)
CONTRACTOR is requested to provide its current purchasing workload and
indicate whether expediting is carried out by buyers or specialists appointed
for that purpose.
iv)
CONTRACTOR shall describe current procurement strategy and envisioned
strategies to accommodate current market conditions as applied for the
following disciplines:
- Concrete
- Structural Steel
- Machinery & Equipment
- Piping
- Electrical & Control Systems
v)
CONTRACTOR shall describe strategies for freight movements and inland
transportation to jobsite of major equipment items (i.e. pressure vessels,
columns, reactors, compressors, etc.).
Material Management System
CONTRACTOR is requested to describe its Material Management System and how
tracking delivery, projections, slippages and initiating expediting actions are carried
out.
8.3
Craft Labor Resources :
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 52
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Contractor is requested to provide Total Craft Manpower Curves and Peak Craft
Manpower for each of the recent Projects for which Contractor has provided as
relevant experience on FORM (1).
8.4
Construction Management and Craft Supervision practices
For the Projects listed on FORM (1), provide the following breakdowns of your
Construction Management Staff and Craft Supervision as a percent of Total Craft
Manhours reflected in 9.3 (a) above:
8.5
a.
Construction Management Staff as a % of Total Craft Hours (Site Manager
through Area and General Superintendents, including support Staff).
b.
Craft Supervision as a % of Total Craft Hours (General Foremen through Craft
Superintendents).
Construction Equipment and Heavy Lift Practices
1)
Rigging/Heavy Lift Engineering Capability and Practices.
Please indicate Contractor’s resources and practices regarding Rigging
Engineering and Heavy Lift Engineering/Planning as follows:
a.
Please provide the Total Number of Permanent Construction Staff
devoted to Rigging/Heavy Lift Engineering currently included in your
Staffing Totals as provided in the resources listed in ATTACHMENT
No. 3:
(i) Total Permanent Staff; Rigging/Heavy Lift Engineers/Supervisors
b.
Please indicate Company Practices and
Rigging/Heavy Lift Engineering and Planning:
Policies
regarding
(i)
Company Policy requires formalized Rigging/Lift Engineering
for all lifts of _____Tons
(ii)
Company Permanent Rigging Engineering Staff reviews and
signs off on all lifts of ______Tons.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 53
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
(iii)
2)
Where Construction Work is Subcontracted to Others,
Company Permanent Rigging Engineering Staff reviews and
signs off on all lifts of _____Tons.
Construction Equipment Resources.
Please indicate the following regarding Contractors Construction Equipment
Resources:
a.
Please indicate Mobile Construction Equipment Inventory of Contractor
as would be utilized on major Projects (similar to those listed on FORM
(1) and the proposed KNPC Clean Fuels Project:
Capacities
Range
1) upto 100 Ton
2) 125-300 Ton
3) 350-500 Ton
4) Over 500 Ton
b)
Contractor Subsidiary
Owned
Provided
Contracted
Local
Supplier
Please indicate what was the Heaviest/Largest Lifts accomplished
directly under the CONTRACTOR’s Supervision for Projects covered in
Form-1:
Project
1
2
3
4
5
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 54
Heaviest
Lifts (MT)
Largest Lifts (T-T
Length/Diameter)
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
9.0
Litigation / Arbitration / Disputes
9.1
Contractor is requested to inform whether its business, regardless of current
company name, is presently or has ever been involved in any litigation or
arbitration proceedings in relation to project work undertaken by EPC for a
claim value exceeding (USD) $10 Million.
If so, kindly provide details and if not, please affirm by “NONE”.
9.2
Contractor is requested to inform whether its business, regardless of current
company name, is presently in dispute with either clients or
subcontractors/suppliers over unresolved contract claims or other matters for a
claim value exceeding (USD) $10 Million.
If so, kindly provide details and if not, please affirm by “NONE”.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 55
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
ATTACHMENT No. 10
Pre-Qualification Questionnaire for EPCs
For Clean Fuels Project
10.
IT Support System.
10.1
CONTRACTOR is requested to list the planning and scheduling systems
currently being used within its establishment.
10.2
CONTRACTOR is requested to list the hardware and peripheral equipment
and software available to support its:
• Planning and scheduling systems.
• Material management systems.
• Document management systems.
• IT communication systems.
10.3
CONTRACTOR is requested to explain its philosophy towards the application
of software in engineering projects including data processing support and
summarize the experience gained in employing CAD techniques directly in
project related work.
10.4
CONTRACTOR is requested to list the hardware and principal peripheral
equipment available for each of its CAD systems and the software available to
support its CAD and Engineering procedures.
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 56
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
FORM (1)
Experience – World-Wide
1-
Project Name
2-
Owner Name
3-
Country & Location
4-
Legal
Name
of
CONTRACTOR’s Entity
Signing the Contract
and
Executing
the
Work
5-
Nature of Project
Yes
abcde-
6-
No
Grass Root
Extension
Revamp
Debottle Neck
Others (Specify)
Product Slate
Product Name
Capacity KTPA
abcdef-
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 57
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
7-
Licensed Technology
Licensor Name
Process Unit
abcdef-
8-
Project Total Value
US. $
9-
CONTRACTOR’s Contract US. $
Value
10- Other
CONTRACTOR’s US. $
earned Values
11- Type of Contract
Yes
abcde-
Lump Sum Turn Key
Cost Plus
Reimbursable
Unit Rate
Others (Specify)
12- Contract Start Date
13- Contract Scheduled End Date
14- Actual End Date
15- Actual Start-up Date
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 58
No
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
16- Number and type of Sub-Contracts
No.
abcdefgh-
Sub-Contractor’s Name
Scope of Service
17- Involvement in Licensed Technology
License
CONTRACTOR’s Scope
abcdef-
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 59
FORM (1.1)
Experience – Worldwide
Summary
NO
1
2
3
4
…
PROJECT
DESCRIPTION
OWNER NAME
LEGAL NAME
OF
CONTRACTOR’
S ENTITY
SIGNING THE
CONTRACT &
EXECUTING
THE WORK
COUNTRY &
LOCATION
PROJECT
TOTAL
VALUE
EPC CONTRACT
VALUE
CONTRACT
OR SCOPE
(E/P/C)
DATES
(FROM START
TO FINISH)
FORM (2)
Contractor Reference Inquiry
This section to be completed by EPC Contractor
Regarding _______________, who is attempting to prequalify for work associated with the
Kuwait National Petroleum Company’s Clean Fuels Project, and who has cited your
Company as a source of reference, please respond to the following:
Your response will remain confidential.
Please complete the following details:
1.
2.
3.
4.
5.
Project Description
Contractor Work scope
Contract Completion Date
Approximate Contract Value
Approximate Labor Hours
This section to be completed by Client Representative
6.
7.
8.
9.
10.
11.
12.
13.
Was Contractor the Main Contractor or a subcontractor?
Did the Contractor perform the major elements of the work without the use of
subcontractors? If not, what was the volume of work subcontracted?
Contract Type (i.e. Lump Sum, Unit Rate, Reimbursable etc.)
Was the work performed by this Contractor on time, taking into account any
awarded completion extensions?
Did the Contractor implement satisfactory Quality Assurance and Control
procedures?
Did the Contractor implement satisfactory Safety Programs and Procedures?
Would you consider awarding further work to this Contractor?
Work Execution
Quality of
Workmanship
Cooperation
Management Quality
Quality of Field
Supervision
Labor Quality
Sufficiency
Good
Average
Poor
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Labor Relations
Safety Performance
Reaction to Changes
Planning Quality
14.
Commercial
Commercial
Relationship
Contractor attitude to
claims
Invoicing Quality
15.
Good
Average
Poor
COMPANY NAME
BY
_____
TITLE/POSITION
DATE
PHONE_____________________________________________________
EMAIL______________________________________________________
16.
Completed forms should be sent to:
Chairman, PQ Committee
Mina Abdullah Admin Building
3rd Floor, Room 313
P.O. Box 69, Safat
Kuwait 13001
Email: cfp.contractor.pq@knpc.com
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 62
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
FORM (3)
Contractor Safety Performance
Injury and Illness Data
a. Employee hours
worked last three
years:
Provide the following data:
Hours Year:
Field:
Total:
2006
2007
2006
No.
Rate
2008
2007
No.
2009
2008
Rate
No
Rate
2009
No
Injury resulting in fatality
Total No. of fatalities x
200,000
Fatality Rate= _________________
Total Employee Hours
No. of Accidents resulting in Lost work
day Cases (LWC)
LWC Rate =
Total No. of LWC X
200,000
________________
Total Employee
Hours
No. of accidents other than lost work
Day Cases
LWC Rate =
No. of Non-LWC X
200,000
_________________
Total Employee Hours
Highest ranking safety/health/environment professional in the company:
Title
Telephone
Fax:
Do you have or provide:
a) Full Time Safety/Health /Environment Engineer
b) Full Time Site Safety/Health /Environment Engineer
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 63
Yes
Yes
Yes
2010
No
No
No
Rate
2010
No
Rate
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
c) Full time Job Safety/Health/Environment Officer
Do you have a written Safety and Health Program?
Does the program address the following key elements?
-Management commitment and expectation
Yes
No
Yes
No
-Employee participation
Yes
No
-Accountabilities and responsibilities for managers,
Supervisors, and employees
Yes
No
-Resources for meeting safety & Health requirements
Yes
No
-Periodic Safety and Health performance appraisals for all
employees
Yes
No
-Hazard recognition and control
Yes
No
Yes
No
Yes
No
Yes
No
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
Do you have written programs for the following:
a) Hearing Conservation
b) Respiratory Protection
Where applicable, have employees been:
Trained
Fit Tested
Medically approved
c) Hazard Communication
Do your employees read, write and understand English/Arabic
such that they can perform their job tasks safety without an
interpreter?
If no, provide a description of your plan to assure that they can
safely perform their jobs.
Medical
a) Do you conduct medical examination for:
-
Pre-employment
-
Replacement job Capability
-
Pulmonary
-
Respiratory
b) Describe how you will provide first aid and other Medical
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 64
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
services for your employees while on site
Specify who will provide these services : _________________
Yes
No
c) Do you have personnel trained to perform first aid and
CPR?
Do you hold site safety and health meetings for:
Field Supervisors
Employees
New Hires
Yes
Yes
Yes
No
No
No
Frequency_____
Frequency_____
Frequency_____
Are the Safety and Health meetings Documented?
Yes
No
Personal Protection Equipment (PPE)
a) Is applicable PPE provided for employees?
b) Do you have a program to assure that PPE is Inspected
and maintained?
Yes
Yes
No
No
Yes
No
Safety, and Environmental specifications for acquisition Yes
of Materials and equipment?
No
b) Do you conduct inspections on operating equipment Yes
(e.g. Cranes, Forklifts, and JLGs) by third party agencies
Yes
eg? Lloyds BV etc
No
Do you have a corrective action process for addressing
individual safety and health performance deficiencies?
Equipment and Materials:
a) Do you have a system for establishing applicable health
No
c) Do you maintain operating equipment in compliance with
Regulatory requirement?
d) Do
you
maintain
maintenance
the
applicable
Certification
records
inspection
for
Yes
No
Yes
Yes
No
No
and
operating
equipment?
Inspection and Audits
a) Do you conduct Safety and Health Inspections?
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 65
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Yes
b) Do you conduct Safety and Health program audits?
No
c) Are corrections of deficiencies documented?
Safety and Health Orientation
New Hires
a) Do you have a Safety & Health Orientation
Program for new hires and newly hired or Promoted
supervisors?
Supervisors
Yes
No
Yes
No
b) Does program provide instruction on the following: Yes
- New worker Orientation?
No
Yes
No
-Safe Work Practices
Yes
No
Yes
No
-Safety Supervision
Yes
No
Yes
No
-Toolbox Meetings
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
-Emergency Procedures
-First Aid Procedures
-Incident Investigation
-Fire Protection and Prevention
-Safety Intervention
-Hazard Communication
c) How long is the Orientation program?
Hours
Safety & Health/Environment training
a) Do
you
now
Environments
the
regulatory
training
safety
requirements
health
and Yes
No
for
your Yes
No
Yes
No
Employees?
b) Have your employees received the required Safety &
Health and Environment training and retraining?
c) Do you have as specific Safety & Health and
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 66
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
Environment training program for Supervisors?
Do you have an Environmental Management System?
Yes
No
If yes, attach a copy of the policy.
Have you obtained accreditation under any Standards/System viz
ISO14001?
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
If Yes, attach the relevant certificates.
Do you carry out Environmental Audit of your facilities?
Please furnish the detail on frequency, internal/external and copy of the
last audit.
Do you practice Environmental guidelines in storage of Hazardous
chemical, Materials at site/facilities?
If yes, furnish the code/standards of guidelines.
Do you take/adopt necessary precautions to control fugitive emissions
form the site/facilities?
If yes, furnish the methods/standards.
Do you practice Environmental guidelines/standards in manufacturing
facilities to reduce the air emissions, water & solid waste at the source?
If yes, brief the measures taken at your facilities.
Do you have procedures for taking appropriate actions to contain
accidental spills/releases from the site/facilities?
If yes, furnish the brief details.
Does your organization any time subject to enforcement action by
statutory authorities for violating Environmental regulations?
If yes, furnish the brief details.
What is the percentage towards Environmental expenses on your
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 67
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
annual turnover?
Are you aware of the prevailing environmental regulations in the state
of Kuwait?
INFORMATION SUBMITTAL
Yes
No
Please provide copies of checked ( ) item with the completed PQF:
____
____
____
____
____
Insurance Certificate (s)
Safety & Health Program
Safety &Health Incentive Program
Hazard Communication Program
Respiratory Protection Program
____ Environmental Policy
____ Accreditation Certification
____ Environmental Audit Reports & Procedures
____ Environmental Training Program (Outlines)
____ Procedure for spill control/fugitive emission
____
____
____
____
____
____
____
Housekeeping Policy
Accident/Incident Investigation Procedure
Unsafe Condition, Reporting Procedure, Control, etc.
Safety Inspection Audit Procedure or form
Safety & Health Training Program (Outline)
Example of Employee Safety & Health Training Records
Safety & Health Training Schedule (Sample)
Authorized Signature:________________________________
Name:__________________________ Date: _____________
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 68
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
TABLE (1)
Contractor’s Interest
No.
1
2
3
EPC Package
Rank Interest
(1 to 3 – 1
being most
favorable)
If qualified,
indicate which
package you
would bid
MAA EPC Package
MAB EPC Package 1
MAB EPC Package 2
Please indicate the maximum number of EPC Packages you are capable / interested
to execute. ________________________
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 69
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
EXHIBIT “A”
Minimum Pre-Qualification requirements for Bidder. (If Bidder is submitting
application individually the limits apply to the individual organization. If Bidder is a
JV, the limits in this Exhibit A applies to the JV combined forces)

Total revenues no less than 5 billion USD per year

Experience of at least 7 major project in the Petrochemical/Refining/Oil & Gas
Industry

Experience of at least 5 Projects larger than 1 billion USD or its JV equivalent

Minimum 400 million USD in global design revenues

Net worth larger than 1.5 billion USD (Combined)

Leader in HS&E. LTR less than .50 per 200,000 hours

Workforce of at least 2,250 Engineers
(Revenues above shall be based on the highest revenue earned per year from amongst the
last 5 years)
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 70
CLEAN FUELS PROJECT (CFP)
EPC CONTRACTOR PREQUALIFICATION QUESTIONNAIRE
EXHIBIT “B”
Minimum Pre-Qualification requirements for Lead JV (In addition to have JV
prequalified as a single entity, the lead JV Partner must meet the following criteria)

Total revenues no less than 3 billion USD per year

Experience of at least 5 major projects in Petrochemical /Refining/Oil & Gas Industry

Experience of at least 3 Projects larger than 1 billion USD or its JV equivalent

Minimum 250 million USD in global design revenues

Minimum 600 million USD in petrochemical/refinery/Oil & Gas contracts

Net worth larger than 1 billion USD

Leader in HS&E. LTR less than .50 per 200,000 hours

Workforce of at least 1350 Engineers
(Revenues above shall be based on the highest revenue earned per year from amongst
the last 5 years)
KNPC CFP PQ QUESTIONNAIRE
KNPC-EPCPQ-CFP-005 Rev. 01
Page 71
Download