DETAILED WORK PLAN CONSULTING SERVICES FOR THE COMPLETION OF THE TRENT RIVER CROSSING AND ARTERIAL ROAD NETWORK ENVIRONMENTAL ASSESSMENT, TRENT HILLS FINAL DRAFT October 22, 2012 IBI GROUP FINAL DRAFT TABLE OF CONTENTS 1. INTRODUCTION ...................................................................................................................... 1 1.1 Background ........................................................................................................................................... 1 1.2 Objective ................................................................................................................................................ 1 1.3 Approach................................................................................................................................................ 1 1 . 3 .1 P r o d u ce an u p d at ed Envi r o n m ent al S t u d y R ep o rt ( E SR) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 1 . 3 .2 Co m p l y w it h m u n ic ip a l cl a s s e a p ro ce s s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 1 . 3 .3 M a x im i z e Exi st in g Inf o rm at io n . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 1 . 3 .4 Us e U p d at e t e ch n i c a l inf o rm at ion w h e r e req u i r ed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 1 . 3 .5 En s u r e E f f e ct iv e C o m m u n it y Eng ag em en t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 1 . 3 .6 Av o id an y p ie c em e al in g . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 1.4 Assumptions and Conditions............................................................................................................... 4 2. DETAILED WORK PLAN TASKS ........................................................................................... 5 3. EA COMPLETION SCHEDULE ............................................................................................. 20 4. EA COMPLETION BUDGET .................................................................................................. 21 Page i. IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 1. INTRODUCTION 1.1 Background In 2007 the County of Northumberland retained an engineering consulting firm, Totten Sims Hubicki (now AECOM), to carry out a Schedule “C” Municipal Class Environmental Assessment (EA) study which at that time was called the Additional Trent River Crossing. Over a two-year period the study progressed through the four phases of the Class EA process, culminating in a report with recommendations to construct a new bridge along the Second/Alma corridor. In December 2009, County Council deferred a decision on that EA, put it on hold, and directed staff to further investigate the feasibility and cost of an additional bridge within the existing Bridge Street corridor. In April 2010 County Council retained GENIVAR Consultants to carry out a Feasibility Study which was completed and submitted to County Council in July 2012. The Feasibility Study recommends widening the existing Campbellford Bridge to accommodate three travel lanes and a recreation trail. The purpose of the assignment document in this Detailed Work Plan is to describe how to resume and complete the EA process to address Trent River crossing and related arterial road network needs in Campbellford for the next 20 years and beyond. The County has retained IBI Group to provide expert and objective advice on how to complete the EA process. 1.2 Objective The objective in recommencing what is recommended be entitled “The Trent River Crossing and Arterial Road Network Environmental Assessment” (EA) in the Municipality of Trent Hills is to successfully complete the provincial EA process by the end of June 2013. This process is required in order to construct any river crossing and arterial network improvements in the former town of Campbellford. The staging and scheduling of these improvements can be implemented based on funding commitments, development opportunities and transportation needs in the town. However, the first stage of construction must begin within ten years from the posting of the Notice of Study Completion, although construction completion has no time limit. This planning of transportation improvements in Campbellford is critical to ensuring that the town remains a single, cohesive community well into the future, with the Trent River as its core rather than a barrier. Both sides of the river must continue to be linked together as part of an effective local transportation network in order to enhance resident mobility, safety and quality of life, and to support economic vitality and resident services for Campbellford and area residents. To implement this prime objective, a Municipal Class EA must be completed that complies with the provincial Municipal Class EA process for Schedule ”C” and “B” projects, and with federal Canadian EA Act requirements as amended in 2011. 1.3 Approach IBI Group’s approach to this assignment was first presented in our proposal dated August 14, 2012, and refined as follows based on preliminary backgrounder meetings with the County, Municipality and Eastern Region of the Ministry of the Environment (MOE). IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 1 . 3 . 1 P R O D U C E A N U P D A T E D E N V I R O N M EN T A L S T U D Y R E P O R T ( E S R ) The updated ESR document needs to be a stand-alone report. It will include a summary of all work tasks conducted as part of the 2009 Final Draft ESR and the 2012 Feasibility Study, with references to these documents where required. This will be augmented with new updated and expanded information prepared as part of the EA completion. This new ESR will cover all topics, and with details on all changes since the 2009 report including summaries of previous findings that do not change. The 2009 and 2012 reports will be separate documents. 1 . 3 . 2 C O M P L Y W I T H M U N I C I PA L C L A S S E A P R O C E S S It has been confirmed with MOE that since the Municipal Class EA process is proponent-driven, the County as the proponent can determine how best to complete the EA. The basic EA principles to be followed in doing this are: Objective by starting the EA recommencement with no pre-conceived solution preferences; Reasonable by considering only reasonable, meaning “feasible” alternatives; Consultative with all affected parties and the general public; Systematic in how impacts on all aspects of the environment are evaluated; and Traceable in how this decision-making process is documented. 1 . 3 . 3 M A X I M I Z E EX I S T I N G I N F O R M A T I O N A considerable amount of work has gone into plans for the Trent River crossing. Some of this work, such as the 60% design review of a new bridge at the existing crossing, has even extended into the detail design stage. Much of this existing information can be incorporated into the EA completion in order to avoid cost duplications, minimize EA completion timing and maximize the use of relevant information already conducted for the project. MOE has also confirmed that since a Final Draft ESR was presented to the public in late 2009, and again in May and September of 2011 focusing on the existing Campbellford Bridge alternatives, further consultation and PICs should deal only with new information, and not repeat information and decisions previously made unless they relate to the ESR update. We recommend that the decision on what information to incorporate into the new process be confirmed with the Ministry of the Environment as part of the recommencement initiation. However, some information will require updating. 1 . 3 . 4 U S E U P D A T E T E C H N I C A L I N F O R M A T I O N W H ER E R EQ U I R E D Three types of previous technical information will need to be updated, namely: Traffic data on volumes, travel patterns and Level-of-Service to update the Problem / Opportunity Statement, including an expanded community-wide traffic analysis; Relevant provincial/federal policies on which the EA process is based; and The evaluation process conducted for the 2009 EA and 2012 Feasibility Study. Page 2 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 1.3.5 ENSURE EFFECTIVE COMMUNITY ENGAGEMENT To recommence this EA process, a proactive and continuous engagement process with involved agencies, stakeholders and members of the public will be required. Based on the project history, a high degree of project interest and community engagement is expected early and continuously through the EA process. This interest must be encouraged as “positive engagement”, rather than dwelling on past experiences, issues and concerns. To do this, community engagement will involve the following principles: Follow the Municipal Class EA planning principles involving objectivity and traceability in the planning process; Contact the community early in the recommencement to explain the project, the completion process and how the community can provide input. This can be done with media notices, press releases and circulation of a project update newsletter; Meet all mandatory consultation requirements required for Phases 1 to 4 of the Schedule C Municipal Class EA Process. During the 2007/09 study, all these requirements were met by the three Public Information Centres (PICs) and associated consultation activities conducted at that time; Provide convenient ways for the public to provide meaningful input to the study through various opportunities including a project web site; Maintain a consistently open, objective and traceable dialogue with interested agencies, stakeholders and members of the public. Proactively respond to their ideas and issues, and minimize any misunderstandings that can negatively impact the EA process; Rely on organized stakeholder groups, organizations and agencies to provide coordinated, efficient and cost-effective input and feedback to the project; and Work interactively with the Steering Committee and Project Team so they understand all alternatives, the selection of the preferred EA solution and have the opportunity to shape it. 1.3.6 AVOID ANY PIECEMEALING The provincial EA process defines piecemealing as the breaking up of a larger project into smaller component parts so each can be dealt with separately. In the case of the Trent River Crossing and Arterial Road Network EA, separation of any arterial road network changes relating to the river crossing would constitute piecemealing and would not comply with the EA Act. The EA completion avoids this situation by including the “Arterial Roadway Network” as part of the new EA process. This means that in addition to the actual Trent River crossing works, the EA will include any associated improvements needed at key arterial intersections. The community-wide traffic analysis will assist in identify network improvements that are required as a result the crossing improvement, and others that are required in response to other traffic changes in the community. These other traffic changes may require only a Schedule “B” or even pre-approved Schedule “A+” EA approach, so they may not need to be included in the Schedule “C” process. Page 3 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 1.4 Assumptions and Conditions 1. The scheduling objective of this assignment is to present the Final Draft ESR document to County and Municipality Council in June, 2013. The subsequent timing of EA completion after that will be determined by Council decisions on the study recommendations and public response following the Notice of Study Completion; 2. Full involvement of the OPP, with the authority to stop traffic, will be required in order to conduct an intercept-type of Origin-Destination traffic survey; 3. Scheduled technical meetings with the Project Team and progress meetings with the Steering Committee will be held on the same day; 4. Decisions of the Steering Committee will be made based on the Committee’s Terms of Reference, (June 2012); 5. IBI Group will use and make reference to all previous consultant reports, designs, notes and other technical information relating to this assignment; 6. The EA completion will be directed by the Steering Committee, with the Ontario Ministry of the Environment and other external agencies providing support services as required; and 7. The focus of all public information and ESR preparation will be on new, expanded or updated information. The EA completion will not be a venue to question or reassess the 2009 EA process or subsequent approval of the 2012 Feasibility Study. 1.5 Role of Steering Committee To direct all aspects of the EA study through to completion, and to make joint recommendations to the Councils of the Municipality of Trent Hills and Northumberland County. The Steering Committee has no formal decision-making authority. It will provide advice and make recommendations to the two municipal Councils that do have decision-making authority. 1.6 Role of the Project Team The Project Team, comprised of County and Municipality staff representatives and IBI Group staff, will provide a technical review of all EA study research, findings, conclusions and recommendations, including identification of issues to be resolved either before or at Steering Committee meetings. Page 4 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 2. DETAILED WORK PLAN TASKS TASK 1 – RECOMMENCED CONSULTATION Rationale: To reintroduce the study to external agencies, stakeholders, members of the public and the media explaining the new completion process, why the study was put on hold, new information and how to get involved. Existing Documentation: Previous Steering Committee minutes and subsequent County staff reports. Sub-Tasks: Prepare draft newsletter and media release for Project Team approval; Prepare draft Notice of Study Re-Commencement for Project Team approval; and Prepare draft re-commencement letters to previously contacted external agencies and stakeholders, including the Canadian Environmental Assessment Agency (CEAA) confirming what new role they may play in the study. Completion Schedule: Submit draft newsletter and media release to Municipality of Trent Hills council for information at November 20, 2012 meeting, and to County Council on November 21, 2012 for decision. Assuming County Council approves and authorizes commencement of this assignment on November 21st, preliminary consultation material should be published and circulated by November 31, 2012 Key Staff Assignment: D. Drackley, M. Radue Deliverables: Finalized preliminary consultation newsletter, notification letters and media notice. Budget: $4,000 EA PHASE 1: PROBLEM OR OPPORTUNITY TASK 2 – CONSULTATION: COMMUNITY OUTREACH Rationale: Completing the Trent River crossing and Arterial Road Network EA is expected to generate considerable local interest. Therefore, an open and continuous consultation process is required. Similar to the 2008/09 EA process, members of the public and interest groups will have the opportunity to ask questions and offer comment throughout the process. This consultation community outreach task is needed so that the consulting team can assist the County and Municipality in responding to this expected community interest. Existing Documentation: None Sub-Tasks: Prepare draft responses to questions and comments from the public and groups; Prepare project update material for a study web page of the County’s web site; and Liaise with local media as required. Completion Schedule: Continuous through the EA process. Key Staff Assignment: D. Drackley and consulting team members as required. Deliverables: Draft response materials Budget: $10,000 (based on 50 hours) Page 5 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 3 – UPDATE PROBLEM / OPPORTUNITY STATEMENT Rationale: Ensure the Problem Statement is up-to-date as it relates to the existing Campbellford Bridge traffic volumes, traffic Level-of-Service during the peak vs. off peak periods and seasons and the structural condition of the bridge. Expand information on the opportunities provided by improved long-term Trent River crossing capability in the Campbellford area, and related improvements to the arterial road network for example involving emergency response, accessibility, community cohesiveness and downtown urban design. Existing Documentation: August 2009 Final Draft ESR:1 Section1.3 Problem and Opportunity Statement Section 3.0 Future Conditions Section 4.0 Need and Justification Sub-Tasks: Task 3A: Updated Traffic Data Collection Task 3B: Updated Existing Arterial Road Network Traffic Conditions Task 3C: Travel Origin-Destination Survey Task 3D: Updated Traffic Forecasts Completion Schedule: See Tasks 3A, 3B, 3C and 3D Key Staff Assignment: S. Johnston, A. Ortlieb Deliverables: Updated ESR Sections on: Problem / Opportunity Statement Existing arterial road network transportation conditions Future traffic conditions Budget: $48,100 (Task 3A-3D) TASK 3A – UPDATED TRAFFIC DATA COLLECTION Rationale: Enhance acceptability of existing traffic condition information by using current traffic turning movement data at strategic arterial road network intersections. Existing Documentation: New traffic data will replace data reported in 2009 ESR document. Sub-Tasks: Confirm 15 strategic intersection locations for turning movement counts; Retain sub-consultant to conduct counts and document results; and Discuss emergency response conditions with Police, Fire and Ambulance officials. Completion Schedule: December 7, 2012 Key Staff Assignment: S. Johnston, traffic data collection sub-consultant Deliverables: Current off-season (off-peak) turning movement counts and factored summer season counts at 1 Additional Trent River Crossing Schedule “C” Class Environmental Assessment, Environmental Study Report, AECOM Canada Ltd., August 2009. Page 6 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 3A – UPDATED TRAFFIC DATA COLLECTION strategic arterial road network intersections. Budget: $3,000 plus $5,250 traffic data collection (15 locations) TASK 3B – UPDATED EXISTING ARTERIAL ROAD NETWORK TRAFFIC CONDITIONS Rationale: To review and evaluate existing and future traffic conditions in the Campbellford arterial roadway network associated with short-listed Trent River crossing alternatives, and to account for growth and changes to traffic conditions since 2009. Existing Documentation: Traffic analysis from 2009 ESR Sub-Tasks: Review 2009 ESR traffic analysis in detail; Identify, with Task 3A, additional intersections for analysis; Develop Synchro / HCS analysis of intersections and prepare Level-of-Service output; Assess seasonal variation in traffic flow; Review emergency response conditions and compare to provincial targets; and Document any deficiencies. Completion Schedule: December 17, 2012 Key Staff Assignment: S. Johnston, C. Hwang Deliverables: Technical memo for existing conditions analysis, to be incorporated into final ESR report. Budget:.$7,000 PROJECT TEAM / STEERING COMMITTEE MEETING #1 Rationale: Review traffic analysis (Tasks 3A, 3B), O-D Survey plan and screening of alternative solutions. Existing Documentation: None Sub-Tasks: Agenda and Minutes; Memo summarizing overall study issues, previous decisions, new information and EA need; Memo describing proposed screening process for alternative solutions including screening criteria; and Other meeting information Completion Schedule: week of January 14, 2013 Key Staff Assignment: D. Drackley, S. Johnston Deliverables: Agenda and minutes; and Approved O-D survey plan Budget: $3,950 Page 7 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 3C – TRAVEL ORIGIN-DESTINATION (OD) SURVEY Rationale: Provide solid data from which to analyze potential diversions of traffic to alternative Trent River crossing locations. OD survey will enhance the rationale for the preferred alternative. Existing Documentation: 2009 ESR did not include OD survey. Diversion analysis was based on 1996 report. Sub-Tasks: Study Initiation and Research – Meet with all stakeholders including representatives of the Municipality, Northumberland County, Ontario Provincial Police (OPP) downtown BIA and Chamber of Commerce to review the survey. Develop detailed Survey Plan including draft survey form and survey dates (with backup dates for bad weather). Solicit input on survey design from stakeholders. Confirm what approvals are necessary to conduct survey. Survey Preparation – Organize survey staffing consisting of supervisor and surveyors. Initiate approvals with OPP, County and Municipality. Conduct a field investigation to finalize survey procedures. Train field personnel of survey procedures and safety precautions. Notify the public through use of “Upcoming Traffic Survey” signs and media coverage. Conduct Survey – includes the following (preliminary, subject to change): o Confirmation of OPP management of traffic intercept role using Paid Duty officer(s). o Survey will be run from 7 AM to 7 PM on one weekday followed by one weekend-day, with a target to survey 10% of vehicles per day. o An OPP officer will be stationed on Bridge Street westbound, near the intersection with Queen Street / Grand Road. Officer will intercept westbound vehicles and direct drivers to turn right (north) onto Queen Street. Second OPP officer and survey team will be located on Queen Street north of Bridge Street to receive vehicles. Interviews will be conducted on road shoulder. o Drivers will be informed of the survey and told that participation is voluntary. Drivers will be informed of privacy policy. Drivers can leave if desired and will be given directions to return to Bridge Street. o Conduct interviews verbally with interviewer recording answers on survey form. Data Coding and Processing – Staff will perform manual entry of survey data. Trip start and end points will be geo-coded (assigned coordinates). Survey database will be cleaned and error-checked. Survey data will be expanded based on traffic counts. Analysis – Trips will be assigned to suitable zone system. Origin-destination (OD) matrix will be developed. Maps indicating travel patterns and volumes will be prepared. Assessment of traffic diversions for bridge alternatives will be coordinated with traffic analysis tasks. Summer traffic volume will be accounted for in the analysis. Develop Origin-Destination Survey Report – Draft report will document all aspects of the survey including adherence to survey plan, error checking, expansion process, and analysis of results. Following review, final report will incorporate comments as necessary. Options to intercept survey would be 1) license plate trace survey or 2) mail-back OD survey. Completion Schedule: Approvals to proceed by January 14, 2013. Complete survey by January 31, 2013. Survey Report submittal February 22, 2013. The option of conducting the survey during the summer would delay the study completion by at least six months. Key Staff Assignment: B. Mori, A. Mori, S. Johnston, D. McElroy, J. Wang. Deliverables: Origin-Destination Survey Report Budget:.$29,350 plus $5,000 OPP Paid Duty and $5,125 OD Survey Expenses/Contingency (Total $39,475) Page 8 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 3D – UPDATE TRAFFIC FORECASTS Rationale: Given new origin-destination data and any updated land use changes (proposed, planned, approved) since 2009, revised traffic forecasts will be developed for each of the short-listed river crossing alternatives. Updated traffic forecasts will be very defendable due to the OD survey. Existing Documentation: 2009 ESR provides forecasts for comparison Sub-Tasks: Import origin-destination matrix from Task 3C; Develop peak period and peak hour factors for time-of-day analysis; Evaluate traffic diversions under each roadway alternative for the base-year (2012); Develop population and employment forecasts and growth rates to expand local trips; Research overall economic growth to expand recreation and vacation trips; and Extrapolate future traffic forecasts for each road network alternative. Completion Schedule: February 22, 2013 Key Staff Assignment: S. Johnston, J. Wang, C. Hwang Deliverables: Technical memo detailing updated traffic forecasts, to be incorporated into final report. Budget: $8,750 EA PHASE 2: ALTERNATIVE SOLUTIONS TASK 4 – UPDATE / EXPAND INVENTORIES Rationale: Ensure that the inventory of existing socio-economic, cultural, natural and archaeological conditions is up to date and covers all alternative solutions. Existing Documentation: August 2009 Final Draft ESR: Section 2.1 Socio-Economic Environment with any updates on growth and development in the town; Section 2.3 Natural Environment to include the existing Campbellford Bridge crossing area; and Section 2.4 Archaeology to include the existing crossing area. Sub-Tasks: Task 4A - Update and expand 2009 ESR Appendix C Natural Environment Site Review Report, Warme Engineering and Biological Services by adding new aquatic inventory in the Campbellford Bridge area; Task 4B – Add Stage 1 Archaeological Assessment of Campbellford Bridge footprint expansion; Task 4C – Add Environmental Noise Assessment of Campbellford Bridge crossing; Task 4D - Add air quality impact assessment; and Update Draft ESR text and Appendices as required. Completion Schedule: All additional inventories completed by January 31, 2013 Key Staff Assignment: D. Drackley Page 9 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA EA PHASE 2: ALTERNATIVE SOLUTIONS TASK 4 – UPDATE / EXPAND INVENTORIES LGL Limited, natural environment Archaeoworks Inc., Stage 1 Archaeological Assessment IBI Group, noise John Chandler, air quality. Deliverables: Updated 2009 Draft ESR Sections 2.1, 2.3 and 2.4 and additional Appendix reports Budget: $37,760 including LGL Limited $12,360, Archaeoworks Inc. $3,500 and J. Chandler $7,000 TASK 4A – UPDATE / EXPAND NATURAL ENVIRONMENT INVENTORY Rationale: Replacement or modifications to the existing Campbellford Bridge, and construction of a new bridge at this location would likely necessitate in-water work which may constitute a harmful alteration of fish habitat. Since no detailed fisheries investigation was conducted in the vicinity of the existing bridge as part of the 2009 ESR, a fisheries investigation is required to supplement previous investigations, including documentation of existing conditions, impact assessment and mitigation and identification of potential compensation strategies. It is expected that the alternative of replacing the existing Campbellford Street Bridge will be based on the analysis and design prepared by GENIVAR as documented in their July 2012 report. Existing Documentation: August 2009 Final Draft ESR: Appendix C Natural Environment Site Review Report Section 2.3 Natural Environment Trent River Crossing in Campbellford Feasibility Report, July 2012 Sub-Tasks: Background information related to fisheries will be collected from the original ESR, the Ministry of Natural Resources (MNR), the Trent-Severn Waterway, the Lower Trent Conservation Authority, the County of Northumberland and the Municipality of Trent Hills. A field investigation will be undertaken at the subject site following the Stream Assessment Protocol for Ontario (MNR 2005). Given the nature of this study area and the availability of existing information on the fish community in the Trent River, no fish sampling is proposed, although a detailed habitat assessment will be performed to document habitat conditions. The sensitivity/significance of the fish habitat at the existing Campbellford Bridge location will be determined in relation to provincial, regional and local municipal policies. Impact analysis will be performed to identify the likelihood and significance of potential adverse effects on fish and fish habitat and to identify impact management measures including avoidance, mitigation, enhancement and compensation. Recommendations will be made for environmental monitoring during and post-construction. The results of the fisheries investigation will be documented in a stand-alone Fisheries Assessment Report. Meetings will be held with regulatory agencies during the study to identify and secure environmental approvals-in-principle required as a result of this project. A total of two meetings with regulatory agencies are included in the work plan. Completion Schedule: Field investigations will be completed by December 1, 2012 assuming authorization to commence work is received in a timely manner. Key Staff Assignment: Grant Kauffman, M.E.S., LGL Ltd. Joseph Cavallo, B. Sc., LGL Ltd. Technicians, LGL Ltd. Page 10 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 4A – UPDATE / EXPAND NATURAL ENVIRONMENT INVENTORY GIS Analyst, LGL Ltd. D. Drackley, IBI Group Deliverables: A stand-alone Fisheries Assessment Report of the existing Campbellford Bridge crossing to document the results of the fisheries investigation. Budget: $12,360 excluding HST assuming: The fisheries investigation will be carried out during a single site visit; and LGL will attend two meetings with regulatory agencies, and any additional meetings are not included in the budget and will be charged as incurred. TASK 4B – EXPAND STAGE 1 ARCHAEOLOGICAL ASSESSMENT Rationale: Ensure than any surface or sub-surface ground disruption beyond the existing Campbellford Bridge shore footprints is included in the archaeology inventory. Existing Documentation: 2009 Final Draft Report Section 2.4 Archaeology ESR Appendix D: Archaeological Assessment ESR Appendix B: Cultural Heritage Assessment Report (no added work required) Sub-Tasks: Stage 1 background research; Archaeological site potential evaluation; and Report preparation to augment April 2008 report. Completion Schedule: Completion by December 31, 2012 Key Staff Assignment: Archaeoworks Inc. Deliverables: Stage 1 report of existing Campbellford Bridge crossing Budget: $3,500 TASK 4C – EXPAND ENVIRONMENTAL NOISE ASSESSMENT Rationale: The Environmental Noise Assessment report prepared by RWDI dated June 3, 2009 covers only the Second Street/Alma Street river crossing alternative preferred at that time. As a result, any comparative noise impact assessment for the existing Campbellford Bridge crossing alternative is not available and needs to be conducted in order to quantitatively compare the noise impacts of the Second/Alma alternative with that of the existing crossing location. Existing Documentation: August 2009 Final Draft ESR: Appendix F Environmental Noise Assessment Sub-Tasks: Follow established Ontario MOE protocol to forecast roadway noise and determine warrants for related noise attenuation; Confirm “noise sensitive areas” associated with the existing Campbellford Bridge crossing area; Use existing and forecasted crossing traffic data at the Campbellford Bridge as input to the most recent Page 11 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 4C – EXPAND ENVIRONMENTAL NOISE ASSESSMENT version of the STAMSON noise forecasting model including the following factors: 1) traffic volume, 2) percentage of medium and heavy trucks, 3) terrain including vertical slope of bridge crossing, 4) traffic speed, and 5) any existing sound barrier; and Compare warranted noise mitigation of existing river crossing with previously preferred Second/Alma alternative. Completion Schedule: Noise forecasting can be conducted once future traffic forecasts across the Trent River as part of the arterial road network analysis have been conducted. Tentative completion by January 31, 2013. Key Staff Assignment: S. Lang, IBI Group Technicians, D. Drackley, S. Johnston Deliverables: Environmental Noise Assessment of the existing Campbellford Bridge crossing to compare with the previous Second Street/Alma Street noise assessment from the 2009 Final Draft ESR. Budget: $7,900 TASK 4D – ADD AIR QUALITY IMPACT ASSESSMENT Rationale: No air quality impacts were investigated as part of the AECOM 2008/2009 EA process. However this impact was identified as a concern by some members of the public and stakeholders during the consultation process in 2010. Furthermore, air quality has become a major impact consideration for most urban transportation projects today. Also, during construction there can be the possibility of short-term air quality impacts, especially in the relatively small context of downtown Campbellford. Traffic congestion generates air quality problems. If improved road capacity can reduce road congestion, it can heave beneficial air quality effects. This should be added to the impact assessment in Campbellford. Existing Documentation: None Sub-Tasks: Confirm existing and future (20 year) traffic Level-of-Service deficiencies in the Campbellford arterial road network as the Do-Nothing alternative; Qualitatively describe air quality impacts of the Do-Nothing alternative based on forecasted traffic growth and river crossing bridge design; Describe air quality mitigation opportunities associated with the Do-Nothing and alternative river crossing alternatives; and Incorporate this new comparative impact evaluation into that prepared as part of the AECOM 2009 ESR. Completion Schedule: January 31, 2013 Key Staff Assignment: John Chandler, A.J. Chandler and Associates Deliverables: Air quality impact report Budget: $7,000 Page 12 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 5 – UPDATE ALTERNATIVE SOLUTIONS AND EVALUATION Rationale: Maintain all alternative solutions from Section 6.1 of the 2009 Draft ESR and add “Improve / Replace Existing Campbellford Bridge” as a feasible alternative solution based on results of the GENIVAR Feasibility Study”.2 Existing Documentation: August 2009 Final Draft ESR:3 Section 6.1 Development and Initial Screening of Alternative Solutions; and Trent River Crossing in Campbellford Feasibility Study (GENIVAR). Sub-Tasks: Document rationale for adding “Improve / Replace Existing Campbellford Bridge”. Prepare visualization renderings of the short-listed finalist solutions; Update screening methodology and criteria for screening alternative solution and selecting short-listed final alternatives; and Update recommendations for arterial road network improvements associated with Campbellford Bridge alternative solution. Completion Schedule: February 22, 2013 Key Staff Assignment: D. Drackley, T. Brumfit, A. Ortlieb, graphics staff Deliverables: Revised 2009 Draft ESR: Section 6.1.1 Traffic Operations Improvements Along Bridge Street; Section 6.1.2 Improve The Existing Bridge on Bridge Street; Section 6.3.1 Planning Alternatives; Section 6.3.2 Initial Evaluation; Section 6.3.3 River Crossing Alternatives; Section 6.3.4 “Improve / Replace Existing Campbellford Bridge” Feasibility Assessment; and Section 6.3.5 Evaluation. Budget: $28,800 (including $10,000 for renderings) PROJECT TEAM / STEERING COMMITTEE MEETING #2 Rationale: To review results of the expanded inventories, updated alternative solution evaluation, preferred solution and information to be presented at Public Information Centre (PIC) #1. Existing Documentation: None Sub-Tasks: Agenda and Minutes; Technical inventory reports; and Draft PIC #1 exhibits and public information material. Completion Schedule: week of March 11, 2013 2 Trent River Crossing in Campbellford Feasibility Report, GENIVAR, July 2012 Additional Trent River Crossing Schedule “C” Class Environmental Assessment, Environmental Study Report, AECOM Canada Ltd., August 2009. 3 Page 13 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA PROJECT TEAM / STEERING COMMITTEE MEETING #2 Key Staff Assignment: D. Drackley, A. Ortlieb, M. Radue Deliverables: Agenda and minutes; and Draft technical inventory reports; and Final PIC #1 exhibits and public information submitted to Councils for information prior to PIC. Budget: $5,600 TASK 6 – CONSULTATION: PUBLIC INFORMATION CENTRE #1 Rationale: Inform review agencies, stakeholders and the public on the results of the updated evaluation of alternative solutions with the “Improve / Replace Existing Campbellford Bridge” alternative included. . Existing Documentation: 2009 Draft ESR section 6.3 on the evaluation of alternative solutions including the preferred alternative. Previous comments and responses on the preferred alternative as reported in the 2009 ESR Appendix A and Section 5. Sub-Tasks: Finalize Public Information Centre date, time and location; Prepare Draft PIC exhibits, information handout, comment sheet, web page material and Notice of PIC for Project Team approval and conduct PIC; and; Prepare PIC Summary Report including review of comments. Completion Schedule: March 29, 2012 Key Staff Assignment: D. Drackley, A. Ortlieb, T. Brumfit, S. Johnston Deliverables: PIC materials, summary report and revised 2009 Draft ESR Section 5.0 and Appendix A. Budget: $11,420 TASK 7 – CONFIRM PREFERRED SOLUTIONS Rationale: Select the best solutions to the long term Trent River crossing and associated arterial road network needs in Campbellford based on an expanded evaluation of alternative solutions that includes “Improve / Replace Existing Campbellford Bridge”. Existing Documentation: 2009 Draft ESR Section 6.3 Sub-Tasks: Incorporate “Improve/Replace Existing Campbellford Bridge” into 2009 Draft ESR evaluation methodology. Update of previous ESR Section 6.3.6. Preferred Alternative. Completion Schedule: March 29, 2013 Key Staff Assignment: D. Drackley Deliverables: Revised ESR Section 6.3. Budget: $6,100 Page 14 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA PROJECT TEAM / STEERING COMMITTEE MEETING #3 Rationale: To review public feedback from PIC #1 and confirm the preferred river crossing and arterial road network solutions. Existing Documentation: None Sub-Tasks: Agenda and Minutes; PIC #1 Summary Report; and Technical memo on preferred solutions Completion Schedule: April 17, 2013 DECISION POINT #1 Key Staff Assignment: D. Drackley, A. Ortlieb, M. Radue Deliverables: Agenda and minutes; and Draft technical inventory reports; and Edits for PIC #1 exhibits and public information material. Budget: $5,600 EA PHASE 3: ALTERNATIVE DESIGN CONCEPTS FOR PREFERRED SOLUTION TASK 8 – EVALUATE ALTERNATIVE DESIGN CONCEPTS FOR FINAL PREFERRED SOLUTION Rationale: In the 2009 Draft ESR, the preferred planning solution was a new bridge crossing of the Trent River about 400m south of the existing Campbellford Bridge linking Second Street and Alma Street. The resulting identification, evaluation and selection of the design concept were all based on this second bridge solution. The alternative solution of improving and replacing the existing Campbellford Bridge had been screened out from further consideration and so was not evaluated in the 2009 report. The rationale for Task 8 is to reintroduce the existing Campbellford Bridge as a feasible alternative solution, and compare the design features of this crossing with those of the Second Street/Alma Street new bridge selected in 2009. At its meeting on June 25, 2012, the project Steering Committee endorsed these final two alternative solutions. The rationale for Task 8 is then to compare these two alternatives using an evaluation methodology and criteria that combines the 2009 AECOM evaluation with the 2012 GENIVAR evaluation. Existing Documentation: 2009 Draft ESR Section 6.4 Trent River Crossing in Campbellford Feasibility Report, GENIVAR, 2012 Sub-Tasks: Incorporate the previous 2009 AECOM evaluation with the 2012 GENIVAR evaluation of alternative designs for the Second Street/Alma Street alternative and existing Campbellford Bridge alternative respectively; Expand the evaluation criteria and process as required to ensure that all considerations identified through the Draft ESR consultation process are reflected in this updated evaluation, including: Provision of river crossing redundancy; Road network classification and responsibility (County or Municipality); Page 15 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA EA PHASE 3: ALTERNATIVE DESIGN CONCEPTS FOR PREFERRED SOLUTION TASK 8 – EVALUATE ALTERNATIVE DESIGN CONCEPTS FOR FINAL PREFERRED SOLUTION Impacts on provision of social housing; Direct and indirect property impact compensation needs. Identify the comparative pros and cons of each of the finalist alternative designs. Completion Schedule: April 30, 2013 Key Staff Assignment: A. Ortlieb, T. Brumfit, D. Drackley, Deliverables: Revised ESR Section 6.4 Budget: $15,400 TASK 9 – DETAILED INVENTORY FOR FINAL PREFERRED SOLUTIONS Rationale: Ensure any impact and required mitigation needs associated with the existing Campbellford Bridge alternatives has been identified and assessed so that this information can be compared against the impact assessment carried out for the Second Street/Alma Street alternative. Existing Documentation: New information collected in Task 3: Update/Expand Inventories Sub-Tasks: Document any significant impacts and required mitigation measures required by the existing Campbellford Bridge option; Update capital cost estimates to 2012 dollars for the Campbellford Bridge and Second Street/Alma Street alternatives; and Update capital cost estimates for updated arterial road network improvements associated with the river crossing alternatives. Completion Schedule: April 30, 2013 Key Staff Assignment: A. Ortlieb, T. Brumfit, G. Kauffman Deliverables: Updated Section 7.6 of the 2009 Draft ESR on mitigation measures and monitoring. Budget: $5,600 TASK 10 – CONSULTATION: PUBLIC INFORMATION CENTRE #2 Rationale: Present the recommended design concept for the Trent River crossing and associated arterial road network improvements. Invite agency, stakeholder and public feedback and comment. Existing Documentation: new task Sub-Tasks: Circulate draft PIC exhibits and materials to Project Team and Steering Committee members prior to finalization; Page 16 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA TASK 10 – CONSULTATION: PUBLIC INFORMATION CENTRE #2 Finalize Public Information Centre date, time and location; Finalize PIC exhibits, information handout, comment sheet, web page material and Notice of PIC; Conduct PIC; and Prepare PIC Summary Report including review of comments Completion Schedule: week of May 20, 2013 Key Staff Assignment: D. Drackley, A. Ortlieb, T. Brumfit Deliverables: PIC materials, summary report and revised 2009 Draft ESR Section 5.0 and Appendix A. Budget: $12,420 TASK 11 – SELECT AND FINALIZE PREFERRED DESIGN Rationale: Considering public response to the recommended design concept presented at PIC #2, the study Steering Committee will be asked to confirm the preferred design for inclusion in the ESR document. Existing Documentation: 2009 ESR Section 7.0 2012 Trent River Crossing in Campbellford Feasibility Study Section 13: Recommended Alternative Sub-Tasks: Consulting team and Project Team recommendation to Steering Committee; and Steering Committee decision. Completion Schedule: May 31, 2013 Key Staff Assignment: D. Drackley Deliverables: New ESR section describing preferred design decision process and recommendation. Budget: $6,600 PROJECT TEAM / STEERING COMMITTEE MEETING #4 Rationale: To review results of PIC #2 and how they relate to the confirmation of the preferred design. Existing Documentation: None Sub-Tasks: Agenda and Minutes; Draft PIC #2 Summary Report. Completion Schedule: May 31, 2012 DECISION POINT #2 Key Staff Assignment: D. Drackley, A. Ortlieb Deliverables: Agenda and minutes; and Draft PIC #2 Summary Report including public comments and draft responses. Page 17 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA PROJECT TEAM / STEERING COMMITTEE MEETING #4 Budget: $3,600 EA PHASE 4: ENVIRONMENTAL STUDY REPORT TASK 12 – UPDATE ESR DOCUMENTATION Rationale: The updated ESR document needs to be a stand-alone report. It will include a summary of all work tasks conducted as part of the 2009 ESR and the 2012 Feasibility Study, with references to these documents where required. This will be augmented with new updated and expanded information prepared as part of the EA completion. This new ESR will cover all topics and with details on all changes since the 2009 report, including summaries of previous findings that do not change. The 2009 and 2012 reports will be separate documents. Existing Documentation: August 2009 Final Draft ESR July 2012 Trent River Crossing In Campbellford Feasibility Study Sub-Tasks: First Draft ESR for Project Team and Steering Committee review; Final Draft ESR for project Team and Steering Committee review including approval recommendation to County and Municipality Councils; and Reconfirm federal EA requirements and commitments for the study. Completion Schedule: June 14, 2013 Key Staff Assignment: D. Drackley, A. Ortlieb Deliverables: Final Draft ESR and associated new technical appendices Budget: $18,150 PROJECT TEAM / STEERING COMMITTEE MEETING #5 Rationale: To review the first Draft ESR with the project Team, and the final Draft ESR with the project Team and Steering Committee. Existing Documentation: None Sub-Tasks: Agenda and Minutes; First Draft ESR preparation and editing; and Final Draft ESR preparation. Completion Schedule: week of June 24, 2013 DECISION POINT #3 Key Staff Assignment: D. Drackley, A. Ortlieb Deliverables: Agenda and minutes; and First Draft ESR; and Final Draft ESR. Page 18 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA PROJECT TEAM / STEERING COMMITTEE MEETING #5 Budget: $3,600 TASK 13 – PRESENTATION FOR APPROVAL / NOTICE OF STUDY COMPLETION PUBLIC REVIEW Rationale: The Municipal Class EA requires a mandatory notice of study completion prior to fling the ESR and completing the process. A minimum 30 day public review period is also mandatory following the notice, when any person or party with an unresolved issue can request the Minister of the Environment to enact a Part II Order to upgrade the EA process to that of a more rigorous Individual EA. Existing Documentation: August 2009 Final Draft ESR July 2012 Trent River Crossing In Campbellford Feasibility Study Sub-Tasks: Presentation to Councils with Steering Committee recommendation to post Notice of Study Completion; Minimum 30-day public review period and response to public input; If no Part II Order request is made, file the ESR following the review period to complete the EA process. NOTE: This task does not include response to or negotiation with any Part II Order requester since the number and natural of any possible requests are not known at this time. Completion Schedule: June 28 – July 31, 2013 Key Staff Assignment: D. Drackley Deliverables: Final ESR document with new technical appendices Budget: $4,600 TASK 14 – PROJECT FILING Rationale: Complete the Municipal Class EA process by filing the approved ESR with the Environmental Assessment Branch, Ministry of the Environment Existing Documentation: August 2009 Final Draft ESR July 2012 Trent River Crossing In Campbellford Feasibility Study Sub-Tasks: Write filing letter; and Reconfirm federal EA commitments which may include preparation of a Project Description to the responsible Authority Completion Schedule: August 2013 Key Staff Assignment: D. Drackley Deliverables: Filing letter, final ESR document and potential Project Description Budget: $2,000 Page 19 IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 3. EA COMPLETION SCHEDULE The following study schedule has the Detailed Work Plan approved by County Council at their regular meeting on November 21, 2012. Completion of the four EA phases is then scheduled to extent eight months to the end of June when County and Municipality Councils will be asked to approve the Final Draft ESR document and issue the Notice of Study Completion. The minimum 30-day public review period extends to the end of July, at which time the ESR documentation will be filed with MOE to complete the EA process. Page 20 Project Schedule Completion of the Trent River Crossing and Arterial Roadway Network Environmental Assessment TASKS ( see Work Plan): 2012 November December January February March April May June July PHASE 1: PROBLEM OR OPPORTUNITY Task 1 Preliminary Consultation Task 2 Consultation: Community Outreach Task 3 11/21 Update Problem/Opportunity Statement 3A Updated Traffic Data Collection 3B Updated Existing Arterial Road Network Traffic Conditions 3C Travel Origin-Destination Survey 3D Update Traffic Forecasts Project Team / Steering Committee Meeting #1 PHASE 2: ALTERNATIVE SOLUTIONS Task 4 Update / Expand Inventories Task 5 Update Alternative Solutions and Evaluation Project Team / Steering Committee Meeting #2 Task 6 Task 7 Consultation PIC #1 Confirm Preferred Solution Project Team / Steering Committee Meeting #3 PHASE 3: PREFERRED SOLUTION ALTERNATIVE DESIGN CONCEPTS Task 8 Evaluate Alternative Design Concepts for Final Preferred Solution Task 9 Detailed Inventory for Final Preferred Solution Task 10 Consultation PIC #2 Task 11 Select & Finalize Preferred Design Project Team / Steering Committee Meeting #4 PHASE 4: ENVIRONMENTAL STUDY REPORT (ESR) Task 12 Update ESR Documentation Project Team / Steering Committee Meeting #5 Task 13 Presentation for Approval/Notice of Completion/Public Review Min 30 Day Review Task 14 Project Filing Critical Decision Points August IBI GROUP DRAFT REPORT Detailed Work Plan Trent River Crossing and Arterial Road Network EA 4. EA COMPLETION BUDGET The budget required to complete this Detailed Work Plan is tabulated in the following budget spreadsheet which includes the following major cost items: FEES DISBURSEMENTS TOTAL Phase 1: Problem or Opportunity $66,050 $5,000 Paid Duty OPP $5,125 OD Survey Expenses $5,250 Traffic Counts $81,425 Phase 2: Alternative Solutions $72,420 $12,360 LGL Ltd. $ 3,500 Archaeoworks Inc. $ 7,000 J. Chandler $95,280 Phase 3: Preferred Solution Alternative Design Concepts $43,620 $43,620 Phase 4: Environmental Study Report $28,350 $28,350 $8,000 Travel & Reproduction $8,000 PROJECT COST excluding HST $210,440 $46,235 $256,675 Allowance for Part II Order Management $15,000 $1,000 $16,000 TOTAL COST excluding HST $272,675 An allowance to manage responses to Part II Order requests (maximum 5) has been included in the Total Cost. This will ensure that funds are available for the consulting team to assist the County in having any Part II Order requests resolved to the mutual satisfaction of the County and the requestor, with the goal of having the requests withdrawn. Page 21 COUNTY OF NORTHUMBERLAND Detailed Work Plan Budget Consulting Services for the Completion of the Trent River Crossing and Arterial Road Network Environmental Assessment Total Hours 20 IBI GROUP Mori PROJECT PHASES / TASKS 304 Drackley Hrs Hrs 146 Ortlieb 61 Brumfit Hrs 136 Johnston Hrs Hrs 230 Dela Cruz Hrs 125 Hwang 30 Lang Hrs 124 Radue Hrs 50 Tech I Hrs 350 Tech II Hrs 70 Surveyor Hrs Hrs 30 1676 Admin Hrs TOTAL TASK COST Total Hrs PHASE 1: PROBLEM OR OPPORTUNITY Task 1 - Preliminary Consultation 0 10 0 0 0 0 0 0 20 0 0 0 0 30 $4,000.00 Task 2 - Consultation: Community Outreach 0 50 0 0 0 0 0 0 0 0 0 0 0 50 $10,000.00 Task 3 - Updated Problem/Opportunity Statement 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 Task 3A - Updated Traffic Data Collection 0 2 0 0 20 0 0 0 0 0 0 0 0 22 $3,000.00 Task 3B - Updated Existing Arterial Road Network Traffic Conditions 0 2 0 0 20 0 40 0 0 0 0 0 0 62 $7,000.00 Project Team / Steering Committee Meeing #1 0 10 0 0 15 0 0 0 0 0 0 0 0 25 $3,950.00 Task 3C - Travel Origin-Destination Survey 5 5 0 0 45 0 60 0 0 50 70 70 0 305 $29,350.00 Task 3D - Update Traffic Forecasts 5 2 0 0 20 0 25 0 0 0 25 0 0 77 $8,750.00 10 81 0 0 120 0 125 0 20 50 95 70 0 571 $66,050.00 Task 4 - Update / Expand Inventories 0 15 0 0 0 40 0 30 0 0 50 0 0 135 $14,900.00 Task 5 - Update Alternative Solutions and Evaluation 0 25 20 15 0 60 0 0 0 0 145 0 0 265 $28,800.00 Project Team / Steering Committee Meeting #2 0 10 10 10 0 0 0 0 0 0 0 0 0 30 $5,600.00 Task 6 - Consultation PIC #1 2 20 8 8 8 0 0 0 30 0 0 0 0 76 $11,420.00 Trask 7 - Confirm Preferred Solution 2 10 10 0 0 20 0 0 0 0 0 0 0 42 $6,100.00 Project Team / Steering Committee Meeting #3 0 10 10 10 0 0 0 0 0 0 0 0 0 30 $5,600.00 4 90 58 43 8 120 0 30 30 0 195 0 0 578 $72,420.00 Task 8 - Evaluate Alternative Design Concepts for Final Preferred Solution 0 10 20 10 0 50 0 0 0 0 40 0 0 130 $15,400.00 Task 9 - Detailed Inventory for Final Preferred Solution 0 10 10 0 0 20 0 0 0 0 0 0 0 40 $5,600.00 Task 10 - Consultation PIC #2 2 25 8 8 8 0 0 0 30 0 0 0 0 81 $12,420.00 Task 11 - Select & Finalize Preferred Design 0 15 10 0 0 20 0 0 0 0 0 0 0 45 $6,600.00 Project Team / Steering Committee Meeting #4 0 10 10 0 0 0 0 0 0 0 0 0 0 20 $3,600.00 2 70 58 18 8 90 0 0 30 0 40 0 0 316 $43,620.00 Task 12 - Update ESR Documentation 4 30 20 0 0 20 0 0 40 0 0 0 30 144 $18,150.00 Project Team / Steering Committee Meeting #5 0 10 10 0 0 0 0 0 0 0 0 0 0 20 $3,600.00 Task 13 - Presentation for Approval/Notice of Completion/Public Review 0 15 0 0 0 0 0 0 0 0 20 0 0 35 $4,600.00 Task 14 - Project Filing 0 8 0 0 0 0 0 0 4 0 0 0 0 12 $2,000.00 4 63 30 0 0 20 0 0 44 0 20 0 30 211 $28,350.00 Subtotal PHASE 2: ALTERNATIVE SOLUTIONS Subtotal PHASE 3: PREFERRED SOLUTION ALTERNATIVE DESIGN CONCEPTS Subtotal PHASE 4: ENVIRONMENTAL STUDY REPORT (ESR) Subtotal PROJECT MANAGEMENT (included above) TOTAL FEES TOTAL HOURS DISBURSEMENTS TOTAL COST (excluding HST) $210,440.00 1676 $46,235 $256,675.00 Disbursements: LGL Limited, Natural Environment Archaeoworks Inc. J. Chandler, Air Quality OPP Paid Duty OD Survey Expenses/Contingency Traffic Data Collection 15 locations Travel Reproduction IBI Group $12,360 $3,500 $7,000 $5,000 $5,125 $5,250 $4,000 $4,000 $46,235