Roads Service Plan 2012 - Shetland Islands Council

advertisement

SHETLAND ISLANDS COUNCIL

ROADS

Service Plan

2011-12

Roads

Infrastructure Services Department

Shetland Islands Council

Gremista

Lerwick

Shetland

ZE1 0PX

Table of Contents

SERVICE PLAN - ROADS ...................................................................................... 3

1.

INTRODUCTION .............................................................................................. 3

1.1.

S ERVICE A IMS ............................................................................................. 3

1.2.

Q UALITY M ANAGEMENT A IMS ........................................................................ 3

1.3.

Q UALITY P OLICY .......................................................................................... 3

2.

WHO WE PROVIDE THE SERVICES TO ........................................................ 4

2.1.

O UR CUSTOMERS ......................................................................................... 4

2.2.

O UR PLEDGES TO CUSTOMERS ...................................................................... 5

2.3.

O UR ENGAGEMENT WITH CUSTOMERS ............................................................ 5

3.

HOW WE ENGAGE WITH OUR STAFF .......................................................... 6

4.

WHAT WE DO AND WHY ................................................................................ 6

4.1.

O UR CORE ACTIVITIES ................................................................................... 7

4.2.

L EGAL REQUIREMENTS TO PROVIDE THE SERVICE ............................................ 7

4.3.

O THER LOCAL PLANS / STRATEGIES ................................................................. 8

5.

HOW WE WILL DELIVER ON SINGLE OUTCOME AGREEMENT

OUTCOMES ............................................................................................................ 9

6.

OUR DELIVERY OF CROSS-CUTTING CORPORATE THEMES ................... 9

6.1.

S USTAINABLE D EVELOPMENT ........................................................................ 9

6.2.

E QUALITIES ............................................................................................... 10

7.

RESOURCE MANAGEMENT......................................................................... 11

7.1.

R ESOURCE A NALYSIS ................................................................................. 11

7.2.

W ORKFORCE RESOURCES .......................................................................... 12

7.3.

I NFRASTRUCTURE RESOURCES .................................................................... 13

7.4.

F INANCIAL RESOURCES

– R EVENUE ............................................................. 15

7.5.

F INANCIAL RESOURCES C APITAL ................................................................ 17

7.6.

E FFICIENCY S AVING TO BE DELIVERED IN 2011-12 ........................................ 18

8.

SETTING OBJECTIVES AND TARGETS ...................................................... 19

8.1.

P ERFORMANCE M ANAGEMENT .................................................................... 19

8.2.

P ERFORMANCE I NDICATOR T ABLE ............................................................... 19

9.

ACTION PLAN 2011-12 ................................................................................. 21

10.

EQUALITY IMPACT ASSESSMENT .......................................................... 22

“YOUR VOICE” SURVEY RESULTS FROM 2005 AND 2008 COMPARED ........ 25

General Road Maintenance ............................................................................ 25

Gritting and Snow Clearing Operations ........................................................... 26

Street Lighting ................................................................................................. 26

CONDITION OF ISLAND ROADS – 2004 TO 2011 (RCI) .................................... 27

Page 2 of 27

SERVICE PLAN - ROADS

1. Introduction

1.1. Service Aims

The Roads Service exists to manage, maintain and improve our road network in a safe and cost-effective manner in order to support the economic and social development of Shetland. We do this by providing the services which are outlined in ‘Our Pledges to Customers’ in Section 2.2 of this plan.

The purpose of this Service Plan is to provide a management tool to achieve robust performance management and to secure continuous improvement and delivery of high quality services by:

identifying the correct resources required to deliver a quality service

analysing past performance and planning for future requirements

monitoring current service delivery

providing an Action Plan for service improvements

The Action Plan details the main activities that will be undertaken during the year based on:

an analysis of the service

service reviews

the legislative, local and corporate context within which the service operates

revenue and capital expenditure

The Service Plan will be reviewed periodically and performance indicators and projects will be reported to senior management and elected Members through service performance review sessions. Through the monitoring of targets and the

Action Plan, the Service Plan will assist in providing evidence for continuous improvement and add to the process of demonstrating best value for all areas of service delivery within the Roads Service.

1.2. Quality Management Aims

The aim of the Roads Service is to:

ensure the provision of a quality Roads Service which satisfies the needs of its customers

continually improve the quality of its operations

maintain and enhance Shetland’s road network and environment

1.3. Quality Policy

The Roads Service is committed to the following Policy:

All operations will have appropriate arrangements and resources in place with clear management responsibilities and documented procedures.

Page 3 of 27

Regularly monitor and review performance and set clear objectives and targets to ensure continuous improvement in how the service is provided.

Aim to provide a satisfactory service at the first attempt; any incident of underperformance will be investigated to identify its cause and improvements will be implemented to prevent its recurrence in a timely and professional manner.

Enable staff to be individually responsible for achieving a quality service in what they do.

Ensure staff who can influence the quality of the service are aware of their duties and responsibilities and are provided with adequate resources to fulfil them.

Provide training for staff to enable them to fulfil their duties and responsibilities and to support their personal development.

Identify and comply with all appropriate legislation and recognised best practice in roads, and anticipate future developments whenever possible.

Promote and encourage carbon footprint and waste awareness; encourage waste prevention, reuse of materials, recycling and good practice in order to reduce the impact on Shetland’s environment of the Roads Service’s operations.

Actively consult with customers and staff on the quality of the service provided.

Satisfy customers by continuously adapting the Roads Service to meet their current needs and future requirements.

The Policy is reviewed periodically in order to ensure its continuing suitability and to identify improvements in its effectiveness.

2. Who we provide the services to

2.1. Our customers

Our customers include:

all road users

all residents in Shetland

all visitors to Shetland

commercial and industrial businesses and enterprises

The provision of a comprehensive road and footway network benefits every business, visitor and person in Shetland and contributes to the social and economic well being of the community. It is not just car users and pedestrians that benefit; all transport, emergency and other services (including utilities) require a safe and well maintained road network to operate effectively and serve their customers. We also provide civil engineering advice, design and construction works for other Council departments and public bodies.

Page 4 of 27

2.2. Our pledges to customers

We will manage and maintain all public roads in Shetland as economically as possible to a standard that is satisfactory.

We will inspect all public roads and footways at the frequency given in the

Roads Maintenance Plan, and when asked to do so by the public.

We will identify those defects that exceed agreed local intervention limits, and carry out repairs, replacements and improvements as necessary.

We will check streetlights every 2 weeks (4 weeks in summer) to see that they are working, and repair any found to be faulty.

We will provide a winter service of gritting or snow clearing daily as required

(except Christmas day and New Year’s day) from 6am to 6pm (reduced service Sundays and public holidays), to minimise the danger to road users of ice or snow.

We will assess proposed improvements to ensure that they are the best solution with regard to environmental impact, safety, economy, integration with the plans of others, and social inclusion.

We will design and supervise the carrying out of these improvements.

We will work closely with ZetTrans to seek the best possible integration of all forms of internal and external transport.

We will provide professional engineering advice to other departments.

We will maintain a materials testing facility accredited to UKAS standards.

We will undertake construction works for other Council departments and services with our in-house workforce, supplemented as necessary by external contractors or sub-contractors.

We will operate the Scord Quarry to manufacture both coated material and dry products for road maintenance. We will sell quarry material to the wider construction industry at competitive prices.

We will endeavour to obtain Best Value for the Shetland Community from the resources allocated to Roads.

2.3. Our engagement with customers

Community Councils were consulted in Winter 2009/10 with regard to the biennial review of the Action Plan for the Maintenance, Improvement and Use of the Road

Network. This provides an opportunity for local input to our programmes of road maintenance and improvement, and allows local prioritisation of some minor works of greatest local concern, as well as our own prioritisation on technical grounds.

Community Councils were also consulted in 2009 for their views on the standard of

Road maintenance service we provide. We consult a wide range of organisations and individuals with respect to proposed traffic orders etc.

Statutory performance indicators have been collected and published annually allowing both changes to be monitored over time and also comparisons to be made with other authorities. We have developed a draft Roads Asset Management Plan

(RAMP) that is now available on the Internet. We are continuing to work with the

Society of Chief Officers of Transport in Scotland (SCOTS) to complete our RAMP

Page 5 of 27

and to develop a range of indicators to give improved comparisons between roads authorities across Scotland.

We provide information to the public via the press, local radio and the Roads section of the Council Internet site. Weather information (updated hourly) from our roadside weather stations is displayed on the Council web site, with the same information now also available on a web enabled mobile phone.

Councillors, Community Councils and the public often give us information or send us queries. Staff attend Community Council meetings from time to time as necessary, or when requested.

3. How we engage with our staff

Staff appraisals are now being carried out in line with Council policy. This provides an opportunity at least once a year to discuss performance generally and to identify development and training needs. The development of Job Families under Single

Status has introduced some additional development and training requirements for particular members of staff.

Service Management Meetings are held regularly, giving an opportunity to exchange information and monitor progress. Service Managers then pass on information and get feedback from the staff of their own section. For site-based staff, "toolbox talks" are used to pass on information and get feedback.

A Health and Safety Forum for Roads takes place every three months attended by management, union and non-union representatives. This provides an opportunity for health and welfare issues to be discussed, as well as safety.

4. What we do and why

The Roads Service is responsible for the maintenance, management and improvement of 1045 km (650 miles) of public roads in Shetland, including all bridges, footways, streetlights and other assets associated with them. As well as routine maintenance of the Road network, we also provide a winter service to treat ice or clear snow as necessary.

We also provide services to others from time to time. Examples include the provision of a winter service to schools, community facilities and the NHS. We also from time to time provide design, undertake construction or test materials for others.

We operate the Scord Quarry providing the only source of bituminous coated material in Shetland.

Page 6 of 27

4.1. Our core activities

Activities undertaken by the Roads Service include:

To ensure that all roads, footways, streetlights, traffic signals, culverts and bridges are inspected and maintained in accordance with our Roads

Maintenance Plan, and that defects, repairs, and planned maintenance works carried out are recorded.

To provide an early morning road inspection service as necessary during winter (except Christmas day and New Year’s day), and use the result of those inspections to decide if gritting or snow clearing is required. When required, to carry out gritting or snowclearing to minimise the danger and inconvenience to road users of ice or snow on public roads and footpaths.

To provide, in conjunction with the Police, an emergency call-out service in order to respond to any emergency situation affecting a public road anywhere in Shetland at any time.

To manage and operate the Scord Quarry, including the only bituminous coating facility available in Shetland, ensuring that a satisfactory supply of road making material is available locally at an acceptable price.

To work with the Police and others to minimise the number of deaths and injuries on roads in Shetland.

To implement traffic management measures, traffic orders or other measures to assist traffic flow and road safety.

To maintain the register of roadworks (excavations) by utilities and others, coordinating their work as far as possible to minimise disruption.

To provide Professional Engineering advice, Laboratory Services and carry out works for other departments of the Council, and other organisations.

To assess proposed road improvemen ts under the Council’s policy for the management of the Capital Programme, using the principles of the Scottish

Transport Appraisal Guidance (STAG).

To design and supervise works being done under the Councils capital or revenue programs, and in many cases to carry out the construction of these works.

4.2. Legal requirements to provide the service

The Council as Roads Authority has a statutory duty to manage and maintain all public roads in Shetland, but with some discretion allowed with respect to the standards of maintenance applied, subject always to the policies and priorities of the Council. The main legislation relevant to Roads in Scotland is:

The Roads (Scotland) Act 1984

The Road Traffic Regulation Act 1984

The Road Traffic Act 1988

The New Roads and Street Works Act 1991

The Transport (Scotland) Act 2005

Other relevant legislation includes:

Page 7 of 27

The Health and Safety at Work Act 1974

The Town and Country Planning (Scotland) Act 1997

The Road Traffic Reduction Act 1997

The Local Government in Scotland Act 2003

The Water Framework Directive

The Water Environment and Water Services (Scotland) Act 2003

The Water Environment (Controlled Activities) Regulations 2005

The Climate Change (Scotland) Act 2009

4.3. Other local plans/strategies

The Roads Service contributes to the Council's Corporate Plan of having good

Internal Transport within Shetland by continuing to maintain the road network to a high standard and improving it where appropriate.

Shetland’s Regional Transport Strategy was developed by ZetTrans and approved by the Scottish Government in 2008. It provides guidance to us in helping maintain good internal transport in Shetland. The Shetland Local Plan is used to help identify and prioritise the need, scope and scale of future road improvements required to accommodate future development in Shetland.

Our draft Roads Asset Management Plan (RAMP)provides an overview of the

Roads Assets under the stewardship of Shetland Islands Council. This plan has been developed in conjunction with other Scottish Authorities through the Society of Chief Officers of Transportation in Scotland (SCOTS). It provides a strategic approach that aims to identify the optimal allocation of resources for the management, operation, preservation and enhancement of the roads infrastructure to meet the needs of current and future customers, and to plan for the future renewal or replacement of those assets.

The Action Plan for the Maintenance, Improvement and Use of the Road Network provides a strategy and programme for the maintenance and improvement of the road network. It was sent out for consultation in November 2009 and was approved by the Infrastructure Committee in August 2010.

The Council approved our Roads Maintenance Plan in March 2006. It follows the principles laid out in the national Code of Practice for Maintenance Management

2005. Our Roads Maintenance Plan sets frequencies for safety inspections and intervention limits for defects to be rectified.

The Winter Maintenance Policy identifies the level of service that is provided in order to ensure that as far as reasonably practicable the road network remains safe and usable during periods of frost or snow. It was reviewed in 2010 and will be looked at again as the Council seeks to make budget savings.

The Verge Maintenance and Grass-cutting Policy identifies the level of service that is provided in order to ensure that as far as reasonably practicable the road

Page 8 of 27

network remains safe and convenient for use by both drivers and pedestrians while protecting the environment and biodiversity found along the roadsides.

It is Council policy to apply STAG appraisals or similar to transport projects before prioritising them and seeking to place them in the capital program.

5. How we will deliver on Single Outcome Agreement

Outcomes

The single outcome agreement doesn't have any directly measurable indicators that we can give values for. However there are a number of indicators that are indirectly relevant, as follows:-

Reduced incidence of accidents resulting in casualties, particularly home fires, road accidents and marine incidents.

Prioritisation of alcohol misuse as key community safety activity, including reducing drink-driving levels and alcohol related crime

Everyone should be able to access the places, services and opportunities that they need to reach.

Decrease road traffic levels

Decrease the use of single occupancy private cars

Two indicators in particular have direct relevance to the service we provide, these are: -

LI 25: Increase percentage of residents who rate the area within 15 minutes walk of their home as fairly safe or very safe

LI 26: Reduce number of people killed or seriously injured on our roads and

St 1.1: Percentage of journeys to work made by public or active transport

6. Our delivery of Cross-cutting Corporate Themes

6.1. Sustainable Development

Most road inspections are now carried out using tablet computers which not only provide a better record, but also minimise the amount of paper usage. An added advantage is that it has allowed us to put in place an arrangement where one of our inspectors living in the North Mainland is able to carry out inspections in the north part of Shetland, wirelessly link into the Council computer network by parking near the Community Work Office at Brae, download the work he has done and return home without having to travel into Lerwick.

Roads is one of a small number of services within the Council where the majority of our staff work locally in the area in which they live. In addition to that, we have put

Page 9 of 27

in place a system where the majority of road workers travel directly from home to the site at which they are working rather than incur unnecessary mileage and time travelling to a central depot at the start and end of a day’s work. Using a shared

Council vehicle to do this reduces mileage and expense to the Council and also reduces private mileage to and from work by the individuals concerned, minimising our carbon footprint in respect of travel to and from work by staff.

In common with all other services across the Council, we are working towards a

5% per annum reduction in fuel usage by Council vehicles.

As part of the Winter Service we purchase weather forecasts for our road network and use these to ensure that pre-salts are only carried out when necessary. We also calibrate and check all of our gritters before the start of each season. Both of these measures ensure that we minimise salt usage to keep down costs and to protect the environment.

An Environmental Audit of our service has been carried out by the Waste

Prevention Unit (Environment), we are working with them to implement the recommendations of their report.

The Scord Quarry is now able to recycle road construction materials. We have just processed around 2000 tonnes of excavated road construction materials, which would previously have been sent to landfill.

We are currently looking at a project to replace our steam heated bitumen storage tanks at the Scord Quarry. The bitumen currently held in those tanks is heated by an oil-fired boiler producing steam. Those tanks have no insulation, the boiler is over twelve years old and the heating system is very inefficient. We are developing a spend to save project to replace these tanks with insulated tanks with integral electrical heating. If we are also able to increase storage capacity, we will be able to benefit from greater discounts for bulk purchase of bitumen. If this project gains approval then there will be a significant reduction in both the quarry’s costs and carbon footprint.

We are also looking at a scheme to replace the current fuelling and fuel tank system (Gas Oil) with a new tank and fuel (Kerosene). This will provide a substantial cost saving to the Council and is a cleaner burning fuel.

6.2. Equalities

Managers and other staff are trained to ensure that they correctly follow the

Council’s recruitment and selection Policy and procedures. That ensures that all applicants for jobs are treated properly and equally, in line with Council policy.

We have agreed flexible working arrangements with staff to help accommodate their childcare arrangements etc. Examples include flexitime and changes in working hours or working partly from home.

Page 10 of 27

To help members of the public with a disability or with mobility problems, we provide dropped kerbs at new junctions and have a programme of upgrading existing junctions wherever possible. We have provided tactile paving at all Pelican crossings. We have provided disabled parking spaces in most of the larger public car parks, and we regularly provide disabled parking spaces in residential areas in response to individual needs.

7. Resource Management

7.1. Resource Analysis

The length of the road network is increasing gradually, as the Council adopts roads in new housing developments for example. However use of the road network is increasing more significantly, with traffic volumes increasing at approximately 2.5% per year. The increasing weight of individual vehicles using the road, for example articulated lorries serving fish firms, has a detrimental effect on the structure and edges of the road, particularly narrow single track roads with inadequate foundations. There are no signs that the growth in traffic volumes is likely to reduce in the near future.

Extensive cracking and potholes developed in many of our minor roads following the long and severe frost of winter 2009/10 and similarly 2010/11. It has been necessary to divert money from other road maintenance budgets to seal these cracked roads before further deterioration develops. The extent of the problem is such that we will not be able to address all of the cracked roads during this surface

-dressing season (May to September) so a system of prioritisation has been implemented.

The difficulty encountered in obtaining sufficient salt supplies has highlighted the need for increased salt storage in Shetland. We are investigating the acquisition of a salt store to give more storage and allow salt to be kept longer without it deteriorating. A salt store will also avoid the environmental issues of open storage.

Recent increases in crude oil prices have fed through to significant increases in the cost of bitumen, fuel and electricity. That has led to a significant increase in the cost of bituminous-coated material used for road maintenance. With budget reductions this means that the amount of resurfacing and surface dressing that can be done in any one year is reduced. We strive to minimise the effect of this through efficiency savings and more efficient working, but to keep within existing budgets the lengths of road we will be able to resurface this year is less than was possible in the past.

Above inflation increases in the cost of electricity have an effect on our street lighting budgets, as does the adoption of roads in new housing schemes that add more streetlighting to maintain. We are worki ng to reduce the Council’s carbon footprint, and our electricity costs, by ensuring that only energy efficient lighting is installed in new schemes and that older inefficient lights are replaced with more efficient lighting units whenever the opportunity arises.

Page 11 of 27

The increasing number and age of streetlights is adding extra pressure to our streetlighting maintenance operation. The present work team of one vehicle with two men has difficulty in the winter months in maintaining all the streetlights throughout Shetland, although it would be difficult to justify a second team. That is a resource issue that will have to be considered over the next year.

7.2. Workforce resources

The present staff structure and numbers are as follows:

Amended Structure from 2006

Head of

Roads

Network & Design

Manager

Maintenance

Manager

Materials Laboritory

2 staff

17 Network &

Design Staff

8 Maintenance Staff Quarry Manager

+ 9 Operatives

Description

Head of Service

Service Managers

Network and Design – Senior Engineers/QS

Network and Design – Engineers/Technicians

Network and Design - Inspectors/Clerk of Works

Maintenance - Area Engineers

Staff (FTE)

1

2

5

7 (plus1 apprentice)

4

4

Maintenance - other Engineers/Technicians

Maintenance - Area Foremen

Maintenance - Roads Operatives

Scord Quarry Manager

Scord Quarry - Foremen

Scord Quarry Operatives

Materials Laboratory

3 (plus1 apprentice)

4

70

1

2

7 (plus1 apprentice)

2

Total Roads Staff 112 (plus 3 apprentices)

The present review of Infrastructure Services means that the Roads Service is also being reviewed. In order not to pre-empt the outcome of that review, any new staff appointments are being kept to a minimum, and any that are essential are only being filled on a temporary basis. This means that one of our service managers is on a temporary contract, and the duties of one of our area engineers is being undertaken on a temporary "acting up" basis. Over the last 5 years we have reduced the number of office based staff by 3 and site staff by 8. This is a result of our efforts to improve efficiencies and our need to work within reduced budgets.

Page 12 of 27

All office staff are based at Gremista. Site staff are based at Gremista, Murrister,

Sellaness, Mid Yell and the Scord Quarry. Staff numbers have been gradually falling over the last few years; the present and expected high workload in the private sector is making it more difficult to recruit and increasing our concerns for future staff retention. Our workforce has been relatively stable for some time which means that the age profile is increasing and beginning to cause concern.

We have an ongoing programme of staff development and training to meet changing service needs. Both Health and Safety, and operator competence are important parts of our training programme. The Council has recently received a four-star rating out of five from the Health and Safety Executive from a survey of all

32 Scottish Local Authorities in relation to the Construction Skills Certification

Scheme. The rating is assessed on the overall participation within each Council, and on their competency checks of external contractors.

We are now an approved Training/Assessment centre for plant operations under

Construction Skills and have two approved trainer/testers and an internal verifier to ensure that the centre adheres to the scheme’s quality assurance requirements.

We are also approved to deliver S/NVQ level 2 awards in plant.

7.3. Infrastructure resources

Our office, main depot and store are at Gremista, and reflecting the fact that staff operates throughout Shetland, we have smaller depots at Sellaness, Murrister,

Dunrossness and Mid Yell. There is also an office with other buildings and plant at the Scord Quarry. The office accommodation at Gremista is adequate inside, although the external cladding is in poor condition and is now being replaced as part of a programme of works by Building Services. The building at Murrister is in poor condition and the replacement building is under construction. We had to vacate a building at Sellaness used as an area office and mess facilities for staff in order to provide accommodation for the Total project. It has recently been replaced by providing these facilities as an extension to our existing workshop/store.

We continue to update records of roads related assets on our computer based

Roads Maintenance Management System (RMMS). We have made good progress on most of this, although determining the age and true condition of some assets is difficult.

We have joined with all other Roads Authorities in Scotland in a SCOTS initiative to develop an Asset Management Framework for roads and road related infrastructure. This will allow a common approach to be taken to the assessment and valuation of roads and associated infrastructure throughout Scotland. The first version of our RAMP has been completed and is now in use.

A breakdown of road length by road classification is listed in the following table:

Page 13 of 27

Road

Category

A Class

B Class

C Class

Unclassified

Total

Length

2 Lane

181

34

27

85

327

Length

Single Track

44

128

172

374

718

Total Length

(kilometres)

225

162

199

459

1045

Built on

Peat*

20%

19%

12%

16%

*Note – definition of “Built on Peat” includes only those roads with a structural depth of less than 650mm carrying more than 20 HGVs per day. These figures are approximate, being taken from an estimate made some years ago.

In common with all local authorities in Scotland, road maintenance expenditure has fallen in real terms and resulted in the deterioration of the condition of roads in

Shetland. We undertake an annual Road Maintenance Condition Survey jointly with all other roads authorities in Scotland. It is a machine-based survey and measures rutting, surface texture, longitudinal profile and cracking. This provides independent and consistent information on road condition over time throughout

Scotland. Every year 100% of the Class A network is surveyed, along with 50% of

Class B roads and 10% of the remaining roads. This provides a Road Condition

Index (RCI) which is used as a Statutory Performance Indicator.

The results of the road condition survey for Shetland, Orkney and the Western

Isles over recent years is shown at Appendix 2. An increase in the RCI indicates deterioration in the condition of the road. The deterioration in RCI by road class of

Shetland’s roads over the last five years is given below. From it you will see that after five years 3.8% or an additional 40.5 km of the road network is no longer considered to be in an "acceptable condition".

Shetland Roads

Length of road (Km)

Class

A

Class

B

225 162

Class

C

199

Unclassified

459

Total/ overall

1045

RCI - 2009/11

RCI - 2004/06

Deterioration during last 5 years (RCI)

Length deteriorated in last 5 years until it is no longer in an

"acceptable condition" (Km)

24.7% 38.2% 38.8%

18.3% 33.1% 34.5%

6.4%

14.4

5.1%

8.3

4.3%

8.6

50.3%

40.3%

2.0%

9.2

40.7%

36.9%

3.8%

40.5

Our Roads Maintenance Plan developed a hierarchy for road maintenance that addresses some of the anomalies found in the national road classification. The result of that revised classification is as follows; M1 = 225km, M2 = 186km, M3 =

231km, M4 = 404km. Essentially we have identified that for maintenance purposes some of our local roads are more important than the national classification suggests.

We have approximately 7500 traffic signs, over 4000 streetlights, 432 Cattlegrids and 56km of crash barriers to maintain, as well as several thousand bridges and culverts throughout Shetland, 300 of which are larger than 900mm span/ diameter.

Page 14 of 27

7.4. Financial resources – Revenue

Revenue Estimates 2011/12

Support General Trading

Ledger

£

Ledger Account

£ £

Client Receipts

Overall

Total

£

(74,639) (25,000) (6,658,715) (6,758,354)

Financing 0

Grants

Reimbursements

Rents

(250) (70)

0

(320)

0

Total Income (74,889) (25,000) (6,658,785) (6,758,674)

Employee Costs:

Allowances

Basic Pay

National Insurance

Other

Overtime

Pension Contributions

64,356

928,990

77,792

(39,594)

16,957

206,065

136,460

12,418

396

24,153

162,920

1,617,014

140,109

5,387

227,850

315,683

363,736

2,546,004

230,319

(33,811)

244,807

545,901

Sub-Total Employee

Costs

Operating Costs:

Administration

Agency Payments

Property & Fixed Plant

Supplies & Services

Transport & Mobile Plant

1,254,566 173,427

50,565 56,800

200 4,000

299 4,092,233

25,600 311,200

66,662 272,747

2,468,963

23,320

157,514

2,584,745

2,799,728

3,896,956

130,685

4,200

4,250,046

2,921,545

3,139,137

Sub-Total Operating

Costs

Transfer Payments

Total Expenditure

Net Controllable

Expenditure 2011/12

143,326 4,736,980

1,397,892 4,910,407

1,323,003 4,885,407

5,565,307 10,445,613

0

8,034,270 14,342,569

1,375,485 7,583,895

Net Controllable

Expenditure 2010/11

Net Controllable

Expenditure 2009/10

1,441,369 5,548,702 1,457,408 8,447,479

1,313,343 5,401,461 1,818,031 8,532,835

Page 15 of 27

From the preceding table you will see that "Net Controllable Expenditure" has been reduced by almost a million pounds over the last three years at a time when construction inflation has been higher than general inflation. This means that in order to stay within budgets the amount of maintenance that can be carried out has been significantly reduced.

This can be seen in the table below, for examples it has been necessary to reduce the "Resurfacing" budget by about 30% for 2011/12, in addition to cuts made to this budget in earlier years. The effect of this over the years has become apparent with increasing numbers of potholes now appearing in our roads.

Revenue Budgets (Operating Costs Sub-Codes)

Code Description 2010/11 £k No Growth 2011/12 £k

GRY6501 Grass Cutting - Verges

GRY6511 Drainage Maintenance

44

432

44

292

40

292

GRY6521 Traffic Signs

GRY6531 Road Markings & Cats Eyes

GRY6541 Roads Sweeping

GRY6551 Street Lighting - Maintenance

72

228

61

326

72

225

61

369

52

225

61

369

GRY6552 Christmas Lighting & Trees

GRY6555 Routine Maintenance General

GRY6601 Localised Reconstruction

GRY6605 Patching

GRY6611 Resurfacing

GRY6615 Footpath Maintenance

GRY6625 Surface Dressing

GRY6635 Road Drainage Improvements

GRY6645 Verge Maintenance

GRY6655 Crash Barriers and Railings

GRY6665 Minor Improvements

GRY6675 Streetlighting (Renewals)

GRY6681 Sea Defences

GRY6685 Structures (Retaining Walls)

GRY6691 Structures (Bridges & Culverts)

GRY6692 Cattlegrids

GRY6695 Structural Maintenance General

14

0

300

160

1,164

125

498

236

148

43

42

43

19

19

54

98

15

13

300

325

1,139

125

498

236

149

40

40

43

18

18

54

86

13

23

7

18

54

43

13

13

300

325

802

75

498

166

104

20

0

GRY6701 Road Authority Functions

GRY6711 Surveys & Inspections

GRY6721 Winter Service

GRY6731 NRSWA Functions

GRY6741 Road Safety

GRY6761 Roads Asset Management

Total Revenue Budget

15

49

1,105

6

2

57

5,375

8

56

1,312

3

2

57

5,598

8

56

1,279

3

2

57

4,905

Page 16 of 27

(Operating costs)

7.5. Financial resources - Capital

Capital Programme - Roads Rolling Programmes

Code Programme

GCY 9200 Minor Works and Purchases

GCY 9201 Development Related Roads

GCY 9202 Bridge and Culvert Replacement

GCY 9203 Footways

GCY 9204 Streetlighting Replacements

GCY 9206 Traffic Management

GCY 9207 Accident Investigation and Prevention

GCY 9208 Minor Works Air Services

GCY 9209 Minor Works and Purchases Bus Services

GCY9210 Road Reconstruction

GCY 9211 Roads Drainage Improvements

GCY 9212 Crash Barrier Replacements

Total – Rolling Programmes

Capital Programme - Named Schemes

Code Programme

GCY 6125 B9071 Bixter to Aith Phase 2 (Contract issue & start)

GCY 6130 B9082/3 Gutcher to Cullivoe (Design)

GCY6129 B9071 Parkhall to Sand Junction

GCY 6126 Sletts Road Sea Wall (Works)

GCY 6131 Gulberwick road (Design)

GCY 6298 Advance Design of Schemes (Design)

GCY 6127 Replacement Murrister Depot (Works)

GCY 9213 School Speed Limits (carried forward from last year)

GCY 6401 Scord Quarry Fixed Plant Replacement (Equipment)

B 9071 Effirth

GCY 6132 Gremista Footways

GCY 6205 Laxaburn Bridge

GCY 6207 Strand Loch Brig

Total – Named Schemes

2011/12

£k

£50

£100

£310

£75

£200

£50

£100

£20

£40

£445

£80

£120

£1,590

2011/12 £k

£1000

£30

£11

£5

£10

£110

£135

£82

£223

£20

£272

£10

£10

£1,918

Page 17 of 27

7.6. Efficiency Saving to be delivered in 2011-12

Description of

Efficiency Measure(s)

Procurement

Asset Management

Street Lighting

Shared Services

Absence Management

Reducing Bureaucracy

Vehicles

Other

Amount to be saved (£)

Significant, but not quantified.

Significant, but not quantified.

5% of fuel used

Impact on service delivery and performance / other information

The majority of materials used by

Roads come through the stores at

Gremista who have experienced staff to ensure that procurement is done efficiently. The Council decision to join Scotland Excel gives another opportunity for efficient procurement. A significant amount of maintenance and improvement work is subject to competitive tender. Works done by ourselves is subject to an annual review.

We undertake regular inspections of the road network and associated assets to allow us to effectively plan road maintenance in line with our agreed road hierarchy.

When old streetlights are replaced, more energy efficient lamps are used whenever possible.

Through the Society of Chief

Officers of Transport in Scotland, we have joined with all other

Scottish authorities to develop and share the costs of an Asset

Management Plan for roads.

Return to work interviews are carried out in line with council policy to minimise absences.

We now have the majority of inspection processes computerised to minimise paperwork.

Council policy to reduce fuel use by

5% with minimum effect on service.

Regular staff training is undertaken to ensure that work is done as efficiently as possible.

Page 18 of 27

8. Setting objectives and targets

8.1. Performance Management

Managers Performance Indicators

Employee sickness absence rate

Employee review and development sessions carried out

Percentage of Key Service Performance

Indicators met or exceeded target

Health and Safety - days lost due to injury/accidents at work

Reduction in diesel usage

Reduction in Gas Oil usage - Scord

Reduction in Gas Oil usage - others

Reduction in electricity usage - Scord

Reduction in electricity usage - others

Reduction in energy use

Customer complaints (formal)

Actual

2008-09

4.28%

Actual

2009-10

4.95%

3.4% 17.5%

29.5%

(39%)

6.3%

0

15.5%

(32%)

0

8.2. Performance Indicator Table

Service Performance Indicator

Carriageway condition - Road network that should be considered for maintenance; Overall

Carriageway condition - A Class Roads

Carriageway condition - B Class Roads

Carriageway condition - C Class Roads

Carriageway condition - Unclassified

Roads

Carriageway treatment - Percentage resurfaced

(Statutory)

Carriageway treatment - Percentage surface dressed (Statutory)

Traffic light failures (Pelicans) - Repair completed within 48 hours (Statutory)

Street light failures - Repair completed within 7 days (Statutory)

Street lighting

– Columns over 30 years old

Bridge Condition - Percentage failing assessment (Statutory)

Emergency jobs rectified or made safe within

24 hours - Percentage compliance

Actual

2008-09

38.5%

16.3%

29.9%

32.4%

55.1%

Actual

2009-10

39.3%

21.8%

33.9%

35.9%

51.2%

1.8%

4.1%

6.9%

88.1%

1.2%

13.1%

71%

2.1%

6.1%

26%

91%

3.8%

20%

71%

Target

2011-12

4%

100%

60%

Vision

Zero

5%

1%

0

Target

2011-12

39.3%

21.8%

33.9%

35.9%

51.2%

1.3%

6%

50%

80%

1%

6%

95%

Page 19 of 27

Service Performance Indicator

Actual

2008-09

Actual

2009-10

Target

2011-12

Winter Service - Presalts done in afternoon

Winter Service - Morning or daytime treatments of ice or snow

27

50

46

94

23 (As below)

46

(Ave. over last 5 years)

Workforce completed H&S construction skills test - site staff

100% 100%

Workforce completed H&S construction skills test

– office based staff

94% 100%

The performance of Roads is monitored in line w ith the Council’s Performance

Management Framework by service performance review sessions with elected members and senior management. In addition to monitoring performance and informing members and senior management of progress within the service, these review sessions also provide useful feedback to service managers.

Well over 90% of the workforce has a valid CPCS/CSCS competency card demonstrating a good understanding of health and safety on site and if appropriate their ability to operate construction plant safely.

We take part in a benchmarking exercise using APSE’s (Association of Public

Service Excellence) Performance Network scheme, which compares our performance against similar UK authorities over a range of indicators.

Indicator SIC result Group Average

93.75% 93.17% Damaged roads/pavings made safe within target time

Percentage of staff absences (front-line) 5.19% 5.82%

66.96

7.62

Community consultation and quality assurance 119

Number of accidents reported to HSE per 100 1.16 employees

Staff absence – all employees excluding long 1.81% term sickness

Annual cost of salting per kilometre of treated network

£1,186

2.14%

£2,118

Page 20 of 27

9. Action Plan 2011-12

Description of Action Officer Involved Expected Outcome

Carry out a review of the Winter Service to seek further savings.

Review Streetlighting Maintenance

Arrangements

Complete further STAG studies

Prioritise Footway Schemes

Head of Service

Network & Design

Manager

Network Engineer

Network & Design

Manager

Consult stakeholders, review service and consider options for change.

Review streetlighting maintenance policy to allow existing staff to cope with increasing number of lights

Complete a further 2 STAG studies to

Stage 2 for road improvements

Collect data required for 10 footway schemes to further develop a prioritisation scheme

Decision by Scottish Government Get all permissions in place for the A971

Haggersta road improvement

20mph speed limits at schools

Review single track road network

Review bitumen storage

Review budgets and seek further efficiencies and savings

Maximise efficiency of staff resources

Network & Design

Manager

Network & Design

Manager

Network & Design

Manager

Maintenance

Manager

All B RO’s

Complete 20mph speed limit programme at schools

Develop prioritised list of single track roads for improvement

Present a spend to save proposal to the

Council for the Scord Quarry

Introduce further efficiencies, as budgets are reduced

Provide design and construction services to others

Carry out a Traffic Study of Lerwick

Review NR&SW procedures

Improve B9071 Bixter to Aith road

Network & Design and Maintenance

Managers

Traffic Engineer

Network Engineer

Network & Design and Maintenance

Managers

Traffic Study of Lerwick

Review of NR&SW procedures following comments from the Road Works

Commissioner

Construct B9071 Bixter to Aith phase 2 road improvement

*EIA = Equalities Impact Assessment; SEA = Strategic Environmental Assessment

Completion

Date

Assessments

EIA* SEA*

July 2012 N/A N/A

November 2011 N/A N/A

February 2012 N/A N/A

February 2012 N/A N/A

March 2012

March 2012

October 2011

October 2011

October 2011

July 2012

August 2011

July 2012

N/A Yes

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

N/A N/A

Page 21 of 27

10. Equality Impact Assessment

Examination of Available Data

Data collection could include: consultations; surveys; Your Voice; Ethnic Minority

Profile; in-depth interviews; pilot projects; reviews of complaints made; user feedback; academic publications; consultants’ reports etc

9.a. What do we know from existing data and research?

From the “Your Voice” surveys done in 2005 and repeated in 2008, we have found that a majority of the public questioned found the service provided by

Roads satisfactory or better. See Appendix 1.

Within the “Your Voice” results, footpath maintenance had a lower satisfaction rating than most other operations. That may impact on groups like the elderly, disabled or young people who often have less access to motor vehicles.

National research has found that elderly drivers benefit from clear road markings, good levels of street lighting, etc.

9.b. What gaps in knowledge are apparent?

We don’t know if groups like the elderly are more disadvantaged than others by footpath maintenance or other of our operations.

9.c. If there are any potential difficulties in getting the data to fill these gaps, please describe these.

…………………………………………………………………………………………

…………………………………………………………………………………………

Step 3

10. Use the table to indicate:

(a) Where you think that the service / strategy / project / policy could have a negative impact on any of the equality target groups i.e. it could disadvantage them/unlawful racial discrimination.

(b) Where you think that the service / strategy / project / policy could have a positive impact on any of the groups or contribute to promoting equality, equal opportunities or improving/promote good relations within equality target groups.

Page 22 of 27

Gender

Women

Men

Race

Asian or Asian

British people

Black or Black

British people

Chinese people

People of mixed race

White people

People who’s first language is not English

Disabled people

Learning

Disabilities

Physical

Disabilities

Sensory

Impairment

Elderly/ Infirm

Mental Health

Lesbian, Gay men, Bisexuals and Transgender

Age

Older people

(60+)

Younger people

(17-25), and children

Children

Positive impact – it could benefit

Negative impact – it could disadvantage

Reason

Yes May not understand some road signs

Yes

Yes

Yes

Yes

Yes May not understand some road signs

Improvements, for example provision of drop kerbs, could reduce barriers to travel

Ditto

Ditto

20mph speed limits at schools should improve safety of children

Faith groups

Equal opportunities and/or improved relations

Yes Ditto

Ditto

Page 23 of 27

11. If you have indicated there is a negative impact on any group, is that impact:

Legal?

(i.e. it is not discriminatory under anti-discriminatory legislation)

YES

Intended?

NO

Level of impact

LOW

12. a) Could you minimise or remove any negative impact that is of low significance? Explain how:

............................................................................................................................

Our policy is to use nationally (and internationally) recognised road signs, many of which are pictorial, so minimising dependence on language for understanding.

..............................................................................…..........................................

……………………………………………………….………………………………… b) Could you improve the strategy, project or policy’s positive impact?

Explain how:

............................................................................................................................

............................................................................................................................

..........................................................................................................................

…………………………………………………………………………………………

………………………………………………………………………………………….

13. If there is no evidence that the strategy, policy or project promotes equality, equal opportunities or improved relations – could it be adapted so that it does?

How?

............................................................................................................................

............................................................................................................................

............................................................................................................................

............................................................................................................................

14. Do you have any further comments to make:

…………………………………………………………………………………………

…………………………………………………………………………………………

…………………………………………………………………………………………

Please sign and date this form, keep one copy and send one copy to the

Policy Unit.

Signed ................................................................

Date ....................................................................

Page 24 of 27

Appendix 1

“Your Voice” Survey Results from 2005 and 2008 Compared

A number of questions related to roads were included in the Autumn 2005 “Your

Voice” public opinion panel, with exactly the same questions repeated in Autumn

2008. By repeating exactly the same questions, it is possible to monitor changes in satisfaction levels.

General Road Maintenance

The responses were as follows to the question

“How would you rate the Council’s

Road Maintenance operation in each of the following areas of activity”

Operation

Repair of potholes and road surface defects

General standard of road surface

Road Markings

Roadside drainage, ditches and gullies

Survey date

Very

Poor

Poor Satisfactory

Good Excellent

2008 4% 15% 41% 29% 9%

2005

2008

8%

3%

22%

10%

47%

36%

16%

40%

2008 5% 11% 46% 32%

2005 7% 13% 45% 29%

7%

10%

2005 2% 13% 42% 29% 15%

2008 0% 5% 37% 47% 10%

2005 3% 10% 44% 32% 10%

5%

6%

Satisfactory or better

79%

70%

86%

86%

94%

86%

83%

80%

Road signs

2008 1% 6% 36% 45% 11%

2005 1% 7% 49% 33% 9%

2008 5% 18% 41% 32% 3%

92%

91%

76% General standard of footway maintenance

Frequency of cutting of grass verges

Extent of verges cut throughout the summer

2005

2008

2005

2008

2005

6%

6%

7%

6%

15%

13%

22%

15%

11% 19%

49%

43%

42%

42%

44%

23%

32%

23%

31%

21%

6%

6%

5%

6%

6%

78%

81%

70%

79%

71%

Note:- All sample surveys are subject to a degree of random error. It has become customary to provide an indication of the error margin by calculating the 95% confidence intervals for a simple random sample of the same size Of the 600 questionnaires sent out in autumn 2008, approximately 51% were returned. This means that statistically, for this size of the sample (308 questionnaires returned), the margin of error is +/-7%.

Therefore, although the majority of 2008 results show an improvement compared to those from 2005, none of those improvements are statistically significant at the 95% level. This is the same for all 3 tables in this Appendix.

Page 25 of 27

Appendix 1

Gritting and Snow Clearing Operations

The responses were as follows to the question “How would you rate the Council’s

Gritting/Snow Clearing operation in each of the following areas of activity”

Operation

Rural main roads

Rural minor roads

Survey date

Very

Poor

Poor Satisfactory

Good Excellent

2008 1% 5% 33% 45% 15%

2005 4% 8% 40% 36% 13%

2008 7% 22% 43% 22% 6%

Satisfactory or better

93%

89%

71%

Main Roads in

Lerwick

Minor Roads in

Lerwick

Residential areas/housing scheme roads

Main footways in

Lerwick

2005 12% 22% 39% 21% 6%

2008 1% 2% 22% 49% 26%

2005 1% 4% 32% 40% 23%

2008

2005

2005

2008

2005

1%

2%

4%

2%

5%

10%

13%

29%

7%

14%

40%

38%

45%

44%

39%

38%

33%

2008 5% 19% 49% 19%

24%

34%

30%

11%

13%

9%

6%

12%

12%

66%

97%

95%

89%

84%

77%

75%

90%

81%

Footways in residential areas

Provision of grit bins

2008 5% 19% 52% 16%

2005 13% 16% 44% 20%

2008

2005

2%

5%

18%

18%

45%

44%

29%

27%

7%

8%

6%

7%

75%

72%

80%

78%

Street Lighting

The responses were as follows to the question “How would you rate the Council’s

Streetlighting provision and maintenance”

Operation

Survey date

Very

Poor

Poor Satisfactory

Good Excellent

2008 2% 11% 38% 39% 9%

Satisfactory or better

86% Speed of repairs of street lights

Level of lighting provided

Extent of street lighting provided

2005

2008

2005

2008 3% 3% 35% 42% 17%

2005

2%

1%

2%

2%

5%

3%

4%

5%

53%

39%

47%

47%

30%

46%

37%

37%

10%

12%

11%

9%

93%

97%

95%

94%

93%

Page 26 of 27

Appendix 2

Condition of Island roads

– 2004 to 2011 (RCI)

RCI - Percentage of roads that need or should be considered for treatment

Year Shetland Orkney

Western

Isles

Scotland

A Class Roads

2004/06

20005/07

20006/08

2007/09

2008/10

2009/11

Average

18.3

21.0

19.9

16.3

21.8

24.7

20.3

18.1

26.0

27.1

19.0

26.3

24.4

23.5

41.8

41.8

43.6

42.6

45.8

48.8

44.1

27.4

28.6

29.2

28.5

29.6

30.3

28.9

B Class Roads

2004/06

2005/07

2006/08

2007/09

2008/10

2009/11

Average

33.1

34.5

33.1

31.5

33.9

38.2

34.1

16.7

17.8

20.9

18.3

27.5

29.3

21.8

39.5

37.9

37.9

39.1

41.8

45.2

40.2

32.2

33.4

34.2

33.6

34.9

35.8

34.0

C Class Roads

2004/06

2005/07

2006/08

2007/09

2008/10

2009/11

Average

34.5

35.8

35.7

32.4

35.9

38.8

35.5

15.8

24.0

19.9

9.8

15.7

17.4

17.1

43.3

46.3

46.5

44.6

47.5

51.6

46.6

31.0

31.9

33.0

32.7

33.2

34.3

32.7

All Classified Roads

2004/06

2005/07

2006/08

2007/09

2008/10

2009/11

Average

27.9

29.7

28.9

26.0

29.9

33.2

29.3

16.8

22.2

22.5

15.9

23.6

24.2

20.9

41.6

41.9

42.8

42.2

45.1

48.6

43.7

30.4

31.5

32.4

31.8

32.7

33.6

32.1

Unclassified Roads

2004/06

2005/07

2006/08

2007/09

2008/10

2009/11

Average

48.3

48.1

54.6

54.1

51.2

50.3

51.1

24.6

27.9

26.8

23.6

31.7

24.2

26.5

56.7

56.4

53.4

50.5

49.2

46.5

52.1

41.3

42.8

42.5

36.6

39.4

58.0

43.4

Overall Network

2004/06

2005/07

2006/08

2007/09

2008/10

2009/11

Average

36.9

37.6

40.2

38.3

39.3

40.7

38.8

20.4

24.8

24.5

19.5

27.3

24.2

23.5

48.0

48.0

47.3

45.7

46.9

50.6

47.8

35.9

37.2

37.4

34.2

36.0

37.9

36.4

Page 27 of 27

Download