IEEE P1653.4/D1, November 2009 Standard for dc Traction Power System Field Testing and Acceptance Criteria for System Applications up to 1500 Volts dc Nominal Sponsored by the Rail Transit Vehicle Interface Standards Committee of the IEEE Vehicular Technology Society Copyright © 2008 by the Institute of Electrical and Electronics Engineers, Inc. Three Park Avenue New York, New York 10016-5997, USA All rights reserved. This document is an unapproved draft of a proposed IEEE Standard. As such this document is subject to change. USE AT YOUR OWN RISK. Because this is an unapproved draft, this document shall not be utilized for any conformance/compliance purposes. Permission is hereby granted for IEEE Standards Committee participants to reproduce this document for purposes of international standardization consideration. Prior to adoption of this document, in whole or in part, by another standard development organization permission shall first be obtained from the IEEE Standards Activities Department (stds.ipr@ieee.org). Other entities seeking permission to reproduce this document, in whole or in part, shall also obtain permission from the IEEE Standards Activities Department. IEEE Standards Activities Department 445 Hoes Lane, P.O. Box 1331 Piscataway, NJ 08855-1331, USA 1 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 Introduction This introduction provides background on the rationale used to develop this standard, which may aid in the understanding, usage, and applicability of this standard. This standard is intended to apply to field testing of installed dc traction power substation (TPSS) equipment rated at 1500 V dc nominal or less. Installed traction power substations may be ready for revenue service once the tests included in this standard are performed and accepted by the authority. Factory testing, “design and production tests” of a traction power substation and its individual equipment is covered in other standards. This standard is designed to verify the integration of individual pieces of equipment covered in other standards to achieve their intended function once they are assembled and integrated as a complete traction power substation configured into a system-wide traction power system. Notice to users Laws and regulations Users of these documents should consult all applicable laws and regulations. Compliance with the provisions of this standard does not imply compliance to any applicable regulatory requirements. Implementers of the standard are responsible for observing or referring to the applicable regulatory requirements. IEEE does not, by the publication of its standards, intend to urge action that is not in compliance with applicable laws, and these documents may not be construed as doing so. Copyrights This document is copyrighted by the IEEE. It is made available for a wide variety of both public and private uses. These include both use, by reference, in laws and regulations, and use in private self-regulation, standardization, and the promotion of engineering practices and methods. By making this document available for use and adoption by public authorities and private users, the IEEE does not waive any rights in copyright to this document. Updating of IEEE documents Users of IEEE standards should be aware that these documents may be superseded at any time by the issuance of new editions or may be amended from time to time through the issuance of amendments, corrigenda, or errata. An official IEEE document at any point in time consists of the current edition of the document together with any amendments, corrigenda, or errata then in effect. In order to determine whether a given document is the current edition and whether it has been amended through the issuance of amendments, corrigenda, or errata, visit the IEEE Standards Association Web site at http://ieeexplore.ieee.org/xpl/standards.jsp, or contact the IEEE at the address listed previously. For more information about the IEEE Standards Association or the IEEE standards development process, visit the IEEE-SA Web site at http://standards.ieee.org. 2 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 Errata Errata, if any, for this and all other standards can be accessed at the following URL: http://standards.ieee.org/reading/ieee/updates/errata/index.html. Users are encouraged to check this URL for errata periodically. Interpretations Current interpretations can be accessed http://standards.ieee.org/reading/ieee/interp/index.html. at the following URL: Patents Attention is called to the possibility that implementation of this standard may require use of subject matter covered by patent rights. By publication of this standard, no position is taken with respect to the existence or validity of any patent rights in connection therewith. The IEEE is not responsible for identifying Essential Patent Claims for which a license may be required, for conducting inquiries into the legal validity or scope of Patents Claims or determining whether any licensing terms or conditions provided in connection with submission of a Letter of Assurance, if any, or in any licensing agreements are reasonable or non-discriminatory. Users of this standard are expressly advised that determination of the validity of any patent rights, and the risk of infringement of such rights, is entirely their own responsibility. Further information may be obtained from the IEEE Standards Association. 3 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 At the time this standard was completed, the working group had the following membership: Jay Sender, Chair Sam Kundu, Vice Chair Ahmed Zobaa Alexander Kline Arthur McVitty Ashton Robinson Benjamin Stell Bob Fisher Chris Pagni Chuck Ross Dave Prakash Constantinos Orphanides David Groves Dev Paul David Reinke Earl Fish Fred Rooney Gary Touryan Gilbert Cabral Greg Thompson Herb Zwilling Jeffrey Sisson Jeftic Mladen John Pascu John Whitney Keith Miller Mark Griffiths Mike Dinolfo Nerendra Shah Nick Rassias Oscar Ravarra Paul Forquer Peter Lloyd Raj Ganeriwal Ramesh Dhingra Ray Davis Raymond Strittmatter Richard Shiflet Roger Avery Ron Clark Sergo Sagareli Stephen Norton Steve Bezner Stuart Kuritzky Tanuj Khandelwal Theodre Bandy Tim Fink Timothy McBride Tom Langer Tom O’Hara Tom Young Tristan Kneschke Vince Paparo Yunxiang Chen The following persons were on the balloting committee: (To be provided by IEEE editor at time of publication.) 4 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 Contents 1. Overview ..................................................................................................................................................... 2 1.1 Scope ..................................................................................................................................................... 2 1.2 Purpose .................................................................................................................................................. 2 2. Definitions, Abbreviations, and Acronyms .................................................................................................. 2 2.1 Definitions ............................................................................................................................................. 2 2.2 Abbreviations and Acronyms ................................................................................................................ 2 3. Testing Requirements .................................................................................................................................. 3 3.1 General………………………………………………………………………………………………3 3.2 Procedures ............................................................................................................................................. 3 3.3 Test Equipment ……………………………………………………………………………………….4 3.4 Substation Physical Inspection and Mechanical Operation ………………………………………….. 4 3.5 Electrical Insulation Tests …………………………………………………………………………… 5 3.6 Ground Verification Test …………………………………………………………………………….. 5 3.7 Substation Functional Test ................................................................................................................... 5 3.8 Short Circuit Test ................................................................................................................................. 7 3.9 Train Starting Tests .............................................................................................................................. 8 3.10 Audible Sound Level Test .................................................................................................................. 9 3.11 Infrared Thermographic Inspection/Test ………………………………………………………… 9 Annex A Bibliography …………………………………………………………………………………………….10 Annex B B.1 Short Circuit Test 5 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 B.2 Train Start Test B.3 Stray Current Structure - to - Earth Voltage Test ........................................................................... 12 B.4 Running Rail - to - Earth Resistance Test ………………………………………………………… 1 6 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 Standard for dc Traction Power System Field Testing and Acceptance Criteria for System Applications up to 1500 Volts dc Nominal 1. Overview 1.1 Scope This standard provides field test and acceptance criteria for transportation system applications powered by a dc traction power system up to 1500 volts nominal. 1.2 Purpose The purpose is to ensure that the installed equipment will function as intended by the plans and specifications, thereby providing reliable service for the anticipated life of the equipment. 2. Definitions, Abbreviations, and Acronyms 2.1 Definitions 2.1.1 General For purposes of this standard, the following terms and definitions apply. IEEE 100, The Authoritative Dictionary of IEEE Standards Terms, Seventh Edition, should be referenced for terms not defined in this clause. 2.1.2 authority – The owner/user as defined by the contracting document. 2.1.3 contingency operation – The condition occurring when power normally supplied to a segment under test is restricted due to one or more traction power substations being deenergized and/or one or more dc feeder breakers being open. 2.1.4 safety/security equipment – Certain equipment including intrusion alarm, fire protection, safety interlocks, and annunciation devices. 7 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 3. Testing Requirements 3.1 General This standard provides field test and acceptance criteria for equipment once it is assembled and integrated as a complete traction power substation. Where there are field testing requirements for certain components addressed in other applicable standards, these standards are referenced in the appropriate clauses of this standard. This standard does not attempt to identify or address the detailed testing or sequence of the tests performed on ancillary components associated with a system-wide traction power system in the vicinity of a traction power substation. As a standard it is limited to addressing the traction power substation components and the corresponding criteria that are required for safety and effective functioning after installation. This standard is intended to provide a set of uniform field test requirements to verify that installed traction power substation equipment satisfies safety and performance criteria when assembled and integrated as a complete traction power substation to serve as a source of dc traction power for the train propulsion system. This standard references contract documents for the technical requirements needed to perform a test. In lieu of an authority incorporating specific technical requirements into the contract documents the authority’s design criteria may be referenced in the contract. 3.2 Procedures 3.2.1 General This clause describes the criteria and requirements for test planning, performance, recording of data, and reporting of test results. 3.2.2 Test Plan A test plan shall identify the approach to be used for accomplishing each of the specified tests, and include the projected test schedule, installation verification procedures, test execution and acceptance criteria. 3.2.3 Failure and Retesting Failure of equipment to meet test specifications or ratings shall be grounds for rejection of equipment. Failed equipment shall be retested in accordance with this standard after renewal or repair work and conforming test(s) witnessed by the authority for acceptance have been successfully completed. Revised drawings or diagrams shall be prepared if modifications or changes affect any drawings, diagrams, or other documents previously submitted to and accepted by the authority. The requirements for specified tests, performance specifications, drawings and design calculations of the original unit shall be applicable to the new unit. 3.2.4 Test Procedures and/or Reports Test procedures and/or reports shall include as a minimum: 8 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 a. Title of test(s), including equipment model and serial numbers (where applicable). b. Scheduled location and date of test(s). c. Equipment to be tested. d. Objective and scope of test(s). e. Test set-up, physical and wiring diagrams of test(s). f. Test equipment to be used, with manufacturer’s name and model number. g. Abbreviations and references used in the test(s) description. h. Personnel required for the test(s), including primary and supporting personnel. i. Estimated duration of test(s). j. Pass/fail criteria of each test and probable results, including calculations, curves, photographs, and other supporting data. k. Samples of test(s) data sheets to be used for recording test(s) parameters and results. l. Step by step instructions for performing the test(s), identifying the points where data are to be recorded and the limits for acceptable data. m. Instructions for recording data on data sheets or verifying that individual procedural steps have been completed. n. Ambient condition limitations including temperature, altitude, barometric pressure, air humidity, maximum available short circuit fault current from utility company, noise, and vibration. o. Signature space(s) provided with printed name/title/company below on test(s) data sheets. p. Company performing instrument calibration and date calibration performed. In addition to the requirements specified above, test reports shall include accuracy and calibration data of the test equipment used, summary and conclusions, results including calculations, curves and photographs, descriptions of any failures and/or modifications including reasons for such failures and/or modifications, names of individuals approving such modifications, other supporting data, and signature(s) of test witness(s). Revisions to the test procedures may be proposed based upon the results of the first items tested. Modified test procedures shall be resubmitted to the authority for acceptance and shall meet the same submittal requirements indicated herein unless waived by the authority. 9 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 3.3 Test Equipment Instruments and devices used quantitatively shall be within current calibration period and current certificates shall be provided to the authority. 3.4 Substation Physical Inspection and Mechanical Operation A physical inspection and mechanical operation shall be conducted on all substation equipment prior to energizing the rectifier transformer. For this inspection all compartment doors/panels shall be opened and/or removed to allow access to the equipment. During this inspection special instructions to transit operators shall be given so that adjacent traction power substations do not back-feed dc power on the load side of the dc feeder breakers. The isolated dc sections shall be properly grounded, and/or the appropriate dc feeder breaker(s) shall be opened, locked and tagged. Likewise ac primary power switch(es) outside the traction power substation shall be opened, locked and tagged to electrically isolate the substation under test from all sources of ac and dc power. The purpose of performing this inspection/operation is to verify all equipment is properly secured, bolted connections are tightened within torque specifications, bus bars and/or cables are adequately supported, grounding and testing devices function properly, insulation levels are not compromised, no undesirable material and/or tools have been inadvertently left inside the equipment, protective and safety/security equipment are operational, battery cases are not cracked or leaking, and safety labels are affixed. 3.5 Electrical Insulation Tests The following electrical insulation tests shall be performed prior to energizing the rectifier transformer, control power circuits, and dc feeder cables to verify that no equipment damage occurred during delivery and installation, and the equipment is effectively grounded: a. Wiring insulation resistance testing. b. Ac and dc bus dielectric testing. c. Ac and dc circuit breaker dielectric testing. d. Rectifier transformer dielectric testing. e. Rectifier unit(s) dielectric testing. f. Insulated floor dielectric testing. 3.6 Ground Verification Test 3.6.1 General The following tests shall be performed to verify that grounding at each substation location meets the contract requirements. A detailed visual inspection of all bond and grounding wires shall be conducted prior to performing the following tests: a. System grounding test conforming to maximum acceptable grounding resistance. 10 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 b. Equipment grounding/bonding test per maximum acceptable resistance value criteria. 3.6.2 Test Description 3.6.2.1. Measure the resistance of the bond wires between metallic enclosures/surge arresters and a substation grounding system using a low resistance ohm-meter. Connect the test point between the enclosure and the station perimeter ground, or ground bus. 3.6.2.2. Measure the resistance between the ground grid and conductors connected to the substation ground bus using a low resistance ohm-meter. The low resistance ohm-meter shall provide 1 micro-ohm measurement resolution. 3.6.2.3. Measure the resistance of the substation ground grid(s) in accordance with IEEE Std. 81. 3.6.3 Acceptance Criteria Total resistance of a bond and/or ground connection shall not exceed contract requirements (typically between 5 µΩ and 1 mΩ excluding conductor resistance) measured between an enclosure and perimeter ground or copper bus. The substation grounding system resistance shall not exceed contract requirements (typically 5 Ω). 3.7 Substation Functional Tests 3.7.1 General The following tests shall be performed to verify proper operation of traction power substation equipment. 3.7.2 Prior to Rectifier Transformer and DC Feeder Cable Energization These tests shall be performed after the batteries reach full charge and control circuit low-voltage services are energized, but before the traction power rectifier transformer and dc feeder cables are energized. For safety reasons, operation of all of the protective devices and medium voltage switchgear shall be confirmed before the feeder is energized. Relay contacts shall be blocked, jumpers installed, or digital signals generated to simulate an energized traction power rectifier transformer, main dc bus and dc feeders. Equipment shall be isolated and grounded according to applicable safety standards prior to proceeding with functional tests. Timing devices shall be set in this phase. Test procedures shall simulate the operation of each device under test by manipulation, contact jumpering, or digital signal generation. The operation of a relay having multiple inputs shall be confirmed from each and every input device. (i.e.: a lockout relay having multiple inputs from various devices shall be operated from each device to confirm operation of the lockout relay). Test records shall provide means to document that all functions have been verified for compliance with the control schematics, plans and specifications; and the relays and meters are calibrated. Devices tested shall include as a minimum: 11 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 a. Control circuits, annunciator circuits, supervisory circuits, load measuring circuits, emergency trip system (ETS) circuits, transfer trip circuits, and safety/security circuits. b. Protective relays. c. Metering equipment. d. Safety/security equipment including but not limited to smoke alarms, emergency lighting and intrusion devices. e. Circuit breaker and interlock(s) operation. f. Station battery system and charger. The battery shall be subjected to a battery load test in accordance with the battery manufacturer’s test procedure once the battery is fully charged. The individual battery cell voltages shall be measured and recorded. g. Environmental control devices integral to the equipment. This test may be delayed until subclause 3.7.4 if insufficient power prevents testing of these devices at this time. h. Grounded structure and hot structure protection. Each protected surface shall be tested by actually applying a ground and ac and/or dc voltage to the surface. i. Remote monitoring and control devices. Each I/O point shall be tested using a diagnostic computer to verify proper operation. 3.7.3 Additional Pre-Requisites Prior to Performing Energized Testing The following tasks should be performed prior to performing energized testing: a. Short Circuit and Protective Device Coordination Study - completed by the authority or its designate. b. Recommended equipment short circuit ratings and protective device settings implemented. c. Utility Provisions - reviewed and approved by the utility(s). d. Transfer trip scheme - tested at adjacent substations. The following task shall be performed prior to performing energized testing: e. Arc Flash Hazard Analysis and equipment labeling - completed and implemented per NFPA-70E or IEEE STD 1584 and as specified by the authority for specific application. 12 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 3.7.4 After Rectifier Transformer and DC Feeder Breaker Energization (No Load) The following tests shall be performed to verify proper operation of a substation after the rectifier transformer and dc feeder breakers are energized, but before load is applied by closing the dc feeder breakers. Test records shall provide means to document that all control functions have been verified prior to proceeding to energized testing. Devices tested shall include as a minimum: a. Incoming ac power supply feeder alive device (27/47 or 27/59). The device shall be tested by removing and restoring the feeder PT fuses. b. Rectifier unit polarity and voltage. c. Rectifier transformer tap voltage. d. Ac incoming power supply voltage circuit breaker (device 52) and rectifier output circuit breaker (device 72) electrical interlocks. e. Voltage sensing circuits at dc switchgear. 3.7.5 After Substation Energization (Load Test) In the final stage of traction power substation equipment functional testing the rectifier shall be energized and the dc feeder breakers closed. Proper operation of dc and ac ammeters, dc and ac voltmeters, and dc feeder load measuring shall be confirmed as load is applied as described under clause 3.9. Short circuit current testing and train start testing shall be performed in accordance with clauses 3.8 and 3.9. 3.7.6 Acceptance Criteria All traction power substation equipment shall function as intended and as specified in the contract. 3.8 Short Circuit Test 3.8.1 General These tests shall be performed to verify the correct selective tripping sequence of all protective devices in the event of an applied short circuit, and to optimize adjustment of substation protective devices. Other tests (subclause B.1) may be specified in the contract to verify proper operation of all protective devices at adjacent substations. 3.8.2 Test Description 3.8.2.1 Close In – TPSS External Fault With the traction power substation to be tested energized and all other substations connected to the line segment under test de-energized and the dc feeder breakers of adjacent de-energized substations serving the line open, and the electrical overhead contact system or third rail section configured according to contract requirements, apply a switched connection between the positive 13 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 and negative current collection points just outside the traction power substation where maximum substation fault current magnitude is likely to occur. Obtain digital or analog oscillographic recordings of current and voltage, impulse time, clearing time, and recovery voltage. For safety reasons, remote tripping of dc feeder breakers connected to the line segment under test shall be provided so the breaker can be tripped in the event the protective devices fail to operate properly. 3.8.2.2 Remote Distance – TPSS External Fault With the traction power substation to be tested energized and all other substations connected to the line segment under test de-energized and the dc feeder breakers of adjacent de-energized substations serving the line segment under test open, and the electrical overhead contact system or third rail section configured according to contract requirements, apply a switched connection between the positive and negative current collection points at the track position where the minimum fault current magnitude supplied by the traction power substation is likely to occur. Obtain digital or analog oscillographic recordings of current and voltage, impulse time, clearing time, and recovery voltage. For safety reasons, remote tripping of dc feeder breakers connected to the line segment under test shall be provided so the breaker can be tripped in the event the protective devices fail to operate properly. 3.8.3 Acceptance Criteria The ac and dc protective relay settings shall achieve the desired relay coordination between protective devices, and shall operate to trip and lockout the appropriate circuit breakers without any adverse event. 3.9 Train Starting Test 3.9.1 General This test shall be performed to verify proper operation of the ac and dc protective devices under the vehicle loading specified in the contract. Other tests (subclause B.2) may be specified in the contract to verify proper performance of the vehicles.. 3.9.2 Test description With the traction power substation under test energized and all other substations normally connected to the line segment under test de-energized and the dc feeder breakers of adjacent deenergized substations serving the line segment under test open, and the electrical overhead contact system or third rail section configured according to contract documents, simultaneously accelerate the maximum number of fully loaded vehicles as specified in the contract for normal operation (loaded weight per contract) away from the energized substation. The vehicles shall operate at maximum specified acceleration to attain the maximum permitted speed for the area under test, and then brake to a full stop using full service brake. A high resolution chart record of dc feeder current and dc bus voltage shall be obtained. Other measurements such as rail to ground voltage (subclause B.3) may also be recorded by the authority to estimate the level of stray leakage current for short time intervals. The test shall be conducted with the vehicles starting at a location just outside the energized substation.. 14 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 3.9.3 Acceptance Criteria Traction power substation equipment shall sustain the train currents produced with no indication that substation protective devices have operated improperly. 3.10 Audible Sound Level Test 3.10.1 General These tests shall be performed to verify that the sound generated from a traction power substation does not exceed contract requirements with all substations normally connected to the line segment under test energized, and the electrical overhead contact system or third rail section configured according to contract requirements. During this test the maximum number of fully loaded vehicles as specified in the contract for normal operation shall be in operation. 3.10.2 Test description Record ambient sound level at the substation location under no-load conditions per the contract. Simultaneously accelerate the maximum number of fully loaded vehicles permitted within an overhead contact system or third rail section as specified in the contract for normal operation (loaded weight per specification) away from the energized substation,. The vehicles shall operate at maximum specified acceleration to attain the maximum permitted speed for the area under test, and then brake to a full stop using full service brake. Record the maximum sound level while the vehicles are accelerating. 3.10.3 Acceptance Criteria The sound level generated by the substation under vehicle operation shall not exceed contract specified levels. 3.11 INFRARED THERMOGRAPHIC INSPECTION /TEST (Load) 3.11.1 General Thermographic inspection shall be performed to check for manufacturing/installation flaws after energizing and loading the substation equipment for a sufficient time to raise the equipment temperature to operating limits, and before short circuit tests are performed. During this test the maximum number of fully loaded vehicles as specified in the contract requirements for normal operation shall be in operation. 3.11.2 Acceptance Criteria All traction power substation equipment shall function as specified in the contract with no hot spots detected by the thermographic inspection. 15 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 ANNEX A (Informative) Bibliography [A1] IEEE/ANSI C2, NESC, National Electrical Safety Code (NESC) [A2] IEEE C57.12.90, Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers and Guide for Short-Circuit Testing of Distribution and Power Transformers [A3] IEEE C57.12.91, Test Code for Dry-Type Distribution and Power Transformers (Revision of IEEE Std C57.91-1981, IEEE Std C57.92-1981, and IEEE Std C57.115-1991) [A4] IEEE C57.18.10, Standard Practices and Requirements for Semiconductor Power Rectifier Transformers (Revision and redesignation of ANSI/IEEE C57.18-1964) [A5] IEEE Std 81, Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials [A6] IEEE Std 1584, IEEE Guide for Performing Arc-Flash Hazard Calculations [A7] IEEE 1653.1, IEEE Standard Practices and Requirements for Semiconductor Traction Power Rectifier Transformers [A8] IEEE 1653.2, Draft Standard for Uncontrolled Traction Power Rectifiers [A9] IEEE 1653.3, Draft Standard Wiring Practices and Requirements for Traction Power Metal-Enclosed DC Switchgear [A10] NFPA 70, National Electrical Code [A11] NFPA 70E, Electrical Safety in the Workplace [A12] ANSI/IEEE Std. 902, Maintenance, Operation, and Safety of Industrial and Commercial Power Systems, Standard Techniques for High Voltage Testing [A13] ANSI/IEEE Std. 141, IEEE Recommended Practice for Electrical Power Distribution for Industrial Plants [A14] ANSI/IEEE Std. 142, IEEE Recommended Practice for Grounding of Industrial and Commercial Power Systems [A15] IEEE Std. 242, IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems Plants [A16] J.E .Bowen, M.W Wactor, G.H Miller and M. Capelli-Schellpfeffer, “Catch the Wave”, IEEE Ind. Appl, Mag.,Vol 10, PP 59-67, Jul-Aug, 2004 16 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 [A17] Electrical Safety-Related Work Practices, OSHA 29 CFR 1910 1910.331-335 [A18] Subpart1, Personal Protective Equipment, OSHA 29 CFR 1910,1910.132 [A19] “Design Aspects of Industrial Distribution Systems to Limit Arc Flash Hazard”, J.C.Das, IEEE Transactions on Ind. Appl, vol.41, No.6, Nov/Dec, 2005 17 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 ANNEX B (Informative) B.1 Short Circuit Test B.1.1 General This test may be specified to verify the correct selective tripping sequence of all protective devices in multiple substations service a single line segment in the event of an applied short circuit, and to optimize adjustment of substation protective devices. B.1.2 Test Description With all traction power substations normally connected to the segment under test energized, and the electrical overhead contact system or third rail section configured so that adjacent substations are electrically interconnected (jumper placed across air gap separating adjacent substations), apply a switched connection between the positive and negative current collection points at the track position located midway between two adjacent substations. Obtain digital or analog oscillographic recordings of current and voltage, impulse time, clearing time, and recovery voltage. For safety reasons, remote tripping of dc feeder breakers in all energized substations connected to the line segment under test shall be provided so breakers can be tripped in the event protective devices fail to operate properly. B.1.3 Acceptance Criteria The ac and dc protective relay settings of all energized traction power substations connected to the line segment under test shall achieve the desired relay coordination between protective devices, and shall operate to trip and lockout the appropriate circuit breakers without any adverse event. B.2 Train Starting Test B.2.1 General These tests may be specified in the contract to verify proper operation of the substation ac and dc protective devices, and the performance of the vehicles under test. B.2.2 Test description With all traction power substations normally connected to the line segment under test energized, and all other substations normally connected to the segment under test de-energized, and the electrical overhead contact system or third rail section configured according to contract documents, simultaneously accelerate the maximum number of fully loaded vehicles as specified in the contract documents for normal operation (loaded weight per specification) toward the substation under test. The vehicles shall operate at maximum specified acceleration to attain the 18 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 maximum permitted speed for the area under test, and then brake to a full stop using full service brake. A high resolution chart record of dc feeder current, dc bus voltage and vehicle line voltage shall be obtained. Other measurements such as rail to ground voltage may also be recorded by the authority for the purpose of estimating hazardous contact voltage at the vehicle surface during train starting as well as allowing the authority to estimate the level of stray leakage current for short time intervals. The test shall be conducted with the vehicles starting at a location furthest from the substation under test which would produce the lowest line voltage. The test shall be repeated with the train loading specified in the contract for contingency operation, with one substation energized and all other substations de-energized. The vehicles shall be located at a point furthest from the energized substation which would produce the lowest line voltage. All other parameters of the second test shall be identical to those stated in the first test (normal operation). B.2.3 Acceptance Criteria Traction power substation equipment shall sustain the train currents produced with no indication that substation protective devices have operated improperly, and the train performance shall be within manufacturer specified limits. B.3 Stray Current Structure-to-Earth Voltage Test B.3.1 General These tests may be specified in the contract to verify that adjacent structures located in a predetermined influence area of the dc traction power system experience structure-to-earth potential variations within predefined limits. B.3.2 Description These tests shall be conducted in accordance with IEC 62128-2, Railway Applications – Fixed Installations. B.3.3 Acceptance Criteria DC traction power system operation shall not cause unacceptable loss of the cathodic protection, or cause overprotection on the structure under test as established by the criteria in NACE RP0169-02 and ANSI/NACE RP0502. The criteria for non-cathodically protected structures has to be individually determined by the authority for each structure within the zone of influence of the negative return system. B.4 Running Rail - to - Earth Resistance Test B.4.1 General 19 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change. IEEE P1653.4/D1, November 2009 These tests may be specified in the contract to verify that the negative return rail (track) to earth resistance is not less than the contract-specified value. These tests shall be conducted after track work completion, which forms the return path for train operating current. B.4.2 Description Theses tests shall be conducted in accordance with ASTM G 165-2005 - Standard Practice for Determining Rail-to-Earth Resistance. B.4.3 Acceptance Criteria Acceptance shall be based on the evaluation of what is reasonable for the specified construction (100 Ω per 1000 feet of track, 2 rails in parallel, is used by some authorities). 20 of 20 Copyright (C) 2009 IEEE. All rights reserved. This is an unapproved IEEE Standards Draft, subject to change.