Building Safety Division Planning and Development Services 8500 Santa Fe Drive Overland Park, Kansas 66212 913-895-6266 Fax: 913-890-1266 www.opkansas.org January 7, 2008 Brian Foxworthy Incite Design Studio / The Phoenix Group of Overland Park brian@incitedesignstudio.com 7311 West 75 Street Overland Park, KS 66204 Plan Review Number: PRS2007-00592 Project Name: 7924 SANTA FE BUILDING Project Address: 7924 Santa Fe The Planning and Development Services Department reviewed the plans submitted on December 20, 2007. The following comments are from various divisions within the Planning and Development Services Department. When resubmitting your plans, include a cover letter complete with project name, address, and plan review number, and indicate how you have addressed each plan review comment. Building Safety Division - Plan Review The following comments are from the Building Safety Division-Plan Review. Direct any questions regarding these issues to Steve Mosebach at (913) 895-6266. 1. The revised electrical drawings submitted to the city were not sealed by a design professional licensed with the state of Kansas. 2. Repeat comment: The supporting construction for the stair terminating on the second floor shall be 1-hour fire rated per Section 706.5 of the 2006 International Building Code. This would include any walls, beams, and columns that are supporting the masonry stair enclosure. The two beams (W21x44 & W 24x62) on Grid Line D, between Grid Line 1 and 3 shall also be fire rated. The columns at Grid Lines B6, B-10, D-1, D-2, D-3, and D-6 shall also be fire rated. Just as the plans identify U.L. assemblies for wall construction, the designer shall also indicate the U.L. or other accredited agency designs for all fire rated beams and columns on the plans as well. Brian Foxworthy January 7, 2008 Page 2 3. Repeat comment: The supporting construction for the fire barrier walls enclosing the Office Lobby A205 (exit passageway) shall afford the required fire-resistance rating of the fire barrier supported per Section 706.5 of the 2006 International Building Code. This would include all beams, girders, columns, floor slab, etc. The two beams (W24x62 & W21x44) on Grid Line D, between Grid Line 2 and 6 shall also be fire rated. The columns at Grid Lines D-2, D-3 and D-6 shall also be fire rated. 4. New comment: Just as the plans identify U.L. assemblies for wall construction, the designer shall also indicate the U.L. or other accredited agency designs for all fire rated beams and columns on the plans as well. 5. Repeat comment: The plans do not show how sufficient working clearance in front of the electrical panels will be maintained per Section 110.26 of the 2005 National Electrical Code. Provide a floor plan that clearly diagrams the working clearances at Service Room A109. Page E2.1 does not show a physical barrier or other method to keep trash dumpsters or other equipment from being placed within the required working clearances of the electrical equipment (MDP1 and MDP2) as required by the 2005 National Electrical Code. The following shall be completed at a later date, but will not delay the issuance of a building permit: 1. Submit complete fire sprinkler plans and hydraulic calculations for review and approval, prior to installation of the system. The system shall be designed per NFPA 13 – 02. 2. Submit complete plans for the fire alarm system per Section 907.2.9 of the 2006 International Building Code, prior to installation of the system. An emergency/voice alarm communication system is required per Section 907.2.12.2 of the 2006 International Building Code. 3. All exterior plywood sheathing shall be fire-retardant treated per Section 603.1 of the 2006 International Building Code. See pages A7.2, A7.3 and A7.4. 4. Where there are four or more dwelling units to be occupied as a residence in a single structure, every unit shall be a Type B dwelling per Section 1107.6.2.1.2 of the 2006 International Building Code. 5. An electronic drawing showing impervious surfaces for use in calculating the Storm Water Utility Fee shall be provided to Planning and Development Services prior to issuance of Certificate of Occupancy or Certificate of Compliance. Please refer to the enclosed Impervious Surface Drawing Requirements. Questions should be directed to Dave Fullerton at (913) 895-6228 or dave.fullerton@opkansas.org. Overland Park Fire Department The Overland Park Fire Department has approved the plans as submitted. Brian Foxworthy January 7, 2008 Page 3 Current Planning Division The following comments are from the Current Planning Division. Questions regarding these issues should be directed to Keith Gooch at (913) 895-6181. 1. Staff has requested more information on the brick paneling system and the ability to limit the visibility of the joints between the panels. Please let staff know if there is an update. 2. The transformers shall be screened by landscaping on both the north and south sides. Staff is checking with the Park’s Department to determine if they are willing to maintain this new landscaping. Engineering Services Division The Engineering Services Division has approved the plans as submitted. Permit applicants must obtain a Johnson County Contractor License prior to issuance of a building permit in the City of Overland Park. For more information, please contact Johnson County Contractor Licensing, (913) 715-2233, 111 South Cherry, Room 1056, Olathe, Kansas 66061, or http://contractorlicensing.jocogov.org. If you have questions or alternatives to discuss on the above-mentioned items, please contact the appropriate person above. Steve Mosebach, MCP - Senior Plans Examiner G:word(common)\PRS2007Comments\PRS00592-4-7924 Santa Fe Building