CERN LHC Project Document No. CH-1211 Geneva 23 Switzerland LHC-VBMB-IP-0001.00 rev. 2.0 CERN Div./Group or Supplier/Contractor Document No. AT-VAC-EN/AV-01 the EDMS Document No. Large Hadron Collider 369533 project Date: 2016-02-16 Installation Procedure BEAM LINE ARC INTERCONNECTS PLUG-IN MODULES Abstract The purpose of this Installation Procedure is to define the sequence of operations required to install the Plug-in Modules on the beam lines V1 and V2. These operations shall be performed in the tunnel during the interconnection of cryomagnets and before the inductive soldering of the main superconducting bus bars (ref. 1). Prepared by : Checked by : Approved by : Alexis Vidal AT/VAC/EN1 Juan Knaster AT/VAC/EN1 Raymond Veness AT/VAC/EN1 Alexis.Vidal@cern.ch Juan.Ramon.Knaster@cern.ch Ramond.Veness@cern.ch Didier Chauville AT/VAC/EN1 Patrick Lepeule AT/VAC/EN1 Didier.Chauville@cern.ch Patrick.Lepeule@cern.ch Distribution list: LHC Interconnections: M. Bajko, P. Bonnal, D. Bozzini, J. Casas-Cubillos, I. Collins, P. Cruikshank, K. Dahlerup-Petersen, L. Evans, G. Favre, C. Garion, N. Gilbert, C. Hauviller, R. Herzog, A. Jacquemod, K. Kershaw, J. Knaster-Refolio, F. Laurent, Ph. Lebrun, P. Lepeule, E. Manola, S. Marque, K-H. Mess D. Missiaen, L. Nielsen, R. Ostojic, V. Parma, G. Passardi, A. Perin, J-L. Perinet-Marque, L. Perrollaz, A. Poncet, P. Proudlock, J-P. Quesnel, G. Riddone, F. Rodriguez-Mateos, P. Rohmig, L. Rossi, E. Roy, S. Russenschuck, R. Saban, F. Savary, W. Scandale, F. Schauf, G. Schneider, N. Siegel, A. Siemko, F. Simon, B. Skoczen, P. Strubin, L. Tavian, J-Ph. Tock, D. Tommasini, Th. Tortschanoff, R. Trant, R. Veness, A. Vidal, J. Vlogaert, L. Walckiers, R. van Weelderen, W. Weingarten, L.R. Williams. LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 2 of 15 History of Changes Rev. No. Date Pages 0.1 – draft 2003-01-20 All 1st draft prepared by A. Vidal & D. Chauville. 0.2 – draft 2003-04-29 All 2nd draft checked by J. Knaster and P. Lépeule and sent for approval to the above list. Deadline: 15th May 2003. 1.0 2003-05-23 All Updated after circulation in accordance with comments given by the members of the LHC Interconnections list. Version 1.0 released. 2.0 2005-01-25 5 8 9 10 Table 1 updated. Information added in step 4. Position measurement card suppressed in step 6. Compression tooling identified in step 12 and step 13 updated. Reference added in step 16 and 17. Reference added in step 22. Definition of RF bellows protection in step 35 and step 36 completed. Paragraph 5.1 – Tooling list updated and new reference in section 7. Record card updated. Version 2.0 released. 11 12 13 14 15 Description of Changes LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 3 of 15 Table of Contents 1. INTRODUCTION ..........................................................................................4 2. GLOSSARY OF ACRONYMS ...........................................................................4 3. SAFETY WARNINGS .....................................................................................4 4. SEQUENCE OF OPERATIONS ON A VACUUM LINE ........................................4 4.1 GENERAL COMMENTS ................................................................................... 4 4.2 LOCATION OF BEAM LINES IN THE TUNNEL ..................................................... 5 4.3 GLOBAL SECTION THROUGH A PLUG-IN MODULE (MB-MB)................................ 6 4.4 GLOBAL SECTION THROUGH DOWNSTREAM AND UPSTREAM SIDES (MB-MB) ..... 6 4.5 GLOBAL SECTION THROUGH DOWNSTREAM AND BPM SIDES (MB-SSS) ............. 7 4.6 GLOBAL SECTION THROUGH DOWNSTREAM AND UPSTREAM SIDES (SSS-MB) .... 7 4.7 DESCRIPTION OF OPERATIONS ...................................................................... 7 5. THE REQUIRED EQUIPMENT ......................................................................14 5.1 TOOLING ................................................................................................... 14 5.2 MATERIAL ................................................................................................. 14 6. RECORD CARD ...........................................................................................14 7. REFERENCES .............................................................................................14 8. ANNEXES...................................................................................................15 8.1 RECORD CARD ........................................................................................... 15 LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 4 of 15 1. INTRODUCTION The purpose of this Installation Procedure is to define the sequence of steps required to install the Plug-in Modules in the beam line V1 and V2, in order to ensure the quality and the reliability of this operation. This activity shall be performed in the tunnel during the interconnection of cryomagnets and before the inductive soldering of the main superconducting bus bars (ref. 1). All positions, control and test results, observations and remarks will be recorded in the “Record Card” (see section n 8). 2. GLOSSARY OF ACRONYMS LHC: Large Hadron Collider V1: Outer beam lines V2: Inner beam lines SSS: Short Straight Section MB: Cryodipole AT/VAC: Accelerator Technology Division – Vacuum Group RF bellows: Radio Frequency Bellows QRL: Cryogenic distribution line BPM Beam Position Monitor 3. SAFETY WARNINGS Before starting the operations in the tunnel, a global authorisation should be obtained from CERN safety division. 4. SEQUENCE OF OPERATIONS ON A VACUUM LINE 4.1 GENERAL COMMENTS The line V1 (outer) should be installed before the line V2 (inner) in order to ensure the best accessibility. This remark is applicable to all types of interconnects, see table 1. The operations to perform the installation of the plug-in module are similar for the beam lines V1 and V2 and applicable for all interconnects, MB-MB, MB-SSS and SSS-MB. A visual inspection shall be performed on the 2 interconnects extremities (see step n5 in section n4.7). A check of the relative position of the extremities of V1 and V2 lines is required (see step n6 in section n4.7). An inspection of plug-in modules installation (see step n37 and ref. 1) will be performed by a final visual inspection (not under the present Contractor's responsibility). Attention: the sequence of operations is similar but there are dedicated plug-in modules for each type of interconnects, see table 1. All welds shall be performed by an automatic orbital welding machine. The tacking operations should be done manually with the compression tooling in place (prototype supplied by AT/VAC). LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 5 of 15 Table 1 – References of plug-in module Interconnect Dipole-Dipole (MB-MB) LHCLVIBB0008 Dipole-SSS (MB-SSS) LHCLVIBB0009 SSS-Dipole (SSS-MB) LHCLVIBB0010 Plug-in module MB-MB Plug in module - series LHCVBMB_0001 Identification boxes: MMxxxx (x=serial numbers) MB-SSS Plug in module - series LHCVBMB_0003 Identification boxes: MSxxxx (x=serial numbers) SSS-MB Plug in module - series LHCVBMB_0002 Identification boxes: SMxxxx (x=serial numbers) Extremities definition Downstream – Upstream Downstream – BPM SSS – Upstream The following points must be respected during the operations: All manipulations with the beam line extremities and plug-in modules must be performed with clean gloves. All manipulations of plug-in modules must be performed with care and any damage of RF bellows, contact strips, insert parts and pollution shall be avoided. All tooling must be kept clean during each operating phases. The nested bellows protection (Aluminium shields) must be kept always in place. 4.2 LOCATION OF BEAM LINES IN THE TUNNEL Beam lines V1 and V2 Magnet Space reserved for transport QRL LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 6 of 15 4.3 GLOBAL SECTION THROUGH A PLUG-IN MODULE (MB-MB) Downstream side RF Bellows Contact Strips Copper Transition Tube Upstream side RF fingers Contact Strips RF-Contact 4.4 GLOBAL SECTION THROUGH DOWNSTREAM AND UPSTREAM SIDES (MBMB) Beam Screen Pin MB Downstream side MB Upstream side LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 7 of 15 4.5 GLOBAL SECTION THROUGH DOWNSTREAM AND BPM SIDES (MB-SSS) Pin MB Downstream side Remark: No pin SSS side 4.6 GLOBAL SECTION THROUGH DOWNSTREAM AND UPSTREAM SIDES (SSSMB) Pin SSS Downstream side MB Upstream side 4.7 DESCRIPTION OF OPERATIONS The operation sequence described in this section corresponds to the line V1 (outer) of DipoleDipole interconnects. However, this procedure is applicable for both lines (V1 and V2) and for each type of interconnects (see Table 1). The operations of tacking (step 15-21) and welding (step 26-32) can be performed in series by the Contractor. LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 8 of 15 Beam line V1 (outer) Step 1 Description Picture Unpack the Plug-in module with care from cardboard tube and polyethylene bag (clean gloves shall be used). Check the type of Plug-in module on the Traveller sheet. Tooling 2 2 Remove the tooling n1 (ref. 2). Tooling 1 3 Visual inspection of Plug-in module in order to check eventual damage on: - RF bellows - Flange extremities - Contact strips - External and internal envelope The reference must be recorded in the installation Traveller. 4 Remove the extremities protection of the line V1 (metallic flanges). Keep the nested bellow protection (Aluminium shields). The extremities protection of V1 shall be returned to a surface building (to be defined). 5 Visual inspection of the 2 interconnects extremities. Check the presence of the pin in each extremity (Not applicable for SSS side). Look inside the beam lines, in both directions and survey carefully (with a torch and mirror) the absence of objects in the beam lines. If any damage is detected, the defect must be reported to Traveller sheet and another plug-in module must be installed. Downstream side Nested bellow Upstream side LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 9 of 15 6 Check the relative position of the extremities of the V1/V2 lines and record the result on the “Record card”. REMARK: Measurement tooling (to be defined) and “Record card” supplied by AT/VAC. If the position of the extremities is out of tolerances, the installation process has to be stopped temporally until the decision of CERN responsible. 7 Introduce manually the plug-in module between both beam line extremities. 8 Insert the downstream flange of the Plug-in module into the downstream extremity. WARNING: This operation must be performed smoothly so as not to damage the RF contact strips. The pin inserted will address the orientation. Part of operation #LI-1-02 (ref. 1). Downstream side Knurled nuts 9 10 Extend the RF bellows progressively with the knurled nuts (ref. 2). Turn smoothly the Plug-in module until the pin is housed in the copper component on the upstream side. WARNING: This operation must be performed smoothly so as not to damage the RF contact strips. Upstraem side LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 10 of 15 11 12 Install the RF bellows protection (Kapton foil). WARNING: This protection must be not electrically conductive in order to preserve the RF bellows during the tack weld phases. Insert the compression tooling n3 (ref. 4) on the downstream flanges. Tooling n3 Downstream side 13 Apply a torque (to be defined) on screw in order to obtain a force of 60 kg with the compression tooling. Check the distance between flanges (this distance must be 1 mm on whole circumference within a tolerance to be determined after the pre-series assembly). 14 Install the ground cables of the welding machine on both sides (downstream and upstream side). WARNING: If this procedure is not followed, the plug-in module may be destroyed during the tack welding. 15 Tack welds manually the downstream flanges (between 4-8 points at equally distance). NOTE: The oxidation from the weld must be removed with a stainless steel brush. 1 mm Downstream side Ground cable LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 11 of 15 16 17 Remove the compression tooling n3 (ref. 4). Insert the compression tooling n3 (ref. 4) on the upstream flanges. WARNING: The knurled nuts should be unscrewed during the insertion of the compression tooling on the upstream side. Upstream side 18 Apply a torque (to be defined) on screw in order to obtain a force of 60 kg with the compression tooling. Check the distance between flanges (this distance must be 1 mm on whole circumference within a tolerance to be determined after the pre-series assemblies). 19 Remove tooling n2 of the Plug-in module (ref. 3). 20 Check if the ground cables of the welding machine are installed on both sides (downstream and upstream side). WARNING: If this procedure is not followed, the plug-in module may be destroyed during the tack welding. 1 mm Upstream side LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 12 of 15 21 22 Tack welds manually the downstream flanges (between 4-8 points at equally distance). NOTE: The oxidation from the weld must be removed with a stainless steel brush. Remove the compression tooling n3 (ref. 4). WARNING: Keep the RF bellows protection in place (Kapton foil). RF bellow protection 23 Install rolling shells on the RF bellows for welding of downstream side. 24 Install orbital welding machine on rolling shells. 25 26 27 Install the ground cables of welding machine on both sides. WARNING: If this procedure is not followed, the plug-in module may be destroyed during the welding. Make the welding. NOTE: The oxidation from the weld must be removed with a stainless steel brush. Visual inspection of the welding. Category B See ISO 5817 LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 13 of 15 28 Remove orbital welding machine and keep in place the ground cables in both sides. 29 Install rolling shells on the RF bellows for welding of upstream side. 30 Install the orbital welding machine on rolling shells. 31 32 Check if the ground cables of welding machine are installed in both sides. WARNING: If this procedure is not followed, the plug-in module may be destroyed during the welding. Make the welding. NOTE: The oxidation from the weld must be removed with a stainless steel brush. 33 Visual inspection of the welding. Category B See ISO 5817 34 Remove orbital welding machine, ground cables and rolling shells. 35 36 37 Install the RF bellows (Aluminium shields). protection The plug-in module assembly is finished for the line V1 (outer). Repeat steps from 1 to 36 for the second line V2. Inspection of the plug-in module assembly (not under the present Contractor's responsibility). Operation #LI-1-04 (ref. 1). LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 14 of 15 5. THE REQUIRED EQUIPMENT 5.1 TOOLING The tooling required for performing the plug-in module assembly is given in the following list: Orbital TIG welding machine with double ground cables (this welding machine must be equipped with a system to archive the welding parameters after each operation). Manual TIG welding machine with double ground cables or equivalent. Torch and mirror. Rolling shells. RF bellows protection (one prototype supplied by AT/VAC). Compression tooling n3, see ref. 4 (one prototype supplied by AT/VAC). Torque wrench. Measurement tooling (one prototype, supplied by AT/VAC). Empty “Record Card” sheet provided by AT/VAC. 5.2 MATERIAL The material required for performing the plug-in module assembly is given in the following list: Clean gloves (scem number: 50.43.20.750.8 or 50.43.20.760.6). Alcohol ethylic (scem: 58.04.38.220.0). Clean waste (scem: 30.41.20.200.3). Scotch tape (scem: 04.95.45.263.4). Aluminium foil (scem: 44.01.35.900.4). Protection gas (Argon). Stainless steel brushes (scem: 34.90.08.010.4). Kapton foil (scem: 44.88.80.010.6). 6. RECORD CARD The “Record Card” ensures the traceability of the installation parameters, records remarks pertaining to the installation phases and the location of each plug-in module. The operator responsible shall fill in this Card after each operation as part of the Quality Assurance Programme. The Card will be transmitted to the Quality Officer who is in charge of the follow-up of the installation." An example of this “Record Card” is presented in Annex 1. 7. REFERENCES 1 LHC-LI-ES-0009 Interconnection Work Package 1 (IWP 1) Interconnections: Interconnection of the inner lines 2 LHCVSS_H0074 Plug-in Module Assembly Tooling 1 3 LHCVSS_H0075 Plug-in Module Assembly Tooling 2 4 LHCVSS_H0184 Compression Tooling 3 – Cryomagnets LHC Project Document No. LHC-VBMB-IP-0001.00 rev. 2.0 Page 15 of 15 8. ANNEXES 8.1 RECORD CARD Plug-in module – Record Card Interconnection: …………………………………………… Line number:……………………… Contractor responsible:…………………………………. Date: .. / .. / .. Plug-in module number Starting time: …. H …. …………………………………………………………………………………………………….. Visual inspection result(step n°3)* OK NO Remarks Interconnects extremities Visual inspection result (step n°5)* Pin installed* Downstream side Upstream Side OK NO OK NO YES NO YES NO Measurement result of extremities offset for the line V1 (step n°6) …………………… …………. …………………… Extremities offset of of line V1 Measurement result extremities offset for the line V2 …………. …………………… …………. …………………… Measurement result of the distance between extremities for the line V1 Measurement result of the distance between extremities for the line V2 …………. Remarks Tacking phases Differences with procedure (step n°15-21)* Name of welder:……………………………………………………………………….... Downstream side NO Upstream Side YES NO YES If yes, details Welding phases Differences with procedure (step n°26-32)* Name of welder:……………………………………………………………………….... Downstream side NO Upstream Side YES NO YES If yes, details Final control (Attached the “welding parameters”) Differences with procedure* Downstream side NO Upstream Side YES NO YES If yes, details Visual inspection result* In conformity with ISO 5817, category B YES * Make a cross to give result (for example: √ No or √ YES ) NO