5/31 edits Need to fix terminology “option” to “alternative on Figure 6-4 Do we have LMP contour maps showing projects in July in the reference case and each alternative scenario? Chapter 6 2013 Alternative Cases Modeled The location of new generation is the primary factor determining the level of congestion on the transmission system. Historically, transmission and generation planning were conducted in tandem by vertically-integrated utilities. Nearly all of the transmission constructed in the Western interconnection was built to move power from specific new generating resources to the customers of utilities that constructed the generation. FERC’s 1996 open access order effectively decoupled generation planning from transmission planning. The major challenge in evaluating transmission needs in 2013 is estimating the location of new generation. To address this uncertainty, the RMATS RAWG developed four alternative generation scenarios. One of the major difficulties in linking generation expansion and transmission expansion is the mismatch between the time it takes to develop new generation and the time it takes to develop the related transmission expansion projects. Transmission projects typically require five to 10 years to complete, comparable to the time required for the development of new coal-fired generation. Gasfired generation requires significantly less time (e.g., 2-3 years), but may not require much additional transmission. Wind generation can be constructed in as little as 18 months but may require significant transmission additions. Alternative 1 reflects the resource plans of the major load serving entities in the RMATS region. Alternative 2 is a “pseudo” regional integrated resource plan for the RMATS region that attempts to optimize the location of new generation within the region to meet forecasted load (with added reserves) in 2013 (3,900 MW). Alternative 3 meets forecasted load growth within the RMATS region and allows for exports from the region equal to load growth within region (7,800 MW). Alternative 4 provides sufficient generation to meet load growth in the RMATS region and exports equal to twice the load growth within the region (11,700 MW). To the maximum extent possible, Alternative 1 reflects company announced generation plans within the RMATS region plus additional generation added by the RAWG. In developing Alternative 2, the RAWG made its own judgments about the location of new generation to lower overall costs for the sub-region. Alternatives 3 & 4 were developed by the RAWG with generation to support export from the sub-region. Figure 6-1 shows the type and location of generation modeled in all four scenarios. 6-1 Figure 6-1 Generation Alternatives for 2013 State Bubble Gen Type 2013 ALTERNATIVE CASES Colorado East Colorado Colorado West KGB Idaho Mid Point/Boise/Snake Montana West Montana Broadview Colstrip/Crossover Bonanza IPP Utah Utah North Utah South Big Horn Basin Black Hills Wyoming LRS SW Wyoming Wyoming WYO(IDA) WYO(MT) Jim Bridger Yellowtail Total Coal Total Gas Total Wind Nameplate Total Firm Energy Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Coal Gas Wind Name Plate Generation Values 1 1250 210 800 125 575 2 500 210 500 125 3 1540 210 800 4 2500 603 1500 250 250 125 125 440 225 280 250 260 500 500 260 1000 750 359 950 609 1000 1109 50 100 200 0 200 950 950 250 575 525 100 575 140 200 575 140 120 320 575 140 250 250 250 250 250 Alternative 1- Compilation of existing IRP’s - minimal new transmission Configured incremental resource additions in each state to meet projected load growth plus reserves in that state. (Load growth is 3900 MW from 2008 – 2013 for RM states). Major wind in CO-E and SW Wyoming close to load centers Alternative 2- “Pseudo” IRP for subregion Focus on Powder River coal and open range wind. Solves for same load growth as Alternative 1. Requires more transmission than Alternative 1 Alternative 3- Export 1 X RM load growth Builds off Alternative 2. Additional Powder River and Utah coal and open range wind necessitating more transmission for export Alternative 4- Export 2 X RM load growth Still more Powder River (and Utah) coal and open range wind, and additional DC line 125 925 500 500 1500 1150 700 1000 1400 50 575 575 2450 2100 50 800 575 160 230 6149 660 4955 7800 8559 1053 10440 11700 50 2600 785 2575 3900 2959 350 2955 3900 6-2 Alternative 1: Compilation of Existing Utility Resource Plans Alternative 1 reflects the generation proposed in the resource plans of the major load serving entities within the RMATS region. These plans tend to emphasize the development of new generation close to load centers and thus represent a minimal new transmission case. Figure 6-2 shows the location and type of new generation in each of the bubbles modeled. A total of 3,900 megawatts of new generation is added to meet forecasted load growth within the RMATS region in 2013. Figure 6-2 Alternative 1 Incremental Resource Additions (MW) 225 Wind 250 Wind 575 Coal 125 Wind 50 Gas 925 Wind 250 Wind 200 Coal 575 Coal 525 Gas 1250 Coal 210 Gas 800 Wind 6-3 Figure 6-3 shows the most congested transmission paths in the RMATS region the generation in Alternative 1. The percentage within the blue circles is the percentage of time during a year that the transmission constraint would prevent economic power transfers. The dollar number next to the transmission constraint represents how much interconnection-wide variable operating and maintenance costs would decline by adding one additional megawatt to the transfer capacity of the path. This value will decline as each additional megawatt of transfer capacity is added. 3,900 MW added to Rocky Mtn. States % Montana 5% Percent of Time at Binding Limit Interface Name Opportunity Cost/Savings ($) Montana – NW $9,136 Idaho Alternative 1- no transmission additions Figure 6-3 Congestion in Alternative 1 If No Transmission Is Added Wyoming 6% Utah Path C $19,322 14% 30% Bridger West $61,729 West of Naughton $40,571 9% Bonanza West $17,736 40% TOT 2C $74,557 Colorado Graphs were developed to show the duration of congestion on each of the highlighted paths. For example, the blue line on Figure 6-4 shows the duration of transmission congestion on Path C in eastern Idaho that Figure 6-3 shows as congested 6% of the time. The horizontal brown line at 1000 megawatts shows the capacity of the line to handle flows moving from East to West. The blue line is above that capacity 6% of the time. The turquoise line at minus 1000 megawatts shows the capacity of the line to move power from West to East. The other lines of the graph show congestion in the other generation scenario alternatives assuming the generation is built, but not transmission is added. These graphs were used to help the TAWG target proposed transmission additions. In some cases, the frequency of congestion and the value of relieving the congestion were too small to warrant making transmission investments to relieve the congestion. 6-4 Duration curves for the each of the major paths can be found in Appendix 1. Figure 6-4 Duration of Congestion in Different Scenarios Path C Desired power transfers in Alternative 1 exceed the capacity of the line 6% of the time 1,500 1,000 MW 500 0 (500) 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% (1,000) (1,500) (2,000) Percent of Time No Tx Additions Option 1 Option 2 Option 3 Option 4 Current Forward Capacity Current Reverse Capacity Figure 6-5 shows the transmission additions identified by the RMATS TAWG (LINK) that would alleviate much of the congestion identified in Alternative 1. A phase shifter would be added on existing path between Montana and Idaho. A transformer would be added at Flaming Gorge. In addition a new 345 KV line would be added from Miners to Ben Lomond and a new to 230 KV line would be added between Midpoint in Boise. No transmission would be added to alleviate constraints outside the RMATS region. 6-5 Figure 6-5 Transmission Additions in Alternative 1 Transmission Additions Alternative 1 500 kV Boise 345 kV Midpoint Jim Bridger 230 kV Naughton Ben Lomond Miners Added Phase Shifter Added Transformer The addition of new generation and transmission in Alternative1 would lower annual variable and operating maintenance costs by $3.1 billion throughout the Western Interconnection. Most of those savings would occur outside the RMATS region. Within the RMATS region, the largest benefit would accrue to eastern Colorado. Figure 6-6 shows the table developed to calculate the change in variable operating and maintenance from the base case when new generation and transmission are added in Alternative 1. The four right columns show the change in variable operating and maintenance cost from the reference scenario. The annual interconnection-wide savings in variable operating and maintenance costs would be $1.333 billion. Most of that annual savings ($1.318 billion) is from the addition of generation. The annual savings attributable to adding the transmission in Figure 6-5 would be $15 million. If sufficient transmission was added to alleviate all congestion in Alternative 1(last column), the annual savings would be $133 million. However, the TAWG judged that cost of transmission investments to relieve all the congestion would be higher than the $133 million in savings. 6-6 Figure 6-6 Summary Table of Annual Savings in Operating and Maintenance Costs in Alternative 1 Annual VOM with Transmission Solutions Alternative 1 – ($Millions) Reference Case ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 18 19 20 22 23 24 25 26 28 29 30 32 33 Area New Mexico Arizona Nevada WAPA- LC Mexico- C Imperial San Diego So. California LADWP IPP PG AND E Northwest BC Hydro Aquila Alberta Idaho- West Montana- West Sierra Wyoming- Central Bonanza Utah- North Utah- South Colorado- East Colorado- West Black Hills LRS JB Broadview CRSOVRCO Total (a) No Tx Add Add Constraints Gen/No Tx Gen/Add Tx (b) ( c) (d) Value of Gen Additions Delta Value of Gen & Tx Additions Delta 482 4,245 1,226 503 888 22 896 1,684 358 253 3,599 2,329 585 33 1,452 14 0 305 50 69 213 369 931 200 76 83 261 17 165 470 4,295 1,215 514 943 15 647 1,016 202 275 2,813 2,188 553 34 1,743 0 0 253 68 69 173 589 911 200 66 83 307 17 165 449 3,958 1,192 448 880 18 780 1,493 304 274 3,359 2,191 540 32 1,433 0 0 235 62 68 163 524 732 200 58 83 331 17 165 449 3,934 1,145 453 879 18 787 1,510 290 274 3,315 2,202 540 32 1,434 2 0 235 65 68 162 538 783 200 60 83 334 17 165 (c - a) (34) (286) (33) (55) (8) (3) (116) (191) (54) 21 (240) (138) (44) (1) (19) (14) 0 (70) 13 (1) (50) 155 (199) (1) (19) (0) 69 (0) (0) (d - a) (33) (310) (81) (50) (8) (4) (108) (174) (68) 21 (284) (127) (45) (1) (18) (13) 0 (70) 15 (0) (51) 169 (148) (0) (16) 0 72 (0) (0) 21,307 19,826 19,989 19,974 (1,318) (1,333) Value of Tx Additions Delta VOM Savings with No Tx Constraints (d - c) (b - c) 1 (24) (48) 5 (0) (0) 7 17 (13) 0 (44) 11 (1) (0) 1 1 0 0 2 0 (1) 14 51 0 2 0 3 (0) (0) 21 337 23 65 64 (3) (133) (476) (101) 0 (546) (3) 13 2 310 (0) 0 18 6 1 10 65 180 1 9 0 (24) 0 0 (15) (163) Negative (red) values indicate reduction in fuel cost due to displacement Total Annual VOM Savings Positive (black) values indicate increased fuel cost due to higher dispatch Similar tables were developed for each of the alternative generation scenarios and can be found in Appendix 1. 6-7 Alternative 2: “Pseudo” IRP for the RMATS Region Figure 6-7 shows the location and type of new generation that would be added in the RMATS region under a “pseudo” regional integrated resource plan to meet load growth of 3,900 megawatts. The major differences between Alternative 1 and Alternative 2 are the addition of 359 megawatts of coal generation and 380 megawatts of wind. New gas-fired generation would drop from 785 megawatts to 350 megawatts. But the location of new coal and wind generation would move from eastern Colorado, Idaho, and Utah to the Powder River Basin and southern Wyoming. The rationale for relocating the generating resources was the assumed lower cost of mine-mouth coal plants in the Powder River Basin compared to hauling coal by rail to a plant elsewhere and the higher quality wind resources in southern Wyoming. Continuing proposals by generation developers for coal-by-rail power plants in Nevada rather than coal-by-wire plants in Wyoming challenge the cost assumptions used in Alternative 2. Figure 6-7 Incremental Resource Additions in Alternative 2 250 Coal 280 Wind 359 Coal 50 Wind 250 Wind 125 Wind 700 Coal 575 Coal 1150 Wind 500 Wind 100 Wind 500 Coal 575 Coal 140 Gas 210 Gas 500 Wind Figure 6-8 shows the resulting congestion from the generation additions in Alternative 2. Congestion duration curves can be found in Appendix 1. 6-8 Figure 6-8 Congestion is No Transmission Is Added in Alternative 2 Alberta - BC $53,112 B.C. 7,800 MW added to Rocky Mtn. States % Percent of Time at Binding Limit Alberta 71% Interface Name Opportunity Cost/Savings ($) Montana 60% Wash. West of Broadview $187,948 Montana – NW $157,469 100% Idaho Black Hills – C. Wyoming $288,392 82% Oregon Alternative 3- no transmission additions 73% Bridger West $241,727 Wyoming Utah 31% Nevada TOT 3 $140,590 50% Bonanza West $48,990 IPP DC $69,519 TOT 2C $157,912 Colorado California 90% 46% New Mexico Arizona Mexico Figure 6-9 shows the transmission added to relieve congestion in Alternative 2. The transmission additions in Alternative 2 incorporate the additions in Alternative 1 plus new 345 KV lines from Wyoming to the Colorado Front Range, from Idaho to Utah, and from Wyoming to Idaho. A new 500 KV line would be added from Montana to Idaho which would include a phase shifter. 6-9 Figure 6-9 Transmission Additions in Alternative 2 Townsend Broadview Ringling 500 kV Midpoint Boise 345 kV 230 kV Existing 500kV Borah Treasureton Dave Johnson Ant Mine/Reno Jim Bridger LRS Naughton Ben Lomond Miners Cheyenne Tap Ault Green Valley Added Phase Shifter Added Transformer Under Alternative 2, the Interconnection-wide changes in annual operating and maintenance costs would be $1,520 billion, of which $250 million is attributable to the transmission added. A complete table of changes in annual operating and maintenance costs under Alternative 2 can be found in Appendix 1. Alternative 3: Exports to Load Growth in the RMATS Region Figure 6-10 shows the generation additions in Alternative 3 which equal 7,800 megawatts (3900 megawatts to serve load growth in the RMATS region; 3900 megawatts for export outside the RMATS region). The type and location of new generation reflects the known plans of generation developers. 6-10 Figure 6-10 Incremental Generation Additions in Alternative 3 500 Coal 950 Wind 260 Gas 500 Wind 609 Coal 100 Wind 250 Wind 1400 Coal 125 Wind 50 Gas 575 Coal 160 Wind 1000 Wind 500 Wind 200 Wind 950 Coal 250 Wind 1540 Coal 575 Coal 210 Gas 140 Gas 800 Wind 120 Wind Figure 6-11 shows congestion in Alternative 3 if no transmission is added. The map shows congestion on paths within and outside the RMATS region. The addition of generation for export significantly increases the amount of congestion and the value of relieving such congestion through transmission expansion. See Appendix 1 for duration curves associated with transmission paths identified in Figure 6-11. 6-11 Figure 6-11 Congestion If No Transmission Is Added in Alternative 3 Alberta - BC $53,112 B.C. 7,800 MW added to Rocky Mtn. States % Percent of Time at Binding Limit Alberta 71% Interface Name Opportunity Cost/Savings ($) Montana 60% Wash. West of Broadview $187,948 Montana – NW $157,469 100% Idaho Black Hills – C. Wyoming $288,392 82% Oregon Alternative 3- no transmission additions 73% Bridger West $241,727 Wyoming Utah 31% Nevada TOT 3 $140,590 50% Bonanza West $48,990 IPP DC $69,519 TOT 2C $157,912 Colorado California 90% 46% New Mexico Arizona Mexico There are a number of options for relieving transmission in Alternative 3. The TAWG determined that it is necessary to have at least two 500 KV transmission paths out of the RMATS region and that such paths should not be in the same corridor. Figure 612 shows the four optional combinations of 500 KV lines that were modeled. Additional combinations are feasible but were not examined because the analysis showed little difference in variable and operating maintenance costs among the four paths that were studied. 6-12 Figure 6-12 Transmission Additions in Alternative 3 Transmission Additions Alternative 3 Bell Noxon Great Falls Taft Ashe Hot Springs Broadview Missoula Colstrip Ringling Grizzly Midpoint 500 kV Boise Kinport 345 kV Dave Johnson Borah LRS Ben Lomond Naughton Table Mtn. IPP Additional DC Added Series Compensation Only Ant Mine Jim Bridger 230 kV This export alternative requires two- 500 kV lines Option 1 Miners Mona Cheyenne Tap Ault Option 2 Emery Grand Junction Tesla Green Valley Red Butte Crystal Added Phase Shifter Option 3 Market Place Added Transformer Option 1 only Adelanto Option 4 Option 2, 3, &4 only The major differences in new transmission between Alternative 2 and Alternative 3 within the RMATS region were: elimination of a second 345 KV line from Wyoming to the Colorado front Range; the addition of a 345 KV line from Colorado to Utah; the upgrading of transmission from Wyoming to Idaho and from Wyoming to Utah from 345 KV to 500 KV; the addition of a 500 KV lines between Idaho and Utah; and additional series compensation on the existing 500 KV line within Montana. To move power from Montana to Washington State a new 500 KV line was investigated. To move power from Utah to Southern Nevada a new 500 KV line was investigated. Three optional 500 KV lines were identified to move power from Idaho to southern Nevada, Northern California, and central Oregon. The combined options modeled were: New transmission from Montana to Washington plus from Idaho to Northern California; New transmission from Utah to southern Nevada plus from Idaho to Northern California; New transmission from Utah to southern Nevada plus from Idaho to central Oregon; and New transmission from Idaho to southern Nevada plus from Idaho to California. Common to all the options was the addition new converter equipment to the 500 KV DC line from Utah to Southern California (the IPP line) to increase its capacity by 500 MW. The TAWG did not propose two new 500 Kv lines terminating in the Northwest because 6-13 it is believed the delivery of that much power in the Northwest would require upgrades of the Pacific Intertie to then move the power to California. All of these combinations of optional routes to move power out of the RMATS region resulted in roughly similar reductions in annual variable operating and maintenance costs throughout the interconnection, between $741 million and $774 million. Most of those savings in reduced variable operating and maintenance costs fell outside the RMATS region. DO WE KNOW HOW MUCH OF THE SAVINGS IS ATTRIBUTABLE TO TRANSMISSION CONSTRUCTION? A complete table of changes in annual operating and maintenance costs under Alternative 3 can be found in Appendix 1. The analysis showed that each of the transmission configurations for exports under Alternative 3 would result in significant cycling of coal-fired power plants due to the addition of large amounts of wind generation. Such cycling of coal generation can create transmission instability and excessive wear and tear on power plants. However, this analysis needs additional refinement since the dispatch of hydroelectric generation and wind generation were “hardwired” into the model (as opposed to allowing the model to optimizing the dispatch of generation based on variable costs, as is done for other resources) and did not consider ways of altering hydroelectric and wind generation to minimize cycling of coal-fired power plants. Alternative 4: Exports Equal Two Times RMATS Load Growth Figure 6-13 shows resource additions in Alternative 4. As with Alternative 3, the additions reflect the announced plans of generation developers. No attempt was made to optimize the location of new generation to minimize costs. Generation in Alternative 4 is sufficient to meet load growth within the RMATS region and export power equal to two times the load growth within the region. Total generation in Alternative 4 is 11,700 megawatts. 6-14 Figure 6-12 Incremental Resource Additions in Alternative 4 750 Coal 1000 Wind 260 Gas 1000 Wind 1109 Coal 100 Wind 250 Wind 440 Wind 2100 Coal 125 Wind 125 Wind 50 Gas 800 Wind 575 Coal 230 Wind 320 Wind 1500 2450 Wind 950 Coal Wind 2500 Coal 575 Coal 140 Gas 250 Wind 603 Gas 1500 Wind 250 Wind Alternative 4 would create significantly more congestion than Alternative 3. 6-15 B.C. 11,700 MW added to Rocky Mtn. States % Percent of Time at Binding Limit Alberta Wash. Interface Name Opportunity Cost/Savings ($) Montana 42% West of Broadview $128,921 79% Montana – NW $251,693 Idaho 9% Idaho- Montana $103,932 100% Black Hills – C. Wyoming $175,556 96% Oregon Bridger West $272,351 Wyoming Utah 60% Nevada TOT 3 $100,932 55% Bonanza West $132,741 IPP DC $73,000 Alternative 4- no transmission additions Figure 6-14 Congestion If No Transmission Is Added in Alternative 4 (I don’t think the following figure could be right for Alternative 4.) TOT 2C $176,124 TOT 2A $86,407 California Colorado 47% 82% 50% New Mexico Arizona Mexico To accommodate the addition of new resources for export, the Transmission Work Group investigated two 500 KV DC lines from Wyoming to northern or southern California. 6-16 Figure 6-15 Transmission Additions in Alternative 4 Transmission Additions Alternative 4 Taft Missoula Broadview Colstrip Ringling DC Grizzly Midpoint 500 kV Wyodak Boise Kinport 345 kV Dave Johnson Borah Option 1 Jim Bridger 230 kV LRS Ben Lomond Naughton IPP Additional DC Added Series Compensation Only Miners Mona Cheyenne Tap Ault Option 2 Emery Grand Junction Tesla Midway Green Valley Red Butte Added Phase Shifter Added Transformer Ant Mine Crystal Market Place Vincent Adelanto Mira Loma Reductions in variable operating maintenance costs in Alternative 4 would amount to approximately $4.397 billion annually, of which $1.742 billion is attributable to the transmission additions. A complete table of changes in annual operating and maintenance costs under Alternative 4 can be found in Appendix 1. Summary of Variable Operating and Maintenance Costs in Scenarios Figure 6-16 summarizes the Interconnection-wide variable operating and maintenance (VOM) costs in the scenarios compared with a reference case. The reference case assumes that resources added outside the RMATS region are those assumed in the natural gas scenario in the transmission study done by the Seams Steering Group-Western Interconnection (SSG-WI) released in October 2003. 6-17 Figure 6-16 Total Interconnection-wide Variable Operating and Maintenance Costs in Scenarios Alt 4- Opt 2 Alt 4- Opt 1 Alt 3- Opt 4 Alternativ Alt 3- Opt 3 e Alt 3- Opt 2 Alt 3- Opt 1 Alt 2 Alt 1 Reference Case 16,000 17,000 18,000 19,000 20,000 21,000 22,000 Total VOM Cost ($Millions) Sensitivity Analysis Note: I can’t put this note above “Sensitivity Analysis” so I’ll put it here. We need an additional figure with the deltas form the graph above. To examine the sensitivity of the model to different assumptions, the results of Alternative 3, option 3 (export of 3900 megawatts by the addition of new 500 kV lines from Utah the southern Nevada, from Idaho to Northern California, and from Utah to Southern California) were tested using alternative assumptions about hydro conditions, natural gas prices, and the addition of new generation in Nevada. In addition, model results were tested to determine the impact of potential carbon dioxide constraints and more aggressive demand side management programs. Hydro, Gas Price, Nevada Generation Sensitivity Analysis: High and low hydro conditions were assumed to be those which occur once every ten years. Low gas prices were assumed to be $4.50/mmbtu in 2013 nominal dollars ($3.60 in 2004$), compared with the base case of $6.50/mmbtu in 2013 nominal dollars ($5.20 in 2004$). To reflect the transmission impacts of potential new coal-fired generation and wind development in Nevada, the existing 1580 megawatt Mojave power plant in southern Nevada was assumed to be on line. The base case assumption is that the Mojave plant would be retired. Figure 6-17 shows the sensitivity of an export case (Alternate 3, option 3) to assumptions about additional generation in Nevada, low natural gas prices, high hydro conditions, and low hydro conditions. 6-18 Figure 6-17 Summary of Sensitivity Analyses Total Interconnection-wide Variable Operating and Maintenance Costs (Millions of Dollars) Add Mohave $4.50 Gas High Hydro Low Hydro Alt 3- Option 3 14,000 15,000 16,000 17,000 18,000 19,000 20,000 21,000 VOM Cost ($Millions) In summary, additional generation in Nevada, $4.50 gas prices and high hydro conditions would result in lower variable operating and maintenance costs than the reference case (Alternative 3, Option 3). Low hydro conditions would result in greater variable operating and maintenance costs than the reference case. Demand-side sensitivity analysis: To reflect more aggressive demand-side management programs, it was assumed that energy use within the RMATS region would grow by 1.0% less per year than assumed in the reference case and energy use outside the RMATS region would grow by 0.5% less per year than assumed in the reference case. Peak load reduction would be 1.5 times the energy reduction. With a couple of years of phase in and the 5 year period between 2008 and 2013, peak loads in the RMATS region in 2013 would be reduced by 12% and energy by 8% while in the coastal states the deduction would be half that due to their already more aggressive demand-side programs See Appendix 1 for discussion of these assumptions. Figure 6-18 shows load growth in each of the regions of the Western interconnection using these assumptions. For example, using these demand-side management assumptions, load growth in the RMATS region between 2008 and 2013 would be only 100 megawatts. 6-19 Figure 6-18 Change in Loads with DSM Est. Load After Assumed DSM Factor Region Annual Energy MWh RMATS 149,196,529 Az, NM, S. Nv 149,915,758 California 323,394,364 Or,Wa, N. Nv 185,403,864 Canada 134,489,410 Mexico 19,896,003 Totals Summer Peak MW 23,803 29,432 58,965 25,610 16,446 3,626 962,295,928 Winter Peak Peak Growth MW Summer (from 2008) 21,823 100 21,241 883 45,070 522 31,003 753 21,831 132 2,600 1,130 157,882 143,568 3,520 Using these assumptions, there is little need for new generation or transmission to meet demand within the RMATS region in 2013. To test the value of transmission to support exports from the RMATS region under the DSM assumptions, the resources in Alternative 2 (“Pseudo” IRP for the RMATS region) were modeled using two of the 500 kV transmission additions in Alternative 3 (MT to the Northwest and Utah to Southern California). ( Replace this figure with Alternative 3 or eliminate it.) Transmission Additions Alternative 4 Taft Missoula Broadview Colstrip Ringling DC Grizzly Midpoint 500 kV Wyodak Boise Kinport 345 kV Dave Johnson Borah Option 1 Jim Bridger 230 kV LRS Ben Lomond Naughton IPP Additional DC Added Series Compensation Only Miners Mona Cheyenne Tap Ault Option 2 Emery Grand Junction Tesla Midway Green Valley Red Butte Added Phase Shifter Added Transformer Ant Mine Crystal Market Place Vincent Adelanto Mira Loma Total Interconnection-wide variable operating and maintenance costs under these assumptions were $17,905 million annually, which is $1,921 million less than the 6-20 variable operating and maintenance costs in Alternative 1 (RMATS utility IRPs and predominately gas-fired generation additions outside the RMATS region). Carbon constraints: To reflect potential carbon dioxide constraints, a sensitivity analysis was conducted assuming a $5/ton tax on carbon and a $15/ton tax applied to new plants (not existing plants). This level of taxation does not impact on the dispatch of plants that the model assumes are built. The impact of a CO2 adder on the decision on which existing plants to dispatch is much less than the impact of the adder on the choice of generation plant to build. Just as economics of choosing between driving a car or riding a bus become dramatically different if you already own a car, all the fixed costs of owning the car are not relevant and you only have the incremental running costs of the car to compare with the cost of the bus ticket. Thus, the greatest ability to reduce CO2 emissions occurs in the choice of which resources to build. The ABB Market Simulator focuses on the use of the transmission system and has limited abilities to analyze resource choices. Models utilities use in IRP efforts are better at evaluating resource addition options, however, these types of models typically have very limited capabilities to model the transmission system. For example, a quick analysis using various assumptions (e.g., $6/mmBtu gas, 35% capacity for wind, 85% for coal and gas, and assumptions on capital costs and carrying charges), shows that at a $5/ton CO2 adder coal is the lowest cost option. However, at $10/ton CO2 adder, wind becomes the lowest cost option. [LINK TO KURT’S SPREADSHEET ANALYSIS] 6-21 Summary of Changes in Monthly Locational Marginal Prices in the Alternatives The following maps show average monthly locational marginal prices in July 2013 in the reference case and for each of the four alternatives after transmission is added. DO WE HAVE SUCH CONTOUR MAPS? Transmission Technology Options The identification of transmission solutions to reduce variable operating maintenance costs in 2013 focused on the addition of new 230 kV, 345 kV, and 500 kV transmission lines, the addition of series compensation, and installation of phase shifters. New technologies are being developed to increase transfer capacity on existing lines within existing corridors. Many of these technologies may become commercial in the next few years. Figure 6- __ summarizes these technologies Figure 6Emerging Transmission Technologies Technology High-Temperature Superconducting Cables Overview of Technology Superconducting ceramic cables can carry much more current than standard wires of the same size, with extremely low resistance, allowing more power to flow in existing right-ofways. But the required refrigeration results in higher initial and ongoing costs. Underground Cables Underground cables transmit power with very low electromagnetic fields in areas where overhead lines are impractical or unpopular. Costs are 5 to 10 times that of overhead lines, and electrical characteristics limit AC lines to about 25 miles. New transmission conductors with composite cores, as opposed to steel cores, are both lighter and have greater current carrying capacity, allowing more power to flow in existing right-of-ways. A new core consisting of composite fiber materials shows promise as stronger than steel-core aluminum conductors and is 50 percent lighter in weight with up to 2.5 times less sag. New computer-optimized transmission line tower designs allow for more power to flow in existing right-of-ways. Advanced Composite Conductors More Compact Transmission Line Configurations Polyphase (six or twelve phase) Transmission Line Configurations Modular Equipment Ultra High Voltage Lines High-Voltage DC (HVDC) Practically all AC high voltage power transmission is performed using three phases. The use of six or even twelve phases allows for greater power transfer in a particular right-ofway with reduced electromagnetic fields due to greater phase cancellation. Modular equipment designs provide greater transmission system flexibility, allowing the grid to quickly adapt to changing usage. They could also facilitate emergency deployment from a “strategic reserve” of critical devices, such as transformers. Higher voltage lines can carry more power than lower voltage lines. The highest transmission voltage line in North America is 765 kV. Higher voltages are possible, but require much larger right-of-ways, increase need for reactive power reserves, and generate stronger electromagnetic fields. HVDC provides an economic and controllable alternative to AC for long distance power transmission. DC can also be used to link asynchronous systems and for long distance transmission under ground/water. Conversion costs from AC to DC and then back to AC 6-22 Technology Flexible AC Transmission System (FACTS) devices Energy Storage Devices Controllable Load Enhanced Power Device Monitoring Direct System State Sensors Overview of Technology have limited usage. Currently there are several thousand miles of HVDC in North America. FACTS devices use power electronics to improve power system control, helping to increase power transfer levels without new transmission lines. But currently they are expensive, making FACTS uneconomic for most transmission owners. Energy storage devices permit use of lower cost, off-peak energy during higher-cost peakconsumption periods. Some specialized energy storage devices can be used to improve power system control. Technologies include pumped hydro, compressed air, superconducting magnetic energy storage(SMES), flywheels, and batteries. Fast-acting load control has the potential to become an important part of transmission system control. Flexible load allows higher normal-power transfer levels since during system emergencies the load can be rapidly curtailed. Automatic load shedding (underfrequency, under-voltage), operator-initiated interruptible load, demand-side management programs, voltage reduction, and other load-curtailment strategies have long been an integral part of coping with unforeseen contingencies as a last resort, and/or as a means of assisting the system during high stress, overloaded conditions. Future advances in loadcontrol technology will leverage the advent of real-time pricing, enabling consumers to “back off ” their loads (either automatically through grid friendly appliances or through manual intervention) when the price is right. The operation of many power system devices, such as transmission lines, cables, and transformers is limited by the device’s thermal characteristics. The high operating voltages of these devices make direct temperature measurement difficult. Lack of direct measurements required conservative operation, resulting in less power transmission capacity. Newer dynamic sensors have the potential to increase transmission system capacity. In some situations the capability of the transmission system is limited by region-wide dynamic constraints. Direct system voltage and flow sensors can be used to rapidly measure the system operating conditions, allowing for enhanced system control. Wide area measurement systems (WAMS) use phasor measurements that are synchronized digital transducers that can stream data, in real time, to phasor data concentrator (PDC) units. The general functions and topology of this network resemble those of dynamic monitor networks. Data quality for phasor technology appears to be very high, and secondary processing of the acquired phasors can provide a broad range of signal types. Source: J. Hauer, T. Overbye, J. Dagle, and S. Widergren. 2002. Advanced Transmission Technologies. Issue Papers Several of these technologies have the potential of minimizing environmental impacts and local opposition to transmission expansion projects. Project sponsors should carefully examine the application of such technologies in their transmission plans. 6-23