MARKING GUIDELINE NATIONAL CERTIFICATE CARPENTRY AND ROOFING THEORY N2 14 NOVEMBER 2012 This marking guideline consists of 8 pages. Copyright reserved Please turn over MARKING GUIDELINE -2CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T QUESTION 1 1.1 1.2 1.1.1 Temporary structures (1) 1.1.2 Vertical pegs (1) 1.1.3 Horizontal members (1) 1.1.4 Foundation (1) 1.1.5 Walls (1) 1.1.6 1 metre (1) A benchmark should be permanent and easy to find. It is essential that a locality sketch be available for each benchmark. If possible, a benchmark must be shown in relation to other permanent structures e.g. roads, etc. Measurements should be taken from at least THREE defined objects. (4) [10] QUESTION 2 2.1 (10) Copyright reserved Please turn over MARKING GUIDELINE 2.2 -3CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T By means of hurricane clips By using a combination of wire and nails By using a combination of wire clips and nails By using a combination of nails and hoop iron (ANY TWO) 2.3 2.4 (2) Nail the truss from both sides with 100 mm nails into the wall plate Strap hoop iron firmly over the truss and nail securely Ensure that the hoop iron is long enough to tie down both the wall plate and the truss. 2.4.1 2.4.2 2.4.3 (3) Rafter: 38 mm x 228 mm or 38 mm x 152 mm Grade: 6 of 8 (2) Tie beam: 38 mm x 228 mm Grade: 6 of 8 (2) Maximum spacing: 760 mm (1) [20] QUESTION 3 3.1 3.1.1 Class A, Class B, Class C 3.1.2 A: Metal and/or fibrecement sheets B: Concrete tiles, clay tiles and thatching C: Metal roof tiles Copyright reserved (3) (ANY ONE) Please turn over (3) MARKING GUIDELINE -4CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T 3.2 (9) [15] QUESTION 4 4.1 E (1) 4.2 F (1) 4.3 G (1) 4.4 A (1) 4.5 H (1) 4.6 C (1) 4.7 B (1) 4.7 D (1) [8] Copyright reserved Please turn over MARKING GUIDELINE -5CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T QUESTION 5 5.1 5.2 5.3 (5) [15] QUESTION 6 [12] SUB TOTAL: Copyright reserved Please turn over 80 MARKING GUIDELINE -6CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T QUESTION 7 THIS QUESTION IS FOR CARPENTRY CANDIDATES ONLY 7.1 (6) 7.2 7.2.1 Wall piece/plate (1) 7.2.2 Needle (1) 7.2.3 Rider (1) 7.2.4 Cleat (1) 7.2.5 Top shore/raker (1) 7.2.6 Middle shore/raker (1) 7.2.7 Braces (1) 7.2.8 Wedge (1) 7.2.9 Bottom shore/raker (1) 7.2.10 Back- or supporting shore/raker (1) 7.2.11 Sole plate (1) 7.2.12 Transverse timbers or grillage (1) Copyright reserved Please turn over MARKING GUIDELINE 7.3 -7CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T Formwork is a temporary mould to serve as a system of support into which concrete and reinforcement/steel is cast to form a required shape and a predetermined strength until it has set sufficiently. (2) [20] QUESTION 8 THIS QUESTION IS FOR ROOFING CANDIDATES ONLY 8.1 (4) 8.2 (9) Copyright reserved Please turn over MARKING GUIDELINE 8.3 8.4 -8CARPENTRY AND ROOFING THEORY N2 T270(E)(N14)T It is obtainable in long lengths It can be applied temporarily No extra glue necessary to fix the membrane (3) 8.4.1 Slate cutter (1) 8.4.2 Slate ripper (1) 8.4.3 Slater’s hammer (1) 8.4.4 Guillotine (1) [20] TOTAL: Copyright reserved 100 Please turn over