Agenda No. HERTFORDSHIRE COUNTY COUNCIL DEVELOPMENT CONTROL COMMITTEE 5 THURSDAY 27 FEBRUARY 2014, AT 10.00 A.M. EAST HERTS DISTRICT APPLICATION TO EXTEND THE IMPLEMENTATION PERIOD UNTIL 2017 FOR PLANNING PERMISSION 3/0629-06 FOR AN EASTERN EXTENSION FOR SAND AND GRAVEL EXTRACTION AT RICKNEYS QUARRY, HERTFORD, HERTS. Report of the Chief Executive and Director of Environment Author: Iain Leech Tel: 01992 556225 Local Member: Ken Crofton 1. Purpose of Report 1.1 To consider planning application reference 3/2077-13 to extend the implementation period of planning permission 3/0629-06 and accompanying Environmental Statement for an eastern extension to Rickneys Quarry for sand and gravel extraction until 31 December 2017. The committee report for planning permission 3/0629-06 is in Appendix two of this report. 2. Summary 2.1 Planning permission for an eastern extension at Rickneys Quarry to allow sand and gravel extraction was granted in 2009 by Hertfordshire County Council. The permission provided a period of four years (until 31 December 2013) to implement the development. 2.3 Due to the economic downturn, the applicant has not commenced development within that four year period and seeks to extend the implementation period for a further four years until 31 December 2017. 2.4 The application is accompanied by an Environmental Statement and regulations provide that account must be taken of the environmental information in reaching a decision. 2.5 The proposed extension area would measure approximately 10.4 hectares allowing about 1.24 million tonnes of sand and gravel to be extracted. Extraction would occur in four phases with extraction taking between 4 and 5 years to complete with up to 300,000 tonnes of material being extracted per annum. Restoration would be to a low level profile and would not require the importation of any waste or any land filling/raising. CM071 Rickneys extension of time 3/2077-13 1 2.6 A public right of way (Bengeo Footpath 12) that crosses the proposed extraction area would need to be permanently diverted. 2.7 Extraction would be with excavators with the sand and gravel loaded into dumper trucks. The material would then be placed onto a field conveyor that would carry material to the processing plant. 2.8 The proposed hours of operation would be 0700-1800 Monday to Friday and 0700-1300 on Saturdays. The proposed level of extraction would result in an average of 6 lorry loads of material leaving the site every hour during weekdays (12 vehicle movements in total per hour) and 3 per hour on Saturdays (6 vehicle movements per hour in total). A right-hand turn lane would be constructed on the B158 for HGVs to turn into the existing site access. 2.9 During phased extraction the area would be progressively restored to a low level so that as extraction finished on a phase, restoration would commence. 2.10 The site would be restored to woodland, low fertility grassland (a suitable habitat for invertebrates) and agricultural grassland. Two new hedgerows would also be planted, one running north to south through the eastern extension area and one following any diverted public right of way (Bengeo Footpath 12). 2.11 The application site is located within land at Rickneys Quarry which has been identified as a “Preferred Area” for sand and gravel extraction in the Adopted Hertfordshire Mineral Local Plan Review 2002-2016. The inclusion of land at Rickneys Quarry as a Preferred Area was endorsed by an independent Planning Inspector following a Local Plan Inquiry. 2.12 The principal issues to be taken into account are: Green Belt the status of the site as a Preferred Area for future extraction the need for the development, balancing this need against strategic mineral planning policy for mineral supply and any associated detrimental impact of the development; the landscape and visual amenity implications; the potential impact on groundwater resources; potential highway impacts impact on the archaeology and ecology of the area, and; the noise, dust and other environmental impacts of the proposal, including cumulative impact. CM071 Rickneys extension of time 3/2077-13 2 4. Background to Environmental Assessment 4.1 The planning application is accompanied by an Environmental Statement. This is the same as previously submitted except that an up to date ecological survey has been carried out to update the ecology section. 4.2 The Environmental Statement included a technical section with chapters on landscape and visual impact assessment; soils and agricultural impacts; ecology, archaeology, hydrology and hydro-geology; highways and traffic impact; noise; and air quality. Further appendices included extracts from the Minerals Local Plan Review Inquiry Inspector’s report into objections; agricultural land classification report; Annexes to the ecological impact assessment, archaeological desk based assessment, and traffic assessment. 4.3 It also included additional environmental information a revised Transport Assessment (flow diagrams of existing and predicted traffic flows); a revised Noise Assessment (corrected figures in the Noise Assessment and Annexe 1 and an amended assessment of noise sensitive properties); a revised Final Restoration Plan (scheme for the proposed extension area and existing plant area as well as further improvements to previously restored areas to create habitat for wildlife conservation); a revised Ecological Impact Assessment (further analysis of the ecological impacts of the proposal on different species of wildlife with particular regard to protected species including Grizzled Skipper Butterflies, reptiles, dormice and mitigation measures to minimise disturbance to wildlife); an additional Assessment of Reptiles and Dormice (results and analysis of reptile and dormice surveys carried out on site in 2006 [post submission], including mitigation measures); an Archaeological Evaluation (results of the geophysical survey and trial trenching within the proposed extension area); and an assessment of Cumulative Impact (cumulative impacts of other current mineral workings around Hertford, Ware and Welwyn Garden City). An updated ecological survey of the proposed extension area. CM071 Rickneys extension of time 3/2077-13 3 5. Description of the site and proposed development 5.1 Rickneys Quarry is located approximately 3.4km north of Hertford between the village of Chapmore End to the northeast and Bengeo to the south. In addition, there are a number of residential properties within 1km of the site. Planning permission for extraction was originally granted in the 1950s and extraction from the original permitted area ceased in 2001. 5.2 The quarry is located on a plateau between the valleys of the River Beane and River Rib on undulating arable land. The geology is glacial sand and gravel overlying chalk. 5.3 The proposed eastern extension area would measure 10.4ha (25.5 acres) creating a new eastern boundary parallel with Bengeo Footpath 14. Extraction would occur over 4 phases with each phase having two subphases (a and b). Each sub-phase would take between 6 and 8 months to complete with working of the whole extension area taking up to 5 years. Up to 300,000 tonnes of sand and gravel would be extracted per annum with a maximum of approximately 1.24 million tonnes of material being extracted in total. Extracted material would be loaded into dumper trucks, and then transported to the plant site via a conveyor. The existing plant and site infrastructure would be refurbished and a new site office installed. 5.4 Phase 1a of extraction would commence with the stripping of top and subsoils from Phase 1 and 2a. Top soil would be put into two 3m high bunds, one along the eastern boundary and one adjacent to and just south of Bengeo Footpath 12. Sub soil would be stored in a bund on the existing plant site with a maximum height of 5m. Overburden would be used to construct silt lagoons in the plant site. Following full extraction, overburden stripped from Phase 2 would be used to construct a silt lagoon in Phase 1a. 5.5 Extraction of Phase 1b would then start with interburden (mineral waste material) from it being kept to construct a silt lagoon in Phase 1b following extraction. 5.6 Phase 2a would start once Phase 1b had been fully worked. Overburden from it would be placed in Phase 1a as the first stage of progressive restoration. Silting would transfer to the silt lagoon in Phase 1b. A silt lagoon would be created in Phase 2a as working proceeds. A similar pattern of phasing would occur over the rest of the site and details of all of the phasing are set out in Appendix 3. 5.7 Once all extraction had taken place all plant, buildings and hardstanding would then be removed from the site. 5.8 Restoration would be to mixed grassland and woodland. There would be three distinct grassland areas; a low fertility substrate, agricultural grassland and acid grassland. Woodland would be planted to the northwest and southeast of the site to provide links with Flowersash Wood, Bardon Clumps and St. Johns Wood. A band of low fertility substrate would be planted to CM071 Rickneys extension of time 3/2077-13 4 the south of the northwest woodland planting. The remaining western half of the site (including the plant area) would be restored to acid grassland. The eastern half of the site would be restored to agricultural grassland. Two new hedgerows would be planted. One would run north to south from the southeastern corner of Flowersash Wood to St. Johns Wood. The other would follow the diverted Bengeo Footpath 12. 5.9 The proposed hours of operation would be 0700-1800, Monday to Friday and 0700-1300 on Saturdays with no working on Sundays and bank holidays. 5.10 Traffic movements would average 12 per hour on weekdays. The applicant has indicated that there would be peaks of traffic movements in the morning and early evening. There would be approximately 30 traffic movements between 0700 and 0800 and approximately 16 traffic movements between 1700 and 1800 on weekdays. In between these hours there would be an average of approximately 9 traffic movements per hour. Hourly traffic movements on Saturdays would number 3. Vehicle movements would be limited by condition to 130 a day during the week until a right hand turn lane had been brought into use when any limits on vehicle movements would be lifted. 6. Consultations 6.1 East Herts District Council does not object subject to previous conditions being imposed onto any new planning permission. . 6.2 Ware Town Council and Hertford Town Council have not responded. 6.3 Bengeo Rural Parish Council has no comments to make. 6.4 Hertford Civic Society has verbally raised concerns about the impact upon local residents in terms of continued uncertainty as a result of the development not proceeding. 6.5 The Environment Agency does not object but recommends the imposition of an additional condition as follows: No development should take place until a long-term monitoring and maintenance plan in respect of contamination including a timetable of monitoring and submission of reports to the Local Planning Authority, shall be submitted to and approved in writing by the Local Planning Authority. Reports as specified in the approved plan, including details of any necessary contingency action arising from the monitoring, shall be submitted to and approved in writing by the Local Planning Authority. Any necessary contingency measures shall be carried out in accordance with the details in the approved reports. 6.6 Natural England does not object and refers to their standing advice with regards to protected species. CM071 Rickneys extension of time 3/2077-13 5 6.7 Hertfordshire County Council as highway authority has no objections subject to the construction of a right hand turn lane as per the previous requirements. 6.8 The Campaign for Rural England (CPRE) has no comments to make. 6.9 An advert was placed in the Herts Mercury newspaper on 5 December 2013 and a site notice was erected on the same day. A total of 364 properties were consulted on the application and 1 letter objecting to the application was received. The issues of concern can be summarised as: The continuing delay in works commencing causes great uncertainty to local residents and has impacted house prices, sales and is blighting properties. It would extend the period of time to which mineral activities would harm the wellbeing of local residents and by which the local environment would be degraded. 7. Planning Considerations 7.1 The relevant development plan policies are: Hertfordshire Minerals Local Plan Review 2002- 2016 (adopted March 2007) Policy 1 - Aggregates Supply Policy 2 - Need for Mineral Working Policy 3 - Sites for Sand and Gravel Extraction and Preferred Areas Policy 9 - Contribution to Bio-diversity Policy 11 - Cumulative Impact Policy 12 - Landscape Policy 13 - Reclamation Scheme Policy 14 - Afteruse Policy 16 - Transport Policy 17 - General Criteria for the Control of Mineral Development Policy 18 - Operational Criteria for the Control of Mineral Development East Hertfordshire Adopted Local Plan Review 2007 (adopted April 2007) Policy GBC1 - Appropriate development in the Green Belt Policy GBC14 - Landscape Character Other relevant material considerations are: The National Planning Policy Framework Technical Guidance to the National Planning Policy Framework 7.2 The principal issues to be taken into account in determining this application are: Green Belt CM071 Rickneys extension of time 3/2077-13 6 the status of the site as a Preferred Area for future extraction the need for the development, balancing this need against strategic mineral planning policy for mineral supply and any associated detrimental impact of the development; the landscape and visual amenity implications; the potential impact on groundwater resources; potential highway impacts impact on the archaeology and ecology of the area, and; the noise, dust and other environmental impacts of the proposal, including cumulative impact. 7.3 In determining the planning application the County Council should have regard to the provisions of the development plan insofar as they are material to the application and to any other material considerations in accordance with Section 70 of the Town and Country Planning Act 1990 as amended. Section 38(6) of the Town and Country Planning Act 1990 (as amended) further clarifies the considerations for determination of planning applications in that they should be determined in accordance with the development plan unless material considerations indicate otherwise. The development plan should be the starting point then for consideration of the planning application. 7.4 The application is also accompanied by an Environmental Statement and in determining the application the County Council must take account of environmental information. This includes the Environmental Statement and further information submitted as part of the Statement by the applicant, the replies of statutory bodies in respect of consultations required by the Environmental Assessment Regulations and any other replies which relate to the environmental matters. Green Belt 7.5 The NPPF continues the well enshrined principle that there is a presumption against inappropriate development and permission will not be given for such development except in very special circumstances. 7.6 It does however allow certain types of development which (as set out in paragraph 90 of the NPPF) are considered appropriate in the Green Belt subject to preserving openness and not conflicting with the purposes of including land within the Green Belt. 7.7 One such development is mineral extraction which is listed as a form of development that is considered appropriate in the Green Belt. The NPPF also states that minerals can only be worked where they are found. 7.8 The permanent openness of the Green Belt would be preserved as mineral extraction would be a temporary activity for a period of five years. CM071 Rickneys extension of time 3/2077-13 7 Operations would include progressive restoration so that phases would be restored once they had been worked for sand and gravel further reducing the impact of mineral working upon openness of the Green Belt. 7.9 There would be temporary impacts upon openness as a result of top and sub soil storage bunds. These bunds are also necessary to provide visual screening and noise attenuation as well as segregating the workings from users of Bengeo Footpath 14. In addition, they would be relatively modest in height (a maximum of 3m) so would not have any significant impact. 7.10 In addition, mineral processing plant would have an adverse temporary impact upon openness. With regards to processing plant, it should be noted that the former processing plant has been removed from the site and the applicant would be required to submit a further planning application for a mobile processing plant where these matters would be further examined in detail. 7.11 With regards to the five purposes of including land within the Green Belt, the proposed development would not conflict with any of these purposes. As set out in the NPPF, the fundamental aim of Green Belt policy is to prevent urban sprawl by keeping land permanently open. This aim would be achieved. Overall, it is considered that the proposed development would have no permanent adverse impact upon the openness of the Green Belt. 7.12 Nevertheless, there would be temporary harm to the openness of the Green Belt for a period of up to five years. However, it is considered that this harm would be clearly outweighed by very special circumstances associated with the proposal. These would be the economic benefits of mineral extraction both in terms of generating employment at the quarry and providing a supply of sand and gravel to local markets to allow other built development and to support further economic growth. In addition, temporary bunding would provide benefits in terms of noise attenuation and visual screening. Need and the status of the site as a Preferred Area for future extraction 7.13 The application site is identified in Minerals Policy 3 of the adopted Minerals Local Plan Review as one of three preferred areas for mineral extraction. These areas are namely Land at BAe Hatfield, Land adjoining Rickneys Quarry, Hertford and Land at Coursers Road, London Colney. Preferred areas are areas within which there are known sand and gravel resources and where planning permission might reasonably be anticipated, subject to the usual tests of environmental acceptability and if necessary through the use of appropriate conditions to mitigate adverse impacts. 7.14 This proposal at Rickneys covers only part of the Preferred Area, as shown on the Plan attached to the report. Minerals Policy 3 goes on to say: CM071 Rickneys extension of time 3/2077-13 8 “Proposed mineral working within the Preferred Areas defined in this Plan will be permitted only when: they contribute to maintaining the County’s appropriate contribution to local, regional and national aggregate needs, including the maintenance of a land bank in accordance with Mineral Policy 1;” 7.15 Minerals Policy 1 states that “Planning permission for the extraction of proven economic mineral reserves will only be granted where it is necessary to ensure that adequate supplies are available to meet the county’s agreed apportionment of regional supply. The County Council will seek to maintain an appropriate land bank of sand and gravel reserves in accordance with government guidance, throughout the Plan period, consistent with the above apportionment, to enable an appropriate contribution to be made to meet the region’s varying needs.” 7.16 The text accompanying the adopted Minerals Policy 1 states that the Council is committed to ensuring the county meets the regional requirements for primary aggregates supply. The regional apportionment for Hertfordshire has been reduced from 1.99 million tonnes (mt) per annum to 1.39mt by the East of England Aggregates Working Party (AWP) 7.17 Under the current guidance within the NPPF, land banks of at least 7 years should be maintained. This means that at any one time there should be planning permission for at least 9 million tonnes of sand and gravel (7 years x 1.39 mt) unless exceptional circumstances prevail. The NPPF also states that land banks should principally be used as an indicator of the security of aggregate mineral supply. Overall, a mineral planning authority should plan for a steady and adequate supply of minerals. 7.18 The current land bank in Hertfordshire stands at 11.4 years. This includes the contribution of some 1.24mt of sand and gravel to be won from Rickneys Quarry. If Rickneys was not to contribute, the available land bank would fall to some 10.3 years. 7.19 In addition, it is instructive to consider the permitted life and remaining reserves of the sites which currently contribute to the land bank. The current active sites are: Panshanger- .remaining reserves until 2016; Hatfield/Symondshyde- planning permission until 2020; Westmill- planning permission until 2017 although reserves likely to remain after that date and application expected for an extension for mineral extraction until 2020; Tyttenhanger- planning permission until 2032 CM071 Rickneys extension of time 3/2077-13 9 7.20 The current planning application seeks planning permission for a further four year period in which to implement the planning permission for mineral extraction at Rickneys. This would mean that the planning permission would be implemented by the end of 2017at the latest. 7.21 As part of the current legal agreement, there is a requirement for a right hand turn lane to be provided. Furthermore, the applicant is also required to seek planning permission for mobile processing plant. The former plant has been removed from site due to its poor state of repair. It had also become a target for graffiti and vandalism. Taking into account the potential timescales for these matters, it is most likely that the commencement of mineral extraction would occur towards to middle or end of the proposed implementation period. 7.22 This would mean that mineral extraction at Rickneys would replace those sites coming to an end for mineral extraction and would be likely to continue after 2020 by which time three of the above sites would cease to operate. The land bank after 2020 would solely rely upon Tyttenhanger (with permitted reserves of some 7.1 million tonnes) which would mean that the land bank would fall to 5 years and be provided by one site only as things stand. 7.23 No planning application for the final preferred area (BAe at Hatfield) has come forward so any future contribution from this site with regards to reserves and timescales is uncertain. 7.24 Rickneys Quarry would therefore make a valuable contribution to the land bank in Hertfordshire and would mean that the land bank is not bound up only in one site (Tyttenhanger) with regards to competition. 7.25 It is therefore concluded that the proposal meets the requirements of Minerals Policies 1 and 3 a) Planning proposals for Preferred Area 2: Land adjoining Rickneys Quarry 7.26 Minerals Policy 3 goes on to say that: “Proposed mineral working within the Preferred Areas defined in this Plan will be permitted only when: ”the application satisfactorily fulfils the requirements of the Proposals for that Preferred Area as identified with the Inset Maps.” CM071 Rickneys extension of time 3/2077-13 10 7.27 The Proposals are set out fully in the appended original committee report which remain applicable and to which the proposal complies save in one respect. 7.28 This is that the site should ideally be worked earlier in the plan period: the Minerals Local Plan Review was adopted in 2007 and covers a period between 2002 and 2016. It is getting towards the end of the plan period and mineral extraction at Rickneys has not commenced. However, the purpose of specifying when in the plan period preferred sites should come forward is to ensure continuity of available mineral within Hertfordshire. The contribution that Rickneys would make to the land bank has been considered and forms part of the current land bank calculations. There would be an additional benefit in terms of Rickneys being worked in the coming four years as other consented sites and reserves are due to end and a continued supply to meet at least a 7 year land bank is required. Rickneys would assist in providing this. 7.29 In conclusion, therefore, the proposals meet the requirements of Minerals Policy 3 b) However; the proposals also need to satisfy the other relevant policies of the Minerals Local Plan Review. Environmental Impacts 7.30 The former planning application and accompanying environmental statement was subject to detailed consultation and assessment by the County Council as mineral planning authority. The ES was also independently reviewed and found to be complete. Following a resolution to grant planning permission by the Development Control Committee in May 2007, the details of the legal agreement and conditions were the subject of very detailed discussion and negotiation between local residents (as represented by members of the liaison group), the applicant and Hertfordshire County Council. These discussions took place before the issuing of the planning permission in 2009 in order to reach agreement on the precise wording of conditions and the legal agreement. 7.31 Environmental impacts were carefully considered in the previous committee report (appended to this report) and those conclusions are still considered to be valid and are summarised and updated as necessary below. Landscape and visual impact 7.32 The ES includes a landscape and visual impact assessment. This and the assessment in the previous committee report have been reviewed and remain valid. The proposal would accord with Minerals Policy 12 (Landscape) which requires account to be taken of existing and where appropriate, historic landscape character and maintain its distinctiveness. CM071 Rickneys extension of time 3/2077-13 11 Proposals should respect the landscape character both during operations and in proposals for reclamation. 7.33 The application site is located within Landscape Character Area 69 – Stonyhills. It is not considered that the landscape character would be adversely impacted except for a temporary period during mineral extraction. Furthermore, the proposed restoration scheme would assist in meeting the aims of the landscape character assessment for this area which recommends a strategy of “improve and restore”. Restoration would include the replanting and improvement of hedges (to replace one hedge which would be lost) and improve links between habitats in and around the site. 7.34 The location of the proposed development on top of the plateau, together with existing woodland and hedgerows, limits the visual impact of the operations. The main viewpoints would be from rights of way in the vicinity of the site, which are well used by local residents and other users. Other viewpoints with partial views include residential properties and more distant rights of way. Proposed mitigation measures are in terms of screen bunds in accordance with Minerals Policy 18 iv). 7.35 The creation of adequate screening bunds and prompt progressive restoration would be covered by conditions and the proposal would be in accordance with Mineral Local Plan Policy 12 and the general aim of conserving landscapes set out within the NPPF. Groundwater resources 7.36 Hydrology and groundwater matters have been assessed within the ES and were the subject of detailed discussion between the applicant, Veolia Water (formally Three Valleys Water) and the Environment Agency as part of the original application. Neither body objected. It is considered that the assessment remains valid and robust. The application site overlies the ground water source protection zone for the Wades Mill Road water supply borehole There could be the potential for pollutants to enter the underlying ground water particularly with the removal of sand and gravel deposits above the chalk aquifer. 7.37 Mitigation includes leaving 1m of sand and gravel in-situ. 1m of overburden or soils would also be placed above this so that there would be a minimum depth of material of 2m. The Environment Agency has recommended the imposition of an additional condition to any planning permission to require the long term monitoring and maintenance of groundwater for any contamination but have no objection to the proposal. Highway impacts 7.38 Highways and traffic impacts have been assessed within the ES. Hertfordshire County Council as highway authority does not object to the CM071 Rickneys extension of time 3/2077-13 12 proposal subject to the construction of a right hand turn lane on the B158 to access the site. The applicant has given an undertaking that this would be provided in advance of the installation of any processing plant (which would require planning permission in any event), soil stripping or mineral extraction. 7.39 In addition, the applicant has previously submitted draft protocols to be given to all HGV drivers and to be enforced on site in relation to HGVS not passing through Bengeo/Hertford (unless they are delivering mineral to a property in that area) and for dealing with any mud/debris on the B158. These were discussed and agreed as part of detailed liaison group meetings and would remain in place. There is an existing weight restriction on the B158 towards Bengeo which would prevent HGVs going in this direction notwithstanding the draft protocol. 7.40 It is considered that subject to the provision of a right hand turn lane and implementing the protocols described above, that there would be no adverse impact associated with HGV movements in terms of highway safety, highway operation or local amenity and that the proposal would comply with Policy 16 of the Mineral Local Plan. Archaeology 7.41 An archaeological evaluation of the site has been carried out which involved the digging of trial trenches and a geophysical survey of the site following liaison with the Historic Environment Unit. The identification of areas within the proposed extraction area with high and low archaeological potential would inform appropriate mitigation measures during extraction. As such a condition would be attached to any planning permission granted requiring further investigations where deemed necessary of areas considered to have higher archaeological potential and for ongoing monitoring of ground works (including the contingency for the preservation of artefacts). It is considered that the imposition of such a condition would be sufficient to ensure the monitoring and protection of any potential artefacts. Ecology 7.42 The ES includes an ecological assessment and an updated survey of the proposed extension area that took place in 2013 to accompany the current planning application. Minerals Policy 9 (Contribution to Bio diversity) requires that, where appropriate, opportunities should be provided to contribute to bio diversity targets. In addition, the NPPF states that planning authorities should aim to conserve and enhance biodiversity when determining applications. 7.43 The final restoration plan for the site covers both the existing restored areas and the proposed extraction area and would provide an enhancement for biodiversity. In addition, a steering group to oversee restoration and CM071 Rickneys extension of time 3/2077-13 13 aftercare is already set up with a site visit and the next meeting is arranged for May this year. Annual monitoring of butterflies on the restored land takes place by Herts and Middlesex Butterfly Conservation. Additional hedgerow planting has taken place to improve dormouse habitat and to create links between existing blocks of ancient woodland and other habitats also. 7.44 The NPPF advises that planning permission should be refused for development resulting in loss of irreplaceable habitats including ancient woodlands. The application site adjoins three areas of ancient woodland (St. Johns Wood, Bardon Clumps and Flowersash Wood). In light of concerns regarding the risk of mineral extraction hitting a perched water table and thus depriving ancient woodland of water, the applicant has provided an undertaking to monitor these areas of ancient woodland (subject to landowner consent) for any change in flora which could be attributable to mineral operations. This would be secured by condition. 7.45 It is considered that the proposed restoration scheme would assist in enhancing biodiversity and meet the aims of Mineral Local Plan Policy 9 and the NPPF. Noise 7.46 Minerals Policy 18 viii) of the Minerals Local Plan Review states that proposals for mineral extraction must demonstrate that no significant noise intrusion would arise from the development. The NPPF requires the setting if noise limits and the control, mitigation or removal of unavoidable noise emissions. 7.47 This application was accompanied by a noise survey which measured existing background noise levels. The survey indicates that predicted noise levels of quarry working would be below the maximum acceptable daytime noise levels of 55dB (recommended in the NPPF Technical Annexe). The highest predicted noise levels at Rickneys Barns would be 46.2 dB LAeq (excluding bund construction. It is considered that the noise survey remains valid and robust and there have been no changes to the noise climate in and around the application site with regards to existing back ground noise levels. 7.48 Taking into account the close proximity of workings to Rickneys Barn Conversions, it was previously and is still considered appropriate for a condition to be imposed limiting noise levels to no more than 5dB above background levels and in any event not more than 55dB LAeq except during soil stripping operations when a higher limit of 70 dB would be allowed but only for a total period of 8 weeks over a year. A noise monitoring scheme has previously been submitted and agreed by the liaison group and by the mineral planning authority and the implementation of this scheme would be secured by condition. CM071 Rickneys extension of time 3/2077-13 14 Dust 7.49 Minerals Policy 18 ix) requires that proposals should demonstrate that there would be no significant degradation of the air quality. A dust assessment was submitted as part of the application. This concluded that any adverse impacts of dust associated with the application would be low. A dust monitoring and management scheme has been submitted by the applicant and has been agreed by the liaison group and by the mineral planning authority. The implementation of this scheme would be secured by condition. Wheel washing/spinning facilities would also be in place in accordance with Minerals Policy 18 xi). Rights of Way 7.50 Minerals Policy 18 x) requires that proposals should ensure that public rights of way are not adversely affected or, where this is not possible, that good quality, safe and convenient temporary alternative provision is made and long-term reinstatement or suitable replacement of rights of way is secured. Proposals should enhance the public rights of way network through the creation of new rights of way and/or open space, or the improvement of public access 7.51 Only Bengeo Footpath 12 would be physically affected by the proposed development. During Phases 4a and 4b the footpath would be permanently diverted through Phase 2a (as restored). The applicant has advised that if there were delays with restoration of Phase 2a that there could be a delay with creating a new diversion so that for a time Bengeo Footpath 12 would not be in place either in its current designated position or as diverted. 7.52 It could therefore be unavailable for a period of time. However, alternative routes would remain available to rights of way users so it is not considered that they would be unduly disadvantaged and it would be for a temporary period only. Users of Bengeo Footpath 14 would be segregated from the workings by a screening bund. 7.53 Some rights of way improvements on the existing network have been provided by the applicant already and are obligations within the existing legal agreement. These are the upgrading of a short section of Bengeo Footpath 12 to bridleway with a new dedicated bridleway link to BOAT 22. Hertford Footpaths 6 and 7 have also been upgraded to bridleway. A painted traffic table and warning signs would be put onto the haul road where Bengeo Footpath 14 crosses it. The applicant has also installed a footpath link between the entrance to Footpath 6 along the quarry side of Sacombe Road to the residential properties opposite the eastern end of Vicarage Lane. Cumulative Impact 7.54 Minerals Policy 11 (cumulative impact) states that development which would result in an unacceptable cumulative impact on the environment of an area CM071 Rickneys extension of time 3/2077-13 15 either in relation to an individual proposal having regard to the collective effects of different impacts or in relation to the effects of a number of minerals developments occurring either concurrently or successively will not be permitted. Consequently, impacts that are acceptable individually should not be regarded as an acceptable in combination without a proper assessment. 7.55 The supporting text to Minerals Policy 11 indicates that regard should be had to cumulative impacts of simultaneous and/or successive working of a number of sites in a wider area of commercially viable deposits as these may affect communities and localities over an extended period depending on the nature age and size of the sites. Cumulative impacts will therefore be considered in terms of their spatial and temporal dimensions, as well as acceptability or otherwise of the impacts arising from the proposed development itself. This will take into account the extent to which the environment could be impacted on by workings including habitats and species, landscape character, cultural heritage, air quality, ground and surface water resources and quality, agricultural resources and flood risk. 7.56 The proposal is for a projected four to five years working and restoration of both the new workings and those of the existing plant site. Whilst the existing site has not been fully restored no extraction has taken place within the site for the past 5 - 6 years. The previous mineral workings at Rickneys started in the late 1950s and continued until 2001; thereafter the quarry has been dormant. The main considerations in this instance are the cumulative impacts of a number of minerals operations occurring at once in and around Hertford and also the cumulative impact that the working of Rickneys Quarry and other sites in the area has had on the local area since extraction first commenced. 7.57 The nearest other active sand and gravel quarry to the proposed site is Westmill Quarry on the A602. It is approximately 1.7km from Rickneys. At this distance, it would be very unlikely that airborne dust from one site would be carried towards the other and contribute to dust levels in that locality. In addition Westmill Quarry has dust suppression measures in operation and Rickneys Quarry would also have dust suppression measures in place as described above. 7.58 Considering the distance between the two sites, the existing background noise levels, topography and intervening buildings and vegetation that would act as barriers, it would be very unlikely that the noise of operations at either site would carry a sufficient distance for them both to be audible from any location. 8. Conclusions CM071 Rickneys extension of time 3/2077-13 16 8.1 It is not considered that there has been any significant change in planning policy or other change in circumstance since the original planning application was determined to warrant refusal of the application to extend the implementation period for a further four years. Consideration has been given to the environmental statement and the assessment of potential environmental impacts previously. This analysis remains valid except where updated elsewhere in this report with the conclusion that subject to mitigation as set out within the conditions that these could be adequately controlled so as not to have any adverse impact. 8.2 The NPPF advises that great weight should be given to the benefits of mineral extraction including to the economy. Rickneys is designated as a preferred area and is necessary to contribute to the land bank in Hertfordshire. 8.3 The proposed eastern extension is located within a Preferred Area for mineral extraction as identified in the Adopted Minerals Local Plan Review. There is a need for the mineral to contribute to the county’s agreed subregional apportionment for land-won sand and gravel and for the maintenance of a mineral land bank in Hertfordshire. 8.4 The extension would cover a relatively small area and operations would occur over a relatively short time period over which the extraction area would be progressively restored. It is considered that the proposal, together with appropriate conditions and a legal agreement, would adequately mitigate any adverse environmental impacts. 8.5 The NPPF advises that mineral extraction is appropriate development within the Green Belt. Nevertheless, there would be a temporary adverse impact upon openness. However, this temporary impact would be clearly outweighed by very special circumstances in the form of the provision of a steady supply of sand and gravel and associated economic benefits including supporting further economic growth. The proposal would not have any permanent adverse impact upon the openness of the Green Belt. 8.6 Having taken into account the environmental information submitted with the application and that arising from consultation, the report concludes that subject to the conclusion of a legal agreement to reflect the obligations contained in the existing Section 106 agreement, planning permission should be granted subject to conditions as set out below in Appendix 1. Background information used by the author in compiling this report Planning application reference 3/0629-06 and accompanying Environmental Statement Consultee responses and representations Relevant policy documents Hertfordshire County Council Structure Plan Review Minerals Local Plan Review Adopted 2007 East Hertfordshire Adopted Local Plan Review 2007 CM071 Rickneys extension of time 3/2077-13 17 Appendix 1 - Conditions Time Limit for Commencement. 1. Written notification of commencement of the first work or works required by the development hereby permitted shall be sent to the Minerals Planning Authority at least seven calendar days prior to their commencement. Reason: To define the date by which all pre-development requirements specified in this schedule shall have been satisfied and at which the development hereby permitted shall be deemed to have been commenced for all purposes other than those detailed in Condition 2. 2. Written notification of the date when the winning and working of minerals has begun shall be sent to the Minerals Planning Authority not later than seven calendar days subsequent to that date, which, for the purposes only of Sections 91 and 94 of the Town and Country Planning Act 1990 as amended, shall be deemed to be the date of commencement of the permitted development and shall be not later than the expiration of a period of three years beginning with the date of this permission. Reason: To comply with the requirements of Sections 91 and 94 of the Town and County Planning Act 1990 as amended, in particular, by Regulation 3 and the Schedule of the Town and Country Planning (Minerals) Regulations 1995. Time Limit for Completion: 3. The development to which this planning permission relates shall be completed within 6 years of the date of the commencement of the development as notified under Condition 2. For the purposes of this condition this shall include all operations authorised or required by the permission including site restoration but shall exclude those relating to aftercare. Reason: To ensure that the restoration of the land to a beneficial afteruse is achieved within a reasonable timescale. Limit of Operations: 4. The development hereby permitted shall, except where modified by this Schedule of Conditions and associated legal agreement, be undertaken in accordance with the provisions of: a) the planning application dated 27 February 2006; b) Environmental Statement dated February 2006; c) Ecological Impact Assessment dated January 2007; d) drawings reference: Plan 1– Site Location Plan (February 2006) Plan 2 – Site Context Plan (February 2006) Plan 3 – Existing Site Layout (February 2006) Plans 4 to 7 – Phase 1 to 4 Working Plans (February 2006) Plan 9 – Final Restoration Plan (January 2007) CM071 Rickneys extension of time 3/2077-13 18 e) f) g) h) i) j) k) Plan B3/1 – Proposed Eastern Extension Phase 1 Habitat Survey (February 2006) Noise Assessment dated September 2008; Code of Operating Practice and Emergency Response Procedure between Hanson Aggregates and Three Valleys Water Company (now Veolia Water Central Ltd) dated 1st May 2009 or any subsequent variation; Code of Practice regarding measures to remove any spillage on the highway dated October 2008 or any subsequent variation; Code of Practice regarding traffic routeing measures dated October 2008 or any subsequent variation; Protocol for Heavy Goods Vehicles using B158; and Woodland Evaluation and Monitoring Report dated June 2009 or any subsequent variation Letter of Undertaking dated 23 November 2009 titled “Undertaking of Regarding the Timing of the Construction of a Right Hand Turn Lane – Rickneys Quarry”. Reason: To ensure that an orderly programme of operations is carried out in such a way that the adverse effects on local amenity are kept to a minimum. Pre-Development Requirements: 5. The development to which this planning permission relates shall not commence until the details required by conditions 6, 13, 14 19, 37, 39 and 48 have been submitted to and approved by the Mineral Planning Authority, and the development shall be carried out in accordance with those approved details. Reason: To ensure that an orderly programme of operations is carried out in such a way that the adverse effects on local amenity are kept to a minimum. 6. No soil stripping shall take place within the proposed development site until the applicant, or their agents, or their successors in title, has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation, which has been submitted to the Minerals Planning Authority and approved in writing. The approved scheme shall be implemented in full. Reason: To enable sites of archaeological interest to be adequately investigated and recorded. Previous investigations have revealed the presence of important archaeological remains within the application site. Landscaping: 7. All trees, hedges and shrubs planted shall be maintained throughout the duration of the operations permitted by this permission or for a period of five years, whichever is the longer. Any tree, shrub, bush or hedgerow which, within 5 years of planting dies, is removed or becomes seriously damaged or diseased shall be replaced with others of a similar species within the first available planting season. Reason: To comply with Section 197 of the Town and Country Planning Act 1990, to improve the appearance of the site in the interest of visual amenity, to screen the workings, and assist in absorbing the site back into the local landscape. 8. Existing trees, bushes and hedgerows not identified to be removed as stated in CM071 Rickneys extension of time 3/2077-13 19 the Ecological Impact Assessment (dated January 2007) and Plan B3/1 (Proposed Eastern Extension Phase 1 Habitat Survey) shall be protected from damage, which, without prejudice to the foregoing, shall involve preventing disturbance to soil levels within the root spread of a tree or hedgerow and provide for the erection of protective fencing around trees affected by works in accordance with BS 5837 (1991). The means of protection shall be retained until all plant, equipment and surplus material have been permanently removed from that phase of working. Nothing shall be stored or placed within any protected area as identified above and the ground levels within these areas shall not be altered without the prior written agreement of the Mineral Planning Authority. Reason: In order to ensure that the possibility of damage to the retained trees, shrubs and hedges is minimised in the interests of amenity. 9. Prior to the commencement of extraction, a written scheme for the annual monitoring of the condition of St. Johns Wood, Flowersash Wood and Bardon Clumps shall be submitted to and approved in writing by the Mineral Planning Authority. The approved scheme shall be implemented in full. Reason: To assess the risk of damage arising from the development hereby permitted to areas of ancient woodland. Restriction of permitted Development Rights. 10. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development Order) 1995 or any order amending, replacing or reenacting that order, planning permission shall be obtained from the Mineral Planning Authority for the erection of any processing plant, building, fixed plant, fixed machinery or fixed structures at the site. Prior approval in writing shall be obtained from the Mineral Planning Authority for the placing of any other portable buildings or structures1. Reason: To enable the Mineral Planning Authority to assess any impact and proposed mitigation or control compared to the original proposal as identified in the submitted Environmental Statement and Impact Assessment. Local Amenity Safeguards: 11. Unless otherwise agreed in writing in advance by the Mineral Planning Authority, no operations at the site, other than water pumping, servicing, environmental monitoring and maintenance of plant and equipment, shall be carried out except between 07.00 hours and 18.00 hours Monday to Friday; Unless otherwise approved in writing in advance by the Mineral Planning Authority, no operations at the site with the above exceptions, shall take place on Sundays or Public Holidays. Any such approval will require the prior submission by the operator of a written scheme of work which shall be implemented in full. Any such approval may be revoked by the Mineral Planning Authority where, in its opinion, there has been a breach of the terms of the approved scheme. 1 This restriction does not apply to the use of machinery necessary for the removal of overburden, extraction and distribution of sand and gravel and restoration works. CM071 Rickneys extension of time 3/2077-13 20 Reason: To minimise the adverse impact of operations on the surrounding area in terms of noise, associated traffic generated and general disturbance. 12. The operator shall ensure at all times that areas outside of the boundary of the site are not affected by dust nuisance resulting from the development hereby permitted. A meeting shall be held with the Mineral Planning Authority by 31 March in each year to review all operations giving rise to dust emissions and consider any required amendments to the scheme to be approved under Condition 14. Reason: To minimise the adverse impact of dust generated by the operations. 13. No stripping or spreading of overburden, topsoil or subsoil, including the construction of soil mounds, shall take place when the wind speed at the site equals or exceeds 28 knots. Prior to any stripping or spreading of overburden, topsoil or subsoil taking place an anemometer shall be installed at the site and maintained throughout the duration of the development hereby permitted in accordance with details which shall have been submitted to and approved in writing by the Mineral Planning Authority. Reason: To minimise the adverse impact of dust generated by the operations. 14. Monitoring of dust shall be carried out in accordance with a Scheme and Programme for the Monitoring of dust to be submitted to and approved in writing by the Mineral Planning Authority prior to the commencement of the development. The approved scheme shall be implemented in full. Reason: To minimise the adverse impact of dust generated by the operations on the local community. CM071 Rickneys extension of time 3/2077-13 21 Noise: 15. During the hours of operation as defined in Condition 11, except for temporary operations (defined as site preparation; soil stripping; bund formation and removal; and restoration), the noise levels arising from the development shall not exceed the LA90 (1hour) values (measured when the site is not operational) at any noise-sensitive property by more than 5dB(A) and shall not in any event exceed 55dB (LAeq) (1 hour), freefield2 at any noise-sensitive property. Reason: To minimise the adverse impact of noise generated by the operations on the nearest noise-sensitive properties. 16. For temporary operations as defined in Condition 15, the noise levels arising from the development shall not exceed 70dB(LAeq) (I hour), freefield at any noise-sensitive property. Such temporary operations shall not exceed a total of forty days in any period of twelve consecutive months. Reason: To minimise the adverse impact of noise generated by the operations. 17. No temporary operations as defined in Condition 15 shall take place until the Mineral Planning Authority and Bengeo Rural Parish Council have been given notice. Notice shall be given at the earliest opportunity and in any event not less than 2 clear working days before any proposed temporary operation is to begin. Temporary operations shall be carried out only during the normal hours of work (See Condition 11) between Monday to Friday. A log of all dates and duration of temporary operations shall be kept and be available for inspection by the Mineral Planning Authority at the site office. Reason: To minimise the adverse impact of noise generated by the operations. 18. Effective sound insulation shall be employed for all plant and machinery utilised on the site. All vehicles, plant and machinery shall be maintained to manufacturers’ specifications at all times. Any reversing alarms fitted to machinery and vehicles utilised for on-site works shall be to a specification agreed in writing by the Mineral Planning Authority prior to their use. Operational practices will, so far as is practicable, avoid the need for all other vehicles to reverse on site. Reason: To minimise the adverse impact of noise generated by the operations on the local community. 19. 2 Prior to the commencement of development, a written scheme for monitoring noise levels arising from the site shall be submitted to and approved by the Mineral Planning Authority. The scheme shall provide for an annual review of the scheme by 31 March each year to consider any required amendments to the scheme and identify the monitoring points for the following year. The approved scheme shall be implemented in full. For the purposes of Condition 15, freefield is defined as being at least 3.3 metres away from the façade of a property or building at a height of 1.5 metres. CM071 Rickneys extension of time 3/2077-13 22 The locations for monitoring during the first 12 months of operations on site, including preparatory works shall be as follows: Position 1: At the SE corner of the Rickneys Barn Conversion Position 2: At the mid-point of the NE boundary of Waterworks Cottage Position 3: At the NE corner of the intersection between the highway and the access lane to the residential development at Bull’s Mill. Position 4: At the most southerly point of built development on the NW side of Chapmore End Position 5: At the NE corner of the Sports Ground at Crouchfield Position 6: At the boundary between No 164 Sacombe Road and the former workings Position 7: At the SE corner of the intersection of the Orchard with Sacombe Road. Reason: To enable the effects of the development to be adequately monitored during the course of the operations. Water Resources: 20. Any chemical or fuel storage containers on the site shall be sited on an impervious surface with bund walls; the bunded areas shall be covered to exclude the ingress of rainwater and be capable of containing 110% of the container’s or containers’ total volume and shall enclose within their curtilage all fill and draw pipes, vents, gauges and sight glasses. There shall be no drain through the bund floor or walls. Reason: To minimise the risk of pollution of watercourses and aquifers. 21. Repair, maintenance and refuelling of plant and machinery shall only take place in accordance with the Code of Operating Practice and Emergency Response Procedure between Hanson Aggregates and Three Valleys Water Company dated 1st May 2009 or any subsequent variation Reason: To minimise the risk of pollution of watercourses and aquifers. 22. No herbicides or pesticides shall be used on site until written details of their use have been submitted to and approved in writing by the Mineral Planning Authority. Reason: To prevent pollution to the water environment. 23. A minimum of 1 metre of undisturbed material shall be left in place above the surface of the chalk and a minimum of 1m of overburden shall be reinstated above this in accordance with mitigation measures as set out in paragraph 4.9.5 of the Environmental Statement dated February 2006. In the event that the chalk is exposed then all operations shall be temporarily suspended until the remedial measures necessary to enable operations to continue in a safe manner have been approved by the Mineral Planning Authority. Reason: To protect the ground water environment 24. No development should take place until a long-term monitoring and CM071 Rickneys extension of time 3/2077-13 23 maintenance plan in respect of contamination including a timetable of monitoring and submission of reports to the Local Planning Authority, shall be submitted to and approved in writing by the Local Planning Authority. Reports as specified in the approved plan, including details of any necessary contingency action arising from the monitoring, shall be submitted to and approved in writing by the Local Planning Authority. Any necessary contingency measures shall be carried out in accordance with the details in the approved reports. Reason: To ensure the protection of groundwater. The site is located within 350m of the Wadesmill Public Water Supply. The proposed activity on site will reduce the protection of the underlying Chalk aquifer to make it more vulnerable to surface contamination. Soil Handling, Stripping and Storage. 25. No topsoil, subsoil or overburden shall be removed from the site. Reason: To ensure that all soils and restoration materials are retained for use on site to achieve the best possible standards of restoration. 26. No topsoil or subsoil stripping shall take place until the Mineral Planning Authority has been given at least 7 days and not more, than 21 days notice in writing of any proposed topsoil stripping operations. Reason: To ensure that soils and restoration material are handled and stored in such a way as to minimise compaction and damage to soil structure in order to achieve the best possible standard of restoration. 27. No plant or vehicles shall cross any area of unstripped topsoil or exposed subsoil except where such trafficking is essential and unavoidable for the purposes of undertaking the permitted operations. Essential trafficking routes shall be marked in such a manner as to give effect to this condition. No part of the site shall be excavated or traversed or used for a road or for the stationing of plant and buildings, or storage of subsoils or overburden until all available topsoil and subsoil has been stripped separately to its full depth from that part. The exception is that topsoils may be stored on like topsoils and subsoils may be stored on like subsoils. Reason: To prevent unnecessary trafficking of soil be heavy equipment and vehicles to achieve the best possible standard of restoration. 28. Soil stripping shall not commence on any phase until any standing crop or vegetation has been cut and removed. Reason: To avoid incorporation of concentrations of decaying vegetation in soils. 29. Topsoil and subsoil shall be stripped only when they are in a dry and friable condition. No movement of soils shall occur: a) during the period 1 October to 31 March inclusive, unless, prior to such movement commencing, the Mineral Planning Authority agrees in writing that the movement of soils can take place satisfactorily within this period; b) when any material part of the soils or sub-soils to be stripped has a moisture content which is equal to or greater than that at which the soil becomes CM071 Rickneys extension of time 3/2077-13 24 plastic, tested in accordance with the ‘Worm Test’ as set out in BS 1377 (1975) – ‘British Standard Methods Test for Soils for Civil Engineering Purposes’. Reason: To ensure that soils and other restoration material are handled and stored in such a way as to achieve the best possible standard of restoration and to minimise compaction and damage to the soil. 30. Soil bunds which are to be stored for over 12 months shall be constructed with a slightly domed top and shall be seeded with an appropriate grass seed mixture unless otherwise agreed in writing by the Mineral Planning Authority. Cutting or spraying of soil bunds shall be undertaken as necessary to prevent the build up of a seed bank of weeds3 or their dispersal onto adjoining land4. Reason: In the interests of amenity 31. Unless otherwise agreed in writing by the Mineral Planning Authority, no topsoil stockpiles shall exceed 3 metres in height and no subsoil stockpiles shall exceed 5 metres in height. Reason: To ensure that soils and restoration material are handled and stored in such a way as to minimise compaction and damage to soil structure in order to achieve the best possible standard of restoration and ensure that the site intrudes visually as little as possible into the local landscape when operations are taking place. Aftercare: 32. A written scheme of aftercare shall be submitted to and approved in writing by the Mineral Planning Authority prior to the commencement of the restoration of Phase 1a of the development hereby permitted. The scheme shall specify the steps as may be required to achieve and maintain the required standard of land for the approved after use and shall include the following matters :i. seeding and planting; ii. cultivation practices; iii. remedial treatments; iv. field drainage system; v. weed control, and; vi. provision for site meetings on at least an annual basis with officers of the Mineral Planning Authority and any relevant consultee in order to assess the progress to date, any remedial action required, and the management of the restored areas for the following year. The steps referred to above shall be carried out during the period of 5 years following the first cultivation, seeding or initial tree, shrub or hedge planting of each phase of the restoration. The approved scheme shall be implemented in full. Reason: To ensure that the best standard of aftercare management of the site is carried out following restoration. For the purposes of Condition 29 the definition of ‘weeds’ is listed in Schedule 9 part 2 of the Wildlife and Countryside Act 1981 and The Weeds Act 1959. 4 See also Condition 40 regarding limitations with regard to cutting and spraying 3 CM071 Rickneys extension of time 3/2077-13 25 33. A detailed annual programme of aftercare shall be submitted in writing prior to the annual aftercare meeting referred to in Condition 31 vi). This shall include a report on the previous year's aftercare; and the detailed programme for the forthcoming year's work and confirm or modify the original proposals. The first detailed programme shall be submitted with the overall scheme required to be submitted pursuant to Condition 30. If required by the Mineral Planning Authority, a revised aftercare scheme shall be submitted to the Mineral Planning Authority in writing within four weeks of the annual site meeting. Any approved revised scheme shall be implemented in full Reason: To ensure that the best standard of after-care management of the site is carried out following restoration. 34. Unless otherwise agreed in writing in advance by the Mineral Planning Authority, all excavated sand and gravel shall be transported to the processing plant by conveyor5. These conveyors shall be located in accordance with a scheme to be submitted to and approved in writing by the Mineral Planning Authority prior to the commencement of extraction. Reason: To minimise the adverse impact of operations on the local community in terms of visual intrusion, noise and dust. 35. No vehicles shall enter the public highway unless their wheels and chassis have been cleaned to prevent material, including sand, mud and debris, being deposited on the public highway. Reason: In the interests of highway safety and to prevent mud and dust getting on the highway. 36. Prior to the commencement of mineral extraction, written details for the relocation of the access gates and for signage instructing vehicles leaving the site that there is no right turn onto the B158 shall be submitted to and approved in writing by the Mineral Planning Authority. The approved proposals shall be implemented in full prior to any export of aggregates. Reason: In the interests of highway safety and to prevent vehicles queuing on the public highway. 5 For the purposes of this condition it is accepted that excavated material shall initially be loaded by the excavator onto dumper trucks for transfer to the conveyor hopper. CM071 Rickneys extension of time 3/2077-13 26 37. All laden lorries entering and exiting the site shall be sheeted. Reason: In the interests of highway safety and safeguarding the amenities of local residents. 38. Details of the areas to be reserved for parking cars and lorries upon the site, including proposed surfacing and drainage shall be submitted to the Minerals Planning Authority for approval before operations commence, and no permanent development, whether or not permitted by the Town and Country Planning (General Permitted Development Order) 1995 or any order amending, replacing or re-enacting that order, shall be carried out upon these areas or so as to preclude access to them. Reason: To minimise the adverse impact of operations. 39. The surfacing of the internal site access road between the B158 Road and the plant site shall be maintained in a good state of repair and kept clean and free of mud and other debris at all times until the completion of site restoration. Reason: In the interests of highway safety Ecology: 40. No operations (including soil stripping) shall commence on the site until full surveys of reptiles and butterflies have been carried out by a suitably qualified person and submitted to and approved in writing by the Mineral Planning Authority. Reason: To ensure that protected species are protected from the effects of the development. 41. The use of herbicides or pesticides or the carrying out of any mowing, cutting, crop removal, or soil stripping on any phase shall have due regard for the presence of breeding birds. If breeding birds are found on any area to be sprayed, mown, cut, or stripped, then spraying, mowing, cutting, or stripping of that area must be postponed until after breeding has ceased for that season. Reason: To ensure that breeding birds are not disturbed by the effects of the development. 42. No removal or cutting back of trees, shrubs, hedges and dense ground cover (brambles) shall take place unless otherwise agreed in writing in advance by the Mineral Planning Authority. Reason: To ensure fauna and flora are protected during the development. 43. A watching brief shall be maintained to check for the presence of badgers and their setts during all operations. Reason: To ensure that badgers are not disturbed from the effects of the development. CM071 Rickneys extension of time 3/2077-13 27 Restoration: 44. Unless otherwise agreed in writing by the Mineral Planning Authority, no material shall be imported onto the site. Reason: To ensure operations are conducted in accordance with the approved scheme. 45. Each right of way, existing, diverted or newly created within the area of the development hereby permitted, shall be clearly signposted including showing the status of the right of way. Each diversion or new path shall be clearly shown on a plan which shall be maintained and kept up to date at all times and shall be located at the boundary of the site at the point/s where the right of way enters the permitted area. Unless otherwise agreed in writing by the Mineral Planning Authority, immediately following completion of restoration (excluding aftercare) any diverted right of way shall be reinstated to its original line and length and be safe and fit for the public to pass and re-pass along its entire route. Reason: To ensure that existing rights of way are fully protected and that rights of way users are not endangered. 46. Prior to the commencement of any operations within 50 metres of a right of way, safeguards, which shall include suitable fencing, to protect persons using the public right of way shall be made. No public right of way within the permitted area shall be obstructed or its surface damaged in any way. Reason: To ensure that existing rights of way are fully protected and that rights of way users are not endangered. Miscellaneous: 47. The applicant shall submit a written report to the Mineral Planning Authority at the end of each calendar year or upon completion of a phase of restoration, whichever is the sooner, detailing progress of extraction and restoration of the site. This report shall include: i. a drawing indicating existing as built site levels related to Ordnance Datum identifying all significant features and boundary details, including the extent of operations and any restored areas of the site; ii. confirmation of the methodology employed in any restoration, soil placement or treatment for any completed phases; iii. details of the volume of extracted material from the site during the year, and; iv. the area stripped of topsoil and subsoil; v. the location of each soil storage mound; vi. the quantity and nature of the material therein. vii. an estimation of whether the practical implementation of the approved restoration scheme is capable of being achieved and whether the development is likely to be completed within the timescales predicted in the application. Reason: To enable the Mineral Planning Authority to review the position in respect of the restoration at the site, to assess whether final restoration is likely to be completed as required by of this schedule and to ensure operations are carried out in a comprehensive and phased manner. CM071 Rickneys extension of time 3/2077-13 28 48. No floodlights shall be used on site without the prior written agreement of the Mineral Planning Authority on the design, location, luminescence and direction of each light. Reason: To safeguard public safety and minimise the risk of environmental pollution. 49. Precautions shall be taken at all times to prevent unauthorised access to the site. No part of the development hereby permitted shall be commenced until a scheme to manage nuisance from motorised vehicles has been submitted to and approved in writing by the Mineral Planning Authority. The approved scheme shall be implemented in full. Reason: To minimise the adverse effects on the local amenity. 50. All machinery, buildings, plant, haul roads and accesses no longer required in connection with the operations or future agricultural use of land, shall be removed from the land within twelve months of the completion of final restoration and the land restored in accordance with the provisions of this planning permission. Reason: To improve the appearance and visual amenity of the areas and minimise the adverse effects on local amenity. 51. The Applicant or their successor in title will continue to attend liaison meetings in accordance with the existing procedure throughout the life of operations, restoration and aftercare of the site. Reason: To ensure ongoing communication between the applicant, HCC and the local community. 52. A copy of these conditions and any schemes referred to within this consent and submitted and approved pursuant to this consent shall be displayed in the site office and the contents shall be made known to any persons given responsibility for operational management and control. Reason: To ensure that an orderly programme of operations is carried out in such a manner to ensure that any adverse effects on local amenity are kept to a minimum. CM071 Rickneys extension of time 3/2077-13 29