City of Covington SE 256th Street/164th Avenue SE Improvement Project Project Statement The SE 256th Street/164th Avenue SE Improvement Project consisted of both capacity and safety improvements on two arterials in the City of Covington. The project widened SE 256th Street from a 2-lane roadway with rural standards to a 5-lane urban arterial standard. It widened 164th Avenue SE from primarily a 2-lane rural standard roadway to a 3-lane urban arterial standard. Project Summary Prior to construction, both roadways had poor pedestrian facilities and thus poor walk routes to Kentwood High School and Mattson Junior High which were within the project limits. At the intersection of SE 256th Street and 164th Avenue SE was an existing traffic signal without any left or right turn channelization which consistently backed up during AM, PM and school peaks. The project constructed over 3,000 lineal feet of 8 foot wide sidewalks connecting several large housing developments directly to the two schools. In addition the project constructed bike lanes on both roadways within the entire project limits. Construction included more than 12,000 lineal feet of curb and gutter, 12,000 square feet of walls and over 100,000 lineal feet of utility conduit. Included in the project was the construction of a modern double lane roundabout at the intersection of SE 256th Street and 164th Avenue SE replacing the traffic signal that was controlling the intersection. During the design phase of the project there was significant concerns and opposition to the installation of the roundabout from both citizens as well as school officials. The City held several public meetings with citizens as well as meetings with Kent School District officials explaining the benefits of the roundabout. The city council supported keeping the roundabout in the design and therefore proceeded to construction. The project was awarded on May 16, 2006 to R.W. Scott Construction Company for $10,463,533.86. The project consisted of a schedule A and schedule B with the breakdown being $9,157,927.40 and $1,305,606.46 respectively. The schedule B work was the result of an interlocal agreement with the Covington Water District (which is a separate public agency from the city) to combine infrastructure needs of the two agencies into one project. In doing this the city was able to share the costs of items that would be common to both projects if they were bid separately. Both agencies were able to share costs in items such as traffic control, mobilization, erosion control, inspection, etc. The process was so successful that we implemented it on two other projects that are currently under construction. As the project approached the construction of the roundabout, there was still considerable public concern that the roundabout would not function well and there would be accidents as students would not know how to drive the roundabout. In attempts to reduce the concern and educate the public, city employees worked closely with the Kent School District in distributing joint press releases and sending several flyers home with all the students attending the two schools in the project limits. When the roundabout was opened to traffic, city staff worked with the school district and conducted a couple of presentations on “How to Drive a Roundabout” to all the bus drivers and the PTSA. City staff also video taped a presentation on driving roundabouts that was played for all the students at both schools. Construction Management The project was awarded on May 16, 2006 with 530 working days. The completion date was scheduled for the fall of 2008. The project was substantially completed on December 29, 2007 with the final lanes opened to traffic. At that time the project had over 176 working days (8 months) remaining on the project. Considerable acceleration of the project had to do with the construction of the roundabout. During the summer of 2007, the contractor and the city worked together to develop a plan to close the intersection of 164th Avenue SE and SE 256th Street for two weeks. The primary reason that this was allowed was to address how the roundabout would be constructed since the final grade of the roundabout would be 18 inches lower than the existing grade. The lowering of the intersection was necessary in order to maintain an acceptable uniform grade for the operational safety of the roundabout. In addition there were existing concrete panels that needed to be removed and the roadway built back up. This would result in the existing roadway being excavated three feet. Therefore, the intersection was allowed to be closed for two weeks during the hours of 7 AM and 4 PM each day. This allowed the entire roundabout to be constructed in those two weeks including final paving. This allowed the roundabout to be operational when school started in the fall of 2007 and avoided several months of traffic control phases as well as temporary signal configurations to construct the roundabout. The closure received very few complaints since it was publicized via press releases and door hangers/flyers were placed in all the neighborhoods in the area. In general, the contractor made considerable efforts to schedule work to minimize disruptions to the traveling public. In addition, school traffic was closely coordinated between the city, Kent School District and R. W. Scott Construction to minimize impacts to bus schedules and student/parent access. A representative of the Kent School District was invited to attend the weekly construction meetings to provide on-site coordination of any school related issues. The school district representative attended on a regular basis which helped in discussions and coordination of project impacts. Access to the two schools was well maintained for the project duration with only minimal delays. The project also came in under budget. The awarded bid was over 10.4 million dollars for the entire project. The actual cost of the project is under 10 million dollars. Although the project did have several unforeseen items that resulted in additional work, the overall construction management of the project, in the end, proved to be a large cost savings. This included closely monitoring quantities with regularly projected project completion costs that allowed the City to make decisions on expanding the scope to enhance and/or fix areas that were just outside the project limits. For example, the grinding and paving limits on the project were expanded to improve an intersection just outside the project limits that had several patches that were in need of repair. Another example was expanding the landscaping of the planter strips to blend and improve the landscaping of some of the older neighborhood planter strips that were just outside the project limits. The city, contractor and consultant worked closely throughout the project to identify, review and implement possible cost savings opportunities, such as the temporary closure of the intersection to construct major components of the roundabout. This closure resulted in a significant cost savings to the City and allowed work to be completed by the contractor with fewer disruptions and increased efficiency. These were just a couple examples of the many that were accomplished with knowing where the project was in terms of budget throughout the construction. Safety The safety performance of the project was exemplary. There were not any lost time injuries during the entire project with a recorded 36,000 work hours during construction. The contractor had a safety program and conducted regular safety meetings with their employees in accordance with their safety plan. The contractor also had certified flaggers as part of their staff versus many contractors that hire a subcontractor to do that work. The city on numerous occasions received compliments from citizens as to their courteousness as well as their professionalism is dealing with traffic. In addition the project did not experience any known pedestrian or vehicle accidents during the entire construction project. There was much of concern that the construction of a double lane roundabout (or any roundabout) would result in unsafe conditions for motorists and pedestrians, especially students. Since the project has opened we have received only positive responses from citizens and school officials as to how the roundabout functions. Environmental Due to the size of the project there were several areas of concern that needed to be protected. These areas included wetlands, potential wetlands, tributaries and seasonal drainage courses. To aid in protecting these resources, the city obtained from the Department of Ecology a “Construction Stormwater General Permit” prior to the project going out for bid. Within the permit there were several requirements and reports that would be needed to demonstrate that the project would be in compliance. It was determined that the most effective way to ensure that the project was in compliance was to transfer the responsibility to the contractor. Therefore, the City put the requirements into the project specifications with the intent that the permit would be the responsibility of the contractor with the city monitoring results. Once the project was awarded, the contractor had an employee obtain the necessary training to become a Certified Erosion and Sediment Control Lead (CESCL) as required by the Department of Ecology. In addition to the implementation of the Stormwater Pollution Prevention Plan (SWPPP) that included temporary erosion and sediment control measures for the entire project, the contractor conducted weekly samples of their stormwater discharges. These samples were tested using a turbidity meter and recorded on a form that was submitted monthly to the Department of Ecology. None of the results of the turbidity tests exceeded the allowable benchmark. Community Relations Ongoing public outreach about the project was provided by the city through a variety of methods such as a series of articles published in the Covington Reporter monthly updates, public meetings, information on the website, distributing informational flyers to all the students at the schools in the area, and issuing joint press releases with the Kent School District. The culmination of these efforts resulted in over twenty separate pieces of information. In addition, city staff gave presentations on separate occasions on driving around the roundabout to the Kent School District Transportation Department and the Parent Teacher Student Association (PTSA). City staff was also video taped explaining how to drive roundabouts and that information was played for all the Kentwood High School students by the Kent School District. The city received many thanks for all their educational and informational efforts. As mentioned earlier, during the two week closure of the intersection there were press releases notifying the public of the closure as well as flyers and door hangers placed in all the neighborhoods in the area. This was well received from the citizens because they understood the need for the closure and they knew the impact early enough to adjust their trips accordingly. The project website was in place during both the design and construction phases of the project. During construction, updates were posted to advise of project status, schedule, upcoming traffic impacts, temporary utility disruption as well as other general project information. The website also provided information regarding the multiple project partners and offered web viewers the opportunity to provided comments on the project. The Kent School district also worked with the City to pick up students at a local church outside the construction area to reduce the amount of vehicle and pedestrian traffic going through the work zone. This was just another example of the collective effort to make the project a success. Unusual Accomplishments One of the issues with the construction site being in the middle of two schools was the impact to walking students. There was a lot of concern that during the construction of the project there would be no safe routes for students to walk to school. The City agreed to place temporary pedestrian fencing to designate where students should walk and placed surfacing as necessary to accommodate pedestrians. In addition the staging of some of the construction did not allow for pedestrians to cross at the crosswalks to get to the schools. In order to get students safely to the schools without crossing the arterial uncontrolled, the contractor placed flaggers in areas to accommodate students needing to cross the road. The Contractor was very responsive to any additional pedestrian needs that arose during the course of the project work and scheduled their work accordingly. These practices reduced the concerns of the parents in facilitating the needs of the walking students and helped enforce the positive relationship between the citizens, Kent School District and city. Another challenge that arose during construction had to do with the main storm drainage trunk line that needed to tie into an existing regional storm water detention pond that was sized to service the roadway expansion. Over the years, houses were constructed in the vicinity of the drainage easement and grading occurred that made the installation of the trunk line within that easement virtually impossible without serious impacts to homeowners. The city, consultant and contractor talked about options to installing the storm drainage trunk line in the existing easement and the impacts to the residents as well as the constructability of the plan. It was decided to acquire additional easement area on the property adjacent to the existing easement that was undeveloped (except for one house). The city negotiated with the property owner a price for the easement which allowed for a constructible installation with minimal impacts to the residents at an overall lower price. Additional Considerations There was much concern during the design of the project on how to construct the roundabout and facilitate traffic. Prior to the construction project, the intersection at 164th Avenue SE and SE 256th Street was controlled by a traffic signal. In order to facilitate the existing geometrics of the roadway and take into account a family grocery store that has been in business since 1927, the intersection (roundabout) had to be shifted north and lowered 18 inches. Therefore the plans reflected temporary signals being installed as the different phases of the roundabout were constructed. During the actual construction of the project, it was observed that traffic had dropped to avoid the intersection because motorists were diverting to other routes in the area. These observations prompted the city, consultant and contractor to evaluate other possibilities in phasing how the roundabout would be constructed. With the changes of the traffic patterns it was observed that traffic was balanced coming from all directions and that a 4-way stop could function well and alleviate the need of temporary signals being installed and reinstalled for the different phases. However, these observations were made during the summer and traffic would significantly increase once school was back in session. The contractor proposed closing the intersection for two weeks and completely reconstructing the roadway and building the roundabout. The closure was allowed for the two weeks on the premise that the roundabout would be open prior to school being back in session in the fall. We placed the signal in 4-way flash while work was being done in the area and witnessed that the traffic actually did function well as expected. The peak hours functioned well so the contractor was allowed to remove the signal and place 4-way stop signs and begin prepping for the roundabout. The intersection was then closed for two weeks in August of 2007. At the end of the two weeks the roundabout was fully constructed and paved (including final lift) prior to school starting in the first week of September. This willingness to “go against the norm” saved over a $100,000 in costs to the project and saved months of impacts to motorists and pedestrians. There were many keys to success in the construction of this project. However, the common factor seemed to come back to the approach taken by the city, consultant and contractor. As issues arose all parties kept an open mind and were willing to consider all ideas and reach the best solution for all stakeholders (motorists, pedestrians, partners, city, consultant, contractor, etc.). The focus was always having a quality end product. This is a rarity to have all parties involved working well together which in the end created a project that was appreciated by all. Contact Don Vondran, PE City Engineer 253-638-1110