Fitzgibbon Potable Roofwater Harvesting (PotaRoo) Scheme Final Report. Prepared for the Department of Environment (DoE) May 2014 Economic Development Queensland Level 7, 63 George Street Brisbane GPO Box 2202 Brisbane Queensland 4001 Australia Telephone +61 7 3452 7880 Website www.edq.qld.gov.au ABN 76 590 288 697 2 2 3 TABLE OF CONTENTS PROJECT CLEARANCE .................................................................................................................................................. 3 EXECUTIVE SUMMARY .................................................................................................................................................. 4 1. Introduction ................................................................................................................................................................ 5 2. The Project ................................................................................................................................................................ 5 2.1 Fitzgibbon Chase ................................................................................................................................................ 5 2.2 Project Overview ................................................................................................................................................. 6 2.3 Roofwater Collection System .............................................................................................................................. 8 2.4 Roofwater Treatment Plant ................................................................................................................................. 8 2.5 Distribution........................................................................................................................................................... 9 2.6 Intended end uses of product .............................................................................................................................. 9 2.7 Objectives and Goals .......................................................................................................................................... 9 3. Project Methodology ............................................................................................................................................... 10 4. Project Governance ................................................................................................................................................ 11 4.1 Steering Committee ........................................................................................................................................... 11 4.2 Project Manager ................................................................................................................................................ 11 4.3 Project activities and conduct ............................................................................................................................ 11 5. Project Activities ...................................................................................................................................................... 12 6. Project Outcomes .................................................................................................................................................... 13 6.1 Supply Quality and Quantity .............................................................................................................................. 13 6.2 Supply Cost ....................................................................................................................................................... 15 6.3 Economic Outcomes ......................................................................................................................................... 15 6.4 Environmental Outcomes .................................................................................................................................. 16 6.5 OHS Outcomes ................................................................................................................................................. 16 6.6 Community / Social Outcomes .......................................................................................................................... 16 7. Project Evaluation ................................................................................................................................................... 16 8. Experience sharing and lessons learnt ................................................................................................................... 17 9. Scheme Finance ..................................................................................................................................................... 17 10. Conclusions ............................................................................................................................................................. 17 PROJECT CLEARANCE Function Position Name Prepared by Senior Development Manager Director – Residential Development Meg Macaulay Approved by Signature Date Peter Smith 3 4 EXECUTIVE SUMMARY The Fitzgibbon Potable Roofwater Harvesting (PotaRoo) scheme has been developed to demonstrate the potential for harvested roofwater to be treated and used as a source of potable water supply at a local level. Conceived in 2009 and constructed and commissioned over a three year period, the PotaRoo scheme will harvest roofwater from approximately 500 houses in Fitzgibbon Chase and will, when fully operational, supply treated water into the water supply grid for general consumption. The PotaRoo scheme is yet to go into full operation, however, commissioning testing and ongoing analysis shows that it will meet the project objectives, i.e. to provide an alternative source of water to reduce potable demand and improve water supply security, and to not increase greenhouse gas emissions. The scheme was successfully completed adopting a comprehensive design and assessment process, including water balance modelling, risk assessment, business case development, baseline water quality monitoring, verification testing and liaison with water supply and regulatory authorities. The PotaRoo scheme will supply 44 ML/year of treated stormwater, 20 per cent of potable demand in Fitzgibbon Chase, at a cost of approximately $2.60 per/kL. The total cost of the PotaRoo scheme is estimated at $8,085,000 million dollars of which the Australian Government contributed $4,050,000 million dollars. Nomura Research Institute (NRI), in conjunction with JFE Corporation (JFE) provided $3,930,500 towards the scheme. Economic Development Queensland provided the balance of the budget at $104,500. The final report covers the entire project period and details the conduct, benefits and outcomes of the project as a whole. The PotaRoo scheme was developed in conjunction with the Fitzgibbon Stormwater Harvesting (FiSH) Scheme, which has been developed to supply treated stormwater to residents within Fitzgibbon Chase for non-potable uses, ie toilet flushing cold water laundry and gardens. Until the PotaRoo scheme is fully operational, treated water from that system will feed into the FiSH scheme. 4 5 1. Introduction This report has been prepared as the Final Report to the Australian Government Department of Environment (DoE) as required under the terms of the funding agreement for the Fitzgibbon Potable Roofwater Harvesting (PotaRoo) scheme in Fitzgibbon, Brisbane Queensland. The PotaRoo project received funding under the National Urban Water and Desalination Plan, Stormwater Harvesting and Reuse Projects program and Japanese Government Construction and commissioning of the PotaRoo scheme is complete, though it is yet to go into full service. This report provides an overview of the project, the methodology and processes adopted in developing the scheme, and the key outcomes from the project to date. 2. The Project The aim of the Fitzgibbon Potable Roofwater Harvesting (PotaRoo) project is to produce potable water from communally harvested roofwater. The scheme collects roofwater runoff from houses in the Fitzgibbon Chase residential development to a central water treatment plant (WTP). Once the process is proven and there is confidence to move forward, it is intended that the treated water will be introduced into the water supply grid as a new bulk water supply. 2.1 Fitzgibbon Chase Within the Fitzgibbon Chase two stormwater Harvesting and reuse schemes were developed. The PotaRoo scheme was developed as part of the Minister for Economic Development Queensland’s (formally the Urban Land Development Authority) Fitzgibbon Chase project. Fitzgibbon Chase is a residential subdivision located in the northern suburbs of Brisbane approximately 12km north of the CBD (refer to Locality Plan Figure 1). The development has a total area of approximately 114ha. Figure 2 shows the extent of the Fitzgibbon Chase development. Figure 1 Locality Plan 5 6 Figure 2 Fitzgibbon Chase Development 2.2 Project Overview The PotaRoo scheme consists of three main infrastructure sections: Collection system – captures roofwater from connected homes and transports it to one of four distributed storages; captured water is pumped from the storages to the roofwater storage tank at the Water Treatment Plans (WTP). Treatment plant – treats captured water to potable standard. Distribution system – pumps the treated water from the potable water tanks into the potable water distribution main. The PotaRoo scheme has been designed in accordance with the Australian Drinking Water Guidelines (NRMMC and NHMRC 2011) and Queensland State Legislative requirements. Water supply systems in Queensland are subject to regulation through the Office of the Water Supply Regulator (OWSR) under the provisions of the Water Supply Safety and Reliability (WSS&R) Act 2008 and related parts of the Public Health Act and Regulations. Under the WSS&R Act a Service Provider for a potable water supply scheme (i.e. supplying drinking water) is required to have in place an approved Drinking Water Quality Management Plan (DWQMP) for the scheme. The PotaRoo scheme is designed to operate alongside, but independently from, the Fitzgibbon Stormwater Harvesting (FiSH) Project, a non-potable water harvesting and reuse scheme developed by Economic Development Queensland (EDQ). The general layout of the PotaRoo is shown in Figure 4. It is also shown schematically in Figure 3 below. 6 7 Potable Water Supply Network Backwash Micro Filtration AutoStrainer Chlorine & Fluoride Ion Exchange Activated Carbon UV Rainwater Storage Tank 800 kL Raw Water Tank 4 kL Treated Water Tank 4 kL Potable Water Tank 100 kL Drain Sewer Overflow Excess to Stormwater Houses Roof water Collection System Distributed Underground Storage Tanks (4 Tanks, Total 900 kL) Figure 3 PotaRoo Schematic Diagram Figure 4 PotaRoo Layout 7 8 2.3 Roofwater Collection System The PotaRoo treats roofwater collected from the Fitzgibbon Chase development. The collection system consists of: House connections, Collection network, Distributed underground storage tanks (total volume 917 kL), Transfer pumps, Rising main, and a 800kL above ground roofwater storage tank. At each house connection the roofwater is diverted from the downpipes to the collection network. The house connection also includes an overflow device which allows roofwater to overflow into the stormwater system when the collection network is at capacity. Leaf boxes installed on the downpipe/gutter system reduce leaf matter entering the system. Approximately 8ha of roof area will be connected to the collection system when the development is complete. The collection network is a gravity pipe network that carries water from each of the house connections to the distributed underground storage tanks. There are 4 separate catchment areas that drain to the distributed underground storage tanks. The distributed underground storage tanks are Humes Rain Vaults® and range in size from 100kL to 330kL. Each tank contains a pump well, transfer pump, level sensors and overflow. The transfer pumps transfer roofwater from the distributed tanks to the roofwater storage tank, via the common rising main. The pumps are controlled by a pressure switch, level switch and timer functions. The 800kL roofwater storage tank is located adjacent to the treatment plant and an actuated valve on the inlet pipe ensures that water with high turbidity cannot be transferred into the tank. Figure 5 Collection System and Distributed Collection Tanks 2.4 Roofwater Treatment Plant The key treatment processes adopted for the PotaRoo treatment train are as follows (refer to Figure 3): Auto-strainer (removal of coarse particulates), NaOH dosing for pH correction, Membrane treatment (microfiltration for removal of pathogens and fine particulates), Activated carbon treatment (removal of organic contaminants), Ion exchange treatment (removal of heavy metal contaminants, particularly zinc), Ultraviolet disinfection (neutralisation of pathogens), Residual chlorination using sodium hypochlorite, and Fluoridation. 8 9 Figure 6 Raw Water Tank, Water Treatment Plant and Treated Water Tank Figure 7 Raw Water Tank and Water Treatment Plan 2.5 Distribution In the short-term, until the PotaRoo Scheme has satisfied all requirements that it can consistently produce water of potable quality, treated water will be used for non-potable purposes through the Fitzgibbon Stormwater Harvesting (FiSH) scheme. Once the treated water is approved as potable standard, it will be injected into the Queensland Urban Utilities (QUU) trunk water main on Telegraph Road, Fitzgibbon. 2.6 Intended end uses of product The objective for the PotaRoo Scheme is to produce water meeting all of the requirements for drinking water and suitable for injection into the water supply grid. Once this occurs, the water will be suitable, and used, for all normal water uses, including drinking, cooking and washing. In the short-term, the water will be used for non-potable water uses through the FiSH dual reticulation network, i.e., toilet flushing, cold water laundry, external household use (car washing and garden watering), and irrigation of public open space. 2.7 Objectives and Goals The over-riding objectives for stormwater harvesting schemes funded under the program are to contribute to: a. Improving the security of water supplies in Australia, without adding to greenhouse emissions, b. Reducing demand on potable water supplies, and c. Helping to reduce the impact of urban runoff on water quality in receiving waters. The specific objectives adopted for the PotaRoo were to: a. Use harvested roofwater to offset potable water demands of approximately 44 ML/yr. within the Fitzgibbon Chase Development Area. 9 10 3. Project Methodology The project was initiated in 2009 by the Japanese consultancy Nomura Research Institute (NRI), in conjunction with a large Japanese industrial company JFE Corporation (JFE), as an opportunity to demonstrate and prove Japanese technology overseas. NRI and JFE were pursuing Japanese government funding provided through its New Energy and Industrial Technology Organisation (NEDO) aimed at supporting Japanese companies to develop overseas markets for their products. Fitzgibbon Chase was identified as a suitable location and EDQ (formally Urban Land Development Authority [ULDA]) was a willing participant. EDQ supported the project as consistent with a broader objective to enhance the environmental sustainability of its developments. The mechanisms and processes implemented for the PotaRoo can best be illustrated with a brief history of the project development, highlighting the key milestones, decision points and activities: JFE signed a Memorandum of Understanding in November 2009 with the Queensland Government for investigation and development of a roofwater harvesting system and a trial stormwater reuse system at a new residential area within the Fitzgibbon Urban Development Area. Initial feasibility investigations and a preliminary design were completed by Bligh Tanner Pty Ltd in November and December 2009 respectively. A funding application was submitted under the National Urban Water and Desalination Plan Stormwater Harvesting and Reuse Projects Funding Scheme in February 2010 and funding was confirmed in September 2010. Design and installation of the roofwater collection system in Fitzgibbon Chase commenced with stage 6 in July 2011. Detailed design of the water treatment plant and associated systems was completed by JFE and Bligh Tanner in November 2009 with expressions of influence called in July 2010. Detailed design of the distributed storage tanks was completed by Bligh Tanner in December 2011 with tenders also called in December 2011. The contract was awarded to Pensar Civil Pty Ltd in February 2012. A detailed Water Quality Risk Management Plan (WQRMP) was developed in conjunction with all key stakeholders (ULDA, QUU, Queensland Health and the Office of the Water Supply Regulator) to inform the design process and ensure that all risks had been identified and addressed; this was completed in November 2011. A Business Case was also developed in November 2011 to consider the cost of operating the system and the likely cost of water from the system. In November 2010, a contract was awarded to Pensar Building Pty Ltd, in conjunction with Amiad Filtration Systems Ltd for water treatment works, to build the PotaRoo treatment plant. Construction of the civil works reached Practical Completion in September 2011. Construction and initial commissioning of the water treatment plant was completed in 2013. In September 2012, JFE undertook the first round of ‘Challenge Tests’ to confirm the plant capacity to remove pathogens (bacteria, viruses and protozoa); a second round of ‘Challenge Tests’ assessing the removal of organic chemical pesticides and metals was completed in October 2012. Between November 2012 and November 2013, JFE temporarily mothballed the water treatment plant to provide time for the connection of adequate roof area to ensure that water would be available to allow verification testing to proceed. In March 2013 development responsibility for Fitzgibbon Chase transferred to Economic Development Queensland (EDQ), part of the Department of State Development, Infrastructure and Planning (DSDIP). Since the early stages of the design, EDQ and Bligh Tanner have maintained continual liaison and coordination with the local water utility QUU with respect to the impact of the system on its services and the potential for QUU to be the ultimate owner and operator of the scheme. Between November 2013 and January 2014, JFE undertook extensive verification testing to obtain baseline data on the untreated roofwater in the system and to demonstrate that the plant could reliably produce potable water. In April 2014, a draft Drinking Water Quality Management Plan (DWQMP), following the Queensland State guidelines for preparation of a DWQMP, was completed. This was prepared to ensure that the risk and requirements for on-going plant operation were well understood and documented and to support the future scheme operator. The plant is now fully commissioned and ready to go into service, subject to identifying a suitable operator. 10 11 4. Project Governance To effectively manage the design and delivery of the PotaRoo scheme the following governance arrangements were made. These are standard for large projects delivered by the Economic Development Queensland. 4.1 Steering Committee A steering committee has been created including members at director and management level. The role of the steering committee was to: Provide advice and guidance to Economic Development Queensland’s contractual commitments to its key funders Monitor relationships with key stakeholders Review and approve whole-of-project budget and cash flow Review and approve the whole-of-project schedule and achievement of milestones Review and authorise project risks and the project risk assessment. Steering committee members included the following people periodically over the life of the scheme: Mr Peter Smith – EDQ Ms Meg Macaulay – EDQ Mr Peter Kelly - EDQ Mr Chris Tanner – Bligh Tanner Mr Damien Stiler – Bligh Tanner Mr Yasuto Ando – JFE Engineering Mr Atsunori Sato – JFE Engineering Mr Inakoshi Osamu – JFE Engineering Director – Residential Development Senior Development Manager Project Manager Civil Engineer Civil Engineer Commercial Manager Commercial Manager Commercial Manager 4.2 Project Manager The project manager is accountable for the successful delivery of the scheme to meet the time, quality and cost parameters agreed with key stakeholders including the Department of the Environment. The role encompasses: Provide management of the scheme Prepare Milestone and Status Reports prior to submission to the steering committee Day-to-day management of budgetary expenditure and schedule Day-to-day management of designers and contractors Manage project risks and project risk assessment Undertake tender process for design activities and construction works Co-ordinate internal stakeholder engagement Co-ordinate the works with other activities occurring within the development site Provide representation to external stakeholders and co-ordination with those stakeholders to achieve required project outcomes. 4.3 Project activities and conduct The design and construction project management was conducted in-house by the residential development division of EDQ. The design for each project was developed through the lead consultant (Bligh Tanner) to tender documentation. The tender process conformed to Queensland Government standards for public tenders. The successful tenders where engaged directly to EDQ with supervision of the contracts through external consultants (Blight Tanner, ETS Engineering and Brown Consulting Group). External expertise was engaged as necessary to ensure the design intent and building standards were complied with. 11 12 5. Project Activities Activities Completed to Date MILESTONE DESCRIPTIONS Fund Agreement executed . INITIAL PROJECT PLANNING MILESTONE COMPLETION DATE 12 May 2011 July 2011 Complete project planning, and amend projections as required. AREA E: STAGE 6 Complete Collection System design and commence construction. A.1.2. WATER TREATMENT PLANT Commence Water Treatment Plant work design, tendering and award of contract. Complete Water Treatment Plant civil and building works. DESIGN VALIDATION Commence design validation. AREA E: STAGES 7 AND 8 November 2011 Complete collection system design for Stages 7 and 8. Commence construction to Stage 7. WATER TREATMENT PLANT Complete Water Treatment Plant. Undertake testing and commission Water Treatment Plant. DESIGN VALIDATION Continue design validation. AREA C Commence Collection System design. May 2012 AREA E: STAGES 7 AND 8 Complete construction to Stage 7. Commence construction to Stage 8. 12 13 AREA C: Complete collection system design. AREA C Commence construction. November 2012 March 2013 AREA E: STAGE 8 Complete construction. Complete Collection System construction. Complete commissioning of Collection System (for Area C). AREA C: March 2014 AREA E: STAGE 6 Complete construction. Complete commissioning of Collection Systems for Stages 6, 7 and 8. WATER TREATMENT PLANT Commissioning of Water Treatment Plant. DESIGN VALIDATION Complete design validation. Activities to be completed MILESTONE DESCRIPTIONS Final Drinking Water Quality Management Plan (DWQMP) Tenders called for operation and maintenance of the PotaRoo ESTIMATED MILESTONE COMPLETION DATE June 2014 June 2014 Confirmation of plant operator and handover September 2014 PotaRoo goes into operation supplying water into the FiSH December 2014 PotaRoo commences supply of drinking water into the water supply grid December 2016 6. Project Outcomes 6.1 Supply Quality and Quantity As noted above, the PotaRoo is yet to supply water into the water supply grid. However, during commissioning testing, it successfully demonstrated that water can be harvested and delivered at a water quality meeting all of the requirements for potable use. A review of system yield completed in 2013 has confirmed that the system performance will be as follows: Total treated roofwater supplied into water supply grid – 44 ML/yr. (average) 13 14 During initial start-up and commissioning it has been demonstrated that the water is successfully collected into the distributed storages and transferred to the main rainwater storage tank. The verification testing program completed in 2014 has demonstrated that the water treatment plant is effective at treating to the specified quality and at the required rate of 200kL/day. Over the 3 month verification testing period, the plant treated 2.0 ML of water and consistently met the design water quality requirements. The verification testing was supported by the challenge testing undertaken in 2012 demonstrating that the plant as installed can achieve the contaminant log reductions required under Australian guidelines. Challenge Test 1 assessed the ability of the treatment train to remove bacteria, viruses and protozoa. High concentrations of laboratory generated test contaminants were inoculated into the process and water test taken upstream, downstream and within the plant to test individual unit process removal. The challenge testing demonstrated that the plant achieves log reductions in excess of guideline performance values and meets minimum treatment requirements. Challenge Test 2 assessed the removal of organic pesticides and metals. The WTP successfully removed all inorganics (metals) below ADWG guideline levels and successfully removed all test organics, with the exception of Glyphosate. Further testing of Glyphosate was recommended to check the influence on the results of the very high feed concentrations. The verification testing program was undertaken by JFE over a 3 month period, with sampling occurring in 3 sets of 3 days at 1 month intervals. JFE adopted a comprehensive test regime; sampling upstream, downstream and through the treatment train to assess feed water quality, treated water quality and individual unit process performance over a comprehensive range of test parameters. The treated water quality test results are summarised below. The system is now fully commissioned and ready to be placed into service. Table 1 Water Treatment Plant Verification Test Results Test Parameters Microbiological Coliforms Faecal Coliforms Escherichia Coli Enterococci Parasites (Giardia & Cryptosporidium) Viruses (Adenovirus & Rotavirus) Others (Salmonella, Legionella, Aeromonas, Clositridium perfringens, f-RNA coliphage, Somatic coliphage, Shigella, Campylobacter Physical Units CFU/100 mL CFU/100 mL CFU/100 mL CFU/100 mL cysts/10L oocysts/10L - No. of Samples 9 9 9 9 Guideline Value Results Mean 95%ile <13 62 <1 <1 <1 Not detected 3 <1.0 2 Not detected 3 Not detected Colour (true) PCU 9 Hardness (as CaCO3) mg/L 9 Total Dissolved Solids @180°C mg/L 9 Aluminium (acid soluble) mg/L 9 Copper Lead Zinc Iron mg/L mg/L mg/L mg/L 9 9 9 9 15 HU (Aesthetic) 200 (Aesthetic) 600 (Aesthetic) 6 9 96 196 303 472 <0.012 0.026 Metals 0.2 (Aesthetic) 2 0.01 3 (Aesthetic) 0.3 <0.001 0.001 <0.001 <0.006 0.011 <0.05 14 15 Units No. of Samples Guideline Value mg/L 3 varies Ammonia mg/L 9 Nitrate Nitrite Inorganics mg/L mg/L 9 9 Chloride mg/L 9 Fluoride mg/L 9 Sulfide mg/L 9 Reactive Silica mg/L 9 Sodium mg/L 9 Sulfate mg/L 9 250 (Aesthetic) 1.5 0.05 (Aesthetic) 80 (Aesthetic) 180 (Aesthetic) 500 Others mg/L 3 varies Test Parameters Others Results Mean 95%ile Significantly below guideline value Nutrients 0.5 (Aesthetic) 50 3 0.03 0.05 0.28 0.36 <0.01 92 153 <0.1 0.1 <0.01 6.08 10.42 71 99 44 78 Significantly below guideline value Organics Organics Hydrocarbons Hydrocarbons Disinfection By-products Chlorate Formaldehyde N-Nitrosodimethylamine (NDMA) Trihalomethanes (thMs) (total) mg/L mg/L mg/L mg/L 3 3 3 1 Others Algal Toxins Microcystin LR Pesticides Pesticides varies Significantly below guideline value varies not detected 0.5 0.0001 0.25 varies mg/L <0.005 <0.1 <0.000003 <0.016 <0.029 Significantly below guideline value 2 1.3 <0.0003 9 (total) Inc. 3 (full suite) varies not detected 6.2 Supply Cost A review of the system yield and operating costs completed in 2014 based on analyses completed and agreed for the PotaRoo scheme has confirmed that the system performance will be as follows: Operating cost of water - $2.60per/kL. Operating costs include labour, electricity, consumables, on-going verification testing, event management / monitoring and source management. 6.3 Economic Outcomes The economic benefits from this and similar schemes arise from the reduction in potable water required and the demonstrated potential for decentralised schemes to reduce the need for major new water supply capacity. The direct benefit to the potable water supply system is 44 ML/year of water, valued at $155,000 that will not need to be supplied. A water supply equivalent to 20per cent of the Fitzgibbon Chase water demand illustrates the potential for 15 16 decentralised water harvesting schemes (or Local Alternative Water Supplies) to make a significant contribution to regional water supply capacity and significantly reduce and defer requirements for future major water supply augmentation. This is significant because future increases in regional water supply capacity are likely to be from costly seawater desalination, as there are only limited opportunities remaining for new surface water storages. 6.4 Environmental Outcomes The primary environmental outcome from roofwater harvesting is the indirect benefit to the stormwater drainage system of removing a proportion of total runoff, with its associated contaminants, from the drainage system, thereby reducing the sediment and nutrient export load and the need for water quality improvement devices. Based on an evaluation by Bligh Tanner in 2012, the combined benefits of the FiSH and PotaRoo schemes, when compared with pollutant reduction targets required under the State Planning Policy 4/10 Healthy Waters, was in excess of 50% of the Suspended Solids removal required and 75% and 90% of the Phosphorus and Nitrogen removal targets respectively. An assessment of energy consumption by the PotaRoo Scheme suggests that it will use perhaps 15 per cent more energy per ML of water supplied than the South East Queensland regional water supply system (2,500 cf 2,200 1 MJ/ML) based on the current sources of supply. Future new sources are expected to have significantly higher energy requirements due to treatment technologies (eg RO) and the distance water has to be pumped to urban centres. The PotaRoo Scheme will be powered by green energy from the grid to further limit its contribution to greenhouse emissions. 6.5 OHS Outcomes Raw water testing has shown that the untreated roofwater is relatively free form contamination. The verification testing program has confirmed that the plant can produce water meeting all potable water quality requirements. With the safeguards and water treatment systems provided, the PotaRoo scheme will meet the minimum requirements for human consumption, ensuring that the community users of the water, and the system operators, are protected from the risk of waterborne disease or other adverse health effects. 6.6 Community / Social Outcomes By making available and maintaining their roof drainage systems, householders are contributing to the realisation of the greater community benefit of roofwater harvesting for water supply. As the treated water will be injected into the drinking water supply, consumers, whether in Fitzgibbon Chase or outside, will not be aware that they are using treated roofwater and will not be affected by it. 7. Project Evaluation While the scheme is yet to supply water to consumers there is confidence that, based on the system that has been developed, and the analyses undertaken, the schemes objectives will be met: 1. The PotaRoo scheme will produce an alternative supply of water for potable uses that will offset 44ML/year of potable water demand; this represents approximately 20 per cent of total water demand in Fitzgibbon Chase. 2. By providing that offset, the PotaRoo scheme demonstrates that local alternative water supplies have the potential to improve the security of regional water supplies in Australia and to reduce and defer the need for major new source augmentations. 3. As a local system, the PotaRoo is a relatively low energy user compared with alternative sources requiring pumping over long distances; in addition, power for the scheme will be sourced from green power ensuring that the overall impact on greenhouse emissions is minimised. 4. By removing 44ML/yr of stormwater runoff, the PotaRoo will significantly reduce pollutant loads from the catchment and improve the quality of stormwater entering local waterways. Fitzgibbon Chase is a developing residential estate and is subject to market forces. This may necessitate a slow down or acceleration of construction. Stages may also be changed or swapped to maintain margins. This may affect the overall program however at this time completion of the estate is on program. 1 Energy use in the provision and consumption of urban water in Australia: an update, Prepared by CSIRO for the Water Services Association of Australia, May 2012. 16 17 8. Experience sharing and lessons learnt The following key learnings have been noted for future projects: There are restrictive and expensive requirements for scheme validation, ongoing verification and auditing presents financial risk to the development of new schemes; There are no clear models for governance of alternative waters sources, including ownership and operation, and how they are integrated into the municipal water system generally; this is perhaps the greatest current challenge to their widespread implementation; Fitzgibbon Chase is a developing residential estate and is subject to market forces. This may necessitate a slow down or acceleration of construction. Stages may also be changed or swapped to maintain margins. This may affect the overall scheme program and agreed funding milestones; An independent assessment of the proposed design of the scheme can be valuable in cross checking suitable design, scheme budgets and viability; and Consistent project management and design/supervision roles is invaluable to ensuring the delivery of the original objectives. Benefit of undertaking complementary projects concurrently (FiSH and PotaRoo Schemes) assist with knowledge sharing and positive project outcomes. 9. Scheme Finance The original scheme budget was set at $8,100,000. The current budget is set at $8,084,842. This is approximately $15,158 less than the cost estimate used for the funding submission. The small budget saving can be primarily attributed to design revisions as the scheme moved from concept to detailed design. The Australian Government provided $4,050,000 towards the PotaRoo scheme. Nomura Research Institute (NRI), in conjunction with JFE Corporation (JFE) provided $3,930,464 towards the scheme. Economic Development Queensland provided the balance of the budget at $104,378. A detailed cost summary is provided in the Financial Report. 10. Conclusions Development of the PotaRoo scheme has confirmed that roofwater harvesting for potable supply is technically feasible, cost effective and could form an important part of the regional water supply strategy, though challenges remain to confirm its acceptance as a viable source by the water community and to determine the best business model for delivery: The technology required is readily available and well understood. Adequate guidelines exist to assist with design, though there is a lack of consistency across jurisdictions and water sources. Restrictive and expensive requirements for scheme validation, ongoing verification and auditing present a financial risk to the development of new schemes. There are no clear models for governance of alternative waters sources, including ownership and operation, and how they are integrated into the municipal water system generally; this is perhaps the greatest current challenge to their widespread implementation. The community has benefitted twice-fold from this project – the use of treated rain water from rooves is reused into the water supply and the excess water is then fed into Carseldine Drain where it is harvested as stormwater, treated and used for non potable water supply within the Fitzgibbon Chase Development. 17 18 18