PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Project Name Region Sector Project ID Borrower(s) Implementing Agency Report No.: AB1851 Changjiang/Pearl River Watershed Rehabilitation Project EAST ASIA AND PACIFIC General agriculture, fishing and forestry sector (35%);Crops (25%);Forestry (25%);Flood protection (15%) P081255 GOVERNMENT OF CHINA People's Republic of China Ministry of Finance International Department China Environment Category Date PID Prepared Date of Appraisal Authorization Date of Board Approval Ministry of Water Resources No. 2, Baiguanglu Ertiao China 100053 Tel: +86-10-63202701 Fax: +86-10-63202738 lige@mwr.gov.cn [ ] A [X] B [ ] C [ ] FI [ ] TBD (to be determined) September 27, 2005 October 24, 2005 March 15, 2006 1. Country and Sector Background Key Development Issues. Despite China’s enormous economic success, the country still faces considerable social and environmental challenges. In many cases, these challenges are closely interconnected. Erosion is one of China’s key environmental problems, with consequences beyond the country’s boundaries. This problem is both, caused by and threatening the livelihood of millions of mainly poor people in China. The proposed project aims at tackling these interrelated problems of environmental degradation and poverty in an area where they are most severe, in the upper watersheds of the Changjiang and Pearl River. According to estimates by the Ministry of Water Resources, about 38.2% of the national territory is eroded of low degree or above1, almost half of which (1.79 million square km) is hydraulic erosion. The most serious areas of hydraulic erosion are located in the middle reaches of the Yellow River, and the upper reaches of the Changjiang and Pearl River. The Changjiang River Basin alone covers a total eroded area of 562,000 square km (36% of the total eroded area in 1 These estimates vary widely. For example, a study by the Institute of Remote Sensing Applications (IRSA) of the Chinese Academy of Sciences undertaken in 1999 estimates that about 50% of China’s total land area is affected by some degree of land degradation. China) and the induced soil loss amounts to about 2.4 billion tons annually, most of which (about 1.56 billion tons) in the upper reaches. Many forms of the most severe forms of land degradation such as landslides, mud rock flow, and ‘stonization’ can be found in the upper reaches of the Changjiang and Pearl River. The impacts of this eco-environmental degradation are very severe. They range from a loss of vegetation, biomass and biodiversity, and a reduction in water storage capacity of the soils, to a complete and irreversible destruction of farmland, increasingly damaging floods downstream, and climate changes of a regional scale. While the environmental impact of the degradation is of national and global significance, the greatest social costs of the environmental degradation occur in the upper reaches of the Changjiang and Pearl River themselves. The rural areas of these parts of the river basins include some of the poorest areas of China. The exploitation of forest resources, especially over the past few decades, and the growth in agricultural production has improved incomes and living conditions of the population, but it has also led to great socio-economic vulnerability and environmental fragility. The increasing pressure on the use of land resources driven by the need to generate income and escape poverty in turn leads to erosion of farm land and limits the ability for agricultural and, hence, livelihood development in these areas. Where this development is not redirected on a sustainable path, it leads to increased poverty and forces people to leave their villages – with severe social consequences. National Government Policies and Strategies The concept of sustainability has become a fundamental principle of China’s development policy and the Government of China is addressing the challenges described above in many ways. This strategy is reflected in a wide range of national Government policies that contribute to an environmentally and socially more sustainable rural development. The legal basis for soil and water conservation is provided by the Water Law and the Law on Soil and Water Conservation. The need to improve water and soil conservation in the Changjiang River was reemphasized in the recent Document No.1 issued in January 2005. Policies in the area of watershed management, poverty alleviation, forestry, agriculture, grassland, land, anti-desertification, and others are highly relevant for the project. They are being implemented with the help of national programs and projects. Of greatest significance for the proposed project are the domestic Changjiang and Zhujiang Water and Soil Conservation Projects, and similar interventions. Moreover, a number of domestic poverty alleviation and other projects are being implemented. The policies provide an overall favorable policy environment for the proposed project, but the project will also be able to enforce or shape these policies through demonstrating a model of sustainable and integrated watershed rehabilitation and management. 2. Rationale for Bank involvement The Government’s policies and interventions in watershed management are clearly contributing to an improvement of the socio-economic or environmental situation. However, an integrated approach to watershed management is still largely lacking in the Changjiang and Pearl River Basins. Consequently, effectiveness and sustainability of the various interventions and policies in these areas are often limited. The World Bank can assist in the transfer of experiences in implementing models of integrated watershed management, for example from the projects it supported in the Yellow River Basin. The Bank’s involvement – and its partnership with the EU – would substantially contribute to the strengthening of various policies. Most importantly, this would be reflected in the strengthening of laws (including the Law for Water and Soil Conservation), policies and programs for the wider Changjiang and Pearl River basins. The Bank’s involvement would also promote a cross-sectoral approach to ensure the implementation of policies that are central to watershed management but not under the core mandate of the River Commissions and Water Resources Bureaus. This includes, first, that the proposed project will support the further development and implementation of grazing policies including closure of areas while compensating farmers with income generating activities in other parts of the watershed. Second, it will also support the land policy requiring that any investment in land improvement such as terraces, economic trees, or forest plantations be made on the basis of 30-50 year land contracts to individual farmers. Third, it will also support a sustainable forestry policy and promote agricultural policies including through training and market information, so that poor farmers with little market experience can make the necessary adjustments. The Bank has a wide range of experience in watershed management concepts, design, and implementation from China as well as other countries. In particular, the Red Soils Area Development Projects and the Loess Watershed Rehabilitation Projects have provided the Bank with rich experience to contribute to the project objectives. The major lessons of these projects include: a) successful watershed development needs be built on an integrated package of measures, which combine income generation for local communities with sustainable resources use practices, b) opting for strong ownership through a high level of participation and stakeholder interaction, c) implementing effective project management with rigorous monitoring and evaluation for successful project implementation, d) identifying social and environmental externalities and understanding these “public goods” elements in the project and defining financial obligations for different stakeholders accordingly, and e) importance of adequate technical standards, TA and training. The proposed project builds on these and other experiences to provide an innovative design suitable for the specific conditions in the project areas. These conditions – and the fact that they are widely differing – pose a challenge to effective watershed management interventions in the Changjiang and Pearl River. The area has an advantage of relatively high rainfall, but great social diversity including a significant share of minorities; a large diversity in terms of agroclimatic conditions including soil types; thin soil layers; a difficult infrastructural situation; etc. The complexity and diversity of the issues require design and implementation of a high quality project, which the Bank would have comparative advantage to help with. 3. Project Development Objectives The two highly interlinked development objectives of the Project are to protect the environment and improve people’s livelihoods in poor and highly degraded watersheds of the Changjiang and Pearl River Basins by promoting an integrated and replicable model of sustainable rural development. The components of efficient and sustainable use of land and water resources would reverse the trend of unsustainable resources management practices that have led to widespread poverty and serious environmental destruction. The project would increase farmers’ livelihood and thereby give them the incentive to protect their environment. The benefits of the proposed project will accrue to different levels, including to farmers and the local communities in the subwatersheds, the wider community and local government, to downstream areas and provinces, to the nation as a whole, and to the global community. Impact/Outcome Indicators. The benefits are of a socio-economic and ecological dimension and would be measured by various impact/outcome indicators in the following categories: (i) erosion reduction by the reduced amount of silt inflow in the downstream river system, (ii) total amount of carbon sequestrated through increases in the amount of biomass; (iii) farmers income (per capita income increase, yield increase, variability of income ); (iv) outreach/equity (number of beneficiary households, gender and ethnic minority disaggregated), (v) replicability and sustainability, which would be assessed through a qualitative indicator assessed by an expert panel looking into such factors as number of projects/programs using the same models, policy impact, linkage of public goods activities with private goods activities at household and village level. 4. Description The project includes a wide menu of activities that would ensure flexibility to respond to greatly varying agro-climatic and socio-economic conditions in the individual sub-watersheds. Through a participatory design process these activities would be packaged into an integrated set of interventions for each individual sub-watershed.2 The total investment of the project is estimated to be about US$200 million, with financing from IBRD (US$100), EU (about US$12 million), and the Government of China, including beneficiaries (about US$88 million). The various activities are categorized into three components. Component 1. Soil and Water Conservation, which would include pre-dominantly physical investments (works and goods) for soil and water conservation which generate primarily ‘public goods’. 2 The design process would involve farmers, community leaders, PMOs, technical experts in the areas of watershed management, forestry, agriculture, animal husbandry, possibly farmer association representatives, private agro-processing representatives, and specialist that would ensure that vulnerable groups are well represented in the process such as those from the All China Women’s Federation or social experts, and would ensure that the various quality aspects are reflected in the final design, including farmers’ priority, water balances and technical design standards, etc. The details of this process are being reflected in a Participatory Watershed Design and Management Manual. a. Minimum capital farmland, i.e. the construction of relatively expensive “stone-faced” terraces in areas with thin layers of soil with and without irrigation facilities. This is an essential component in very poor and mountainous villages, where subsistence food production is of great importance for the local population and a minimum amount of farmland the pre-condition for farmers to stop non-sustainable land use practices. While private individuals will benefits from these investments, there are considerable public benefits. b. Sediment Retention Structures, which would intercept the sediment at its source, to check the water discharge and to slow the flow of flood water in the tributary gullies of the major rivers. Different types of sediment control dams would be constructed such as check dams or barrier for the debris. c. Afforestation and Vegetative Cover, which would include the planting of arbor trees including pines, firs, poplar, cypress etc. and shrubs, and the closing and protection of areas for natural revegetation with primary purpose of soil and water conservation with limited scope for commercial use. d. Village Infrastructure, which would include the construction of drinking water supply systems, small reservoirs, improvement of access roads, tractor roads and field tracks, where they are important to achieve benefits from other project activities and crucial for project sustainability. Component 2. Livelihood Improvement, which would include pre-dominantly physical investments (works and goods) that are primarily designed to improve the income of farmers, but also give the incentives for changes from unsustainable land use practices. a. Terracing of slope land, which would include the cost-effective construction of “earth-faced” terraces and rehabilitation of existing terraces on slope land of 5-15% gradient with incremental crop production expected to generate significant income increases. It is further proposed to include the rehabilitation of existing terraces as a cost-effective way to improve productivity and reduce soil erosion. b. Horticulture and Fruit and Nut Trees, which would include the development of a broad range of high value fruit and nut tree orchards, and other perennial crops such as oranges, tangerines, chestnuts, tea or innovate crops such as Chinese Olive and honeysuckle. c. Grasslands, which would include the establishment of perennial grassland and lucerne and thereby lead to improved fodder production and soil erosion. d. Livestock Development, which include livestock activities that will significantly increase incomes and are fully integrated with soil and water conservation. They are targeted to individual and poorer households that are willing to give up grazing or return slope-land to grass land and forest plantation. d. Irrigation and Drainage, which would include irrigation facilities based on small-scale tanks and cisterns filled by runoff with a holding capacity of some 30-200 m³ to provide emergency water supply in cases of severe drought or for the initial establishment of tree seedlings in plantations or orchards. e. Renewable Energy Supply, which would support small-scale bio-gas production facilities based on manure from livestock to contribute to a reduction of forest resources destruction and replaces household expenditure for fuel. f. Grant Activity for the Absolute Poor, which would finance any of the other Livelihood Improvement Activities, but would be given on a small, but full-grant basis to those households in the sub-watershed that are absolutely poor and do not have the capacity to repay any parts of the costs, but whose involvement in the project in order to achieve the its objective is crucial. Most of these are expected to be minority or women-headed households. Component 3. Project Management and Support Services, which would ensure the participatory design process with inclusion of vulnerable groups, the quality management and implementation of activities under Components 1 and 2, the right institutional setting for sustainable operation and maintenance of project activities, the mitigation of environmental and social risks, and strong project management including M&E. a) Beneficiary/Farmer Training, which would include training and knowledge transfers to farmers, and range from topics such as group formation and participatory watershed design, management, and monitoring to technical training including pesticide management, livestock production, contour planting, forage development, water supply, etc. Different demonstration, farmer field school, and other training approaches would be used. Emphasis would be given to the targeting of women and ethnic minorities. b) Other Training, which would include training for PMO staff as well as for staff of agencies engaged in certain aspects of project management such as, for example, the Water and Soil Monitoring Centers and Stations for performance M&E, PMO and FB staff for strengthening financial management and recollection of funds, or other individuals or consultancies for the implementation of safeguard-related mitigation and monitoring measures. c) Monitoring and Evaluation, which would include M&E of project impact/outcome, financial/input/output monitoring and process/safeguard monitoring. d) Project Management, which would include all expenses related to project management, in particular watershed survey and design, general operation and management, as well as vehicles and office and other equipment. The project is proposed to be implemented in 37 counties of 8 prefectures/cities in the four municipality/ provinces Chongqing, Guizhou, Hubei, and Yunnan. Of these counties, 33 are located in upper and middle reaches of the Changjiang and 4 in upper reaches of the Pearl River. The project areas are characterized by high diversity in terms of natural environment and socioeconomic conditions, but also have common features such as a high level of poverty and a poor resource endowment of the local farming population. Within these 37 counties the project would be implemented in sub-watersheds that are defined by hydrological and administrative boundaries. About 270 sub-watersheds (project areas) of one to a few administrative villages in size have been pre-selected, comprising a total area of about 6,300 square km. About 1.9 million people live in these sub-watersheds, a substantial part of them are national minorities3. The average net income is around RMB1,500 per person. This corresponds to only about three quarter of the counties’ average net rural income or only about two thirds of the average for China. Despite the relative remoteness of many of these subwatersheds, they are densely populated (about 300 persons / square km) and forests make up less than a quarter of the land area. More than half of the land area is classified as eroded. The project would be implemented in a phased approach. During preparation one sub-watershed in each of the project counties is being prepared in great detail and would be implemented during the first 3 to 4 implementation years. The other sub-watersheds, which have been preliminarily identified and surveyed, would be prepared during the first 2 to 3 years of the project and implemented subsequently. 5. Financing Source: BORROWER INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT EC: EUROPEAN COMMISSION ($m.) 88 100 Total 12 200 6. Implementation Institutional and implementation arrangements The proposed Project management structure includes Project Leading Groups (PLGs), a Central Project Coordination Office (CPCO), a Central Project Implementation Office (CPIO), Project Management Offices (PMOs), and Technical Advisory Groups (TAGs). PLGs at the central, provincial, prefecture/city, and county levels would be headed by a high level leader at each level (e.g. Vice-Minister at National, and Vice Governor at Provincial level) and include members from various line agencies including planning, finance, agricultural and animal husbandry, forestry, poverty alleviation office, environmental protection, and possibly others. The main responsibilities of PLGs are to give overall policy support and guidance to the project, ensure project counterpart funds and strong PMOs, support a rational distribution the World Bank loan, coordinate and enlist the support of all relevant agencies, and disseminate the experiences gained under the project. The CPCO, composed of representatives from five departments and offices of MWR, is the key liaison and coordination office between the Central PLG, CPIO, MOF, NDRC the World Bank and the EU. It’s responsibilities include the supervising and overseeing of the project implementation, organizing and implementing certain TA activities and overseas training and study tours; and the arrangements for ICB for relevant equipment and consulting services. The CPIO is located in the Changjiang Water Resources Conservancy Commission and is composed of members from both, the Changjiang and the Pearl River Basin Commissions. PMOs, located in the Water Conservation Bureaus/Departments and working in close cooperation with the Finance Bureaus/Departments, are being established at provincial, prefecture, 3 The share over the total project area is 16 percent, but can reach close to 100% in individual subwatersheds. and county level. The integration of broad expertise including social development, agriculture, and forestry would be ensured within the PMOs, especially at the county level. Moreover, close institutional linkages between the PMO in the Water Resources Bureau and the line agencies such as agriculture, animal husbandry, forestry, etc. are being established. County PMOs will be supported in their work by township-level workstations. The PMOs are in charge of all day-to-day project implementation aspects including preparation of annual project implementation plans (including plans for construction, fund use, procurement, training and study tours, etc); preparation of annual progress reports, quality report for physical works, annual financial management reports; preparation of project completion report, etc; monitoring and evaluation; and actual implementation including coordinating the participatory sub-watershed design, procurement, disbursement, the organization of training, workshops and study tours, etc.. The PMOs would also be responsible for screening and selection of project beneficiaries. The FB/finance stations, assisted by technical experts and PMO staff, would review the design proposals to ensure that the project funds generate the expected returns at the beneficiary level. The exact procedures would be established in the PIP that includes a financial manual and a manual for participatory watershed management. The county-level FBs and township finance stations would be responsible for the disbursement arrangements to the beneficiaries. TAGs are being established at the provincial level. They are composed of experts from relevant line agencies, research and extension institutions, and the private sector. In addition, the project will rely on a number of existing institutions in its implementation – and will strengthen these institutions in this process and through training and TA. This includes the village Government which will play a key role in ensuring the participatory approach at the community level. Other examples are existing survey institutions such as the water and soil conservation monitoring centers and stations or the local statistical bureaus for the M&E of the project. The proposed project will be implemented in line with the National Plan on Ecological Development and National Plan on Soil and Water Conservation, and together with the main national projects, the Changjiang Soil and Water Conservation Project and Pearl River Soil and Water Conservation Project. Close linkages with these projects is ensured through co-financing arrangements and close institutional linkages at the project management level. Flow of IBRD funds would follow the traditional route. Funds would be transfers from the World Bank to Special Accounts (SAs) set up in each of the four project provinces. Provinces would bear the foreign exchange risk and pass on the funds at costs to the municipal and then county FBs. From there the funds would be transferred to the final beneficiary directly or handed to the township (finance station) that would transfer the money to the final beneficiary. Part of the investment costs will be recovered by the Government. This is justified given the substantial private returns of some activities. Repayment will be collected by the township work station or county PMO or FBs and passed on to the municipal FB and on to the provincial FBs. To ensure recollection of funds, responsibilities within the local government for administering this task would be clearly defined. The local PMO or Finance Bureau would make contracts with the individual households before the implementation of activities. These contracts would specify the households’ responsibility to repay parts of the funds according to a specific repayment schedule. The administration of these contracts and the recollection would be facilitated through a computerized MIS. Training activity would strengthen the capacity for recollection and administration of funds. 7. Sustainability Key elements to achieve project sustainability would be financial and economic viability, social inclusiveness and sustainability in natural resources use. The proposed project would be built on a strong level of stakeholder participation and ownership with clearly understood long-term financial profitability (to farmers) and economic viability (to the society as a whole). This will create strong incentives for all stakeholders involved. For farmers the project’s broad menu of diversified income-generating opportunities, including the development of a range of crops, livestock and other income supporting activities such as alternative energy supply will provide stability in income and increase resilience against natural, economic, financial or market risks. The project would promote sustainable resources use practices and reverse the soil deterioration that is taking place, and thus improve the potential for higher and diversified incomes, and reduced risks of landslides as well as floods downstream. 8. Lessons Learned from Past Operations in the Country/Sector The project concept and design draws from China’s own experiences, in particular from Loess Plateau Watershed Rehabilitation Projects and from experiences in other countries. Major lessons for successful watershed development included in the design are the need for: a) an integrated package of measures, which combine income generation for local beneficiaries and communities with sustainable resources use practices, b) strong ownership through a high level of participation and stakeholder interaction, c) effective project management with rigorous monitoring and evaluation for successful project implementation, and d) a strong understanding of the “public goods” elements in the project and defining financial obligations for different stakeholders accordingly. Many of the elements of the design of the Loess Plateau Watershed Rehabilitation Projects would be adopted in the proposed project. This includes, in particular, a menu of public- and private-good activities that would be combined to packages specific to the sub-watershed that are economically attractive enough to induce the change from the currently non-sustainable land use practices to sustainable livelihoods activities for the local population. The proposed project would further strengthen participatory approaches to watershed management by a more programmatic approach to watershed design and implementation4 and through an even stronger inclusion of local communities and households, a process that would be guided through a ‘Participatory Watershed Management Manual’. Successful models of output monitoring that lead to strong accountability in implementation would be extended and a comprehensive M&E system would include strong input and output monitoring (including a computerized MIS) as well as strong M&E of outcomes. During the preparation phase only one of the – between 3 and 12 already pre-selected and initially surveyed – sub-watersheds in any particular county is prepared in detail through a participatory process. The implementation of the design plan would be carried out over a period of about 3 to 4 years while other sub-watersheds would be designed in implementation years 1 to 3 and implemented subsequently. 4 9. Safeguard policies Safeguard Policies Triggered by the Project Environmental Assessment (OP/BP/GP 4.01) Natural Habitats (OP/BP 4.04) Pest Management (OP 4.09) Cultural Property (OPN 11.03, being revised as OP 4.11) Involuntary Resettlement (OP/BP 4.12) Indigenous Peoples (OD 4.20, being revised as OP 4.10) Forests (OP/BP 4.36) Safety of Dams (OP/BP 4.37) Projects in Disputed Areas (OP/BP/GP 7.60)* Projects on International Waterways (OP/BP/GP 7.50) Yes [X] [ ] [X] [ ] [X] [X] [X] [X] [] [] No [] [X] [] [X] [] [] [] [] [X] [X] This project is categorized as an Environmental Risk Category B project. The safeguard screening category of the project is S2. Both the social and environment safeguard aspects are unlikely to have major negative impacts. Applicable safeguard policies for the project are: a) Environmental Assessment, b) Pest Management, c) Involuntary Resettlement, d) Indigenous Peoples, f) Forests and g) Safety of Dams. The draft safeguard documents will be published through the Infoshop and have been made accessible to the public locally. Environmental Assessment. A draft EA has been prepared in accordance with China’s environmental policy and regulations, and the Bank’s safeguard policy. Local stakeholders, NGOs, and project-affected groups of over 600 people have been involved in the public consultation. The disclosure of information is already done by the PMO. The Bank’s safeguard team is reviewing the draft EA. The domestic EA review is being arranged by the Ministry of Water Resources. Pest Management. To assess pest management in the project areas, to support integrated pest management (IPM) and safe use of agricultural pesticides, and to mitigate potential environmental impact, a draft PMP has been prepared in addition to the EA. The proposed project will mitigate any negative effects from pesticide use by promoting an IPM strategy that involves: non-chemical approaches to pest control, monitoring and evaluation procedures, guidelines for use of appropriate chemicals (including both pesticide and fertilizer), and a plan for capacity building. Involuntary Resettlement. The selection of project areas ensures that they have no link to resettlement from national projects. Moreover, no involuntary population relocation is envisaged under the project itself. However, some potential loss of land or assets by individuals in a community might occur due to small, village-level infrastructure construction which will be identified through a community-based planning process. A Policy Framework for Resettlement and Land Acquisition has been prepared by the SA team in accordance with the Bank safeguard policy OP4.12 Involuntary Resettlement. It establishes the principles and procedures to be followed in the event that such development activities requiring land acquisition are determined * By supporting the proposed project, the Bank does not intend to prejudice the final determination of the parties' claims on the disputed areas during project implementation. The borrower is informed that this project or any activity carried out under this project must not be used to directly or indirectly support resettlement activities of any other past, on-going or future infrastructure or water resources projects or national programs involving resettlement. Indigenous Peoples. About 10 ethnic minorities with a population of some 332,000 people are living in the project areas. They comprise some 18 percent of the total of 1.89 million people. The project SA has assessed the situation of the minority groups. Ethnic minority profiles have been prepared for all ethnic groups in the project areas, and their special relationships with land, water and forest resources have been elaborated. Improved understanding of the ethnic minority groups has ensured full integration of ethnic minority interests in the project design. Based on intensive consultation with the ethnic groups a draft Multi-Ethnic Minority Development Plan (EMDP) has been prepared. The EMDP highlights measures to: a) enhance their inclusion and participation in the project process, b) ensure the delivery of culturally appropriate benefits, and c) avoid or mitigate any potential threats or negative impacts on the ethnic minority communities. The Borrower attests that the EMDP will continue to guide project implementation and the provisions in the EMDP will be monitored. Forests. Forests make up a considerable part (about a fifth) of the project sub-watersheds and the increase of forest coverage is a key part of the proposed watershed rehabilitation project. This would be achieved through the promotion of more sustainable forest management policies and management practices, through closure of area so that forest can recover and through planting of trees financed by the proposed project. Guidelines for the establishment and management of forests have been developed and are being finalized. Safety of Dams. The project will invest in sediment retention and check dams. Those dams will be small, less than 10m in height. However, a number of already existing dams and reservoirs are located in the project areas or serve the project areas as water sources for irrigation. Guidelines for project implementation on safety of dams have been prepared for these dams by the Borrower with assistance from the Bank; they include: Guidelines for Dam Safety Review; Small Dams Safety Review Guidelines; Guidelines for Emergency Preparedness Plan, and Guidelines for Operation and Management of Dams. 10. List of Factual Technical Documents 1. Project Concept Note 2. Draft PAD 3. Draft Project Implementation Plan 4. Draft Environmental Impact Assessment, including EMP and Monitoring Plan 5. Draft Pest Management Plan 6. Draft Social Assessment Report (including Annex 4: Policy Framework) 7. Draft Multi-ethnic Minority Development Plan (MEDP) 8. Draft Guidelines on Dam Safety 9. Draft Forestry Guideline 10. Draft Participatory Watershed Design and Implementation Manual 11. Detailed Cost Tables 11. Contact point Contact: Achim Fock Title: Sr Economist Tel: 86 10 58617681 Fax: 86 10 58617800 Email: afock@worldbank.org 2. For more information contact: The InfoShop The World Bank 1818 H Street, NW Washington, D.C. 20433 Telephone: (202) 458-5454 Fax: (202) 522-1500 Web: http://www.worldbank.org/infoshop