1 1.0 Project Description The proposed project is the replacement of the Green Garden Road Bridge carrying S.R. 3016 over Raccoon Creek. The site is located in the municipality of Hopewell Township, Beaver County, for the Pennsylvania Department of Transportation (PENNDOT), District 11-0 (see location map Appendix A.) 2.0 Site Data 2.1 Existing Structures-Although there are structures upstream and downstream of the project site they are not in the immediate vicinity and therefore not affected by the project. 2.1.1 Green Garden Road Bridge – The existing structure is a steel beam concrete filled grid deck bridge with a normal span(s) between abutments of 120’, an average under clearance of approximately 8.6’ and a skew of 90°. The bridge is 25.5’ wide and there are no sidewalks on the structure. The low chord elevation of the bridge ranges from 772.19’ to 773.02’. 2.2 Proposed Structure- The proposed structure is a single span steel plate girder with an c/c span length of 126+’-0 3/4” and a width of 59.375’ The cross section allows for three 12’-0” lanes, one in either direction, as well as a turning lane and 10’-0” shoulders. The single span alternative uses seven beams due to max overhang and spacing restrictions. The depth of the beams is 4.77’ and the estimated depth for the super elevation is 0.8275’ which gives an overall depth of 5.597’. The low chord elevations of the structure are 776.16’ and 774.20’. Since the bottom chord of the proposed structure will be raised, the average under clearance will increase by approximately 3.0’.It should also be noted that upon completion of the proposed structure the existing structure will be removed. Line and grade approval was acquired on 8/19/03. 2.3 Environmental Habitats- Raccoon Creek is listed in the Pennsylvania Department of Transportation design manual, Part 2, Appendix 10.A as a stockable warm water and trout stream; it is also listed as a warm water fishery in PA code, Title 25, Chapter 93, water quality standards. 2 2.4 Flood History- The federal emergency Management Agency (FEMA) Flood Insurance Study (FIS) states that flooding occurred on Raccoon creek in February 1975 and was estimated to be a 10 year flood, according to available high water marks. 2.5 Drift and Ice- There is no evident build up of drift or ice during field views. It should be noted however, that under extreme levels of flow there could be significant accumulation and the hydraulic opening could decrease in size thereby increasing the backwater elevations. The computer programs used to model the hydraulics of the channel do not take into account obstruction of the hydraulic opening and therefore are not representative of high discharge events with significant debris accumulation. 2.6 Streambed and Stream bank Stabilization- The streambed and banks of Raccoon Creek can be characterized as stable. 2.7 Factors affecting Water stages- There are no flood control structures on the Raccoon Creek water-shed. However, there are two large impoundments; the J.C. Bacon Dam on service creek and the Raccoon Creek Park Dam on Traverse Creek which may partially control 34.8 square miles of the watershed. 3.0 Hydrologic Analysis A detailed hydrologic investigation was completed for the 1981 FEMA FIS. The FIS lists peak discharges in cubic feet per second for the 10, 50, 100, 500 year storms as well as the drainage area in square miles for Raccoon Creek which is given as 150 sq. mi. The flood flows were estimated by the Log-Pearson Type III frequency method based on the 50 years of available data for the site. These flows were also adjusted to account for the aerial difference between the gauging station and the area of study. The 10, 50, 100, and 500 year discharges were then plotted against their frequency of occurrence and a best fit line was added to interpolate additional recurrence frequencies which include the 1, 1.25, 2, 5, and 25 year floods. Green Garden Road (S.R. 3016) is considered a minor arterial in the area of the project site. The minimum design flood for the structure is the 25 year flood according to PENNDOT S.O.L. 431-99-11 however, the 100 year flood is also considered due to the fact that the structure lies within a detailed FEMA study area. 3 Peak flows for Raccoon Creek are as follows: Flood Frequency (YEARS) 1 1.25 2 5 10 25* 50 100 500 Peak Discharge (CFS) 5139 5295 5639 6374 6793 7906 8949 9765 11475 Notes: 1. * 25 year frequency = Minimum Design Storm according to PENNDOT S.O.L. 431-99-11 2. Values in bold are from 1981 FEMA FIS. All other values are interpolated For the Flood frequency curve as well as the stage-discharge frequency curve for Raccoon Creek see appendix B. 4.0 Hydraulic Analysis 4.1 Methodology- Using the calculated discharges, hydraulic effects of existing and proposed conditions was studied. Calculations were performed using U.S. Corps of Engineers HEC-RAS river analysis system software, version 3.0.1 Given the site data and hydrologic data, the HEC-RAS models provide flood profiles, cross-section data, and channel velocities. This software was used to compare hydraulic models for the existing and proposed to determine if there were any changes in back water elevations or channel velocity that would occur due to the project. The HEC-RAS output for the existing and proposed conditions are presented in Appendices D and E. 4.2 Existing Condition Model-The HEC-RAS model shows that the existing condition does not accommodate the 10, 50, and 100 year storms as a negative freeboard value is calculated for all cases. The 500 year storm is similarly not accommodated by the structure with the deck elevation being only approximately 3” above the water elevation. 4.3 Proposed Condition Model- The existing condition HEC-RAS model was modified to include the geometric and profile adjustments of the proposed structure conditions. The bottom chord of the proposed 4 structure has been raised an average of 3.0’ in elevation, and the “Bridge open area” has increased from 817.19 sq. ft. to 1238.54 sq. ft. according to the HEC-RAS modeling. The additional clearance of the proposed structure is due partly to the fact that the location of the bridge is at a higher elevation and the superstructure is shallower compared to the existing structure. The results found while modeling the proposed structure are generally similar to the existing condition with the exception of the proposed structure accommodating the 10 year storm while providing 2.06’ of freeboard. This is an improvement over the existing condition which cannot accommodate the 10 year storm and has 0.83’ of the lower chord inundated by flood water. There is also a decrease in most backwater elevations for the 10, 50, 100, and 500 year storms at river stations upstream of the proposed structure while any increases are considered negligible. The hydraulic conditions downstream of the structure are unchanged form the existing condition. 5.0 Risk Assessment or Analysis The proposed structure was designed to minimization the risk of future flooding at the site. The opening size was chosen to reduce the backwater elevations while adhering to the constraints for the road profile. The proposed structure has an improved hydraulic opening due to the fact that there is additional under clearance while maintaining the width of the opening as well as the removal of the pier. The performance of the proposed structure is very similar to the existing structure and does not produce a greater risk of flooding. The 100 year flood discharge is 9,765 cfs. and reaches an elevation of 776.16. The 100-year flood stage for the proposed structure is, according to the HEC-RAS modeling, approximately 1.17’ below that of existing and therefore does not present any increase in flood risk compared to the existing condition. It should also be noted that neither the 100 nor 500 year flood overtop the structure. The proposed structure has a capital cost of approximately $3.8 million. The proposed structure also impacts wetlands in the project area. It has been determined that the project will reduce the current wetland area by approximately 0.04 acres. This includes the 0.42 acres that the roadway realignment will impact as well as the replacement of 0.38 acres that is to be constructed adjacent to the existing wetland area. However, there will be additional investigation performed 5 in order to reduce the impact to the wetlands at the project site. See field view notes Appendix H The proposed structure is the smallest opening, according to the study performed, recommended in order to maintain or improve upon the existing condition. Due to the fact that there is no “significant” encroachment as defined by 23 CFR 650 subpart A Sec.650.105 there was no risk analysis required for the project. 6.0 Alternative Proposal There was also a second proposal investigated. This alternative proposal consisted of a two-span spread box beam structure. This alternative was not chosen because of the obstruction in the channel caused by the pier. The existing structure has a pier and during high discharge floods there is a significant amount of debris buildup that severely diminishes the hydraulic performance of the structure. This problem was alleviated by removing the obstruction to the opening and using a single span structure.