Design and Construction of the PRI - 1 Works PRI-1 Contract Exhibit A Scope of Works and Technical Criteria Appendix 10 - Sustainability Requirements Date: Author: Revision Status: October 2009 Sydney Metro 1.2 ITT (Addendum) Version Confidential PRI – 1 Works Sustainability Requirements Appendix 10 Sustainability Requirements Table of Contents 10 Page Number Sustainability Requirements ......................................................................................................... 1 10.1 Introduction ................................................................................................................... 1 10.2 General Requirements .................................................................................................. 1 10.3 Renewable Energy ........................................................................................................ 2 10.4 Energy Demand Management ...................................................................................... 2 10.5 Recycled Materials ........................................................................................................ 2 10.6 Spoil Management ........................................................................................................ 3 10.7 Recycling and Reuse .................................................................................................... 3 10.8 Transport ....................................................................................................................... 3 10.9 Water Management....................................................................................................... 3 10.10 Temporary Site Facilities .............................................................................................. 3 Confidential Scope of Works and Technical Criteria Appendix 10 Revision 1.2 Page i PRI – 1 Works Sustainability Requirements 10 Sustainability Requirements 10.1 Introduction This Appendix 10 contains the sustainability requirements that the PRI-1 Contractor must comply with during the performance of the PRI-1 Contractor's Activities. 10.2 General Requirements a) The PRI-1 Contractor must ensure that sustainability is addressed throughout the performance of the PRI-1 Contractor's Activities and that sustainability is embedded into the design and construction of the PRI-1 Works. b) The PRI-1 Contractor must perform the PRI-1 Contractor's Activities in accordance with the sustainability framework established for the CBD Metro project in the Environmental Documents and as a minimum must: i. implement good project management and governance incorporating sustainability as well as maximise beneficial outcomes through effective and efficient project management incorporating sustainability; ii. maximise safety; iii. ensure that the PRI-1 Works are designed to withstand the effects of climate change and any landscaping is appropriate to future climatic conditions; iv. minimise contributions to climate change through reducing greenhouse emissions from the PRI-1 Works by: A. minimising direct emissions and indirect emissions from purchased electricity, heat or steam; and B. minimising upstream and downstream indirect emissions; v. minimise energy demand, maximise energy efficiency and use low carbon and renewable energy sources; vi. maximise efficiency of resource use over the project life cycle including at the end of the Design Life of the Assets by: vii. A. minimising construction volumes; B. maximising beneficial use of spoil; C. using and sourcing materials efficiently and from sustainable sources; D. reducing waste generation and recycling all waste and spoil whilst minimising greenhouse gas emissions; E. designing for the end of Design Life of Assets; and F. avoiding the production of hazardous waste; manage water to maximise its beneficial use and minimise flood risk by: A. minimising demand on potable water supply; B. maximising efficiency in water use; C. reclaiming and reusing waste water; Confidential Scope of Works and Technical Criteria Appendix 10 Revision 1.2 Page 1 PRI – 1 Works viii. 10.3 Sustainability Requirements D. maximising reuse of storm water; E. managing aquifer and surface water interference to protect connected ecosystems; and F. avoiding increasing the risk of flooding; and deliver new habitat and minimise habitat for feral animals and weeds. Renewable Energy The PRI-1 Contractor must ensure that as a minimum 20% of the total energy used in the performance of the PRI-1 Contractor's Activities complies with either one or a combination of the following renewable energy requirements: a) the energy used is obtained from an Australian Government accredited renewable energy supplier; and/or b) Renewable Energy Certificates registered with the Australian Government Office of the Renewable Energy Regulator are acquired and voluntarily surrendered for the energy used. 10.4 Energy Demand Management The PRI-1 Contractor must ensure that: a) diesel generators are only used for the provision of emergency power where practicable; b) plant and equipment is not left idling when not in use; c) low emissions vehicles and plant are fitted with catalysts, diesel particulate filters or similar devices; d) all plant is well maintained and serviced in accordance with relevant equipment maintenance documentation to reduce emissions due to poor engine performance; and e) major equipment including TBMs are operated for optimum energy efficiency. 10.5 Recycled Materials a) The PRI-1 Contractor must provide materials and workmanship which minimise the embodied carbon of the Project Works and Temporary Works and must use recycled materials to the maximum extent possible. b) The PRI-1 Contractor must identify opportunities to use blended cement that contains waste industrial products and complies with AS3972 Special Purpose Cement or Blended Cement and where practicable use blended cement containing waste industrial products in the construction of the Project Works and the Temporary Works. c) The PRI-1 Contractor must identify opportunities to use granulated blast furnace slag in concrete and where practicable use concrete containing granulated blast furnace slag in the construction of the Project Works and Temporary Works. d) The PRI-1 Contractor must identify opportunities to use recycled steel in concrete reinforcing and where practicable use concrete reinforcing containing recycled steel in the construction of the Project Works and Temporary Works. e) The PRI-1 Contractor must use recycled timber or timber from independently certified sustainable timber sources in the construction of the Project Works and Temporary Works including temporary site facilities. Confidential Scope of Works and Technical Criteria Appendix 10 Revision 1.2 Page 2 PRI – 1 Works 10.6 Sustainability Requirements Spoil Management The PRI-1 Contractor must, to the maximum extent possible, target 100% reuse or recycling (on or off-site) of virgin excavated natural material (VENM). 10.7 Recycling and Reuse The PRI-1 Contractor must, to the maximum extent possible, recycle spoil and construction waste. Any construction materials and waste and spoil which cannot be incorporated into the Project Works must be removed from the Construction Site and disposed of at a construction waste recycling facility or alternatively re-used for a beneficial use. 10.8 Transport The PRI-1 Contractor must, to the maximum extent possible, limit carbon emissions relating to the transportation of construction materials, spoil and waste. 10.9 Water Management The PRI-1 Contractor must, to the maximum extent possible: a) use water efficient construction methods and equipment; b) recycle water from tunnelling operations and concrete and grout batching processes; c) use non-potable water for the PRI-1 Contractor's Activities undertaken on the Construction Site; d) only use biodegradable hydraulic oils in machinery working adjacent to bodies of water at White Bay; and e) provide designated sealed areas for equipment washdown. 10.10 Temporary Site Facilities The PRI-1 Contractor must provide temporary site facilities that incorporate: a) energy efficient lighting; b) high performance thermal insulation in all walls, ceilings and floors that optimise thermal performance; c) natural daylighting where practicable; d) natural ventilation; e) rainwater harvesting where reuse is practicable; and f) bicycle storage facilities, showers and changing room facilities to meet the requirements of the PRI-1 Contractor's personnel and any Subcontractor's personnel where practicable. Confidential Scope of Works and Technical Criteria Appendix 10 Revision 1.2 Page 3