6900 East Indian School Road, Suite 200 Scottsdale, Arizona 85251 Tel: 480.850.6900 Fax: 480.850.6901 www.armays.com EXHIBIT A SCOPE OF WORK TO: Universal Design Masonry A. JOB SPECIFIC INCLUSIONS – The Subcontractor's "Scope of Work" includes the following: Item No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 JOB NAME: Gilbert Christian High SUBCONTRACT NO: 092017-003 Description The subcontractor agrees to furnish all labor, material, equipment and supervision required to complete all Masonry work. Refer to General Structural Notes, sheets S-101 & S-102 of Construction Documents for general masonry requirements, and in accordance with the Contract documents. Notwithstanding any provision herein to the contrary, in the event that, during the performance of this agreement, the price of material and/or any other necessary commodities significantly increases or decreases, through no fault of the Subcontractor, the price of any materials, components, or goods to be furnished under this agreement shall remain fixed and the Subcontractor shall bear sole responsibility for any cost overruns or retain any cost savings as a result of the change. The subcontractor shall be responsible to coordinate and assist with job site project planning to ensure the work is continuous. The subcontractor shall notify the Project Superintendent of requested inspection dates and times, and be present during all inspections. SITE MASONRY Furnish and install all trash enclosure masonry work per Architectural and Structural drawings. Furnish and install all Brick Veneer per drawings Furnish and install all masonry work for site screen. Furnish and install all Brick Veneer per drawings. Furnish and install all masonry work for site monument sign. Furnish and install all Brick Veneer per drawings Furnish and install all Brick Cap work for the site monument sign and site screen per drawings. Furnish and Grout all masonry work per Architectural and Structural drawings. Furnish and install all steel reinforcing in masonry including rebar and bond beam wire reinforcing. BUILDING MASONRY Furnish and install all Masonry, CMU, work per Architectural and Structural drawings Wall types identified on Drawing A-601, Wall type Details. Wall Type locations identified on Architectural Floor Plans. Furnish and install all CMU Bench/Locker Stand, reference drawing A-203, key note Provide Masonry stem walls per plans and specifications. Furnish and install all Loose Fill Vermiculite in all open cells Furnish and install all Solid Grouted CMU per Structural, Furnish and install all steel reinforcing in masonry including rebar and bond beam wire reinforcing. Signature Print Name Page 1 of 3 Date 6900 East Indian School Road, Suite 200 Scottsdale, Arizona 85251 Tel: 480.850.6900 Fax: 480.850.6901 www.armays.com 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Furnish and install all Brick Veneer per floor plans, elevations and details. Furnish and install all pre-cast materials identified on Exterior Building Elevations and Drawing A-604. The subcontractor shall provide shop drawings for Architect Review of all pre-cast materials. a. Column Base b. Column, including Trim Detail at Top of Column and Cap c. Key Stones d. Vent e. Quoin f. Window Surround Header g. Window Surround Sill h. Window Deltoid Surround Header i. Window Arch Surround Header j. Door Surround Header k. Door Jamb Surround l. Pilaster Header m. Eve Molding Coordinate all openings in walls with other trades. i.e. Mechanical, Electrical, Plumbing, Doors and Fire Protection subcontractors. Verify all openings in masonry with manufacturer’s shop drawings as provided by AR Mays, including elevator doors and reinforcing. Protect all masonry walls and concrete floors from mortar and grout splash. Broadcast sand on floors as necessary. Clean any splash upon completion. Layout and install all steel embed plates; steel lintels and anchor bolts in masonry, Dry pack under all embed plates and lintels. Embed plates and steel lintels provided by others. Furnish and install all required Dry pack in all Masonry penetrations created by Electrical, Fire Alarm, Fire Sprinkler, Mechanical and Plumbing trades. Provide setting and bracing for hollow metal frames in masonry, as provided by others. Grout all hollow metal door frames. Coordinate vertical reinforcement to avoid conflicts with beam bearing conditions as to not require the cutting of vertical reinforcement. Strike all exposed joints including all interior and exterior side of walls and back side of parapet walls. Fill all joist bearing pockets with masonry upon completion of their installation. Provide all reinforcement, grout and block products and methods per specifications. Provide and install all required masonry control joints and materials. Reference structural sheets and specifications. Install weep holes in masonry as required. Provide and place all temporary walls bracing as required. Provide and place all temporary shoring for masonry openings. Provide a designated masonry dumpster, and haul off of masonry debris for disposal in approved landfill. Location of dumpster shall be by the Project Superintendent. Brick veneer and Polyurethane/G.F.R.C/Precast Color Legend per Architectural Drawing A-301. Final Color Selection by Architect. a. FAUX Brick Veneer, Coronado Stone Products, 1A Jolla b. Precast, Light Gray Signature Print Name Page 2 of 3 Date 6900 East Indian School Road, Suite 200 Scottsdale, Arizona 85251 Tel: 480.850.6900 Fax: 480.850.6901 www.armays.com 39 40 41 42 43 44 45 46 Provide all masonry ties and brick ties in order to complete all pier details. Install all bolts for sill angles and flashing for brick and stone in masonry per plan. Bolts provided by others. Install all top plate parapet bolts in masonry per plan. Bolts provided by others Provide all mechanical fasteners. Provide wall patch for fasteners. Mechanically fasten and adhere all precast concrete per plans and General Notes Materials are to be delivered to job site and staged per the job site superintendent. Clean masonry at each lift to deter efflorescence. B. JOB SPECIFIC EXCLUSIONS – The Subcontractor's "Scope of Work" excludes the following items: Item No. Description 1 Taxes C. CHANGES IN SCOPE OF WORK 1 The overhead and profit allowance for extra work performed on a time and material basis shall not exceed ten percent (10%). 2 The Subcontractor agrees to the following prices which include all fringes, insurance, taxes, overhead and profit for changes in "Scope of Work”: Foreman $35.00/hr. Mason: $30.00/hr. Labor: $20.00/hr. D. SCHEDULE AND PERFORMANCE – The Subcontractor shall meet or exceed the following performance requirements. Work tasks shall be accomplished concurrently : 1 Project requirements: Complete All Masonry Work in 90 calendar days. Site Masonry Work in 6 calendar days Building Structural Masonry Work in 50 calendar days Building Brick Veneer in 38 calendar days Precast Products in 26 calendar days E. SUBMITTALS – The Subcontractor shall submit six (6) copies of product data and samples within 10 days after Subcontract Award. F. PAYMENT AND PERFORMANCE BOND WILL NOT BE REQUIRED. Signature Print Name Page 3 of 3 Date