NCREN Network Outage Report

advertisement

 

MCNC  NETWORK  OPERATIONS  

DISRUPTION  OF  INTERNET  PROVIDER  SERVICE  

Postmortem  

11  April  2014  

NOC  Ticket  #6113

 

 

 

EVENT  SUMMARY  

   

(Note:  All  times  noted  in  this  document  are  Eastern  Daylight  Time  (EDT).)  

 

At  approximately  6:00  P.M.,  on  April  11 th ,  2014,  the  NCREN  constituents  listed  below  experienced  an   interruption  of  network  service  when  a  total  and  catastrophic  failure  of  the  MCNC  NCREN  Research  

Triangle  Park  (RTP)  optical  node  occurred.  This  event  caused  an  interruption  of  network   connectivity  service  for  all  NCREN  constituents  that  receive  IP  and/or  transport  services  through  the  

RTP  Regional  Point-­‐of-­‐Presence  (RPoP).  In  addition,  MCNC  Data  Center  constituents  experienced  an   interruption  of  service  during  this  event.  The  RTP  optical  node  was  restored  and  returned  to  service   by  approximately  12:00  A.M.,  April  12 th ,  2014.  The  majority  of  the  disrupted  constituent  connectivity   services  were  restored  at  this  time,  but  several  constituents’  services  remained  unavailable  until   restored  at  approximately  1:30  A.M.,  April  12 th ,  2014.  

 

REASON  FOR  OUTAGE  

The  outage  was  caused  by  a  catastrophic  failure  of  the  MCNC  NCREN  Research  Triangle  Park  (RTP)   optical  transport  node.  Both  the  primary  and  redundant  line  cards  that  are  responsible  for  the  timing   and  control  functions  of  the  optical  node  spontaneously  and  simultaneously  failed  leaving  the  entire   node  in  a  state  such  that  no  network  traffic  could  be  passed.  The  equipment  vendor  performed   exhaustive  diagnostic  tests  post  restoration,  but  ultimately,  to  date  has  not  been  able  to  determine   the  root  cause  of  the  initial  failure.  Restoration  of  service  was  delayed  due  to  two  factors:  1)  a   software  bug  which  resulted  in  continuous  controller  card  switchover  and  resets  and  2)  corruption   of  the  optical  node’s  backup  configuration  database  files  that  are  routinely  created  by  the  vendor’s   management  platform.  

INCIDENT  CHRONOLOGY  

 

At  approximately  5:00  P.M.,  April  11 th ,  an  NCREN  network  engineer  noticed  in  the  vendor  supplied   optical  monitoring  system  that  the  RTP  Optical  Node’s  primary  timing  and  control  card  appeared  to   have  lost  its  connection  to  the  optical  monitoring  system.  The  engineer  attempted  to  reach  the   network  management  interface  on  the  card  via  several  NOC  computer  workstations,  but  to  no  avail.  

At  this  time,  there  was  no  loss  of  service.  

 

At  approximately  5:15  P.M.,  April  11 th ,  the  decision  was  made  to  manually  failover  the  primary  timing   and  control  card  to  the  redundant  card  by  removing  the  primary  card  from  its  slot  based  on   processes  and  procedures  authorized  by  the  equipment  vendor  in  similar  situations  in  the  past.  

Though  the  card’s  status  LEDs  indicated  that  the  redundant  card  was  now  active,  NCREN  network   engineers  were  still  not  able  to  reach  the  network  management  interface  on  the  card.  There  was  still  

  no  loss  of  service  at  this  time.  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  1  

 

At  approximately  5:20  P.M.,  April  11 th ,  the  decision  was  made  to  fail  back  over  to  the  primary  timing   and  control  card  by  reinserting  it  into  its  slot.  At  this  point,  both  the  primary  and  redundant  timing   and  control  cards  began  a  30-­‐minute  rebooting  and  syncing  phase.  Once  complete,  it  appeared  that   the  primary  card’s  status  LEDs  indicated  that  it  had  become  the  active  timing  and  control  card;   however,  the  network  management  interface  on  the  card  could  still  not  be  reached.  There  was  still  no  

  loss  of  service  at  this  time.  

At  approximately  6:00  P.M.,  April  11 th ,  the  decision  was  made  to  make  another  attempt  at  regaining   connectivity  to  the  RTP  Optical  Node’s  network  management  interface  by  removing  and  reinserting   the  primary  timing  and  control  card  from  the  node.  Shortly  after  the  reinsertion,  the  RTP  Optical  

Node  suffered  a  complete  failure  that  resulted  in  the  loss  of  all  services  provisioned  on  or  through  the   node.  

 

The  NCREN  Network  Operations  Center  (NOC)  began  receiving  network  management  system’s   alarms  and  calls  from  multiple  NCREN  constituents  starting  at  approximately  6:00  P.M.  The  issue  was   immediately  isolated  to  the  Research  Triangle  Park  RPoP  optical  node,  where  Senior  Network  

Engineers  were  immediately  engaged  in  troubleshooting  the  issue.  The  incident  was  escalated  to  

 

MCNC  executive  management  within  20  minutes.  

By  6:30  P.M.,  MCNC  senior  network  engineers  felt  that  based  on  the  behavior  of  the  failed  optical   node,  that  the  appropriate  measure  was  to  restore  the  node’s  configuration  from  backup.  After   several  failed  attempts  at  approximately  7:19  P.M.,  a  Technical  Assistance  Case  (TAC)  was  opened   with  the  equipment  vendor.  Senior  engineers  then  worked  with  TAC  to  identify  a  working  backup  file   and  restore  the  failed  optical  node.  

 

At  approximately  7:30  P.M.,  NCREN  Executive  Management  escalated  the  issue  with  the  equipment   vendor  account  team..  MCNC  NCREN  senior  network  engineers  continued  troubleshooting  the  issue  

  with  the  equipment  vendor  to  identify  the  source  of  the  problem.  There  was  no  ETR  at  that  time.

 

After  working  with  the  equipment  vendor’s  TAC  for  several  hours,  a  non-­‐corrupt  backup   configuration  database  file  was  identified  on  the  NCREN  NOC’s  optical  network  monitoring  system   and  the  RTP  optical  node  was  restored  and  back  in  service  by  approximately  12:00  A.M.,  April  12 th .  

The  majority  of  the  disrupted  constituent  connectivity  services  were  restored  at  this  time,  but   several  constituents’  services  remained  unavailable  until  restored  at  approximately  1:30  A.M.,  April  

12 th .    The  delay  in  restoration  of  the  final  circuits  was  due  to  additional  required  fine-­‐tuning  of  the   optical  system.    

COMMUNICATION  DURING  THE  EVENT  

 

The  NCREN  NOC’s  initial  attempt  at  sending  notification  via  email  to  NCREN  constituents  failed  due   to  the  connectivity  issues  created  by  the  loss  of  the  optical  node  at  MCNC’s  RTP  facility.  Available  off-­‐ site  NOC  staff  members  were  notified  about  the  communication  issue  at  6:33  P.M.  An  initial   notification  was  posted  via  Twitter  at  6:54  P.M.  Additional  attempts  to  send  notification  via  off-­‐site  e-­‐ mail  were  made  at  approximately  6:55  P.M,  7:12  P.M.,  and  7:22  P.M.  respectively.  These  attempts   failed  due  to  the  primary  NCREN  constituent  mailing  list  server  being  unavailable  due  to  the  outage.    

 

At  7:22  P.M.,  the  initial  notification  was  posted  via  the  MCNC  website  and  Facebook.  At  7:31  P.M.,  the   initial  notification  was  sent  via  email  and  auto-­‐dial  via  MCNC’s  backup  notification  tool,  targeting   constituents  that  received  IP  services  out  of  RTP.  Another  notification  was  sent  at  approximately  

8:07  P.M.,  via  email  and  auto-­‐dial  specifically  to  MCNC  Data  Center  constituents.  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  2  

 

Another  status  message  was  posted  via  Twitter  at  10:26  P.M.  as  well  as  e-­‐mailed  at  10:36  P.M.,  to  

MCNC  NCREN  constituents  (RTP  and  MCNC  Data  Center  constituents).  At  12:31  A.M.,  a  final   notification  was  emailed  to  all  NCREN  constituents  stating  that  the  failed  optical  node  had  been   restored.  At  that  point,  the  NCREN  backbone  was  no  longer  considered  impaired  and  was  functioning   in  a  normal  state.    

 

NOC  staff  began  calling  NCREN  constituents  that  requested  a  call  back.  An  update  was  made  to  

Facebook  and  Twitter  at  12:44  A.M.  and  1:07  A.M.,  respectively.  Remaining  impacted  constituents’   connectivity  services  were  restored  at  approximately  1:30  A.M.,  April  12 th .  

 

MITIGATING  FACTORS  

 

The  following  items  are  noted  as  mitigating  factors  i.e.,  they  are  things  that  may  have  caused  

  increased  impact  or  some  delay  in  problem  resolution:  

1.

Several  initial  attempts  to  restore  the  optical  node  failed  due  to  the  NCREN  network   engineering  team  using  corrupted  backup  database  configuration  files.  Backup   configuration  files  are  automatically  retrieved  at  scheduled  intervals  from  each  

NCREN  optical  node  and  stored  on  the  vendor  supplied  optical  network  monitoring   system.  This  application  does  not  possess  the  intelligence  to  make  a  determination   that  any  backup  file  or  files  that  reside  on  it  may  be  corrupt.  

 

2.

The  MCNC  Net-­‐Info  list,  which  is  the  primary  application  used  to  communicate  the   status  of  network  events  to  NCREN  constituents,  such  as  the  interruption  of  service   issue  experienced  on  April  11th,  was  not  functioning  correctly.  

 

3.

The  NCREN  Network  engineering  team  delayed  opening  a  TAC  case  with  the  vendor   as  they  felt  that  the  outage  would  be  mitigated  by  restoring  the  optical  node’s   configuration  from  a  backup  configuration  file  located  on  the  vendor  supplied   optical  network  monitoring  system  based  on  this  type  of  guidance  in  past  similar  

  situations.  

4.

Redundant  pre-­‐provisioned  virtual  circuits  to  redundant  NCREN  aggregation   routers  would  have  allowed  for  quicker  restoration  of  and/or  prevented  loss  of   service  to  affected  constituents  on  the  IP  network.  

 

 

5.

NCREN  network  engineers  were  required  to  relocate  from  the  NOC  to  a  different   building  on  the  MCNC  campus  to  leverage  Out-­‐of-­‐Band  Direct  Internet  Access.  

 

These  mitigating  factors  will  all  be  examined  in  a  subsequent  section  titled  “Action  Items.”  

 

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  3  

 

 

 

 

 

 

WORKING  TEAM  

 

MCNC   Tommy  Jacobson   Chief  Operating  Officer  and  VP  Network  

Ray  Suitte  

Matt  Valenzisi  

Infrastructure  Initiatives  

Sr.  Technical  Manager/  

Core  Engineering  &  Network  Deployment  

Chief  Network  Architect/  

Sr.  Technical  Manager  Network  Management  

Jeremy  Buenviaje   Sr.  Manager,  Network  Operations  &  Customer  

Fulfillment  

919-­‐248-­‐1178  

  tjacobson@mcnc.org  

919-­‐248-­‐1454  

  rsuitte@mcnc.org  

919-­‐248-­‐8429   mvalenzisi@mcnc.org  

 

919-­‐248-­‐8429   jbuenviaje@mcnc.org

 

 

 

ACTION  ITEMS  

1) Upgrade  optical  nodes  to  address  equipment  vendor  software  issue  beginning  with  most   critical  nodes  first.   a.

Owner:  Ray  Suitte   b.

Due  Date:  April  21,  2014  

 

 

PLEASE  NOTE:  As  of  this  distribution  of  the  RFO,  on  April  17 th ,  2014,  the  most   critical  operational  optical  nodes  on  NCREN  that  had  contained  the  previously  noted   software  bug  and  corrupted  database  files  have  been  successfully  upgraded.      

2) Plan  for  and  build  backup  virtual  circuits  for  constituents  receiving  MCNC  NCREN  IP  

Connectivity  Service  via  MCNC’s  Owned  and  Operation  MPLS-­‐based  transport  network.   a.

Owner:  Matt  Valenzisi  &  Ray  Suitte   b.

Due  Date:  June    11,  2014  

 

3) Relocate  the  secondary  MCNC  Data  Center  lambda  as  well  as  any  secondary  constituent   lambdas  to  a  diverse  optical  node  in  RTP  as  soon  as  possible.     a.

Owner:  Matt  Valenzisi  &  Ray  Suitte   b.

Due  Date:  Pending  completion  of  new  fiber  infrastructure  currently  being  

  constructed  in  Research  Triangle  Park  to  an  alternate  location  (most  likely  by  June  1,  

2014).  

4) Investigate  potential  deployment  and  value  add  of  additional  independent  optical   infrastructure  at  several  key  NCREN  RPoPs  to  increase  network  availability  and  reduce   disruptions  during  any  network  degradation  or  outage.   a.

Owner:  Matt  Valenzisi  &  Ray  Suitte   b.

Due  Date:  May  30,  2014  

 

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  4  

 

5) Modify  NOC  policy  for  contacting  vendor’s  TAC  when  dealing  with  unreachable  network   management  interfaces  on  optical  nodes  and  critical  routing  and  switching  infrastructure.  

Going  forward,  when  loss  of  connectivity  to  a  network  management  interface  is  detected,  a  

TAC  case  will  be  opened  immediately  and  as  long  as  there  is  no  service  disruption,  no  action   will  be  taken  until  directed  to  do  so  by  the  vendor’s  TAC.  In  addition,  as  long  as  there  is  no   service  disruption,  any  recommended  actions  will  be  taken  during  the  first  available   emergency  maintenance  window.   a.

Owner:  Jeremy  Buenviaje  &  Ray  Suitte   b.

Due  Date:  COMPLETED  

 

6) Review  High  Availability  (HA)  capabilities  of  all  Network  Management  tools  to  ensure   maximum  availability  during  any  network  degradation  or  outage.     a.

Owner:  Matt  Valenzisi  &  Jeremy  Buenviaje   b.

Due  Date:  May  16,  2014  

 

7) Review  the  posture  of  NCREN  network  status  and  NCREN  Constituent  communication  and   notification  tools  to  ensure  that  they  will  function  as  expected  during  any  type  of  network   degradation  or  outage.  In  addition,  verify  current  constituent  contacts  for  each  service   provided  by  NCREN.  Ensure  that  all  constituents  are  aware  of  all  existing  channels  of   communication  available  to  them  for  receiving  information  during  events  of  this  nature  (e.g.,   twitter,  facebook,  e-­‐mail,  etc.).   a.

Owner:  Jeremy  Buenviaje   b.

Due  Date:  May  16,  2014  

 

8) Extend  Out-­‐of-­‐Band  (OOB)  3 rd  Party  Direct  Internet  Access  circuit  (Building  3)  into  the  

MCNC  Network  Operations  Center  (Building  2).     a.

Owner:  Matt  Valenzisi     b.

Due  Date:  May  16,  2014  

 

 

NCREN  CONSTITUENTS  THAT  EXPERIENCED  AN  INTERRUPTION  OF  SERVICE  

Administrative  Office  of  the  Courts  –  Raleigh  

Akamai  Networks  -­‐  RTP  NC  

Albemarle  Regional  Library  

Asheboro  City  Schools  

Barton  College  

Beaufort  Community  College  

Beaufort  County  Schools  

Bertie  County  Schools  

Brunswick  Community  College  

Brunswick  County  Schools  

Burroughs/Welcome  Fund  

Camden  County  Schools  

Campbell  University  –  Law  School    

Campbell  University  –  RTP  Center  

Campbell  University  –  to  RTP  

1-­‐99.147  

1-­‐99.131  

1-­‐99.236  

1-­‐99.102  

1-­‐99.160  

1-­‐99.213  

1-­‐99.225  

1-­‐99.189  

1-­‐99.178  

1-­‐99.200  

1-­‐99.114  

1-­‐99.188  

1-­‐99.18  

1-­‐99.38  

1-­‐99.43  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  5  

 

Cape  Fear  Community  College  

Cardinal  Gibbons  High  School  

CarolinaEast  –  Heart  Center  Newbern  

Carteret  Community  College  

Carteret  County  General  Hospital  

Carteret  County  Health  Department  

Carteret  County  Schools  

Casa  Esperanza  Montessori  Charter  School  

Central  Carolina  Community  College  

Central  Park  School  for  Children  

Central  Piedmont  Community  College  –  MCNCDCS-­‐ChltMyers  

Chapell  Hill  Carbarro  City  Schools  

Charlotte  Mecklenburg  County  Government    

Charlotte-­‐Mecklenburg  County  Government  –  RTP-­‐ChltMyers  

City  of  New  Bern  

Coastal  Carolina  Community  College  

College  of  the  Albermarle  

Craven  Community  College  

Craven  County  Government  

Craven  County  Schools  

Cumberland  County  Schools  

Daymark  Recovery  Services  –  Archdale  Center  

Daymark  Recovery  Services  –  Hoke  Center  

Daymark  Recovery  Services  –  Lee  Center  

Daymark  Recovery  Services  –  Rockingham  Center  

Daymark  Recovery  Services  –  Vance  Center  

Daymark  Recovery  Services  –  Wake  Center  

Daymark  Recovery  Services  –  Harnett  Center  

Department  of  Justice  –  ITS  –  MCNCDCS-­‐RaleighDep  

Department  of  Justice  –  ITS  –  MCNCDCS-­‐RaleighWest  

Duke  University  –  DukeAlex-­‐DukeNorth  

Duke  University  –  RTP-­‐Duke-­‐Naan  

Durham  Public  Schools  

Durham  Technical  Community  College  –  Hillsborough  

Durham  Technical  Community  College  –  Lawson  St  Main  

Campus  

1-­‐99.239  

1-­‐99.46  

1-­‐99.123  

Durham  Technical  Community  College  –  North  Satellite  Campus   1-­‐99.48  

Durham  Technical  Community  College  –  Northgate  Mall   1-­‐99.89  

Durham  Technical  Community  College  –  South  Bank  Building  

Eastern  NC  School  for  the  Deaf    

1-­‐99.41  

1-­‐99.164  

1-­‐99.179  

1-­‐99.218  

1-­‐99.229  

1-­‐99.177  

1-­‐99.165  

1-­‐99.245  

1-­‐99.32  

1-­‐99.124  

1-­‐99.159  

1-­‐99.104  

1-­‐28.911  

1-­‐99.256  

1-­‐99.64  

1-­‐28.910  

1-­‐99.149  

1-­‐99.136  

1-­‐99.214  

1-­‐99.133  

1-­‐99.168  

1-­‐99.151  

1-­‐99.227  

1-­‐99.249  

1-­‐99.251  

1-­‐99.259  

1-­‐99.253  

1-­‐99.254  

1-­‐99.228  

1-­‐99.250  

1-­‐19.910  

1-­‐20.911  

26-­‐40.910  

1-­‐99.122  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  6  

 

Edenton-­‐Chowan  County  Schools  

Elizabeth  City  State  University  

Elizabeth  City-­‐Pasquotank  County  Schools  

Elon  University  

Elon  University  –  Data  Center  #1  

Elon  University  –  Data  Center  #2  

Englehard  Medical  Center  

Exploris  Middle  Charter  

Fayetteville  State  University  –  Seymour  Johnson  AFB  

First  Flight  Venture  Center  

Franklin  County  Schools  

Gates  County  Schools  

Global  Scholars  Academy  Charter  School  

Governor  Morehead  School  for  the  Blind  

Granville  County  Schools  

Hamner  Institutes  for  Health  Sciences  

Hertford  County  Schools  

Hyde  County  Schools  

Information  Technology  Services  –  NCTN  Trunk  to  RTP  RPoP  

Johnston  Community  College  

Juniper  

Kestrel  Heights  Charter  

Louisburg  College  

Magellan  Charter  School    

Martin  Community  College    

Martin  County  Schools  

Mayland  Community  College  

MCNC  Data  Center  –  RaleighWest  

MCNC  Data  Center  –  WSA1A  Primary  

MCNC  Data  Center  –  WSA1A  Secondary  

MCNC  Data  Center  Services  

Meredith  College  

Mooresville  Graded  School  District  

Mount  Olive  Medicine  Center  

Nash  Community  College  

Nash  Health  Care  Systems  

National  Humanities  Center    

National  Institute  of  Statistical  Sciences  #1  

National  Institute  of  Statistical  Sciences  #2  

NC  Biotechnology  Center  #1  

1-­‐99.215  

1-­‐99.207  

1-­‐99.88  

1-­‐99.107  

1-­‐99.163  

1-­‐99.209  

1-­‐99.45  

1-­‐99.85  

1-­‐99.195  

1-­‐99.204  

1-­‐99.210  

1-­‐20.910  

1-­‐3.911  

1-­‐3.912    

1-­‐1.9  

1-­‐99.14  

1-­‐99.191  

1-­‐99.196  

1-­‐99.193  

1-­‐99.255  

1-­‐78.910  

1-­‐78.911  

1-­‐99.226  

1-­‐99.148  

1-­‐99.12  

1-­‐99.134  

1-­‐99.212  

1-­‐99.222  

1-­‐99.132  

1-­‐99.109  

1-­‐99.198  

1-­‐99.128  

1-­‐99.217  

1-­‐99.182  

1-­‐99.153  

1-­‐99.166  

1-­‐99.53  

1-­‐99.52  

1-­‐99.5  

1-­‐99.56  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  7  

 

NC  Biotechnology  Center  #2  

NC  Central  University  –  to  RTP  RPoP  

NC  Independent  Colleges  and  Universities  

NC  Rural  Economic  Development  Center  

NC  State  University  –  RTP-­‐NCSUHills  

NCSU  -­‐  Center  for  Marine  Sciences  and  Technology  (CMAST)  

NCSU  Tape  Library  –  MCNCDCS-­‐NCSUCMDF  

NCSU  Tape  Library  –  MCNCDCS-­‐NCSUHills  

New  Hanover  County  IT  Library  

New  Hanover  Regional  Medical  Center  

NOAA  NOS  

North  Carolina  School  of  Science  and  Mathematics  

North  Raleigh  Christian  Academy  

Onslow  County  Schools  

Orange  County  Schools  

Partnership  for  Defense  Innovation  

Perquimans  County  Schools  

Person  County  Public  Library  

Piedmont  Community  college  

Piedmont  Health  Services  –  Carrboro  

Piedmont  Health  Services  –  Charles  Drew    

Piedmont  Health  Services  –  Pittsboro  

Piedmont  Health  Services  –  Senior  Care  

Raleigh  Charter  High  School  

Ravenscroft  School  

Red  Hat  

RENCI  –  RalDep  to  NLR  

RENCI  –  to  RTP  

Research  Triangle  High  School  

River  Mill  Academy  

Roanoke  Rapids  City  Schools  

Roanoke-­‐Chowan  Community  College  

Robeson  Community  College  –  Pembroke  Campus  

RST  Fiber  Optic  Network   –  Lincolnton  to  Hyde  L2  P2P  

RST  Fiber  Optic  Network   –  Lincolnton  to  Williamston  L2  P2P  

RTI  

Saint  Augustine's  University  

SAS  Institute  

Shaw  University  

Shodor  Education  Foundation  

1-­‐99.192  

1-­‐99.183  

1-­‐99.201  

1-­‐99.172  

1-­‐99.176  

1-­‐99.231  

1-­‐99.174  

1-­‐99.101  

1-­‐99.19  

1-­‐99.144  

5-­‐23.911    

1-­‐99.71  

1-­‐99.135  

1-­‐99.93  

1-­‐99.194  

1-­‐99.220  

1-­‐99.4  

1-­‐99.37  

1-­‐99.17  

1-­‐99.11  

1-­‐99.72  

1-­‐99.143  

1-­‐14.910  

1-­‐21.910  

1-­‐99.185  

7-­‐99.18  

1-­‐99.203  

1-­‐99.70  

1-­‐99.15  

1-­‐99.155  

1-­‐99.152  

1-­‐99.82  

1-­‐99.171  

46-­‐72.01  

46-­‐74.01  

1-­‐99.142  

1-­‐99.75  

1-­‐99.181  

1-­‐99.40  

1-­‐99.106  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  8  

 

South  Piedmont  Community  College  –  Polkton  Campus  

Southeastern  Baptist  Theological  Seminary  

Southeastern  Regional  Medical  Center  

St.  David's  School  

Sterling  Montessori  Charter  School  

The  Institute  for  the  Development  of  Young  Leaders  

Town  of  Chapel  Hill  –  Martin  Luther  King  Jr  Blvd  

Triangle  Math  and  Science  Academy  

Tyrrell  County  Public  Schools  

UNC  Chapel  Hill  –  Chlt-­‐UNCManning  

UNC  Chapel  Hill  –  UNCPhillips-­‐UNC54  

UNC  Charlotte  –  UNCAtkins  to  MCNC  Data  Center  

UNC  Charlotte  –  UNCRUP  to  MCNC  Data  Center  

UNC  Coastal  Studies  Institute  

UNC  Healthcare  –  Meadowmont  to  RTP  via  UNC  Manning  

UNC  Pembroke  –  to  RTP  RPoP  

UNC-­‐Chapel  Hill  Institute  of  Marine  Sciences  to  UNC  Manning  

P2P  

UNC-­‐General  Administration  –  (main  floor  215)  (Backup  

Connection)  

UNC-­‐General  Administration  –  MCNC  Data  Center-­‐UNCManning  

L2  

UNC-­‐General  Administration  –  MCNC  Data  Center-­‐UNCPhillips  

L2  

UNC-­‐General  Administration  –  RTP-­‐UNCManning  L3  

UNC-­‐TV  via  Data  Center  

Urban  Ministries  of  Wake  County  

Vance  County  Public  Schools  

Vance-­‐Granville  Community  College  

Vidant  Health  Beaufort  (Washington)  L2  

Vidant  Health  Bertie  (Windsor)  L2  

Vidant  Health  Chowan  (Edenton)  L2  

Vidant  Health  Greenville  L2  

Vidant  Health  Outer  Banks  (Naghead)  L2  

Vidant  Health  Roanoke-­‐Chowan  (Ahoskie)  L2  

Voyager  Academy  

Wake  County  Government  –  to  RTP  RPoP  

Wake  County  Schools  

Wake  Technical  Community  College  

Warren  County  Schools  

Washington  County  Schools    

Wayne  Community  College  

1-­‐99.167  

1-­‐99.126  

1-­‐99.125  

1-­‐99.100  

1-­‐99.162  

1-­‐99.216  

1-­‐99.232  

1-­‐99.205  

1-­‐99.206  

2-­‐99.79  

24-­‐36.910  

1-­‐29.910  

1-­‐30.910  

1-­‐99.186  

1-­‐99.230  

1-­‐99.161  

99-­‐99.43  

1-­‐99.94  

1-­‐25.912  

1-­‐24.910  

1-­‐99.175  

1-­‐99.246  

1-­‐99.97  

1-­‐99.199  

1-­‐99.184  

74-­‐99.02  

74-­‐99.01  

70-­‐99.01  

8-­‐99.29  

71-­‐99.01  

69-­‐99.01  

1-­‐99.47  

1-­‐99.10  

1-­‐99.224  

1-­‐99.158  

1-­‐99.190  

1-­‐99.202  

1-­‐99.197  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  9  

 

Wayne  County  Schools  

WebAssign  –  LAN  

WebAssign  –  VoIP  

William  Peace  University  –  to  RTP  RPoP  

Willow  Oak  Montessori  

Wilson  Community  College  

 

Wilson  County  School  District  

Woods  Charter  School  

1-­‐99.221  

1-­‐99.233  

1-­‐99.234  

1-­‐99.98  

1-­‐99.208  

1-­‐99.150  

1-­‐99.154  

1-­‐99.119  

MCNC  DATA  CENTER  CONSTITUENTS  THAT  EXPERIENCED  AN  INTERRUPTION  OF  

SERVICE  

 

Bams  Hosting  

CASC  

CFCC  

Campbell  

Catawba  Hosting  

City  of  Ral  Fixd  

DOJ  

Duke  Psychiatry  

Durham  Public  Schools  

Greensboro  College  

ICAN  Fixed  

ICAN  Fixed,  NewTeacherCtr  

ITS  

Learn  NC  

Mecklenburg  

NC  Live  

NCCU  

NCCU  DR  

NCHA  

NCICU  

NCSSM  Hosting  

NCSU  DELTA  WebCT  Vista  Hosting  

NCSU  Off  of  Ext  Tech  Svcs  

NCSU  VCL  

NCVPS  

NDG  

NewTeacherCtr  

ONET  Hosting  

Priveon  

RTI  

Remote  Learner  

Sandhills  CC  

Shaw  Univ  

St  Aug  

Surya  Technologies  

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  10  

 

TRLN  

Tape  Backup  Ntl  Humanitie  

TapeBack-­‐upNC  RuralEconCn  

TrustedMetricsLLC  

UNC-­‐C  

UNC-­‐C  VirtualHstg  

UNC-­‐CH  LEARN  NC  

UNC-­‐Char  Mgd  Hstg  

UNC-­‐GA  Dell  Banner,  Puredisk  UNC-­‐GA  

UNC-­‐GA  Dell  Banner,  UNC-­‐GA  SUN  Banner  

UNC-­‐GA  SUN  Banner  

UNC-­‐GA,  UNCGA-­‐LEARN  NC  Hosting  

UNC-­‐W  Hosting  

UNCFSU  

UNCGA  

UNCW  Hosting  

WebAssign  Hosting  

  e-­‐NC   eLearning  Commission  

Prepared  by  Jeremy  Buenviaje,  Matt  Valenzisi  

Reviewed  by  Joe  Freddoso,  Tommy  Jacobson,  Ray  Suitte  

 

2014-­‐04-­‐11  NCREN  Optical  Node  Outage  -­‐  RTP  Postmortem  FINAL.docx

  11  

Download