Accelerator Operations 1. Introduction The government of Canada has invested significantly in TRIUMF since its inception which has enabled TRIUMF to achieve national and international recognition as Canada’s national laboratory for nuclear and particle physics. TRIUMF is recognized as a world leader in exotic radioactive ion beams produced at the ISAC Facility. TRIUMF contributes significantly to medical applications and research through the Life Sciences PET Program (TR13 cyclotron), the Proton Therapy Program to treat choroidal melanomas (eye tumors) and proton irradiation of rubidium to produce strontium for medical imaging generators. To achieve such results requires an organization of multidisciplined experts working and responding as a coherent team. 2. Proton Delivery The success of TRIUMF programs depends on the ability to reliably deliver protons from the 500 MeV cyclotron. Typically, the cyclotron, although over thirty years old, averages an uptime of greater than 90% (2000 - 2007), the 15 year average is just under 90%. 500 MeV Cyclotron Uptime 1992-2007 100 90 80 70 60 50 40 30 20 Cyclotron Uptime (%) 10 0 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 Figure 1 Cyclotron uptime as a percentage of scheduled operational hours per year Accelerator operation will expand under the new Five-year Plan to support the new initiatives. The cyclotron intensity upgrade will allow higher injected H- intensities into the cyclotron to support high intensity beams for four beamlines (BL1A, BL2A, BL2C and BL4N). Although the potential for high intensity (400 μA) operation was demonstrated in 1988, more recent development initiates have demonstrated that accelerating higher beam intensities is realistic. In 2006 the cyclotron ran for an extended period with a 20% increase in the nominal operating beam current. The total mAhr charge per year has increased, on average, since ISAC has come on-line with no corresponding increase in downtime demonstrating the cyclotron’s capacity to deliver increased beam currents. The total charge delivered in 2007 was reduced by approximately 80-100 mAhr due to the upgrade and re-commissioning activities at the BL2C4 solid target facility. The total charge to BL2A (green) for ISAC has more than doubled in the past four years. Annual Total Charge Delivery 1992-2007 800 700 Charge (mAhrs) 600 500 400 300 200 100 BL1A BL2C4 BL2A 0 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 Year Figure 2 Total annual proton charge (mAhrs) delivered to three beam lines Figure 3 shows the percentage of charge delivered to charge scheduled for BL1A. The 15 year average is 95.5% although the cyclotron uptime during this period averages about 90%. Similar beam charge delivery efficiency is available the ISAC Facilities. BL1A Charge 110 100 90 80 70 60 50 40 30 BL1A Charge 20 10 0 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 Year Figure 3 BL1A charge in mAhrs delivered as a percentage of charge scheduled per year 2 3. Radioactive Ion Beam Delivery The ISAC facility has an Off-Line Ion Source (OLIS) that produces various species of non-radioactive charged particles which can be directed to low energy experiments, or accelerated through the Radio Frequency Quadruple (RFQ), Drift Tube Linac (DTL) and Super Conducting Radio Frequency Linac (SCRF). Since Radioactive Ion Beams (RIB) are of low intensities and are difficult to measure, OLIS beam is required to produce equivalent charge to mass ratio beams for accelerator tuning purposes. The availability of OLIS is therefore a crucial element for the delivery of RIB to experiments. OLIS Uptime 100 90 80 70 60 50 40 30 20 OLIS Uptime 10 0 2001 2002 2003 2004 2005 2006 2007 Figure 4 Off Line Ion Source uptime; average is greater than 97% Drift Tube Linac and Radio Frequency Quadrupole Uptime 2001 -2007 Percentage of Scheduled Operational Hours per Year 100 90 80 70 60 50 40 30 20 RFQ DTL 10 0 2001 2002 2003 2004 2005 Figure 5 The RFQ and DTL accelerators 3 2006 2007 The uptime for the ISAC DTL and RFQ accelerators is demonstrated in Figure 5 and averages well above 95%. The Phase I SCRF linac has an availability of nearly 100% since its completion in 2006. The large overhead for ISAC target changes and the on line development of targets significantly impacts the available time to RIB experiments. This has been identified as a bottle neck in the previous (2005-2010) Five-year Plan request in the form of an additional proton beam line (BL4N) and target stations. Figure 6 represents the lost hours of RIB to experiments as a percent of scheduled hours. This is overhead associated with target preparation and set up for proton beam acceptance. Percent of Scheduled RIB Hours Lost for Target Preparation 30 25 20 15 10 5 0 1999 2000 2001 2002 2003 2004 2005 2006 2007 Figure 6 Percentage of scheduled RIB hours lost (downtime for all systems is non-coincidental) 4. Present Effort Required to Operate Delivery Systems The Accelerator Division maintains repairs and operates (MRO) TRIUMF’s accelerators on a `round the clock’1 basis with an operations group and technical support staff totaling approximately 130 Full Time Equivalents (FTE)2. The technical support staff comes from the Accelerator, Administration and Engineering Divisions (but excludes administrative overhead) and includes the refurbishing and development effort associated with maintaining the high percentage of beam availability. The majority of the total FTE effort comes from the Accelerator Division and relates directly to laboratory operations and development with the balance coming from services and infrastructure support groups. Accelerator physicists/researches account for approximately 10-15% of the 130 FTE, 2025% are in the engineering category and the balance being technical staff. Existing staffing levels need to be augmented to improve RIB delivery, enhance maintenance activities and to meet ever increasing regulatory requirements. As an example, a significant FTE effort is necessary to meet the obligatory Canadian Nuclear Safety 1 2 TR13 operates ~ 12 hours per day, five days per week Based on salary allocation data March 31, 2007 4 Commission mandated Quality Assurance program. The 2005-2010 Five-Year Plan proposal identified the need for increased staffing levels. In particular, the need for 22 additional FTE for increased ISAC operations was identified. Unfortunately the 20052010 budget allocation did not support the proposed staffing increase. Through succession planning, reorganization and ongoing needs analysis some manpower reallocation has taken place. However, this effort is not sustainable and impacts other TRIUMF activities. Additional resources are required irrespective of any new initiatives undertaken at TRIUMF. 5. Future Effort Required to Operate Delivery Systems The new high intensity electron machine will deliver beams to one of the new target stations. Radioactive beam production will expand from one production target at any given time to three targets in simultaneous production. The ISAC beams capability will increase from one RIB and one stable beam simultaneously to up to three RIB beams simultaneously with two of the RIBs accelerated. These new initiatives will require additional resources to provide a comparable level of service as is now provided to existing facilities. The actual operation of the facility would most efficiently be done by an amalgamation of the operations groups in a single expanded control room. Ideally the combined control area would be centrally located to provide quick access to equipment. This concept has significant advantages; the operations group works closely with controls and safety personnel, beam physicists and coordinators who all need to be in close proximity. It would also allow the overall on-shift operations effort to remain at near present levels. The technology of the cyclotron controls make a remote operation upgrade more difficult and time consuming than an EPICS control interface move. However, the anticipated costs and effort associated with such a move are not expected to appreciably increase the overall cost of amalgamation in a combined control area. As an alternative, the existing TRIUMF 500 MeV control room and adjacent area could be expanded to support a combined centralized operation. Support groups however may not have sufficient room to be in close proximity to operations. In either case a Human Factors Engineering study is required by the regulatory agency (CNSC). The expansion of operations area would require an estimated 300-500k of renovations and installations. The electron linac will be installed with an EPICS control interface as will all of the ISAC upgrades. Even though the beam delivery network is significantly expanded (one new cyclotron beamline, one new driver and beamline, two new targets and RIB beams) the number of operators will not have to expand in direct proportion since the accelerator readiness and tuning for technical equipment across the site will not be done simultaneously. It is envisaged that one shift supervisor and four operators per shift would be sufficient to run the facility with an expanded beam delivery team of beam physicists to offer expert tuning and daily interaction. Additional beam physicists at a Post-doc or junior researcher level would be required to handle the expanded beam delivery network. Presently TRIUMF employs 24 operators. Full staffing of five operators per shift would require an additional operator. Additional staffing will be needed to augment coordinating, training and overhead relief tasks for the new initiatives. 5 The technical teams for maintaining and monitoring the facility will need to be expanded particularly in the ISAC target stations, hot cell operations and target production but also in controls, vacuum, cryogenics, RF, safety and beam lines. Three simultaneous beams capability means three times the number of targets and target hall activities. It is intended that the new target stations be designed to facilitate faster target turn around and reduce the possibility of loose contamination. In general the technology that is being added in the Five-Year Plan is not unique to TRIUMF and new hires need not be required at the senior level but could be sourced to fill junior and intermediate ranks. New infrastructures such as the helium recovery and liquefier plant, electrical and mechanical services are anticipated to all require additional support. 6. Summary The heart of TRIUMF, the 500 MeV cyclotron, has operated very reliably (uptime averaging ~90%) for many years and is expected to continue at level as beam intensities increase. The ISAC accelerators average better than 97% availability and highlight the need to reduce ISAC target overhead. Although the present Five-Year Plan did not include sufficient resources to address this and other issues, TRIUMF, through succession planning, reorganization and ongoing needs analysis, has made some resource reallocation to mitigate the operational impact. Additional resources are required tackle this and other impacted areas irrespective of any new initiatives undertaken at TRIUMF. TRIUMF has been successful in its past endeavours. TRIUMF’s highly skilled staff is motivated and committed to excellence and anticipates a stimulating and challenging future. 6