Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 III SUPPLEMENTARY TRANSPORT MODE-SPECIFIC EXPLANATIONS A TRANSPORT MODE: RAIL 1 Operations simulation 1.1 Transport infrastructure networks The analysis of the impacts of rail infrastructure investments is done by comparing a "with" scenario, where the network includes the infrastructure investment to be examined, with the "without" scenario that excludes this project. Each "with" scenario is compared to the same "without" scenario [28]. The network in the "without" scenario corresponds to the one for those sections of the optimised rail network 2015 that are relevant for federal transport infrastructure planning plus the upgraded and new sections in the current investment plan that will have been finished by that time. These are projects that are either well-advanced or are not being examined for other reasons. Thus, when defining the network in the "without" scenario, • the 2003 to 2007 anti-congestion programme, • the ERDF national transport infrastructure programme 2000 to 2006, • the “Zukunftspaket Schiene”1 (Future Rail Project) and • DB Netz AG's current scheme to increase the capacities of sections by improving cabling and safety technology were taken into account. Figure 32 shows this route network. The junctions between the sections of routes were – as in the FTIP '92 – presumed to be of unlimited capacity2. Where options to branch off from junctions were either problematic or non-existent, they were taken into account according to the difficulty of the branching and using various branching resistors in the network. Changes of traction type between electric and diesel were also taken into account by employing a time penalty. 1 Within the framework of the Zukunftspaket Schiene (Future Rail investment project), the German Bundestag (parliament) decided in 2000 to invest part of the interest gained from UMTS licences in improving and maintaining the existing rail network. This was to take place over the following ten to fifteen years. 2 Junctions with existing bottlenecks were examined in detail in separate junction research studies. 100 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail Vergleichsfall FTIP BVWP “without” scenario Flensburg Traktion Traction Elektrifiziert Electrified Diesel Diesel Rostock Hamburg Bremen Berlin Hannover Hbf Magdeburg Dortmund Leipzig Kassel Köln Dresden Erfurt Frankfurt(M) Mannheim Karlsruhe Nürnberg Stuttgart München Basel SBB Figure 32: Network in the "without" scenario 101 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 DB Netz AG provided the following relevant characteristics for the apportionment to passenger and freight traffic for the routes: • the length of route (kilometres), • the type of traction (electrified, non-electrified), • the top permitted speed Vmax (km/h), • the journey time in minutes for the local and long-distance passenger traffic, • the restrictions (no restriction, exclusively freight traffic routes, exclusively passenger traffic routes, freight traffic priority routes), • the number of tracks, • the length of the passing track (metres), • the route category, • the reference mixture ratio 3, • the reference capacity L04. Subdividing by time slices5 allowed the mixture ratio between passenger and freight trains, which fluctuates hugely during the course of the day, to be taken into account when determining the route capacity [29]. The route capacity Lm6 which is significant for the apportionment is determined by • the dependence of capacity on the mixture ratio on a typical standard route • the predetermined reference capacity L0 and • the reference mixture ratio. 3 The proportion of long-distance rail passenger traffic (SPFV), local rail passenger traffic (SPNV) and rail freight traffic trains (SGV) as a percentage of the route volume. 4 Route capacity in trains per day and direction in line with the route standard and a predetermined (reference) mixture ratio (e.g. 30% long-distance passenger traffic, 35% local passenger traffic, 35% freight traffic). 5 Time slice 1: 05.00 – 8.59; Time slice 2: 09.00 – 15.59; Time slice 3: 16.00 – 19.59; Time slice 4: 20.00 – 04.59. 6 Route capacity in trains per day and direction for a route with the mixture ratio actually applicable after apportionment. 102 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail For example, Figure 33 shows for the route types P 300 (fast long-distance passenger traffic) and M 230 (fast mixed traffic route) how the capacity of the route type differs depending on the mixture ratio. It immediately becomes clear that the route types have different capacities with the same mixture ratio and respond with varying degrees of sensitivity to changes in the mixture ratio. Link standard P 300 250 Capacity trains per day and direction 200 150 100 Capacity at 00% local traffic Capacity at 10% local traffic 50 Capacity at 20% local traffic Capacity at 30% local traffic Capacity at 40% local traffic Capacity at 50% local traffic 0 0 10 20 30 40 50 60 70 80 90 100 Share long-distance passenger traffic [%] Link standard M 230 400 Capacity trains per day and direction 350 300 250 200 150 Capacity at 00% local traffic 100 Capacity at 10% local traffic Capacity at 20% local traffic Capacity at 30% local traffic 50 Capacity at 40% local traffic Capacity at 50% local traffic 0 0 10 20 30 40 50 60 70 80 90 100 Share long-distance passenger traffic [%] Figure 33: Capacity for standard routes P 300 and M 230 103 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 1.2 Range of services from rail passenger transport 1.2.1 Local rail passenger transport The requests of the federal states in terms of the range of services on offer from regional rail passenger transport (RegionalExpress, StadtExpress and Regionalbahn) and the S-Bahn transit, as taken from a Federal Ministry of Transport, Building and Housing survey, were systematically captured. Where the requests showed capacity bottlenecks and inconsistencies between the federal states involved, in connection with cross-border lines, experts made suitable adjustments to the range of services on offer and these were presented to the states in a second, coordination phase. The result was a nationwide operations strategy for local passenger rail transport which was used as the basis for the "without" scenario in the FTIP. 1.2.2 Long-distance rail passenger transport Starting from the upgrading of infrastructure and from the services strategy in the 2015 integration scenario developed for the transport forecast, and taking into account • the "German Unity Transport Projecta", projects 8.1 and 8.2 (NurembergErfurt, Erfurt–Halle/Leipzig), • the newly-built route Stuttgart–Ulm with Stuttgart 21 and the Stuttgart airport link and New Ulm 21, • the "Market-Oriented Services for Passenger Transport" scheme drawn up by the DB Reise&Touristik AG, • the planned investments in cabling and safety technology for the rail network the range of long-distance rail passenger transport services on offer was completely re-worked. In the process, the range of available trains was adjusted in some cases to suit the available capacities. In agreement with DB AG, the following train types were defined that are to be available for long-distance rail passenger transport in 2015: Train type 1: Electric ICE (InterCityExpress) with a top speed of 300 km/h, 900 seats in the full train, 450 seats in the half train Train type 2: Electric ICE with tilting technology and a top speed of 230 km/h (ICE T), 900 seats in the full train, 450 seats in the half train Train type 3: Diesel-ICE with tilting technology (ICE V), 378 seats in the full train, 189 seats in the half train. 104 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail On important axes that, as a result of implementing the "Market-Oriented Services for Passenger Transport" scheme are no longer served by the DB Reise&Touristik AG's long-distance services, another train type was added with the working title "LongDistanceExpress". The aims here are to ensure that the main locations on these axes are properly served and to provide a quick connection between these areas and the long-distance rail passenger transport network. The regularly transited night train lines and the motorail trains with a minimum service of 53 trains per year were also taken into account. The assumption was made here that the current range of trains would also be available in 2015 and that these trains will not run on the newly-built sections. Figure 34 shows the long-distance rail passenger transport (SPFV)scheme with the supplementary LongDistanceExpress lines. 105 Part III A: Explanations Transport Mode Rail Train type 1 Train type 2 (tilting, Vmax=230 km/h) Train type 3 Evaluation procedure FTIP 2003 Line with its number and the number of trains per day and direction LongDistanceExpress (electric) LongDistanceExpress (diesel) LongDistanceExpress (loco) Figure 34: 106 Stations where ICE-lines are separated Long-distance rail passenger transport line scheme with the supplementary LongDistanceExpress lines in the "without" scenario Evaluation procedure FTIP 2003 1.3 Part III A: Explanations Transport Mode Rail Range of services from freight transport With freight transport, a distinction is made between the two train types 'block trains' and 'waggonload services', which differ both in terms of their capacity utilisation and the way they are operated. The conversion of the freight flows derived in the integration scenario for the 2015 freight traffic forecast into traffic flows (trains) involves two steps: 1. Conversion of freight flows into waggon flows, 2. Conversion of waggon flows into train flows. The degree of capacity utilisation of the waggons (tonnes/loaded waggon) differs according to the type of train and the sort of freight. Firstly, the block train proportions are separated out from the overall traffic flows for each link and freight area, and then the number of waggon's arriving per day is calculated for the amounts in block trains and single waggon trains for each junction station and link. An empty waggon model is used to determine the empty waggons for the waggonload traffic for each link. Across the network, the proportion of empty waggons in the overall waggonload traffic is around 30 %. For the block train traffic it was assumed that, for every block train in the load direction, there is an (empty) block train in the opposite direction. A train generation model was used to generate trains from the waggons arriving each day at a given junction station. With the single waggon traffic, train generation rules as in Train type Minimum capacity utilisation (Percentage of the train's length) JS-JS 60 % OriginJS-DestinationSY 70 % OriginSY-DestinationJS 70 % SY-SY 75 % JS-own SY At least 1 local freight train per day Own SY-JS At least 1 local freight train per day Figure 35: Train generation rules 107 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 The possible number of waggons on a link at maximum capacity utilisation is determined via the shortest passing track length (significant passing track length) on the route, the average waggon length and the length of the traction unit: N rel = z min rel − Lt Lw Where: N zmin Lt Lw rel Number of waggons Minimum passing track length per link (significant passing track length) Length of the traction unit Average waggon length (15.5 m) Link index Determining the route7 The model grading to determine the routes consists of these steps: • route search in the initial network for shunting yards • train generation in shunting yards • train operation in the route network • build a train line network • route search in the train line network. The freight waggon flows not included in the block train traffic or transported directly between junction stations were related to shunting yards when determining routes. Within this scheme, the shunting yards constitute the key cells, and thus the supply points in the network. The freight waggon flows generated during the modelling process constitute annual values in the first instance. To this extent, the annual values first usually needed to be converted to daily values for the purposes of the apportionment. An average of 256 operating days per year was assumed here. In the first stage, the route search is done firstly only on the basis of the route resistances (transport times on the route), while the junction resistances (turnaround times in the shunting yards) are then gradually introduced into the rest of the process. The total transport times on the routes transited comes from the quotients between the total route lengths and the average route speed. This is 75 km/h on electrified routes and 60 km/h on non-electrified routes. 7 Route = best route; the quickest route in a given network without taking restrictions into account 108 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail The starting point for train generation in the shunting yards are the so-called 'route trees', that hold all the best routes of the junction in question to all the other shunting yards in the network. The sequence of priorities when converting incoming or waiting waggons and waggon groups into departing trains begins with the destination shunting yard for which the longest transport time is required. There is always an option to transfer a waggon from a train arriving in a shunting yard to a departing train where the time between arrival and departure is as long as or longer than the specific turnaround time. These specifications were laid down to calculate the turnaround times: • The transfer time for all shunting yards is at least two hours. • The capabilities of the operating equipment were included in the determination of turnaround times as criteria specific to each shunting yard. The turnaround time (Ur) for an interval I is then determined according to the waggon's volume Ur = WI L Where: WI Number of waggons in the shunting yard in the interval I L Capability of the operating equipment in a shunting yard The trains departing from a shunting yard determined for the train generation processes are "set in motion" during the model simulation's train operating phase. Here, the departure time of the trains is calculated from the arrival time and the transfer time of waggon flows in a shunting yard. At the destination station, each train is then stored with all the data required for the train generation process occurring in the next interval. The duration selected for the interval here, an hour, is less than or at least the same as the minimum transport duration between shunting stations in the network. This ensures that, for the train generation process in the interval n + 1, all the necessary data is available on all the trains that have departed in the previous intervals and those that have arrived in the interval n + 1, and that therefore the train generation process can run correctly. As more trains go into operation between shunting yards, the so-called train line network, which now no longer consists of the physical route sections of the initial network, but is defined by train connections between shunting yards, gets more packed. The route search process in the train line network becomes a stringing together of timetabled connections between shunting yards. This process determines the best routes for each particular time slot. Various best routes, in the form of a train chain or a direct train between two shunting yards is found for each time slot and depending on the structure of the timetable. However, fixed line routes apply in the 109 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 train generation, as they do in actual practice, so that once a route has been found it is only changed if the new route found is quicker than the best route up to that point. Train generation, train operation and route searching in the train line network are resimulated in each time interval. The iteration process continues until the best routes found are no longer changing. Because of the constellation and the transport distances involved in the German rail network, this requires at least 40 to 50 onehour intervals in order to be sure to capture the reciprocal effects of the shunting yards located furthest apart from one another. The optimising of the route structure creates the foundation for identifying network bottlenecks that occur when respecting the best possible routes for the trains. The routes determined for the initial network are used unchanged for all the planning variants, while adjustments to each of the route capacities available is achieved purely by rerouting measures. 1.4 Determining the traffic volume in rail passenger transport The demand for passenger transport in the "without" scenario and in the "with" scenarios that are to be evaluated was calculated using the FTIP passenger transport model. This is explained in detail in the concluding report of the "2015 Transport Forecast for Federal Transport Infrastructure Planning" study. The FTIP passenger transport model was extended by a module to take into account the effects of capacity bottlenecks on the demand for transport. Please refer to the concluding report of the "Consideration of Non-Discriminatory Network Access in Federal Transport Infrastructure Planning" [30] study for a more detailed explanation of this new module. The parameters that determine demand are broken down into individual variables and processed step-by-step when applying the FTIP passenger transport model. This process involves mapping the effects of the parameters on the individual components of the transport demand, i.e. mobility ("traffic generation"), choice of destination ("traffic distribution") and choice of transport ("modal split"). The forecast trends for volume and structures are factored into each step of the forecast by means of changes ("∆-matrices") in the initial matrix. This "marginal approach" has the advantage that the structures for the actual status quo in the forecast, which were largely determined through empirical means, are not lost. 110 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail When forecasting the demand for transport, the model components described below were used: Induced traffic With this model component, on the hypothesis that the budget for generalised costs for transport users' travel activities is stable (a common approach in the transport sector), changes in generalised costs in the forecast year over the base year lead to changes in journey volumes. The induced and (where the availability or the journey deteriorates) deduced traffic is calculated based on the journeys that are not affected by modal shift. Here, for each travel purpose, an estimated average proportion of generalised costs for the travel in relation to the overall generalised costs of the activity for which the travel is intended is taken into account. This accommodates the fact that, for example, a minor improvement in travelling time does not necessarily lead to a corresponding increase in holiday travel, since the holiday as a whole lasts much longer than the journey to and from the holiday location. Rind = GK a − GK p max(GK p ; GK a ) × min( R p ; Ra ) × AR Where: Rind GKp Induced traffic, per transport mode, travel purpose and link ij Generalised costs forecast GKa Rp Generalised costs at the moment of the analysis or in the previous forecast step Forecast of journeys Ra Journeys in the analysis or the previous forecast step AR Proportion of generalised costs within the total costs for the journey, differing for each travel purpose Destination choice model The destination choice model is used to calculate the effects of changed (generalised) costs on the spatial distribution of journeys. This model component plays a particularly significant role with air traffic (shifts e.g. from domestic to foreign travel, also cross-mode). With the relationship functions that differ according to travel purpose, the (empirically demonstrable) border resistance is also taken into account, and even broken down further into national borders and linguistic borders. Suitable hypotheses can be applied in the model to develop these border resistances and to change them in line with the model. An "availability quota" is used to express the fact that, where the spatial and economic structures are largely stable, only a 111 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 portion of the destinations are "available" – i.e. can be displaced - over a given time period (inaction effect). Rijp = Rija + α S pj × GK ijp × Qip ∑ J α S pj × GK ijp ×β − α × Qip S pj × GK ija ∑ j S pj GK ija α ×β Where: Rijp Rija Qip GKijp GKija α β Spj Journeys between i and j forecast Journeys between i and j analysis or in the previous forecast step Origin traffic from i Qi = in the forecast Generalised costs forecast Generalised costs analysis or the previous forecast step Exponent of generalised costs (negative) Availability quota (proportion of journeys that "can be redistributed" in the time period that can be examined) (depends on the forecast time period and the travel purpose) Significant structure feature forecast region j Modal split The competition between the different modes of transport can be mapped using a modal split model. This model component plays a role in relation to economic growth, to the extent that a shift can occur from, for example, the "cheap" (user cost low, time cost high) land-based mode of transport to the "expensive" air mode (user cost high, time cost low). This is calculated using the functions below: Firstly, a resistance function (per transport mode and travel purpose) in the form W = a × GK × eb×GK c Where: W GK a, b, c Resistance value Generalised costs Calibrating weights (vary according to travel purpose and transport mode) Secondly, the logit itself, in a form appropriate to determine the market share (P) for each transport mode, 112 Evaluation procedure FTIP 2003 PLuft = 1 WLuft 1 WBahn + 1 WMIV 1 1 + + WLuft WBus Part III A: Explanations Transport Mode Rail ; PBahn, PMIV and PBus accordingly. The change in journeys (R) determined using the modal split model is applied to the demand in the analysis (Ra) which is derived and forecast from empirical research, as it is not unusual that the modal split in the theoretical model differs from the actual modal split. This so-called marginal approach avoids the model calculation losing the transport mode usage features that relate to specific spaces and links. RVM,p = RVM,a + ( PVM,p – PVM,a ) × RGes Where: RVM,p RVM,a PVM,p PVM,a RGes Demand transport mode VM in the forecast Demand transport mode VM in the analysis or the previous forecast step Modelled market share VM in the forecast Modelled market share VM in the analysis or the previous forecast step Demand over all transport modes Induced traffic, destination choice effects and modal split changes are calculated as ∆-matrices and the effects added or balanced. Route choice and capacity reconciliation The route choice model is used within the framework of the available microforecasts, based on the network model road, rail and air, • to determine the suitable transport links with the corresponding characteristics of the services on offer, for every origin-destination link, • to determine the distribution of transport demand on the available routes and transport links (the route split), • while calculating the effects of capacity bottlenecks on the characteristics of the services on offer and the distribution of transport demand. The road network model comprises the entire network of federal trunk roads, important regional roads and the network in neighbouring countries that affects Germany. With rail and air traffic, alongside the infrastructure, the transport service on offer is captured as a line network model – with rail the train systems are coded (ICE, IC, IR, RE etc.), while with air the airlines and alliances are coded. 113 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 The route choice model takes into account the intermodality between the road and rail network and the road, rail and air network by generating appropriate route chains. The quality of the services on offer is shown via generalised costs as the total of the monetarised service offering parameters. The generalised costs of the link are made up as follows: GK FZ ,k = t k × ZK FZ + u k × UK FZ + p k × TFFZ Where: GKFZ,k tk uk pk ZKFZ UKFZ TFFZ Generalised costs of route k for travel purpose FZ Travel time calculated with discomfort factors for the whole route k Number of changes on route k (rail, air) Transport price (incl. costs for getting to and from the route) on route k Time costs for travel purpose FZ Monetarised discomfort for changes for travel purpose FZ (rail, air) Tariff factor for travel purpose FZ At any given time of the day there are, for rail and air, additional costs due to the "adjustment time", the difference between the desired departure time and the actual departure time possible as per the timetable and thus dependent on frequency. The usage probability p on the individual route k is determined via a function of the generalised costs GKijk and the frequency-dependent waiting time ta. Pk = f (GK ij ,k , t a ) The usage probability is used to also determine the total resistance over all routes per link: k GK ij = ∑ GK ij ,k × Pk At first, the questions were overlooked as to whether the planned capacity expansions in the infrastructure will keep pace with the forecast transport trend, and which effects future capacity bottlenecks might have and, conversely, which effects any possible resolution of those bottlenecks could have on the demand for transport. This capacity reconciliation was carried out in a second forecast step. 114 Evaluation procedure FTIP 2003 1.5 Part III A: Explanations Transport Mode Rail Determining the traffic volume in rail freight transport Train journeys on local and long-distance passenger lines are apportioned per line according to the sequence of stops in the network. The volume-dependent apportionment of freight trains is done on the network which is pre-loaded with passenger trains by using the WIZUG algorithm. The range of train services on offer in rail passenger transport is thus given priority treatment, as is largely the case in actual operating circumstances, so that the capacity of any route section is reduced accordingly. The remaining available capacity then represents the leeway for the most cost-effective freight transport operation possible.8 Unlike the best route search, which does not fix the specific route but only the necessary turnaround points (shunting yards), apportioning freight trains to routes needs to be done according to the individual characteristics of each network case. With rail freight transport in particular, considerable delays can occur where the degree of capacity utilisation on routes exceeds a given critical limit. Therefore the actual processes that occur in rail transportation are depicted realistically, i.e. increases in capacity utilisation on a route are characterised by increasing interference with operating processes and lengthening journey times. Such delays damage the image of Deutsche Bahn AG's performance, which ultimately has consequences for demand. In principle, this process is continuing and ongoing, but it only has a dramatic effect when approaching capacity limits. As the example in Figure 36 shows, the threshold journey time of a train arriving to be added to a route increases where the degree of the route's capacity utilisation reaches around 80 % of the nominal capacity. Journey times increase progressively as capacity utilisation grows, and they asymptotically approach the technical capacity limit. The operation monitoring already mentioned now enables the delays that occur to be distributed across all freight trains. The deterioration in the image of rail freight transport's service offering that occurs in the marketplace when capacity utilisation increases on routes is well approximated using the average delay function for freight trains Figure 37. 8 If the system is expanded there will also be support for giving priority to putting on special quality freight trains. 115 INCREASE IN TRANSPORT DURATION (%) Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 400 350 300 250 200 150 100 50 0 0 20 40 60 80 100 120 DEGREE OF CAPACITY UTILISATION (%) INCREASE IN TRANSPORT DURATION (%) Figure 36: Limit delay of freight trains depending on route volume 140 120 100 80 60 40 20 0 0 20 40 60 80 100 120 140 DEGREE OF CAPACITY UTILISATION (%) Figure 37: Average delay of all freight trains depending on route volume As the network volume grows it leads, because of delays, to an increase in the freight trains' transport time. Starting from the route capacity that is still available for freight trains in the various time slices after apportioning passenger trains, freight trains are apportioned by delay, rerouting and rerouting times, taking into account the best routes and the route restrictions, so that, once the trains have been sorted according to their profit margin, those that have a large profit margin are apportioned first and those with a small profit margin are apportioned last. In this way, an optimal network apportionment of the entire network for the upgrading status in the "without" scenario is achieved for each time slice. 116 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail For rail, where the infrastructure remains constant, this means optimising operations according to the available opportunities, i.e. where necessary, rerouting trains to reduce income lost through reaction in the marketplace. If the tight resources of the rail network infrastructure are to be used optimally, the basic question arises, which trains should mostly reach their destination via their optimal route, which should be rerouted and how the speed of freight trains in general should be slowed (via passing procedures). Here, three different trends need to be taken into account. Passing procedures lead to delays and thus to a deterioration in the service offering and thus to a fall in demand and income, and an increase in the time-dependent operating costs. Passing procedures can, of course, be avoided by rerouting, but longer routes lead to an increase in train running costs. An optimal operations strategy must, therefore, take into account both the possible loss of income and the associated cost increases. A transport mode choice model is used to estimate reactions in the transport market to a deterioration in the quality of rail transport services on offer. Finally, as the last component, an efficient algorithm is required to search for the generalised shortest routes in the network. The various model components required have already been outlined above in the listing of the different impact elements. The initial value for this process is the change in journey time as a consequence of differing route capacity utilisation. The economic success resulting from each individual train stems from the income minus the running- and time-related costs and minus the cost of the waggons in other trains. This train indicator9 is a comprehensive economic criterion for appraising each individual train. In order to properly take into account transport time and cost resistances in the route search procedure, generalised transport costs were introduced as a network resistance criterion. Here, the transport time is valued using a time cost unit rate, the transport distance is valued using a distance cost unit rate and the branching procedures (changing traction and direction) are valued using a piece cost unit rate. The total of all three cost components constitutes the generalised network resistance. Thus this network resistance is minimal on the train's optimal route. This train is then allocated to the network and the capacity and journey time situation is updated. When all the trains in one train type group have been worked through, the procedure described is repeated for the trains in the next group. When the process is over, the average journey time of all freight trains depending on the network capacity is determined and the demand response, in the sense of the modal impact, is estimated. 9 In business literature, the difference between revenue and variable costs is usually known as the profit margin. In this sense, the train indicator is the profit margin that accrues from managing the train. In order to avoid any confusion between the terms employed by the Deutsche Bahn AG, the term "train indicator" has been coined. 117 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 In freight transport, a provider's market success is determined by a large number of individual customer decisions. As Figure 38 shows, the result of these decisions regarding the choice of transport mode depends not only on the individual preferences of the decision-maker, but also on the characteristics of the freight to be transported and the regulatory framework that exists in the transport market. The most significant determinant, however, is the specific quality of the service offering in the different competing transport modes, in all their guises. INDIVIDUAL PREFERENCES DECISIONDECISIONMAKING MAKING PROCESSES PROCESSES CHARACTERISTICS OF OF THE THE CHARACTERISTICS TRANSPORT CASES CASES TRANSPORT QUALITY OF OF THE THE SERVICE SERVICE QUALITY OFFERING OF OF THE THE COMPETITORS COMPETITORS OFFERING REGULATORY REGULATORY FRAMEWORK FRAMEWORK CHOSEN CHOSEN TRANSPORT TRANSPORT MODE MODE Figure 38: Transport mode choice decision-making model Such relationships between the characteristics of the service offering in the transport mode, on the one hand, and the transport mode selected, on the other hand, can be identified and quantified using suitable, mathematical and statistical methods. The relationship components that are relevant here, in the form of direct time elasticities, naturally differ amongst a large number of segments, e.g. type of freight, and categories of distance and weight. Figure 39 shows an example of this type of basic relationship. As all the segmentation values are known from the train generation for each waggon relation, the corresponding elasticity can be determined, in detail, for each individual waggon number and used as a basis for the model's calculation. 118 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail COMMERCIAL ROAD FREIGHT TRAFFIC Shares (%) 80 60 40 RAIL LONG-DISTANCE INDUSTRIAL TRAFFIC 20 0 -50 Loader‘s modal reaction Figure 39: -40 -30 -20 -10 0 10 20 30 40 50 Change in duration of rail transport (%) Time elasticity in transport demand Figure 40 shows the effect of a growth in route volume on the transport demand in rail freight transport. In this way, the lengthening of journey times when there is increased volume on routes can be estimated via the load-dependent resistance function, and from this the demand reaction can be quantified using the elasticity function. Falling demand now leads to poorer train capacity utilisation and thus to the loss of train journeys and corresponding savings in terms of train running costs. However, the loss of train journeys then relieves the route network, the journey time situation improves and this causes modal reactions in the opposite direction. To the extent that – because of significant network bottlenecks – the system suffers lasting destabilisation in the way described, the procedure needs to be repeated iteratively in a feedback loop until there is a renewed equilibrium. 119 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 EFFECT ON JOURNEY TIMES 70 MODAL EFFECT CHANGE IN JOURNEY TIME (%) 60 50 40 30 20 10 0 30 25 20 15 10 DEMAND SHARE (%) Reduced demand Figure 40: 5 0 20 40 60 80 100 120 DEGREE OF CAPACITY UTILISATION (%) Increased capacity utilisation Modal effect of changes in capacity utilisation The resulting network usage is characterised by the fact that direct, qualitatively well-developed rail routes are loaded either to a great degree or beyond the applicable capacity because the weighted cost of losses through delays, rerouting journeys, rerouting times, lost income and lost volume due to longer transport times are lower here than on rail routes that are distant from the main direction of the freight flows and/or are poorly developed. The latter, therefore, are loaded to a lesser degree and partly still have available capacity. The apportionment thus satisfies the evaluation procedure's requirement to optimise the "without" scenario, and at the same time reflects the actual situation whereby, in the technical sense, available rail capacity cannot be marketed given the level of service demanded by customers. This becomes particularly clear if the network load in the main load period (05.00 to 08.59) is compared with the load in the time slice with the lowest load (20.00 to 04.59). While the network is heavily loaded or overloaded almost everywhere during the main load period, there are, with a few exceptions, usually only moderate network volumes during the night. Shifting trains from daytime slices to the nighttime slice cannot be done for passenger traffic and is only possible to a limited degree with freight traffic due to the associated loss in quality (longer transport times) and the resulting drop in demand. Figure 41 shows the network load with all trains for the entire day. The bottlenecks shown in red (more than 110 % capacity utilisation) mostly lie on routes that are 120 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail being directly upgraded in the projects announced by the federal states and the DB Netz AG, or that are indirectly influenced by (wide-ranging) changes to train schedules as a result of infrastructure projects in other locations, so that the bottleneck effect is to be removed or greatly reduced in the "with" scenarios. FTIP „without“ scenario Flensburg Sassnitz/Mukran All trains 200 trains/day Average capacity utilisation < 80 % < 110% >= 110% Rostock Hamburg Leer (Ostfr.) Bremen Berlin Hannover Magdeburg Leipzig Dortmund Kassel Dresden Erfurt Köln Frankfurt (M) Nürnberg Mannheim Saarbrücken Karlsruhe Stuttgart München Basel Figure 41: Network load in the German network with all trains and the resulting route capacity utilisation in the "without" scenario 121 Part III A: Explanations Transport Mode Rail 2 Benefit elements 2.1 Reduction of transportation costs (NB) Evaluation procedure FTIP 2003 The rail transportation costs used in the FTIP 2003 were derived on the basis of existing research, information provided by the DB AG, and of first-hand experience. 2.1.1 Determining link-specific cost unit rates The link-specific costs – e.g. a Hamburg-Mannheim link – consist of the costs of the trains that use different routes on this link, thus e.g. via the upgrade route/new construction route Hanover–Frankfurt to Mannheim, via the parallel old route, or via the Hanover–Giessen–Frankfurt route to Mannheim. The costs here differ according both to the different route lengths and journey times involved, and to the differing levels of capacity utilisation on these routes. Apportioning in line with cost-effective train management ensures that each route is used to the extent that, overall, there is a network load which optimises the relationship between revenue and costs in a sound economic way. The level of the link-specific costs therefore differs according to • which freight groups are being transported • which proportions of the waggonload traffic are being transported in block trains or in individual waggons/waggon groups • how often the waggons are turned around between the origin and destination • which proportion the individual route categories have on the transport route between the origin and the destination • how heavily the individual route sections are loaded. Therefore the link-specific cost unit rates depend on a number of parameters that are calculated during the operating simulation to generate the quantity structure. The simulation differentiates according to 240 junction and border crossing stations, so that link-specific transportation costs can be shown for a 240 x 240 matrix. 122 Evaluation procedure FTIP 2003 2.1.2 Part III A: Explanations Transport Mode Rail Decreased vehicle standby costs (NB1) The vehicle standby costs are based on the calculations in the following specification: • • Waggonload traffic Traction unit standby Waggon standby €/traction unit hour €/waggon hour Long-distance passenger transport Standby for the three ICE traction unit categories, each for full and half train Standby for long-distance express waggon trains Standby for other long-distance passenger trains €/multiple unit train hour €/long-distance express waggon train hour €/train hour other long-distance passenger traffic Positive (and negative) changes in standby costs come from the difference between the journey times required to handle the transport volume on all part-routes of the part-network relevant in each case in the "with" and "without" scenarios. To calculate the NB1, the differences in journey time for each multiple unit train and waggon train hour over all the part-routes were added up and multiplied by the corresponding standby cost unit rates. NB1 = ∑∑ d × (Q vg TW × t vg − Q pl × t pl ) × VHK [€/year] ij Where: TW ij d Qvg tvg Qpl tpl VHK Index for multiple unit train, traction unit or waggon category Index for part-routes Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport) Daily number of multiple unit trains, traction units and waggons on the partroute in the "without" scenario Journey time for the part-route in the "without" scenario (hours) Daily number of multiple unit trains, traction units and waggons on the partroute in the "with" scenario Journey time for the part-route in the "with" scenario (hours) Vehicle standby cost unit rate (€/hour) The journey times for the part-routes depend on the capacity utilisation of the partroutes – they are determined depending on the capacity utilisation in the simulation. 123 Part III A: Explanations Transport Mode Rail 2.1.3 Evaluation procedure FTIP 2003 Decreased vehicle operation costs (NB2) Operating costs include the mileage-dependent material costs and the time-dependent personnel costs required to operate. The operating costs are divided into the costs – dependent on the volume of passengers and freight – of despatching passengers and freight, the costs of train generation which depend on the waggons to be handled, and the costs of moving the trains which depend on the distance and the characteristics of the route. For long-distance passenger traffic, the despatch costs are calculated from the change in volume and the despatch cost unit rate (€/traveller) and for freight traffic from the shifted traffic volume and the despatch cost unit rate (€/t). Positive (and negative) savings from despatch costs in passenger transport (NB2AP) are determined by: NB 2 AP = Where: d Pvg Ppl AKp AP d × (Pvg − Ppl ) × AK P [€/year] Conversion factor for daily to annual mileages (d = 365) Number of travellers per day in "without" scenario Number of travellers per day in "with" scenario Cost unit rate for despatch in long-distance passenger transport (€/P) Passenger transport despatch As well as the despatch costs related to operating the railways, with freight transport transaction costs need to be calculated for the quantities transported additionally in rail transport. By adding these costs, the costs are taken into account that accrue for transshipping when displacing from road to rail transport which always accrue with all transport that cannot be done using sidings at both ends. Thus the despatch and transaction costs in freight traffic come out as NB 2 AG = d × (Nt vg − Nt pl ) × ( AK G + TK G ) [€/year] Where: d vg pl Nt AKG TKG AG 124 Conversion factor from daily to annual values (d = 250) "Without" scenario index "With" scenario index Daily transport quantity (net tonnes) Cost unit rate for despatch in freight transport (€/t) Transaction cost unit rate in freight transport (€/t) Despatch freight transport Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail The train generation costs in passenger train transport are calculated on the basis of the train mileage differentiated by train type. Positive (and negative) savings from train generation costs in passenger transport (NB2,ZP) are determined by: NB 2 ZP = ∑∑ d × (Zugkm NF vg − Zugkm pl )× ZK P [€/year] ij Where: NF ij d Zugkmvg Zugkmpl ZKP ZP Index for train types (ICE type, long distance express or other longdistance passenger vehicle) Index for part-routes of the relevant part-network Conversion factor for daily to annual mileages (d = 365) Number of train kilometres in "without" scenario Number of train kilometres in "with" scenario Train generation cost unit rate (€/Zugkm) Train generation passenger transport The train generation costs in freight transport are calculated from the number of waggons to be used and the cost unit rate (€/waggon). Changes to train generation costs in freight transport are determined by: NB 2 ZG = d × (Wvg − W pl ) × ZK G [€/year] Where: d Wvg Wpl ZKG ZG Conversion factor from daily to annual values (d = 250) Freight waggons to be used in "without" scenario Freight waggons to be used in "with" scenario Train generation cost unit rate (€/waggon) Train generation freight transport In long-distance passenger traffic, the train moving costs were also calculated broken down into the ICE train types, the long-distance express trains and the trains on other long-distance passenger traffic, and in freight traffic for each traction type (diesel / electrical traction) in the dimension €/Zugkm. After these differentiations, the train mileages were captured during the apportionment simulation. Positive (and negative) changes in train moving costs come from the difference between the mileages (Zugkm) in passenger and freight traffic on all part-routes of the part-network relevant in each case in the "with" and "without" scenarios. To calculate the cost changes (NB2,F), the train kilometres for each train category over all part-routes in the "without" and "with" scenarios were multiplied by the corresponding train moving cost unit rates and the difference formed from this: 125 Part III A: Explanations Transport Mode Rail ∑ d × [ (Zugkm NB2 F = ICE vg Evaluation procedure FTIP 2003 − Zugkm plICE ) × FK ICE + (ZugkmvgFE − Zugkm plFE ) × FK FE ij ( ) ( ) G + ZugkmvgSPFV − Zugkm SPFV × FK SPFV + Zugkmvg − Zugkm Gpl × FK G pl ] Where: ij d vg pl ZugkmICE ICE Index for part-routes Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport) "Without" scenario index "With" scenario index Daily mileage (ICE km) on the part-route by ICE train type Train moving cost unit rate by ICE train type (€/ICE km) FK FE Zugkm Daily mileage (Zugkm) on the part-route in long-distance express traffic FE Train moving cost unit rate for long-distance express trains (€/Zugkm) FK SPFV Daily mileage (Zugkm) on the part-route in other long-distance Zugkm passenger traffic Train moving cost unit rate in other long-distance passenger traffic FKSPFV (€/Zugkm) Daily mileage (Zugkm) on the part-route in freight traffic ZugkmG G Train generation cost unit rate freight traffic (€/Zugkm) FK F Train moving 2.1.4 Changes in transport costs due to modal shifts (NB3) In long-distance passenger transport, the rail investment projects to be evaluated lead to increased demands that are very largely at the expense of long-distance road passenger transport. With some investment projects, and for particular links, competition with air transport is also possible. Part of the additional transport demand is also induced by the new traffic caused by the project. The database available for passenger transport differentiates according to the origin of the additional demand from road and air transport. The demand that is shifted from road transport to rail transport is further differentiated according to its origin from bus transport and motorised private transport. The costs accrued from modal shifts are determined for these providing transport modes. In freight transport, the investment projects lead to changes in block train and individual waggon traffic, where the greater part of the additional departing transport volume accounts for individual waggon and waggon group traffic. In the area of individual waggon and waggon group traffic, rail competes primarily or exclusively with road freight transport. Moreover, as only a few of the new or upgrade routes to 126 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail be evaluated lie fully or partly on "wet links" (links with parallel waterways), any possible competition with waterways in part-areas was disregarded. For the quantities shifted between transport modes, the differences between the transportation costs in the 'giving' and 'taking' transport modes is calculated. In freight transport, more than 90 % of the shifted quantities stem from capital goods and consumer goods and are primarily (almost two-thirds) transported in inland traffic. For these goods, the average vehicle capacity utilisation is substantially lower and the macroeconomic costs (€/Tkm) therefore higher than for the average of all goods transported by road. That was taken into account when calculating the cost unit rate to be used in the calculation. In passenger transport, the (positive or negative) benefits from cost changes caused by volume shifts between rail and road are calculated as follows: NB3 P = ( S d × [ VPkmIVS × (BKS IV − BKE P ) + VPkmBUS × BKS BUS − BKE P +VPkm L × (BKS L − BKE P ) ) ] Where: d VPkmSIV VPkmSBus VPkmL BKSIV BKSBus BKSL BKEP Conversion factor from daily to annual values (d = 365) Passenger mileage (Pkm/year) in the "with" compared to the "without" scenarios shifted from motorised private transport on the road to rail Passenger mileage (Pkm/year) in the "with" compared to the "without" scenarios shifted from bus on the road to rail Passenger mileage (Pkm/year) in the "with" compared to the "without" scenarios shifted from air transport to rail Specific transportation costs in motorised private transport on the road (€/Pkm) Specific transportation costs in bus transport on the road (€/Pkm) Specific transportation costs in passenger transport in the air (€/Pkm) Specific transportation costs in passenger transport by rail (€/Pkm) In freight transport, the (positive or negative) benefits from cost changes caused by volume shift between the rail and road modes are calculated as follows: 127 Part III A: Explanations Transport Mode Rail NB3G = Evaluation procedure FTIP 2003 d × VTkm × (BKS G − BKEG ) Where: d Conversion factor from daily to annual values (d = 250 GV) VTkm Freight mileage (Tkm/year) in the "with" compared to the "without" scenarios shifted from road to rail BKSG Specific transportation costs in freight transport on the road (€/Tkm) BKEG Specific transportation costs in freight transport by rail (€/Tkm) 2.2 Transport infrastructure maintenance (NW2) With the rail transport mode, maintenance costs are calculated on the basis of the procurement costs for the investment components using maintenance cost factors: KI = ∑ K g × ig g Where: KI Kg ig g Maintenance costs for infrastructure (€/year) Procurement costs of asset components (€) Maintenance cost factor Index for subject area group The maintenance cost factors to be used are subdivided by the investment's subject area groups and represent average costs that were calculated by the DB Netz AG using extremely finely differentiated cost data. 128 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail 10 Investment component Maintenance cost unit rate Roadbeds 0.0035 Supporting walls 0.0035 Tunnels 0.0014 Viaducts 0.0042 Crossings 0.0042 Soundproofing 0.0007 Track superstructure 0.0308 Buildings and structures 0.0280 Signalling systems 0.0210 Communication systems 0.0350 Traction power supplies 0.0280 Contact lines 0.0210 Figure 42: Maintenance costs for the rail mode (proportion of investment costs) The benefit from the route maintenance costs (NW2) is calculated as follows: NW 2 = ∑ (KI vg − KI pl ) [€/year] M Where: M KIvg KIpl Investment projects Total maintenance costs in the "without" scenario (€/year) Total maintenance costs in the "with" scenario (€/year) 2.3 Increased traffic safety (NS) The level of accident costs related to mileage differs according to the different transport modes. Therefore the shifts in mileage between modes that is caused by the investment projects to be evaluated lead to changes in the macroeconomic accident costs. The accident costs per mileage unit are calculated from the accident rates for each type of damage (accidents per billion person or net tonne kilometres) and from the costs per type of damage (deaths, seriously injured, slightly injured, material damages). When calculating the accident rates, the travellers affected by injury to the 10 Exemplary assumptions 129 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 person were assigned to the passenger transport accident rates, and injuries occurring during shunting were assigned to the freight transport accident rates. The damage to persons and materials that could not be divided in this way were allocated to passenger and freight traffic in proportion to the distribution of train kilometres (63.3 % passenger traffic and 36.7 % freight traffic). This produces the following accident rates: Passenger transport Freight transport Accidents per 1 billion Pkm Accidents per 1 billion Ntkm Dead 1.5 0.4 Seriously injured 3.2 0.9 Slightly injured 4.0 1.1 Material damage 56.9 15.7 Accidents with … Figure 43: Accident rates by type of damage in the rail area Monetary accident cost rates were calculated from the accident rates plus the value of personal and material damages. Passenger transport Freight transport (€ / million Pkm) (€ / million Ntkm) 2,116.74 587.99 Seriously injured 384.49 106.35 Slightly injured 21.11 5.73 Material damage 3,262.04 899.87 Accidents with … Dead Figure 44: Accident cost rates in the rail area The accident costs in the rail area are determined as follows: UK B = ∑ d × (( Pkm E vg − Pkm plE ) ×UKR E , P + ( NtkmvgE − Ntkm Epl ) × UKR E ,G ) ij Where: UKB ij 130 Accident costs per year in the rail area Index for route sections Evaluation procedure FTIP 2003 d Part III A: Explanations Transport Mode Rail Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport) Daily rail passenger mileage (Pkm) on all part-routes of the relevant partnetwork Daily rail freight mileage (Tkm) on all part-routes of the relevant partnetwork Accident cost rate for rail passenger transport Accident cost rate for rail freight transport Index for "without" scenario Index for "with" scenario PkmE NtkmE UKRE,P UKRE,G vg pl Where a project will lead to traffic shift from road to rail, the accident costs in the rail area in the "without" scenario are to be supplemented by the accident costs of the proportion of traffic that moves from road to rail in the "with" scenario. The accident costs on the road here are determined by: UK S = ∑ Fkm S BAB S S S S S ×UKRBAB + Fkm AO ×UKR AO + Fkm IO ×UKRIO ij Where: UKS ij FkmS UKRS Accident costs of the mileage shifted from road to rail (€/year) Index part-routes of the relevant road network In the "with" scenario, mileage shifted from federal motorways (BAB), other rural roads (AO) and roads in built-up areas (IO) to rail Accident cost rates for traffic on: federal motorways (BAB) = 0.02829 €/vkm; other rural roads (AO) = 0.06765 €/vkm; and roads in built-up areas (IO) = 0.10228 €/vkm The benefit contribution to traffic safety (NS) is then, in all: NS = UK S − UK B Where: UKS UKB Accident costs in the road sector (€/year) Accident costs in the rail sector (€/year) 131 Part III A: Explanations Transport Mode Rail 2.4 Evaluation procedure FTIP 2003 Improved accessibility of destinations (NE) The benefit contributions for improving accessibility come from changes to journey times in the "with" compared to the "without" scenario. They arise through projectrelated shorter journey times in rail passenger transport and through the shift of passenger transport volume between road and air, on the one hand, and rail on the other. Journey times in the rail area are determined in the same way for the "without" and "with" scenarios. Because there are different monetary approaches to calculating commercial (business) travel and non-commercial (other) travel, there needs to be a corresponding distinction when determining journey times. TB g ,ng = Fg ×l Fng ×l + v v b b ∑ d × ij Where: TB g ng ij d F l vb Total journey times in rail passenger travel (hours/year) Index of commercial passenger travel Index of non-commercial passenger travel Index of part-routes Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport Daily number of journeys on the part-route Length of part-route in km Train speed (km/h) on the part-route When projects lead to traffic shifts from air to road, the journey times of the railassociated passenger traffic in the "without" scenario needs to be supplemented by the journey times of the 'giving' mode. The journey times on the road here are determined by: TS g ,ng = S Pkm gS Pkmng ∑ij d × v + v S S The journey times for air traffic are determined as follows: TL g ,ng = 132 L Pkm gL Pkmng ∑ij d × v + v L L Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail Where: TS, TL Total journey times of passenger traffic shifted from road or air to rail (hours/year) g Index of commercial passenger travel ng Index of non-commercial passenger travel ij Index of part-routes d Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport) Pkm Daily mileage (Pkm/year) in the "with" compared to the "without" scenarios shifted from road or air to rail v Average speed (km/h) of the shifted traffic S, L Index for road and air traffic The total benefit contribution from improving accessibility (NE) is determined by: NE = (∆TS g + ∆TL g ) × WPg + (∆TS ng + ∆TLng ) × WPng − (∆TB g × WPg + ∆TBng × WPng ) Where: ∆TB, ∆TS, ∆TL g ng WPg WPng 2.5 Change in journey time in rail, road and air traffic between "without" and "with" scenario Index of commercial passenger travel Index of non-commercial passenger travel Monetary valuation in commercial passenger traffic; here 19.94 €/hour Monetary valuation in non-commercial passenger traffic; here 5.47 €/hour Spatial advantages (NR) See Part II, Chapter 5 133 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 2.6 Environmental relief (NU) 2.6.1 Reduction in noise exposure (NU1) A benefit contribution through a change in noise exposure is only taken into account where: 1. the average level Lm (the energy equivalent long-term sound level) exceeds the target level Lz. Here it is only the night that is examined, since observing the nighttime thresholds usually includes observing daytime thresholds. Lz = 42 dB (A) is the target level for the nighttime. 2. the difference in noise exposure dLm of a route section between the "with" and "without" scenarios is at least 2 dB (A): |dLm| > 2 dB(A) This means that the route volume in the "with" scenario must be at least 60 % greater or smaller than in the "without" scenario so that, for the rail mode, usually only newly constructed routes are considered for a benefit contribution, since on existing routes and upgrade routes this degree of change in the traffic volume can rarely be expected. With upgrade sections, this is particularly the case as long as the track axis is not moved or the number of tracks is not changed. The benefit through changing the costs from noise exposure in the rail area is determined by NU 1E = LK vg − LK pl [€/year] Where: NU1E LKvg LKpl Benefit from the difference in costs from noise exposure in a year for the "with" scenario and the "without" scenario in the rail area (€/year) Cost of noise in "without" scenario (€/year) Cost of noise in "with" scenario (€/year) The noise costs in a section of a route are derived in a similar way for the "with" and "without" scenarios: LK 134 = (E A g ) + E gI ×W L Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail Where: LK WL Costs of noise exposure per year (€/year) Value of a weighted resident; 54.71 €/resident per year E gA Weighted residents in rural area E gI Weighted residents in built-up area Outside built-up areas it is possible to approximately determine the degree to which specific residents ei are affected on newly constructed routes using ex-post analyses in the following way: Eg = 4 ∑g i × ei × l a 1 Where: Eg gi ei la 11 Weighted residents (sone residents) Noise weighting of isoband i Specific residents in isoband i (res./km) Length of the newly constructed route under examination (km) Isoband sone-weighting gi Degree of effect on Ei (residents/km) Flat terrain Hills/Mountains 1 82/72 dB (A) 9.51 e1 = 0 e1 = 1 2 72/62 dB (A) 5.66 e2 = 2 e2 = 2 3 62/52 dB (A) 2.83 e3 = 30 e3 = 15 4 52/42 dB (A) 1.41 e4 = 50 e4 = 15 Figure 45: Degree of effect both sides of newly constructed two-lane routes (rural, approximately) If these levels of affectedness are applied, the overall rural exposure then approximately derives to E gA = 167 × l a (sone res.) for flat terrain E gA = 84 × l a (sone res.) for routes in hilly or mountainous areas 11 sone is a unit used to determine the degree to which human beings are aware of noise levels; 1 sone equates to 40 dB (A) at 1000 Hz, while any increase of 10 dB (A) is experienced as a doubling of the noise level (50 dB (A) ≅ 2 sone, 60 dB (A) ≅ 4 sone etc.). sone residents are, therefore, the residents affected by traffic noise in a route under examination. 135 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 Where: E gA Weighted residents in rural area la Length of the newly constructed route under examination in the rural area in km In built-up areas, the level of affectedness is derived depending on the distance to the first row of housing. It was assumed that every building affected on the side near the roadway is made of urban model components. In consideration of sound level reductions caused by soundproofing installations, the distance of the building, vegetation and the building itself, the affected residents were theoretically determined at full exposure to the newly constructed route for distances of up to the most favourable situation L = 42 dB (A) at the edge of the development and with the depth of development affected in each case, and by multiplying this by the corresponding exposure weightings the weighted residents were calculated per kilometre of affected residential development. With this, the residents affected in built-up areas is determined by: E gI = e g × li eg = a - b × log(s) Where: E gI Weighted residents in built-up area eg li Weighted specific residents in the built-up area (residents/km) Length of residential development that is affected on one side of the route (km) Sideways distance of the development from the axis of the track line (m) Coefficients corresponding to the tables below s a, b Route type Applicable range a b One-lane 3,000 1,500 10 < s < 100 Two-lane 3,803 1,748 14 < s < 150 Three-lane 4,425 1,923 18 < s < 200 Four-lane 4,461 1,939 22 < s < 350 Figure 46: 136 Coefficient (m) Coefficients for determining the residents affected in built-up areas for situations with a soundproofing wall Evaluation procedure FTIP 2003 Coefficient Route type Applicable range a b One-lane 5,602 2,202 10 < s < 350 Two-lane 6,809 2,451 14 < s < 600 Three-lane 7,987 2,778 18 < s < 750 Four-lane 9,954 3,318 22 < s < 1.000 Figure 47: 2.6.2 Part III A: Explanations Transport Mode Rail (m) Coefficients for determining the residents affected in built-up areas for situations without a soundproofing wall Reduction in exhaust emissions (NU2) Exposure to exhaust emissions in the rail area is calculated using energy consumption as the basis. Energy consumption mainly depends on • the type of transport (passenger transport, freight transport), • the type of traction (diesel or electric traction). Standard trains corresponding to the rail average were assumed for the following study. For these standard trains, the following levels of energy consumption were derived per train kilometre: Diesel traction freight transport: Electric traction freight transport: Diesel traction passenger transport: Electric traction passenger transport: 3.748 kg/Zugkm 17.204 kWh/Zugkm 2.889 kg/Zugkm 12.939 kWh/Zugkm The consumption data per train kilometre plus emission factors (g/kg diesel or g/kWh) can then be used to determine the pollutant emissions per train kilometre. Using damage cost unit rates for the individual emissions, the following costs are derived from the emission of air pollutants in rail transport: 137 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 Climate damage Vegetation damage All Damage to health and materials Diesel traction 2.43 0.09 2.52 1.43 / u Electric traction 1.70 0.005 1.71 - Diesel traction 1.88 0.06 1.93 0.84 / u Electric traction 1.28 0.05 1.28 - Freight transport Passenger transport u: average wind speed at 10m height in metres/sec. Figure 48: Costs from emitting air pollutants in rail transport in € per Zugkm The benefits from avoiding exposure to exhaust emissions are calculated as follows for the difference between the "without" and "with" scenarios: NU 2B = ∑ d × (Zugkm P D × AK DP + Zugkm EP × AK EP + Zugkm DG × AK DG ij + Zugkm EG × AK EG ) Where: NU2B ij d ZugkmPD ZugkmPE AKPD AKPE ZugkmGD ZugkmGE AKGD AKGE Benefit from reducing exhaust emissions in the rail sector Index for routes Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport) "With" scenario difference train kilometres passenger transport diesel traction "With" scenario difference train kilometres passenger transport electric traction Emission cost unit rate passenger transport diesel traction (€/Zugkm) Emission cost unit rate passenger transport electric traction (€/Zugkm) "With" scenario difference train kilometres freight transport diesel traction "With" scenario difference train kilometres freight transport electric traction Emission cost unit rate freight transport diesel traction (€/Zugkm) Emission cost unit rate freight transport electric traction (€/Zugkm) When traffic mileage is shifted between road and rail, the emission costs in the "without" scenario on the road are: 138 Evaluation procedure FTIP 2003 ∑ d × (Pkwkm × AK NU 2S = Part III A: Explanations Transport Mode Rail S Pkw S S ) + Buskm × AK Bus + Lkwkm × AK Lkw ij Where: NU2S ij d Emission costs on the road in the "without" scenario Index for routes Conversion factor for daily to annual values (d = 365 with long-distance passenger transport; d = 250 with freight transport) Shifted Pkwkm (carkm) Emissions cost unit rate car (€/Pkwkm) Shifted bus kilometres Emissions cost unit rate bus (€/Buskm) Shifted Lkwkm (lorrykm) Emissions cost unit rate lorries on the road (€/Lkwkm) Pkwkm AKSPkw Buskm AKSBus Lkwkm AKSLkw The total benefits from avoiding emissions are derived from the total of the additional costs (negative benefits) in the rail sector and the saved costs (benefits) in road transport: − NU 2 B + NU 2 S NU 2 = 2.7 Improved links to and from seaports and airports (NH) See Part II, Chapter 8 3 Costs 3.1 Investment costs In the evaluation procedure, the benefits described in section 2 are confronted with the investment costs. The preliminary work on these costs was done by DB Netz AG for the upgrading and new construction work being examined in the "with" scenarios. The investment costs provided based on a variety of different prices were converted into a single, uniform price basis in consultation with DB AG. The extrapolation factors listed in Figure 49 were used to do this. 139 Part III A: Explanations Transport Mode Rail Evaluation procedure FTIP 2003 Price index series (1995 = 100) Land acquisition Roadbeds Supporting walls Tunnels Viaducts Crossings Soundproofing Track superstructure Buildings and structures Signalling systems Communication systems Traction power supplies Contact lines Third-party equipment Planning costs Indirect costs 1989 83.9 89.7 81.9 81.7 81.9 81.9 85.8 90.4 78.2 88.0 123.1 92.5 92.5 1990 85.6 93.2 86.9 86.8 86.9 86.9 90.1 94.4 83.0 90.1 122.7 93.4 93.4 1991 89.8 100.2 91.7 92.6 91.7 91.7 96.0 97.0 88.2 92.9 120.9 95.8 95.8 1992 79.6 106.6 95.5 97.3 95.5 95.5 101.1 99.1 92.8 96.1 112.0 97.5 97.5 1993 83.7 104.4 97.5 98.8 97.5 97.5 101.0 99.1 95.8 98.2 103.6 98.3 98.3 1994 92.2 101.4 98.7 99.0 98.7 98.7 100.1 98.3 97.5 99.1 102.9 98.9 98.9 1995 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 1996 115.0 96.7 99.4 98.3 99.4 99.4 98.1 100.8 100.3 101.5 97.6 100.5 100.5 1997 108.8 96.0 98.0 96.6 98.0 98.0 97.0 100.0 99.8 103.0 98.8 99.7 99.7 1998 119.7 96.2 97.4 95.7 97.4 97.4 96.8 102.2 99.9 103.8 103.8 103.8 103.8 1999 120.0 96.9 96.6 95.5 96.6 96.6 96.8 102.0 99.6 99.3 95.8 99.6 99.6 2000 121.2 95.9 95.6 94.5 95.6 95.6 95.8 103.0 98.6 98.3 94.8 98.6 98.6 2001 122.4 95.0 94.7 93.6 94.7 94.7 94.8 104.1 97.6 97.3 93.9 97.6 97.6 76.7 76.7 80.2 80.2 84.7 84.7 89.0 89.0 93.1 93.1 95.5 95.5 100.0 100.0 101.3 101.3 103.2 103.2 105.4 105.4 107.2 107.2 108.3 108.3 109.4 109.4 1992 1.5038 0.9024 1.0199 0.9836 1.0199 1.0199 0.9579 1.0313 1.0765 1.0801 0.9268 1.0646 1.0646 1.0586 1.1843 1.1843 1993 1.4301 0.9215 0.9990 0.9686 0.9990 0.9990 0.9589 1.0313 1.0428 1.0570 1.0019 1.0560 1.0560 1.0472 1.1321 1.1321 1994 1.2983 0.9487 0.9868 0.9667 0.9868 0.9868 0.9675 1.0397 1.0246 1.0474 1.0087 1.0495 1.0495 1.0362 1.1037 1.1037 1995 1.1970 0.9620 0.9740 0.9570 0.9740 0.9740 0.9680 1.0220 0.9990 1.0380 1.0380 1.0380 1.0380 1.0191 1.0540 1.0540 1996 1.0409 0.9948 0.9799 0.9736 0.9799 0.9799 0.9873 1.0139 0.9960 1.0227 1.0635 1.0328 1.0328 1.0124 1.0405 1.0405 1997 1.1002 1.0021 0.9939 0.9907 0.9939 0.9939 0.9979 1.0220 1.0010 1.0078 1.0506 1.0411 1.0411 1.0193 1.0213 1.0213 1998 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1999 0.9975 0.9928 1.0083 1.0021 1.0083 1.0083 1.0005 1.0020 1.0030 1.0453 1.0835 1.0422 1.0422 1.0129 0.9832 0.9832 2000 0.9876 1.0028 1.0185 1.0122 1.0185 1.0185 1.0106 0.9920 1.0131 1.0559 1.0945 1.0527 1.0527 1.0172 0.9735 0.9735 2001 0.9778 1.0129 1.0288 1.0224 1.0288 1.0288 1.0208 0.9822 1.0234 1.0665 1.1055 1.0633 1.0633 1.0214 0.9638 0.9638 Extrapolation factors 1998 for 1989 to 2001 prices Land acquisition Roadbeds Supporting walls Tunnels Viaducts Crossings Sound proofing Track superstructure Buildings and structures Signalling systems Communication systems Traction power supplies Contact lines Third-party equipment Planning costs Indirect costs Figure 49: 3.2 1989 1.4267 1.0725 1.1893 1.1714 1.1893 1.1893 1.1282 1.1305 1.2775 1.1795 0.8432 1.1222 1.1222 1.1715 1.3742 1.3742 1990 1.3984 1.0322 1.1208 1.1025 1.1208 1.1208 1.0750 1.0826 1.2036 1.1521 0.8460 1.1113 1.1113 1.1292 1.3142 1.3142 1991 1.3330 0.9601 1.0622 1.0335 1.0622 1.0622 1.0089 1.0536 1.1327 1.1173 0.8586 1.0835 1.0835 1.0814 1.2444 1.2444 Price index series Present values In the evaluation, all of the upgrading and new construction works are examined for a single, uniform time period of 36 years (2000 to 2035). Here, years 2000 to 2004 account for the construction time, while years 2005 to 2035 are for the usage time. The evaluation is carried out as a capital value calculation. The interest on all receipts (investments) and payments (annual net benefits) is discounted on the year 2000. Therefore all the amounts shown in the evaluation results are present values as at 2000. 3.3 Residual values The service life of the asset components fluctuates between 12 years (communication systems) and 75 years (roadbeds, supporting walls, tunnels, viaducts). Therefore when the 31-year usage time is over, in some subject areas replacement investments will already have been made, while in other areas the original investments will not yet have been "consumed". For all materials areas, the residual values are calculated in the last year of use (2035) and treated as payments, i.e. as a reduction in the 140 Evaluation procedure FTIP 2003 Part III A: Explanations Transport Mode Rail investment costs. As with all the other amounts, the interest on these amounts is discounted to the year 2000. Therefore, the investment amount shown in the evaluation calculations is calculated as follows: • The investment costs supplied by DB AG are converted to a uniform base price level, depending on the subject area. • The replacement investments are taken into account in subject areas where the service life is below 31 years. • The residual values remaining when usage is over are taken into account. • Interest on all the receipts and payments in the cash flow from 2000 to 2035 is discounted to the year 2000. 141