GAINSBOROUGH EDUCATIONAL VILLAGE PROJECT BOARD 20 NOVEMBER 2007 RISK REGISTER UPDATE HEADLINES It has been a quiet month in terms of risk management as much work had previously been carried out to allow a start on site. Site work has started to level the site and insert the concrete piles. Following value engineering, reductions and omissions, the funding for the construction of the new schools is able to meet the cost of £22.323millions. At this early stage of construction, the risk exposure index remains at 58% compared with the optimum risk target level of 46%. EXPECTATIONS/ISSUES The main areas for concern are: Resolving the outstanding cost issues for the access road. Managing the project within the approved budget and timescales for the scheme. Resolving the governance and premises management of the accommodation for the two schools upon completion. G:\Plan_Asset\TCF\TCF Gainsborough\Risk\GEV Risk Register Update 191107.doc