Development Control Committee Meeting to be held on 18th April 2012 Electoral Division affected: Wyreside Wyre Borough: Application ref 02/12/0023 Engineering operations to construct an additional lagoon for the storage of mineral processing tailings and water for mineral washing. Sharples Quarry, Tarnacre Lane, St Michaels on Wyre, Preston. Contact for further information: Jonathan Haine, 01772 534130, Environment Directorate DevCon@lancashire.gov.uk Executive Summary Application - Engineering operations to construct an additional lagoon for the storage of mineral processing tailings and water for mineral washing. Sharples Quarry, Tarnacre Lane, St Michaels on Wyre, Preston. Recommendation – Summary That planning permission be granted subject to conditions controlling time limits, working programme, soils stripping, flood mitigation, noise and dust, protection of water resources, hours of operation, restoration and aftercare. Applicant’s Proposal Planning permission is sought for the construction of a lagoon for the storage and settling of silt from water used in the sand and gravel processing / washing operations. The lagoon would be rectangular in shape and would measure 80m x 50m. A number of soil and overburden (clay) mounds would be created from the materials excavated during the creation of the lagoon. The lagoon would be created by excavating the in situ soils and clay materials to a depth of approximately 5m. A small bund approximately 1m high would be created around the perimeter of the lagoon to act as edge protection required by health and safety legislation. Upon the lagoon becoming full with silt from the processing / washing operations, the lagoon would be allowed to dry out and then restored back to agricultural land using the previously stripped soils. Description and Location of Site The application site is located 4km south west of Garstang and 2 km north east of St Michaels on Wyre. The site is located within a larger area (56 ha) of agricultural land that has planning permission for the extraction of sand and gravel and associated mineral working activities. The southern and eastern boundaries of the quarry site are formed by the A586 Garstang to Great Eccleston road from where access to the quarry is taken. To the north and west of the site are large areas of flat, open arable agricultural land. The northern boundary of the site is formed by Sharples Lane which is an agricultural track and a public footpath. There are a number of properties along the southern and eastern boundaries of the site which are accessed off the A586 one of which is an organic horticultural practice at Brook House Farm. The application site is located within an agricultural field bound by hedgerows and a stream / ditch called the Longback Brook. Quarrying operations have commenced. The works undertaken to date include the stripping of soils and commencement of sand and gravel extraction in Phase 1, the construction of the site access, and stripping of soils and laying of hardcore within the proposed processing plant area. Background History Planning permission for the extraction of sand and gravel including the construction of a new access off the A586, processing plant and site support facilities and restoration of the site to agriculture and lake / wetland areas was granted on 10 th October 2005 (Ref 02/04/0652). The development has commenced. A current application (ref 2/12/0024) for the relocation of a water lagoon and relocation and increase in height of a raw materials stockpile is reported elsewhere on this agenda. Planning Policy National Planning Policy Framework Technical Guidance to the National Planning Policy Framework – Flood Risk and Minerals Policy Regional Spatial Strategy Policy DP7 Policy EM1 Promote Environmental Quality Integrated Enhancement and Protection of the Region's Environmental Assets Lancashire Minerals and Waste Local Plan Policy 2 Policy 7 Policy 8 Quality of Life Open Countryside and Landscape Trees, Woodlands and Hedgerows Policy 23 Policy 24 Policy 75 Policy 108 Policy 112 Water Resource protection Flood Risk Plant and ancillary development (on site) Restoration of agricultural land Standards of Operation Lancashire Minerals and Waste Local Development Framework (Core Strategy) Policy CS5 Achieving Sustainable Minerals Production Wyre Borough Local Plan Policy SP13 Development in the Countryside Policy SP14 Standards of Design and Amenity Policy ENV17 Surface Water Protection Consultations Wyre Borough Council – No objection. Kirkland Parish Council – No objection but are concerned that water will escape into the Longback Brook and ask who is responsible for monitoring such aspects of the operation. Upper Rawcliffe - with - Tarnacre – No observations received. Assistant Director - Highways – No objection. Environment Agency – Initially objected to the application as the area surrounding the site is in flood zone 2 and the design of the lagoons and soil mounds did not ensure that the risk of flooding elsewhere is not increased. They advised that all bunds must have 40mm pipes at ground level at 10m centres so they do not create an obstruction to flood waters. The objection has now been withdrawn subject to the imposition of a condition requiring all soil mounds on the site to be designed in a way that would allow the passage of flood water. The EA also advised that a bund and proposed tree planting belt near the site entrance and adjacent to the Humblescough Brook had not been designed to accommodate flood waters and would be within the 8m easement required for stream maintenance. The bund has now been moved outside of the easement and the EA acknowledge that the planting belt adjacent to the brook was a feature of the original application to which they did not raise objection at that time. Representations – The application has been advertised by press and site notice, and neighbouring residents informed by individual letter. Two letters of representation have been received. One letter has been received from the adjoining organic horticultural practice objecting to the proposal for the following summarised reasons: The operators are in breach of several conditions of the original planning permission. The design of the site has not been approved and therefore the use of this access in order to construct the lagoon will jeopardise highway safety on the A586 The quarry development will require the development of four lagoons. The fact that the operator currently only proposes to construct two lagoons is an attempt to split any larger development into a number of smaller elements thereby avoiding the need to undertake EIA. The site for the lagoon was to have been used for the plant site under the original application but was later amended to reduce the impacts of noise and dust on Brook House Farm. The construction of a lagoon in these fields would reintroduce these impacts. The exaction of the lagoon may encounter sand and gravel horizons rather than clay which would result in aquifer pollution or may impede the stability of the lagoon. The existing bunds have not been constructed with gaps in order to allow the passage of flood waters and have not been grassed to reduce dust. The existing flooding issues in the area prevent the retention of the 1 metre free board as is proposed. The figures on soil volumes are ambiguous The hydrological assessment has not been approved by the County Council or the EA. The organic horticulture business at Brook House Farm is a sensitive land use and therefore appropriate buffer zones should be retained. The bunds will not mitigate noise but additional noise will be created during their construction The dust monitoring equipment has not been installed correctly Great Crested Newts (GCNs) are located within a pond at Brook House Farm The second representation informs that a water vole was observed within the site in November 2011 contrary to the view expressed in the applicant's ecological survey. The resident considers that improvement works undertaken to the ditches within the site would have affected water voles. Advice Director of Transport and Environment – Observations Planning permission for the extraction of sand and gravel from land near St Michaels on Wyre (to be known as Sharples Quarry) was granted in 2005 (ref 02/04/0652). Some works to implement the planning permission including the construction of the site access, soil stripping in phase 1 and the excavation of some sand and gravel have taken place, but no minerals have yet been exported from the site to date. In order to produce clean aggregate materials that conform to the appropriate BS specifications for concreting and building applications, it is necessary to wash the 'as dug' materials to remove fine material (silt and clay) that would otherwise contaminate the processed materials and make them unsuitable as high quality construction materials. Specialist processing plant will be used to wash the minerals and allow the production of a range of high grade aggregate products. At most wet sand and gravel quarry sites, water is simply pumped from worked out parts of the excavation and used in the processing plant for washing purposes. However, at this site, the aquifer in the sand and gravel horizon is sensitive to further dewatering and therefore water pumped from active areas of the quarry must be generally returned to worked out areas of the quarry so that losses from groundwater are minimised. The washing process at this site must therefore operate on a 'closed loop' system with the washing water being continually recycled to be reused in the processing plant. It is therefore necessary to include sufficient lagoon capacity to allow the fine material washed out of the sand and gravel to be settled out allowing the resulting clean water to be reused in the plant. The applicant for this quarry development in 2004 was different to that currently holding the lease for the site. In the original application, no provision was made for any settling lagoons associated with the processing plant. Following the acquisition of the lease, the current operator has undertaken a review of the working scheme with a view to improving the efficiency of the quarrying operation. The operator therefore proposes the construction of a lagoon to be used to provide water storage and silt settling capacity for the site. Over time, this lagoon would fill with silt and therefore, depending on the quantities of silt within the raw materials, it may be that further lagoons are required in the future. However, the need for any further lagoons would be determined as part of future operations and if required would be the subject of further planning applications. The lagoon development is considered by the applicant to be essential to the economic viability of the quarry. If sufficient lagoon capacity cannot be provided, the sand and gravel materials could only be dry screened and consequently could not meet the more exacting standards demanded for higher specification construction materials. It is accepted that the proposed development would improve the quality of materials and is considered acceptable in principle. However, it is necessary to consider any environmental impacts that may arise from the development, in particular the visual and flooding impacts and amenity issues relating to the proximity of the horticultural business at Brook House Farm. In terms of landscape impacts, the lagoon would be sited in a field bound by hedgerows. The lagoon itself would be largely at ground level and therefore its landscape impact would be minor when seen from the nearest viewpoints such as from the A586 and the footpath along Sharples Lane to the north. The main visual impacts would arise from the additional soil and overburden mounds that would be required to store the materials arising from the excavation of the lagoon. As no silt lagoon provision was made in the original planning application, these visual impacts would be additional to those that were assessed when the County Council granted planning permission in 2005. With the exception of a short section of hedgerow that would need removal in order to allow vehicular access into the lagoon field, the new lagoon would not require the removal of any trees or hedgerows beyond those which were permitted under the 2005 permission. It is therefore considered that the visual impact of the proposal would be acceptable, particularly as it would be for a temporary period and would be restored back to agricultural use in the long term. In relation to flooding, the EA state that the area within which the proposed lagoon is to be constructed falls within an area identified as flood zone 2. The EA requires the proposed lagoon to be designed in a manner that would allow any flood waters to pass freely over the land and that failure to do so would increase the risk of flooding on adjacent land. The EA initially objected to the proposal as they considered that the proposed soil and over burden mounds would present a barrier to floodwaters. However, the mound design incorporates gaps to allow the passage of floodwater and a condition could be imposed requiring the mounds to incorporate such drainage measures. The EA have subsequently acknowledged this and have withdrawn their objection to this issue. The EA have also made comments in relation to landscaping works undertaken at the site access. However, these works do not form part of the development currently proposed, they formed part of the parent planning permission and to which the EA raised no objection at the time. Subject to the imposition of a condition requiring the peripheral mounds to incorporate the gaps to provide for the passage of flood water, the development is considered acceptable for the purposes of Policy 24 of the Lancashire Minerals and Waste Local Plan. In terms of impacts on amenity, objection has been received from the occupier of Brook House Farm, a commercial organic horticultural practice with the crops being grown in poly tunnels. The farm house is located approximately 300 metres from the proposed lagoon and, at their closest point, the poly tunnels are located approximately 200 metres from the proposed lagoon. The occupier is concerned with the general impacts on his amenity arising from the construction of the lagoons and that the construction would impact upon the horticultural business by increasing dust which could be deposited on his poly tunnels thereby affecting light levels and reducing plant growth. The creation of the proposed lagoon has the potential to increase noise and dust levels. However, the construction period would be for a relatively short period, the excavated and stockpiled soil mounds would be seeded and there would be no noise or dust generated once the lagoon is in operational use. The lagoon would need to restored on completion of the quarrying operations but this would only consist of the re - spreading of soil materials which would also be for a relatively short period. It is accepted that noise may be generated, but this would be for a temporary period. National Planning Policy Framework and supporting Technical Guidance recognise noise may increase for temporary periods for developments of this nature and which, subject to controls can be found acceptable. Conditions restricting noise levels, hours of working and silencing of plant during the construction phase of the lagoon could be imposed and which would be sufficient to reduce noise levels to acceptable levels. Any temporary increase in noise is therefore considered acceptable in this instance. In relation to dust, the materials to be excavated would consist of soils and clay which are likely to be wet or damp and generally would not generate high levels of dust. The operations most likely to generate dust would be the haulage of excavated materials to their storage locations. However, the excavated soil materials would be mainly stored on the perimeter of the lagoon and the clay would be used to partially backfill the phase 1 quarry excavation both of which would require relatively short haulage distances, reducing potential for dust generation. As part of the parent planning application, it was proposed to use the field within which the lagoon is now proposed for the processing plant and stockpiling area. However, the plant and stockpiling area was subsequently relocated further north to reduce amenity impacts on Brook House Farm. The owner of Brook House Farm has objected to the current application on the grounds that the location of the lagoon would reintroduce noise and dust impacts that had been ‘designed out’ of the original scheme. However, there is a clear difference between the two activities in that, once constructed the lagoon and soil storage would not generate noise or dust in a similar way to that which could be generated by the processing / stockpile area and which would have been active throughout the full period of the quarrying operations. The potential impact of dust on the agricultural practices of Brook House Farm is acknowledged. However, it is considered that the construction of the additional lagoon would not increase noise or dust to unacceptable levels. A scheme of dust mitigation and monitoring has been approved and the monitoring provisions in the scheme would enable the dust impacts of the quarry operation to be assessed and for mitigation measures to be increased if required. It is therefore considered that the development is acceptable in relation to amenity impacts and complies with Policy 2 of the Lancashire Minerals and Waste Local Plan and that there would be no sustainable reasons to object to the proposal. A number of other issues have been raised by the owner of Brook House and which are addressed as follows. Many of these issues are common to application 2/12/0024 reported elsewhere on this agenda. It is acknowledged that the operator has not fully complied with some of the conditions to the existing planning permission. However, the current operator is new to the site; the breaches have been identified as part of the monitoring of the site and the operator has been advised of the need to comply with the conditions. Irrespective of such breaches, the proposal must be considered on its merits and issues of compliance with the existing permission are not a material consideration. A number of issues have been raised with regard to the stability and safety of the lagoon and the risk of the aquifer being contaminated. The lagoon would be constructed by excavating the in situ clays the presence of which has been proven by previous geological investigations. The lagoon would be excavated to a depth of five metres below existing ground levels with the maximum depth of water being four metres. The water in the lagoon would therefore be entirely contained within undisturbed ground with a 1m free board being retained for geotechnical reasons. It is therefore considered that the lagoon has been designed appropriately having regard to the existing ground conditions and the principle of which and means of construction has already been found acceptable as part of the existing planning permission. The design and construction of the lagoon would also be subject to controls under the Mines and Quarries legislation with respect to safety. In response to the issues regarding contamination, it is acknowledged that the geology in this area is highly variable and that it is possible that the operator may encounter patches of sand and gravel rather than clay when constructing the lagoon. However, the silt to be placed in the lagoon would be derived from the sand and gravel materials that have already been excavated from the aquifer following the washing process. It is therefore considered there is no risk of contamination of the aquifer. In relation to Environmental Impact Assessment, the development falls within schedule 2 of the Environmental Impact Regulations as a 'change to or extension of a development listed in Schedule 1'. In such cases, EIA may be required depending on the location, scale and environmental impacts of the proposed development and whether the development as a whole as modified has significant adverse effects on the environment. A screening opinion has therefore been undertaken to assess whether this application should be subject to EIA. In view of the scale, location and nature of the development, it is considered that EIA is not required and that the environmental impacts of the development can be adequately addressed through the planning application process. In the event further lagoons are required to facilitate the future operational needs of the quarry, had those lagoons been the subject of a single planning application, it is considered that the thresholds in the EIA Regulations would not be exceeded to the extent that EIA would be required or that the development as a whole would be modified in a way that would have significant adverse effects on the environment to require EIA. In view of the scale, location and nature of the development, it is considered that EIA is not required and that the environmental impacts of the development can be adequately addressed through the planning application process. The resident has drawn attention to instances where the Longback Brook has been managed in a manner that is perceived to be damaging to ecological interests in particular water voles. However, the management works that have been highlighted appear to have been undertaken as part of normal agricultural management practices and have not been undertaken as part of the quarry development. The submitted ecological protection plan for the site contains provisions in relation to water vole protection but does not specifically prevent maintenance works such as those already undertaken. The resident has drawn attention to the location of a pond at the western end of his property which he states is habitat for GCNs. The applicant has submitted a GCN survey. However, the pond within Brook House Farm was not surveyed; the applicant has advised that access to the pond to undertake a survey was denied by the land owner. It has therefore not been possible to prove the presence or otherwise of GCN's or the numbers of the species that may present. However, the pond is approximately 60m from the proposed lagoon and associated soil storage. The land required for the lagoon is comprised of improved pasture used for agricultural grazing and therefore would not normally be optimal terrestrial habitat for GCNs, particularly in view of the presence of other more favourable habitats in the area such as the existing hedgerows. The lagoon development would not require the removal of any hedgerows in close proximity to the pond and therefore it is considered that the likelihood of any GCN habitat being affected by the proposed development is small. Irrespective, the developer has obligations under the Wildlife and Countryside Act in respect of European Protected Species; a note advising the developer to contact Natural England in the event that any GCN's are encountered during soil stripping operations is proposed. In conclusion, the development is required to ensure that the mineral resources at this site can be processed to allow the production of a range of high quality aggregate materials that meet BS specifications for construction purposes. The development would be acceptable in relation to landscape impacts and provided that conditions are imposed in relation to mitigation of noise and dust, it is considered that the impacts on amenity could be controlled to acceptable levels. Provided that mounds are designed appropriately, it is considered that the development would not increase the risks of flooding on adjacent land. In view of the scale, location and nature of the proposal, it is considered that no Convention Rights set out in the Human Rights Act 1998 would be affected. Summary of Reasons for Decision The development is required to ensure that the mineral resources at this site can be processed to allow the production of a range of high quality aggregate materials that meet BS specifications for construction purposes. The development would be located within an existing quarry environment and is acceptable in relation to local landscape character. Noise and dust levels associated with the construction of the lagoon would be for a short period and would not lead to an unacceptable loss of amenity. The geology of the area would support the construction of the lagoon and the materials which it is designed to accommodate would pose no risk to the aquifer. The design of the lagoon and peripheral soil storage mounds would ensure the free flow of water at times of flooding and the soil storage mounds would be grassed to minimise the migration of dust. There is no evidence that protected species have or would be affected. The development complies with the policies of the Development Plan. The policies of the Development Plan relevant to this decision are:National Planning Policy Framework Technical Guidance to the National Planning Policy Framework – Flood Risk and Minerals Policy Regional Spatial Strategy Policy DP7 Policy EM1 Promote Environmental Quality Integrated Enhancement and Protection of the Region's Environmental Assets Lancashire Minerals and Waste Local Plan Policy 2 Policy 7 Policy 8 Policy 23 Policy 24 Policy 75 Policy 108 Policy 112 Quality of Life Open Countryside and Landscape Trees, Woodlands and Hedgerows Water Resource protection Flood Risk Plant and ancillary development (on site) Restoration of agricultural land Standards of Operation Lancashire Minerals and Waste Local Development Framework (Core Strategy) Policy CS5 Achieving Sustainable Minerals Production Wyre Borough Local Plan Policy SP13 Development in the Countryside Policy SP14 Standards of Design and Amenity Policy ENV17 Surface Water Protection Recommendation That planning permission be granted subject to the following conditions: Time Limits 1. The development shall commence not later than 3 years from the date of this permission. Reason: Imposed pursuant to Section 91 (1) (a) of the Town and Country Planning Act 1990. Working Programme 2. The development shall be carried out, except where modified by the conditions to this permission, in accordance with the following documents: a) The Planning Application and supporting statement received by the County Planning Authority on 6th January 2012 Submitted Plans and documents: Drawing 0140/21/01 - Location Plan Drawing 0140/21/02 - Application Plan Drawing 0140/21/03 - Development Plan Drawing 0140/21/05 - Site Restoration Drawing 0140/21/06 - Lagoon Cross Section c) All schemes and programmes approved in accordance with this permission. Reason: For the avoidance of doubt, to enable the County Planning Authority to adequately control the development and to minimise the impact of the development on the amenities of the local area, and to conform with policies 2, 7, 8, 23, 24, 75, 108 and 112 of the Lancashire Minerals and Waste Local Plan and policies SP13, SP14 and ENV 17 of the Wyre Borough Local Plan. 3. The lagoon shall be restored in accordance with the scheme and programme of restoration approved under the requirements of condition 17 within one year of silt levels in the lagoon reaching a level of 6.9 metres AOD or by 31st March 2017 whichever is the earlier. Reason: To ensure the proper restoration of the site within an acceptable timescale and to conform with policies 2, 7 and 106 of the Lancashire Minerals and Waste Local Plan. 4. All available topsoil and subsoil shall be stripped from any part of the site before that part is excavated or traversed by heavy vehicles. All stripped topsoil and subsoil shall be retained on the site and stored in within the mounds as shown on drawing number 0140/21/03 - Development Plan for future use in the restoration of the lagoon. Reason: To ensure the proper removal and storage of soils to ensure satisfactory restoration and to conform with Policy 106 of the Lancashire Minerals and Waste Local Plan. 5. No movement of topsoil or subsoil shall occur during the period from the 1 October to 1 April inclusive without the prior written consent of the County Planning Authority. At other times the stripping, movement and respreading of top and subsoils shall be restricted to occasions when the soil is dry and friable and the ground is sufficiently dry to allow the passage of heavy vehicles, plant and machinery over it without damage to the soils. Reason: To ensure the proper removal and storage of soils to ensure satisfactory restoration and to conform with Policies 106 of the Lancashire Minerals and Waste Local Plan. 6. All topsoil, subsoil and overburden mounds shall be graded and seeded within six months of their construction and maintained in a fully grassed, weed free condition throughout their duration on the site. Reason : In the interests of the amenity of the area and to conform with policies 2, 7 and 112 of the Lancashire Minerals and Waste Local Plan. 7. With the exception of the raw feed stockpile, all temporary soil and overburden bunds shall be constructed with 400 mm diameter pipes at ground level at 20 metre intervals or 1 metre wide channels running the full width of the bund at ground level at 50 metre intervals so as to ensure the free flow of water. Reason : In order to prevent the flooding of adjacent land and to conform with Policy 24 of the Lancashire Minerals and Waste Local Plan. Noise and Dust 8. All mobile plant used in the construction and restoration of the lagoon shall be fitted with the types of reversing alarms described in the scheme and programme submitted on 13th October 2009 as modified by the email from Halletec Environmental dated 25th May 2010 and such equipment shall be actively employed throughout the development. Reason: To safeguard the amenity of local residents and adjacent properties/landowners and land users and to conform with Policies 2 and 112 of the Lancashire Minerals and Waste Local Plan. 9. All plant, equipment and machinery used in connection with the development, operation and restoration of the lagoon shall be equipped with effective silencing equipment or sound proofing equipment to the standard of design set out in the manufacturer's specification and shall be maintained in accordance with that specification at all times throughout the development. Reason: To safeguard the amenity of local residents and adjacent properties/landowners and land users and to conform with Policies 2 and 112 of the Lancashire Minerals and Waste Local Plan. 10. Noise emitted from the operations to develop and restore the lagoon shall not exceed 55dBLAeq (1 hour) (free field), as defined in this permission, when measured from any of the following properties at a point closest to the noise source: a) b) c) Tarnacre House Farm NGR 474 429 Brook House Farm NGR 473 425 Tarnacre Hall Cottages NGR 470 421 Reason: To safeguard the amenity of local residents and adjacent properties/landowners and land users and to conform with Policies 2 and 112 of the Lancashire Minerals and Waste Local Plan. 11. The noise limits set out in condition 12 above shall not apply during the stripping of soils and overburden from the lagoon site, the construction of storage mounds for these materials and their respreading during restoration of the lagoon. Noise from any of these activities shall not exceed 70 dBLAeq (1 hour) (free field), as defined in this permission, as measured from any of the properties identified in condition 12 at a point closest to the noise source. This condition shall only apply for not more than 20 days in any one calendar year unless otherwise agreed in writing by the County Planning Authority. A written record shall be made of the dates that these activities are taking place and shall be made available to the County Planning Authority on request. Reason: To safeguard the amenity of local residents and adjacent properties/landowners and land users and to conform with Policies 2 and 112 of the Lancashire Minerals and Waste Local Plan. 12. Dust mitigation and monitoring shall be undertaken throughout the duration of the development and restoration in accordance with the scheme and programme submitted under the requirements of condition 30 of planning permission 2/04/652 on 23rd July 2010. Reason: To safeguard the amenity of local residents and adjacent properties/landowners and land users and to conform with Policies 2 and 112 of the Lancashire Minerals and Waste Local Plan. Water Resources 13. Provision shall be made for the collection, treatment and disposal of all water entering or arising on the site to ensure that there shall be no discharge of contaminated or polluted drainage to ground or surface waters. Reason: To safeguard local watercourses and drainages and avoid the pollution of any watercourse or groundwater resource or adjacent land and to conform Policies 22 and 112 of the Lancashire Minerals and Waste Local Plan. 14. With the exception of the raw feed stockpile, all temporary soil and overburden bunds shall be constructed with 400 mm diameter pipes at ground level at 20 metre intervals or 1 metre wide channels running the full width of the bund at ground level at 50 metre intervals so as to ensure the free flow of water. Reason: To prevent flooding of adjacent land and to conform with policy 24 of the Lancashire Minerals and Waste Local Plan. Hours of Operation 15. No soil or overburden excavation or soil replacement in connection with the excavation or restoration of the lagoon, or formation or removal of soil storage mounds shall take place before 0800 hours or after 1700 hours Mondays to Fridays inclusive (except Public Holidays), or before 0800 hours or after 1300 hours on Saturdays or at any time on Sundays or Public Holidays. Reason: To safeguard the amenity of local residents and adjacent properties/landowners and land users and to conform with Policies 2 and 112 of the Lancashire Minerals and Waste Local Plan. Restoration 16. Within six months of the date of this permission, a scheme and programme of restoration for the site shall be submitted to the County Planning Authority for approval in writing. The scheme and programme shall contain details of the following:a) The proposed afteruses of the lagoon b) The depths of replacement of sub and top soils c) Measures for the treatment of soils including ripping to remove compaction and cultivation measures to provide a surface suitable for seeding d) Details of seed mixes to be used including rates of application e) Details of tree and hedgerow planting to close any gaps in the hedgerow required to access the lagoon from the processing plant site. The approved scheme and programme shall be implemented in full. Reason : In the interests of the visual amenity of the area and to secure the proper restoration of the site and to conform with Policy 106 of the Lancashire Minerals and Waste Local Plan. Aftercare 17. Upon certification in writing by the County Planning Authority of the completion of restoration of the lagoon, aftercare of the lagoon site shall be undertaken for a period of five years in accordance with the scheme and programme of aftercare approved under the requirements of condition 41 of planning permission 2/12/0024. Reason ; In order to ensure the proper restoration of the site and to conform with Policy 106 of the Lancashire Minerals and Waste Local Plan. Notes The grant of planning permission does not remove the need to obtain the relevant statutory consents/licences from the Environment Agency. Definitions Free field : At least 3.5 metres away from the facade of a property or building. Completion of Restoration : The date the County Planning Authority certifies in writing that the works of restoration in accordance with condition 17 have been completed satisfactorily. Local Government (Access to Information) Act 1985 List of Background Papers Paper 2/12/0023 2/12/0024 2/04/0652 Date 6th January 2012 Contact/Directorate/Ext Jonathan Haine/Environment/34130 Reason for Inclusion in Part II, if appropriate N/A