GAPEX PROJECT Instructor: Artak Hambarian Students: Anahit Sargsyan Iren Barseghyan Yelena Vardanyan Yerevan, 2006 1 Table of contents 1. Abstract ……………………………………………………………… 2. Introduction …………………………………………………………………… 3. Project goal definition ………………………………………………….. 4. Description of shops 4.1 Glass Shop ……………………………………………………………………. 4.2 Glass Packages Shop ………………………………………………………… 4.3 Multilayer Glass Shop ………………………………………………………. 4.4 Glass & Mirror Processing Shop …………………………………………… 4.5 Laminate Furniture Shop ……………………………………………………… 4.6 Glass Furniture Shop ………………………………………………………….. 4.7 Mechanical Shop ……………………………………………………………… 4.8 Metal Coating Shop …………………………………………………………… 4.9 Stained Glass Shop …………………………………………………………… 4.10 Window & Doors Shop ……………………………………………………… 5. Problems definition / Suggestions 5.1 Human management 5.2 Capacity usage 5.3 Process Layout 5.4 Product manufacturing layout 5.5 Forecasting (seasonal adjustment) 5.5.1 Forecast Control 6. Issues 6.1 Safety 6.2 Environment 7. Conclusion 7. References 2 Abstract Introduction 3 Gapex Ltd. was founded as a manufacturer’s representative company and also Armenia's Commodity Exchange member /broker in 1992 by Robert O. Gabrielyan. In 1993 Gapex began its activity as trade-intermediary company, imported mainly foodstuff to Armenia. In 1996 began to import sheet (architectural) glass. In the same year in Djrvezh a new industrial Region of Yerevan a 1000m2 industrial complex has been built, which has been expended, reconstructed and equipped with modern machinery within two years. From 1998 company started to produce and install double glass doors and windows with the aluminum profiles, glazed facades. In 2002 Gapex Industrial complex was extended up to 2200 m2 and a dye facility has been put into operation. The company’s main activity is glass selling. 90% of provided glass is sold and remaining 10% go to different departments in order to be processed or to be final product.90% of processed glass also could be sold after processing and remaining 10% go to other departments as raw material. Glass of different types mainly imported from Iran & China is the main sale & raw material for Company. They buy the glass as much as they can obtain and this approach is justified by the following: 1. The quantity of glass is decreased in East Region which causes increase in prices and difficulty in getting glass. 2. They have no problem with realization. Besides, Metal tubes of different length & wide, laminate sheets with different colors, aluminum profiles, silica gel & distance frames, and ‘tiacol’ are raw materials for mechanical shop, laminate furniture shop, door & window shop, glass package shop, multilayer glass shop respectively. Gapex offers different kinds of services such as Installation of glass, mirrors, facades, windows and doors Glass processing (grinding, edging, polishing, drilling) Design of facades, windows and doors Design with stained glass Projecting and installing of roof coverings and awnings Coating of metal constructions 4 The company is primarily managed by director, associated director, accounting department and engineering department. The company has make- to- order strategy….. All activities started from engineering department. Customers meet with engineers and explain what they need (preferred product, the size of product, the shape of product and so on).After this meeting engineers draw the order, particularly list the necessary raw material which should be used in order to get ordered product and these two papers touched together send to corresponding departments. But this is not the end of engineers’ task. Their performance is necessary in departments (mostly workers need explanation of drawings), during placement of order, they should get some details from the store and so on. The company has not any training program as well as competition causing motivation programs such as rewards, promotion, and empowerment. As already is mentioned above they expanded the area from 1000sqr.m up to 2200 sqr.m. However the number of departments also rises and some of them are located in second floor. This phenomenon causes many difficulties: Increase manufacturing cycle time – due to a need to carry fragile glass with a special care to the second floor. Although a special elevator is used along with a crane, they are not very convenient and do not provide access to most of the spaces. Worse use of human resources – this is due to poor facilities layout, and is similar to the previous point. Difficult to control – this is due to poor information flow and poor feedback. Inconvenient material flow – again due to facilities layout. Besides, the arrangement of machines in the shops is not well organized (they did not reflect on importance of processes sequence) which also causes similar difficulties. It is a fact that in coherence with the overall economic growth in Armenia, this company also experiences growth of 20% annual during the last decade of its markets and thus needs an investigation for possibilities of capacity increase. Thus, the goal of this work is to explore the potential for increase of the capacity of the company through detailed investigation of all parts of its operation and recommend the ways to achieve the capacity increase. So the main logic of our work is the following: 5 1. Having appropriate data and one-month study in Gapex give analyses of all departments, calculate maximum capacity and actual throughput, find bottlenecks if they exist. 2. Having a data of three years of activities, forecast the amount of glass which is necessary for coming year (for each season) in order to satisfy customers’ demands and keep high service level. 3. Arrange all departments (Process layout) taking into consideration how important are the nearness of any two departments. 4. Arrange machines of glass and mirror department (as an example) according to sequence of processes which should be done in order to get final product. Glass Shop 1. Description of the shop Glass shop (storage) is located on the 1st floor and has area of 300 m2. In this shop work 6 employees. The main activities of the shop are the following: Glass/ Mirror cutting – the largest sizes of glass/mirror in this workshop is 2x3m, the smallest usual size is 0.5x0.5 m, the average size is 1.5x1.5mm which means there is a need to make at least 3 linear cuts from 2x3 in origin. Glass/Mirror transportation by crane - glass/mirror is transported within the shop for car loading and unloading; 6 Glass/Mirror transportation – glass/mirror is transported to the shops related to glass/mirror processing for the next technological step; Machine loading – car loading by glass; Machine unloading - car unloading from glass; Figure 1.1 below depicts the timing of each process: min Processes Timing 15 10 5 0 Placement by crane to table Placement, table Cutting Storage Facilities of the shop include: 3 transferable tables on which glass is cut into pieces; 1 crane by which glass is transferred within shop; 4 glass-cutting tools (glaziers). 2. Capacity The throughput for glass shop is 0.33 m2 of possible 1.8 m2. Figure 1.2 below shows the capacity of each process: 7 sqr m / min Proce sse s Capacitie s 4.0 3.0 2.0 1.0 0.0 Placement by crane to table Placement, table Cutting Storage One can see: 1. Potential bottleneck first can occur for cutting process then for sheet placement by crane to tables. 2. According to throughput, capacity is used only by 18.5%. 3. Potential for the bottleneck solution- 3. Waste The waste of glass there is from the cutting process which is 5% of cut glass and is reworked by 50%. 4Yield In 2006 average glass entrance in glass shop is 39324 m2 per month where 90% or 35391 m2 is sold in batch and 10% or 3932 m2 after cutting is distributed among glass related shops. Total yield for this shop is 39225 m2 where yield from selling is 35,391 m2, which is 100% and yield from cutting and distribution among shops is 3932 m2 which is 98%. Glass Packages Shop 1. Description of the shop Glass packages shop is located on the 1st floor and has area of 50 m2. In this shop work 3 employees. For this shop the final product is glass package. The main activities of the shop are the following: 8 Glass washing & drying – entranced glass pass washing and drying processes in washing & drying machine; Distance frame cutting –the largest size of distance frame is 2.5m, the smallest usual size is 0.5m, the average size is 1.5m which means there is a need to make at least 2 linear cuts; Distance frame filling – distance frame is filled by silica gel; Glass package covering – glass package is covered by tiakol; Figure 2.1 below depicts the timing of each process: min Processes Timing 15 10 5 0 Placement, Washing & Placement, washer drying table Distance frame cutting Filling by Placement, Cover with silica gel second tiakol sheet Storage Facilities of the shop include: Washing & drying machine; 2 special tables for glass placement and glass package covering with tiakol. 3. Capacity The throughput for glass packages shop is 0.10 m2 of possible 1.2 m2. Figure 2.2 below shows the capacity of each process: 9 Processes Capacities sqr m / min 7.0 6.0 6.0 5.0 4.0 4.0 3.0 3.0 2.4 3.0 2.0 1.0 2.4 1.2 0.10 0.0 Placement, washer Washing & drying Placement, table Distance frame cutting Filling by silica gel Placement, second sheet Cover with tiakol Storage One can see: 1. Potential bottleneck can occur first for distance frame cutting then the next for filling by silica gel or covering with tiakol. 2. According to throughput, capacity is used only by 8.5%. 3. Potential for the bottleneck solution- 3. Waste The waste is 3% of entered glass which is reworked by 75%. Waste can be on each step of glass package making such as during glass placement on tables or washing machine, placement of the second sheet of glass, transportation to the storage. 4. Yield For glass packages shop the average entrance per month of glass is 1180 m2. Yield for this shop is 1171 m2 of glass packages per month which is 99% of entranced glass. Multilayer Glass Shop 1. Description of the shop 10 Multilayer Glass Shop is located on the 2nd floor and has area of 25 m2. In this shop work 2 employees. For this shop the final product is multilayer glass: duplex and triplex. The main activities of the shop are the following: Glass washing & drying – entranced glass pass washing and drying in washing & drying machine, the largest size of glass sheet is 2x3m, the smallest size of sheet is 0.5x0.5m. Covering by sticking tape – placed on the table, glass is covered by sticking tape for the next technological step; Fixing by UV machine – duplex and triplex pass fixing in UV fixing machine. Figure 3.1.1 below depicts the timing of each process for duplex: min Processes Timing 50 40 30 20 10 0 Placement Washing & Drying Placement Covering by sticking tape Placement of Transportation Fixing by UV the second machine sheet Storage Figure 3.1.2 below depicts the timing of each process for triplex: Storage Fixing by UV machine Transport ation Placement of the third sheet Covering by sticking tape Placement of the second sheet Covering by sticking tape Placement Washing & Drying 60 40 20 0 Placement min Processes Timing Facilities of the shop include: 1 Washing & drying machine; 1 UV fixing machine; 2 tables for glass placement. 11 2. Capacity The throughput in multilayer shop for duplex is 0.018 m2 /min of possible 0.15 m2/min and for triplex is 0.033 m2/min of possible 0.15 m2/min. Figure 3.2.1 below shows the capacity of each process for duplex. sqr m / min Processes Capacities 6.0 7.0 6.5 6.0 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 6.0 3.0 1.2 0.80 2.4 0.2 0.018 Placement Washing & Drying Placement Covering by sticking tape Placement of Transportation Fixing by UV the second machine sheet Storage Figure 3.2.2 below shows the capacity of each process for triplex. sqr m / min Processes Capacities 12.0 15.0 10.0 5.0 0.0 6.0 Placement 6.0 3.0 Washing & Drying 6.0 1.2 0.80 0.2 0.033 Covering by Placement of Covering by Placement of Transportation Fixing by UV sticking tape the second sticking tape the third sheet machine sheet 0.8 Placement One can see: 1. Potential bottleneck for duplex first can occur for fixing by UV machine than for covering by sticking tape; Potential bottleneck for triplex first can occur for fixing by UV machine than for first and second covering by sticking tape; 2. According to throughput, capacities of duplex and triplex production are used by 12% and 22% respectively. 3. Potential for the bottleneck solution- 3. Waste Total waste for duplex and triplex is 3% of entranced glass. Waste can be during all operations needed for duplex and triplex making. 12 2.4 Storage 4. Yield For multilayer glass shop the average entrance per month of glass is 590 m2, where 206 m2 for duplex production, 383 m2 for triplex production. Yield for this shop is 585 m2, where 205 m2 from duplex production, 381 m2 from triplex production which is 99% for both duplex and triplex production. Glass & Mirror Processing Shop 1. Description of the shop Glass & mirror processing shop is located on the 1st floor and has area of 150 m2. In this shop work 5 employees. For this shop the final products are processed glass and mirror. The main activities for the shop are the following: Glass/mirror edge processing and polishing – edge of glass/mirror is processed according to technological necessity in straight, curve or round glass processing and polishing machines; Glass/mirror edge polishing - edge of glass/mirror is processed according to technological necessity in polishing machine; Glass/mirror hole making - glass/mirror is processed according to technological necessity in hole making machine; Glass/mirror processing - glass/mirror is processed in processing machine; Glass/mirror finger-print making - glass/mirror is processed according to technological necessity in finger-print making machine; Figure 4.1.1 below depicts the timing of each process for straight processing. 13 min Processes Timing 30 20 100 Placement 1st edge Glass turning 2nd edge Glass turning 3rd edge Glass turning 4th edge processing & over processing & over processing & over processing & polishing polishing polishing polishing Storage Figure 4.1.2 below depicts the timing of each process for curve processing. min Processes Timing 50 40 30 20 10 0 Placement Edge processing & polishing Storage Figure 4.1.3 below depicts the timing of each process for round processing. Storage Hole making Placement Edge polishing Edge processing 30 20 10 0 Placement min Proce s s e s Timing Facilities of the shop include: 4 Straight glass straight processing & polishing machines; 2 Curve glass processing & polishing machines; 1 Round glass processing & polishing machine; 1 Thick glass processing machine; 1 Glass polishing machine; 1 Glass hole making machine ; 1 finger-print making machine. 14 2. Capacity The throughput in glass and mirror shop for straight processed glass is 0.2 m2/min of possible 1.2 m2/min, for curve processed glass is 0.09 m2/min of possible 0.3 m2/min and for round processed glass is 0.09 m2/min of possible 0.3 m2/min. As polishing process depends on the particular order so it is used only by 50% in straight, curve and round processing and for calculations there is taken coefficient for polishing equal to 0.5. Figure 4.2.1 below shows the capacity of each process for straight processing. sqr m / min Processes Capacities 12.0 7.0 4.8 2.0 -3.0 4.8 1.2 Placement 4.8 4.8 1.2 0.2 1st edge processing & polishing Glass turning over 2nd edge processing & polishing 1.2 Glass turning over 3rd edge processing & polishing 4.8 1.2 Glass turning over 4th edge processing & polishing Storage Figure 4.2.2 below shows the capacity of each process for curve processing. sqr m / min Processes Capacities 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 6.0 2.4 0.3 0.09 Placement 0.09 Edge p rocessing & p olishing 0.09 Storage Figure 4.2.3 below shows the capacity of each process for round processing. 15 Placement 0.3 0.09 Edge polishing 0.4 0.6 1.2 Storage 3.0 Hole making 3.0 Placement 4.0 3.0 2.0 1.0 0.0 Edge processing sqr m / min Proce s s e s Capacitie s One can see: 1. Potential bottleneck for straight processing can occur for edge 1st, 2nd, 3rd and 4th edge processing and polishing of processed glass/mirror. Potential bottleneck for curve processing can occur for edge processing and polishing process. Potential bottleneck for round processing first can occur for edge polishing processes than for edge processing and hole making processes. 2. According to throughput capacities for straight, curve and round processed glass/mirror are used by 14%, 32%, and 28.5% respectively. 3. Potential for the bottleneck solution. 3. Waste Total waste from straight, curve and round processed glass is 3% of entranced glass. Waste can be during all operations needed for straight, curve and round processing. 4. Yield For glass and mirror processing shop the average entrance per month of glass is 3932 m2, where1966 m2 for straight processing, 983 m2 for curve processing, 983 m2 for round processing. Yield for this shop is 3909 m2, where 1954 m2 from straight processing, 977 m2 from curve processing, 977 m2 from round processing, which is 99%, 99%, 99% for straight, curve, round processing respectively. From total yield of the shop 90% or 3518 m2 of processed glass is sold and 10% or 391 m2 is for glass furniture shop. 16 Laminate Furniture Shop 1. Description of the shop Laminate furniture shop is located on the 1st floor and has area of 50 m2. In this shop work 4 employees. The final product is varies laminate furniture of different sizes. The main activities of this shop are the following: Laminate sheet/ ready furniture transportation by crane - laminate sheet/ ready furniture is transported from the 1st to the 2nd floor or vice versa. Laminate cutting - the largest size of laminate sheet is 3x4m, the smallest usual size is 0.5x0.5m, the average size is 1.5x1.5m, which means there is a need to make at least 3 linear cuts. Laminate drilling – in laminate parts are made necessary works by drilling machine; Assembly of laminate furniture – laminate, glass & metallic parts are assembled; Assembly with handles & knobs – laminate furniture assembly with handles & knobs. Figure 5.1 below depicts the timing of each process: min Processes Timing 40 30 20 10 0 Placement Placement Placement, Laminate to the by the table cutting lifting lifting crane crane Laminate Glass parts drilling arrival Metallic parts arrival Assembly, Assembly laminate, with glass & handles & metallic knobs Facilities of the shop include: 3 laminate cutting machines; 1 drilling machine; 1 lifting crane by which laminate sheet for processing or ready furniture are transported from the 1st to the 2nd floor or vice versa. 2 tables for laminate cutting. 3. Capacity 17 Storage The throughput for laminate furniture is 0.02 m2/min of possible 0.2 m2/min. Figure 5.2 below shows the capacity of each process: sqr m / min Processes Capacities 4.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 4.0 2.4 1.2 1.2 1.2 0.6 0.6 0.2 0.3 0.02 Placement Placement Placement, Laminate to the by the table cutting lifting lifting crane crane Laminate drilling Glass parts arrival M etallic parts arrival Assembly, Assembly laminate, with glass & handles & metallic knobs parts One can see: 1. Potential bottleneck first can occur for laminate, glass & metallic parts assembly then for assembly with handles and knobs, laminate drilling. 2. According to throughput capacities for laminate furniture shop are used by 10%. 3. Potential for the bottleneck solution- 3. Waste Total waste of laminate furniture production is 3% of entranced laminate. Waste can be during placement, laminate cutting, transportation and assembly. 4. Yield For laminate furniture shop the average entrance per month of laminate is 240 m2. Yield for laminate furniture shop is 234 m2, which is 98% of laminate entrance. Glass Furniture Shop 1. Description of the shop Glass furniture shop is located on the 2nd floor and has area of 25 m2. In this shop work 2 employees. The final product of the shop is varies glass furniture of different sizes. The main activities of this shop are the following: 18 Storage Assembly of glass & metallic parts – arrived glass and metallic parts assembling ; Fixing by UV lamp – parts of assembled furniture pass fixing by UV lampe; Figure 6.1 below depicts the timing of each process: Proce s s e s Timing min 40 30 20 10 0 Glass parts arrival Metalic parts arrival Assembly of glass & metallic Gluing by UV lamp Storage Facilities of the shop are 2 UV fixing lamps. 2. Capacity The throughput for glass furniture is 0.03 m2/min of possible 0.2 m2/min. Figure 6.2 below shows the capacity of each process: sqr m / min Proce s s e s Capacitie s 1.5 1.0 0.5 0.0 1.2 0.6 1.2 0.2 0.6 0.03 Glass parts Metalic parts Assembly of arrival arrival glass & metallic parts Gluing by UV lamp Storage One can see: 1. Potential bottleneck first can occur for assembly of glass and metallic parts then for glass parts arrival, gluing by UV fixing lamp. 2. According to throughput capacities for glass furniture production are used by 17%. 3. Potential for the bottleneck solution- 3. Waste Total waste of glass furniture production is 1% of entranced glass parts. Waste can be during glass parts arrival, assembly and storage. 19 4. Yield For glass furniture shop the average entrance per month of glass is 391 m2 Yield for glass furniture shop is 388 m2, which is 99% of glass entrance. Mechanical Shop 1. Description of the shop Mechanical shop is located on the 1st floor and has area of 200 m2. In this shop work 12 employees. The final products of the shop are varies metal details. The main activities for this shop are the following: Metal cutting - the largest sizes of metal in this workshop is 4m, the smallest usual size is 0.1x0.1 m, the average size is 0.75m. As each cut in this shop is a separate project so in each case there are different size of cuttings; Lathe works – metallic detail is processed in lathe machine depending on necessity; Drilling works - metallic detail is processed in drilling machine depending on necessity; Polishing works - metallic detail is processed in polishing machine depending on necessity. Figure 7.1 below depicts the timing of each process: Facilities of the shop include: 4 Metal cutting machines; Lathe machine; 1 Metal drilling machine; 1 Metal polishing machine. 2. Capacity There are produced per month in average 198 m of metallic parts. The throughput of metallic parts is 0.02 m2 /min of possible 0.2 m2/min. Figure 7.2 below shows the capacity of each process: 20 One can see: 1. Potential bottleneck – it can occur during cutting, storage or lathe , drilling, polishing works. 2. According to throughput capacities of metal processing machines are used by 10% 3. Potential for the bottleneck solution- 3. Waste Total waste of mechanical processing is 1% of entranced metal. Waste can be during metal part cutting and lathe, drilling, polishing works. 4. Yield For mechanical shop the average entrance per month of metal is 200 m . Yield for mechanical shop is 198 m, which is 99% of metal entrance. Metal Coating Shop 1. Description of the shop Metal coating shop is located on the 1st floor and has area of 150 m2. In this shop work 2 employees. The final products of the shop are varies metal details coated by varies colors according to customer’s order. The main activities for this shop are the following: Metallic detail washing -entranced metallic details are washed; Metallic detail rust cleaning - washed metallic detail cleaning from rust by special substance; Metallic detail drying – metallic detail initial drying for the next technological step; Metallic detail coating - metallic detail is coated by the powder paint in an equipment for coating (1.7x1.7 m); Processing in oven - coated detail pass thermal processing (polymerization) in oven at 200Co. Figure 8.1 below depicts the timing of each process: Facilities of the shop include: 21 1 Washing equipment (1x4m); 1 Equipment for coating (1.7x1.7m); 1 Oven (2x2m). 2. Capacity There are coated per month in average240 m2of metallic parts. The throughput of coating the metallic parts is 0.02 m2 /min of possible 0.1 m2/min. Figure 8.2 below shows the capacity of each process: One can see: 2. Potential bottleneck can occur during rust cleaning, drying, coating and processing in oven. 2. According to throughput capacities of metal coating shop are used by 20.83%. 3. Potential for the bottleneck solution- 3. Waste The only waste there is paint which is 5% and it is reworked by 100%. 4. Yield As waste in this shop is reworked by 100% so yield is 100%. Stained Glass (Vitrage) Shop 1. Description of the shop Stained glass shop is located on the 2nd floor and has area of 25 m2. In this shop work 4 employees. The final products are stained glasses of various patterns. The main activities for this shop are the following: Cutting – the largest sizes of glass in this workshop is 1x1m, the smallest usual size is 0.1x0.1 m, the average size is 0.5x0.5mm. As each stained glass(vitrage) production is a separate project so in each case there are different size of cuttings; Edge Gluing – this is a technological step to prepare for the next process; 22 Brazing – very similar to soldering, tin is used; Cleaning – acetone is used, Figure below depicts the timing of each process: Stained Glass Storage Stained Glass Cleaning Stained Glass Brazing Stained Glass Edge Gluing Transportatio n Stained Glass Cutting 140 120 100 80 60 40 20 0 Placement min Processes Timing Facilities of the shop are several glaziers and soldering irons. 2. Capacity There are produced per month in average 15 m2 of stained glass. The throughput of stained glass is 0.0013 m2/min of possible 0.01 m2/min. Figure 9.1 below shows the capacity of each process: sqr m / min Processes Capacities 0.20 0.17 0.17 0.15 0.08 0.10 0.05 0.01 0.01 0.0013 0.00 Placement Stained Glass Cutting Transportation Stained Glass Edge Gluing 0.01 Stained Glass Brazing 0.03 Stained Glass Cleaning Stained Glass Storage One can see: 3. Potential bottleneck can occur during cutting, edge gluing, brazing and then at gluing processes. 2. According to throughput capacities of stained glass production are used by 13%. 3. Potential for the bottleneck solution- 3. Waste 23 The waste is 50% of entered glass, which is reworked by 50%. Waste occurs during stained glass cutting which is used lately in the next appropriate orders. 4. Yield For stained glass (vitrage) shop the average entrance per month of stained glass is 20 m2 . Yield for stained glass shop is 15 m2, which is 75% of stained glass entrance. Windows & Doors Shop 1. Description of the shop Windows & doors shop is located on the 2nd floor and has area of 300 m2. In this shop work 7 employees. The final products are frames of windows & doors of vary sizes. The main activities for this shop are the following: Aluminum profiles cutting- the largest size of aluminum profile is 4m, the smallest usual size is 0.5 m, the average size is 1.5m, which means there is a need to make at least 3 linear cuts. Milling- aluminum profiles pass milling processing for the frame assembly; Window/door frame assembly- aluminum profiles are assembled as window/door frame; Pantography – in assembled frame are made holes for installation of door-handles and screws ; Covering by rubber- assembled frame is covered by rubber ; Assembly with door-handles – frame is assembled with door-handles; Assembly with screws – the frame is assembled with screws. Facilities of the shop include: 2 Aluminum cutting machines; 1 Aluminum milling machine; 1 Pantograph. Figure 10.1 below depicts the timing of each process: 24 2. Capacity There are processed per month in average 716 m of aluminum profile. The throughput of aluminum profile is 0.06 m /min of possible 0.5 m/min. Figure 10.2 below shows the capacity of each process: One can see: 4. Potential bottleneck – it can occur during cutting, edge gluing, brazing and then at gluing processes. 2. Spare capacity- according to throughput capacities of window and door frame production are used by 12.4%. 3. Potential for the bottleneck solution- 3. Waste Total waste of windows and doors production is 5% of entranced aluminum profile. Waste can be during aluminum profile placement, cutting, milling and pantograph processing, storage of the final product. 4. Yield For window and door shop the average entrance per month of aluminum profile is 750 m. Yield for window and door shop is 716 m which is 96% of entranced aluminum profile. 25 Problems definition / Suggestions Human management The company’s most important shortage is the following: there are not clearly defined responsibilities and liabilities in each level of management. Successful human resource management depends on the right definition of the roles for each level of management. There has to be a supervising hierarchy and managers of each level have to know exactly how to make decision, which decision to make and be responsible. For example: … Human resources are critical for effective organizational functioning. Managers should now realize that effectiveness of their HR function has a substantial impact on the bottom-line performance of the firm. Poor human resources planning can result in spurts of hiring followed by layoffs – costly in terms of unemployment compensation payments, training expenses, and morale. Haphazard compensation systems do not attract, keep, and motivate good employees, and outmoded recruitment practices can expose the firm to expensive and embarrassing discrimination lawsuits. Consequently, the chief human resources executive of most large businesses is a vice president directly accountable to the CEO, and many firms are developing strategic HR plans and are integrating those plans with other strategic planning activities. Process Layout Kap@ arden nkaragrvats problemneri and with expansion plans. The basic objective of the layout decision is to ensure a smooth flow of work, material, people, and information through the system. 26 Effective layouts also: Utilize space efficiently Utilize labor efficiently Eliminate bottlenecks Facilitate communication and interaction Reduce manufacturing cycle time First step for layout forming is to assign numbers to each department: 1 Glass cutting shop 2 Glass processing shop 3 Glass packaging shop 4 UV fixing shop 5 Windows & doors 6 Mach. Shop 7 Coating department 8 Laminate furniture 9 Glass furniture 10 Stained Glass 11 Glass Storage Then we taking into consideration predicted movement of material between existing or proposed departments. This information is typically provided in the form of a from / to chart, or load summary chart. Load Summary Chart Departments From \ To 1 2 3 1 - 1 1 2 - 5 6 1 5 6 7 8 9 10 11 1 1 - 3 4 4 1 1 1 - 1 - 1 1 1 27 - 7 - 8 - 9 - 10 1 11 1 - In Load summary chart the “1”-s mean that corresponding departments are connected, for example the intersection cell of first row and second column contain 1 because cut glasses should go to glass processing shop for processing. Finally trial layouts are placed on a grid that graphically represents the relative distances between departments in the form of uniform blocks. The grid below will make easy to understand the explained idea. 1 2 3 4 5 6 7 8 9 10 11 12 Figure 1 The objective is to assign each department to a block on the grid so that nonadjacent loads are minimized. Saying nonadjacent we understand a distance farther than the next block, either horizontally, vertically, or diagonally. The trial layouts are scored on the basis of the number of nonadjacent loads. The process of different layout configurations to reduce the number of nonadjacent loads continues until an acceptable layout is found. Ideally the optimal layout would have zero nonadjacent loads. The case of initial arrangement 28 OUTPUT Original Layout 1 2 3 4 5 6 7 8 9 10 11 12 Nonadjacent loads = 1+2+1+1+1+1 =7 The case of final arrangement Revised Layout 3 11 10 5 1 7 2 8 6 4 9 Nonadjacent loads = 0 Product Manufacturing Layout For each shop like glass & mirror processing shop, which has many machines with different function, is very important to have product-manufacturing layout whose main objective is balance the production line. Product layouts arrange activities in a line according to the sequence of operations for a particular product or service. Line balancing tries to equalize the amount of work at each workstation. For this purpose, it is necessary to recognize order of activities and cycle time (the maximum amount of time a product is allowed to spend at each workstation). In many cases, we can increase the efficiency of 29 production line using U-shape line. Because to compensate for the different work requirements of assembling different models, it is necessary to have a flexible workforce and to arrange the line so that workers can assist one another as needed. The advantages of product-manufacturing layout are the following: Better use of human recourses Easier to control Easier to automate Direction of part movement within cell D(10m) P(10m) Paths of workers moving within cell Material movement Pr(15m) S(15m) Key: S = Straighted Processing P = Polishing D = Drilling Pr =Processing Out (10m) Worker 1 In (2m) Figure 2 is showing the machines arrangement within department like U-shape. Balancing U-Shaped Lines Precedence diagram: I S Figure 3 P D Pr O Cycle time = 15 min (a) Balanced for a straight line I S P D Pr (b) Balanced for a U -shaped line O I 2m 15m 10m Efficiency = 10 m 62 = 6(15) 15m 10m S P 30 62 = 0.6888 = 68.9 % 90 D O Pr As already mentioned above for line balancing process we need precedence diagram and calculated cycle time required for the line. Figure3 contain this information. Cycle time = max [2, 15, 10, 10, 15, 10] = 15 Flow time = 2 + 15 + 10 + 10 + 15 + 10 = 62 j t Efficiency = E = i 1 i nC a Where ti = completion time for element i j = number of work element n = actual number of workstation Ca = actual cycle time Efficiency of straight line and U-shape line is calculated in figure 3. We can say that the efficiency is higher in b) case. The difference between straight line and U-shape line is the following: in U-shape we can group first and last element into one workstation in order to equalize the amount of work at each workstation, and in this manner to reduce the number of workstations. This means that one worker can manage first and last activity as it is shown in figure 2. Forecasting (seasonal adjustment) There are many fields where accurate forecasts (which are built on trend analysis) are paying real benefits to those who use them. Examples of applied forecasting are the following: Revenue and profit planning Inventory-level management Production resource scheduling Human resources planning 31 Capital planning Rolling stock allocation Product sales forecasting Project planning Organizations can benefit from accurate forecasts to: Optimize the business to reduce the costs of operations. Increase sales opportunities to maximize profits. Provide accurate information to make better decisions. There are qualitative (based on judgment, past experiment, or opinion) and quite of few quantitative methods (moving average, single and double exponential smoothing, adjusted exponential smoothing, linear regression, seasonal adjustment) to make forecasts. For Gapex Company the most appropriate forecasting method is seasonal adjustment. It can be seen from the chart shown below that there is a seasonal pattern – a repetitive increase and decrease in demand. 80000 70000 60000 50000 40000 30000 20000 10000 0 I II III IV V VI VII VIII IX X XI XII Chart Glass sales (m2 ), 2006 There are several methods for reflecting seasonal patterns in a time series forecast. Here is used a method with seasonal factor. A seasonal factor is the numerical value that is multiplied by the normal forecast to get a seasonally adjusted forecast. Here in order to find normal forecast is used linear regression method. Linear regression or in other words causal method of forecasting is applicable when mathematical relationship exists between demand and some 32 other factor, which cause demand behavior. When time causes demand behavior a least squares, regression line or linear trend line can be used to forecast demand. A linear regression model is as follows: y = a + b*x Where a = intercept (at period 0) b = slope of the line x = the time period y = forecast for demand for period x Having quarterly demand we can find linear trend line and then putting four instead of x we are getting annual forecast of demand. Year Seasons 2004 2005 2006 1 50400.2875 60480.35 72576 2 72049.4792 86459.38 103751 3 109998.764 131998.5 158398.22 4 119475.972 143371.2 172,045.40 Total 351924.503 422309.4 506771 Calculations is done by excel. A Linear Regression Forecast for Gapex Ltd. x Year 1 2 3 6 y Sales ,m2 351924.5 422309.4 506771.3 1,281,005 a= b= y= 272154.9488 77423.39061 272154.95 + 77423.4 x 33 y(4) = 581849 Figure It is obvious from the figure that normal forecast is equal to y (4) = 581849. Using this annual forecast of demand for 2007 and having three years quarterly demand we can find the seasonality adjusted forecasts for 2007. For that purpose, we should first compute the seasonal factors by dividing total quarterly demand for the three years by total demand across all three years and multiply each of them by annual forecast of demand of 2007. Again, calculations done by excel. Computing a Forecast with Seasonal Adjustments Demand per Quarter Year 1 2 3 4 Total 2004 50400 72049 109999 119476 351925 2005 60480 86459 131999 143371 422309 2006 72576 103751 158398 172045 506771 Total 183457 262260 400396 434893 1281005 Linear trend line forecast for 2007 = SF1 = 83328 SF2 = 119122 SF3 = 181865 SF4 = 197534 581849 Fiqure The figure contains the following information: Glass demand in winter 2007 will be 83,328 sqr. m, in spring 2007 will be 119,122 sqr. m, in summer 2007 will be 181,865 sqr. m and in autumn 2007 will be 197,534 sqr.m. 34 Forecast Control Forecast can be in control or out of control. Forecast can go out of control and start providing inaccurate forecast for several reasons, including a change in trend, the unanticipated appearance of a cycle, or an irregular variation such as unseasonable weather, a promotional campaign, new competition, or a political event that distracts consumers. One way to control forecast is tracking signal which indicates the forecast is consistently biased high or low. It is computed by dividing the cumulative error by MAD. TS = (D t Ft ) MAD = E MAD The movement of the tracking signal is compared to control limits; as long as the tracking signal is within these limits, the forecast is in control. MAD- mean absolute deviation is the average, absolute difference between the forecast and demand. Corresponding formula is the following MAD = | D t Ft | n Where t = the period number Dt = demand in period t Ft = the forecast for period t n = the total number of periods || = absolute value The calculations are done by excel Tracking Signal Values |Dt - Ft| ∑|Dt - Ft| MAD Tracking SeasonsDemandForecast Error E Dt Ft Dt - Ft ∑(Dt - Ft) Signal 1 2 3 4 72,576 103,751 158,398 172,045 83,328 119,122 181,866 197,533 -10,752 -15,370 -23,467 -25,488 -10,752 -26,122 -49,589 -75,077 10,752 15,370 23,467 25,488 10,752 26,122 49,589 75,077 10,752 13,061 16,530 18,769 -1 -2 -3 -4 Fi gure 35 Forecast Control 4 3 2 1 0 1 -1 -1 2 -2 3 4 -2 -3 -3 -4 -4 -5 Chart It is obvious from the chart that tracking signal moves beyond the lower limits of following period 4. It means that the forecast has some bias. Safety Workplace safety refers to the working environment at a company and encompasses all factors that affect the safety and health of employees. This can include environmental hazards, unsafe working conditions or processes, drug and alcohol abuse, and workplace violence. The Occupational Safety and Health Administration (OSHA) monitor workplace safety at the national level. OSHA has three stated goals that serve as the cornerstones of its policies and regulations: 1) Improve the safety and health for all workers, as evidenced by fewer hazards, reduced exposures, and fewer injuries, illnesses, and fatalities. 2) Change workplace culture to increase employer and worker awareness of, commitment to, and involvement in safety and health. 3) Secure public confidence through excellence in the development and delivery of OSHA's programs and services. Small businesses also have to pay attention to safety. Indeed, workplace safety is an important consideration on a number of levels. Attention to safety issues cannot only help 36 businesses avoid legal penalties, but also improve employee morale, productivity, and retention. Moreover, effective workplace safety programs often have a tremendous impact on a company. Workplace safety programs can take many forms and cover many potential areas of concern. Such disparate measures as provision of personal safety equipment, installation of equipment controls, creation and dissemination of operational manuals, policies of hazardous materials handling, adoption of drug and alcohol testing policies, introduction of employee counseling services, and implementation of safety training programs are all utilized by companies to minimize their workforce's exposure to workplace injuries. One method that many firms have had success with is to appoint one person in the organization as the safety coordinator. The ideal candidate has a background in safety, but if no one fits that profile, then chooses the candidate who best relates to workers and management, has strong communication skills, and has an interest in and commitment to safety. A common title for this person is "safety manager." For the safety manager to do his or her job, he or she must have direct access to the top manager in the company. The manager must also have access to every department and work area, and must be able to question people freely for gathering information. Regular status reports should be prepared that update management on current safety initiatives and identifies areas that still need improvement. Ideally, the safety manager's role will remain an advisory one: responsibility for implementing the manager's suggestions should fall to upper management and the individuals or teams that singled out by the safety manager. The best starting point for a new safety manager is often to review company records of past safety problems. By drawing up a list of areas that are known problems, the manager can identify the best place to begin implementation of new safety measures. The safety manager should seek to involve all employees and managers in safety initiatives. The personnel of each department, not the safety manager, should conduct inspections. In fact, the manager should let each department handle most of its own safety problems—if proper training has been given to all employees, the safety manager should only have to address serious problems that require his or her knowledge and authority. 37 Many companies having safety manager have also reported some unexpected benefits, including an increased sense of teamwork, better sharing of information and a drop in absenteeism, discrimination claims, grievances, and sick days. In Gapex Company, safety manager has many things to do. The safety problems currently existing in Gapex are the following: Poor lighting in all departments It is very important to have more light in all departments because almost all departments acting with glass and using different machines for different processes. Absence of helmets, gloves and uniforms The usage of crane (crane move glass above workers) is very useful for glass shop but at the same time is very dangerous for workers of that department. Paint dust in metal coating department Broken glass’ existence in all over the place 38 References 39 Different Company’s main activity (major source of profit) is to deal with importing and realizing glass sheets with variable sizes. Along with years they founded deferent kinds of departments especially for their needs. Recently these departments (working strategy - make to order) also bring huge profit offering the certain amount of different kinds of product to the local consumers. Because of that these departments should be kept under control: clearly defining frequency of tasks, level of responsibility, quality responsibility and so on in order to be able not to reject some order. “Human resource focus” of the company is crucial for this situation. Final waste of glass is 1125 m2 per months which is sold to local glass producing company by 5.13$ per kg. Glass of different types mainly imported from Iran & China is the main sale & raw material for Company. They buy the glass as much as they can obtain and this approach is justified by the following: 1. The quantity of glass is decreased in East Region which causes increase in prices and difficulty in getting glass. 2 They have no problem with realization. Besides, Metal tubes of different length & wide, laminate sheets with different colors, aluminum profiles, silica gel & distance frames, and ‘tiacol’ are raw materials for mechanical shop, laminate furniture shop, door & window shop, glass package shop, multilayer glass shop respectively. 40 Go to the top of document 41