Stephanie McGregor

advertisement

1

UK’s Offshore

Transmission Regime:

A case study for financing a low carbon future

Stephanie McGregor

Director Offshore Transmission

June 2011

www.ofgem.gov.uk

Today’s presentation

1.

Big picture

2.

The OFTO

3.

Making the opportunity real

(aka fundable)

4.

Opportunities/challenges ahead

All you can see in 30 mins!

www.ofgem.gov.uk

Critical developments & debates…

Electricity

Market

Reform

Climate change targets

Retail

Market

Review RO review

EU

Renewable

Energy

Directive

European

Intergration

Significant challenges ahead

www.ofgem.gov.uk

…grand ambitions…

UK energy policy aspirations:

• Meeting the 2020 Renewable energy commitment;

• Decarbonisation of electricity by 2030;

• 2050 carbon pathways;

• Marine renewable generation – potentially up to

67GW installed by 2030;

• Nuclear – could have a significant role in decarbonisation.

This will require significant new transmission infrastructure.

Similar aspirations across Europe

www.ofgem.gov.uk

….and a universal challenge for a low carbon future…

www.ofgem.gov.uk

….securing investment

!

Estimates - £200bn +

Capital markets fragile

Market players seeking certainty

(

investors, funders, developers, operators, suppliers….

)

Challenges & opportunities ahead

Xx

OFTO regime

Implementing a model which is…

www.ofgem.gov.uk

...attracting/delivering investment

www.ofgem.gov.uk

What is the OFTO opportunity?

• So what is an OFTO again?

• How do we select an OFTO?

• How does the OFTO licence work?

• Offshore Transmission Owner

(OFTO)

• An entity licensed to provide transmission services

• The owner and operator of the assets relevant to provide the transmission services

• Market activity to date

Xx

What is an OFTO (2)?

Onshore

TO

Offshore Transmission Owner (OFTO)

Licencee

Connection to onshore network

Onshore

Substation www.ofgem.gov.uk

Generator

Offshore Substation

Platform

Subsea cable

132 kV

33 kV Inter Array Cables

www.ofgem.gov.uk

How do we appoint an OFTO ?

• Developer project qualified by Ofgem

˜ financial commitment

˜ detailed data provision

• Ofgem run a competitive process - defined stages & requirements

• Project specific & revenue (20 year) based bidding

• Identified project, known transfer value & clear licence obligations

• Accessible to range of funding approaches

Pre-qualification (PQ)

Pass/fail

Long list of bidders

Qualification to Tender

(QTT)

Scored

Short list of 3-5 bidders

T) (IT

Sco er nd to te on ati vit In

Preferred Bidder &

Successful Bidder

Licence

Grant

The OFTO Licence - how does it work?

1. Obligations

OFTOs are required to:

• achieve the broad obligation to operate assets in line with industry best practice to minimise the effect and duration of any transmission outage

• report details of any service reduction over 21 days

• provide written statement of compliance with best practice if availability below 75% in a year or 80% over two years

This creates an obligation to repair assets

If does not comply, enforcement action could be significant - licence revocation www.ofgem.gov.uk

www.ofgem.gov.uk

OFTO Licence - how does it work?

2. Incentives

• Not to compensate generator for lost revenue – disproportionate

• Incentive designed to encourage behaviour to maintain availability

• OFTO faces reduced revenue if it fails to meet availability target

• Incentive significantly reduces equity returns in case of major outage – does not put OFTO at risk of breaking minimum cover ratios

Design

• Availability target set at 98%

• Revenue uplift for good performance

• Monthly weighting

• 50% of OFTO revenue is at risk for performance below the target in a year

• Revenue impact is spread over five years

Xx

OFTO Licence - how does it work?

3. Enforcement

Authority can take enforcement action against licensees that:

• Contravene licence conditions

• Are likely to contravene licence conditions

Enforcement actions can include:

• Enforcement orders

• Fines

• Licence revocation

Therefore up to 100% of revenue is at risk!

www.ofgem.gov.uk

Making the opportunity real

(aka fundable) www.ofgem.gov.uk

• Clear commercial & regulatory structure

• Transparent & clear process

• Accessible to different funding approaches

• Project pipeline

KEY = CERTAINTY

www.ofgem.gov.uk

Commercial & regulatory structure

Licence

NETSO

O&M

Contract

Government

Consents

Sale &

Purchase

Agreement

Code s

OFTO

Offshore Generator

Transmissio n Licence

Lease

Lease

Crown

Estate

Generation Licence

Ofgem

www.ofgem.gov.uk

Key investment features

Attractive investment sector

Robust new regulatory regime

Transparent competitive process

 Strong UK political & regulatory support

 Rare opportunity for new entrants to UK transmission sector

 Relatively low risk asset class

 20 year revenue stream with limited regulatory intervention

 Pass through of certain key costs

 OFTO protected from wind farm operating risk & risk of stranding

 Upside potential: opex, non-regulated services, increased capacity

 Well defined tender process,

 Structured to ensure level playing field & transparency

 2 qualification stages followed by ITT stage with M&A data rooms

Long term opportunity

 A number of phases over several years: potentially £15 bn of assets

 Early participation will provide valuable experience

 Enduring regime offers design & construction opportunities

www.ofgem.gov.uk

Project pipeline

• Linked to Crown Estates R1, R2 & R3 Zones

• Early tender rounds transitional rounds (TR1, 2a & 2b)

• Under enduring regime it will be developer/generator requirements & choices that influence timing & model for opportunities come to market.

• Enduring regime = generator choice of generator build or ofto build.

• Extensive engagement with generation developers on developing plans

35

OFTO pipeline

2009 2010

Final

Consultation

30

Go-Active

25

20

First Transitional

Tender Process (£1bn+)

2011

15

10

5

Cumulative

UK Offshore

Wind

Capacity

(GW)

Go-Live

2nd Transitional

Tender (up to £2bn+)

Enduring Regime Tender Process

(£12bn+)

2020

0

www.ofgem.gov.uk

Tender Round 1

Project

Robin Rigg (FC/Licensed March

‘11)

G.Sands (S.8A con closed June ‘11)

Barrow

Ormonde

Preferred Bidder/OFTO

• Transmission Capital Partners

(TCP)

Thanet

Walney 1

Walney 2

Sheringham Shoal

Greater Gabbard

Value = £1.1bn & circa 2GW

• Balfour Beatty

• Macquarie

• Green Energy Transmission

(Equitix, Balfour Beatty, AMP)

Savings forecasts positive

Tender Round 2

Humber Gateway

(300MW £218m)

Race Bank

(up to 620MW c.£500m)

West of Duddon Sands

(389MW £255m)

Lincs

(250MW £311m)

Gwynt-y-Mor

(576MW £306m)

London Array

(630MW £476m) www.ofgem.gov.uk

Tranche 2a Projects

(1.5GW & £975m est. value)

TR2a bidders:

• TCP

• Blue Transmission

(Macquarie/Mitsubishi

)

• Green Energy

Transmission (Balfour

Beatty & Equitix)

• National Grid

Offshore Ltd

Expected Tranche 2b Projects

(1.3GW & £1m+ est. value)

www.ofgem.gov.uk

Opportunities & challenges ahead

• Rapid market development

• Moving into the enduring regime – generator choices

• Co-ordination – enhancement

• Wider policy landscape

www.ofgem.gov.uk

Market development

• Market evolving rapidly on bidder & developer sides

• Interest strong to date

• Bidder/consortium configurations evolving

• Market awareness & understanding increasing, breadth & depth in growing phase – bidders & generators

• Particular interest in larger asset opportunities – interest expressed from potential future new entrants

• Bidder/partnering approach may need to evolve for enduring depending on how projects come to market

• Understanding of technology options, innovations & constraints

www.ofgem.gov.uk

Coordinated offshore transmission development

• Ofgem/DECC announced coordination workstream in August 2010 to focus on opportunities for enhancing co-ordination within the offshore transmission regime

• Offshore Transmission Coordination Advisory Group (OTCG) established & work underway with inputs from Stakeholder Community

• Ofgem/DECC conclusions to be informed by a range of evidence & analysis

• Assessment of options which emerge will relate to how they perform against Ofgem & Government objectives & statutory obligations

• Any proposals that are set out in our conclusions report would be subject to public consultation

www.ofgem.gov.uk

…and there are major challenges ahead

Investment challenge:

• Significant capital requirement - £200 billion+ over the next decade to meet our aspirations;

• Capital markets fragile;

• Investors need certainty and stability

• Impact on developers?

• Impact on supply chain?

Future still very uncertain:

• Political uncertainty – eg impact of EMR proposals;

• Scale and timing of onshore development – what role will nuclear play;

• Scale and timing of offshore development – ODIS scenarios has a broad range 25-

67GW.

Network development:

• Long lead time to deliver new capacity;

• Supply chain readiness – volume of new tech.

What is the appropriate network configuration?

25

THANK YOU

Download