FAST Project Annual Report 2009 I. Summary of FAST project development in 2009 1. Conceptual design optimization Leaded by the project manager department, the FAST project has undertaken a series of optimization works of the conceptual design based on experimental studies during 2009 in order to provide technical support for the construction of large scale engineering systems, including the later phase of detailed measurement of the telescope site, survey and construction; manufacture of the reflector elements and actuator prototypes; design optimization of the feed support towers and primary cable support system; photography measurement; early science studies, Sino-England-Australia tripartite international cooperation on receivers design, etc. These optimization works will reduce the cost of the FAST project and improve the operability of the technology. 2. Completion of detailed site survey May 14 of 2009 marked the official launch of the tender process for the FAST site survey. Following the procedure of tender award, opening and evaluation, the Institute for Construction Engineering Exploration of Guizhou (GZCEI) was finally selected as the tender for the detailed survey of the FAST construction site. From August 6 to November 24, 2009, a total of 111 days, GZCEI completed 204 borehole drilling and the total drilling footage reached 6426 meters. On December 30, 2009, a final report of the detailed land survey was formally submitted to the FAST project. 3. The land use procedures In December 2009, FAST’s application for the usage of forest land was approved by the State Forestry Administration, and a related application was also approved by the National Land Agency of Guizhou. In December 2009, an application for construction land use was submitted to the Ministry of Land and Resources. 4. Construction of the local access road In August 2009, drawing design for the FAST site local access road was contracted to the Qiannan Transportation Design Institute. In October 2009, the road survey and measurement were completed; On December 18, construction drawing design and budget plan were completed and successfully passed the design review chaired by the Department of Transportation of Qiannan; In December 2009, the Department of Transportation of Qiannan was appointed as the construction owner’s agent to start the early phase of construction preparation. 5. Logistic construction Under the guidance of the Project Coordination Office, the Institute of Science of Guizhou University was contracted to build an office building for FAST project in Guizhou in August 2009. By December 2009 the main building was completed and can now provide office space and accommodation to FAST staff. 1 Concerning the poor working and living environment at the telescope site Daiwodang, the project management is actively preparing the construction of an on-site office building for the FAST project. By the end of 2009, site preparation for the construction was roughly completed. In January and February 2010, the ground cement layout and fencing wall had been completed. As a plan, all the construction work is expected be finished by early April 2010. II. Major research works 1. NSFC key project “Giant radio telescope (FAST) design and key technology study" (Grant number: 10433020) passed the acceptance review on March 13. 2. Key directional project of CAS intellectual innovation program“Experimental study of FAST key technology” (Grant number: 10433020) has been successfully completed and is now waiting for acceptance review. 3. Statistics of scientific publications Number of SCI papers 8 Number of EI papers 1 Citations Papers published domestically Number of patents 9 4 14 III. Major development of individual sub-system FAST project consists of seven technological sub-systems, namely: 1. site survey and construction; 2. site civil engineering; 3. mechanical and electrical system; 4. structure system; 5. feed support system; 6. measurement and control system; 7. receiver and back-end system. 1. Site survey and construction system Major developments include: successful completion of detailed survey work for FAST project; optimization of the construction center, test and remap of the 1:1000 topographic map; ground penetrating radar exploration of the foundation of the feed support towers (started on 30 November 2009, completed on 20 December 2009). Figure 1 Photos of the detailed survey at the site 2 2. Site civil engineering system 2.1 Application for construction land use: measurement and mapping of the boundary, multi-term evaluation and demonstration, and completing the reports. 2.2 Design of the local access road: geological mapping, construction drawing design and budget planning, initiating the construction and tender for supervision. 3. Mechanical and electrical system 3.1 Theoretical and technological study Major works include: optimization of the design of the reflector element, optimization of the structure of the reflector cable network and the force in the cables, numerical simulation of the wind environment of FAST, analysis of the “solar oven effect” of FAST, design of the actuator prototypes, design of the test platform for testing the cable tension, calculation of the position of the ground anchor points at the site. 3.2 Prototype testing and manufacturing Major works include: manufacture and test of aluminium reflector element prototypes, manufacture and test of actuators and test platform, manufacture of the support frame of the reflector element, manufacture of the ground anchor for the site, manufacture of various nodes and sample steel structures. Figure 2 The prototype of the aluminium reflector 4. Structure system Major works include: study of the scheme for large zenith angle position switching, ground anchor testing, study of the back frame, study of the seismic resistance of the cable network structure, study of fatigue behaviour of the cable network, numerical simulation of the wind environment, sensitivity analysis of inhomogeneous temperature field, etc. 5. Feed support system 5.1 The development of the integrated feed support system on the Miyun demonstrator was completed. 5.2 Design work for the real scale 500-meter telescope, which includes: mountain spot survey and optimization of the tower base, design of the support towers, design of the cable driving system, design of the cabin and fine-tune platform. 3 Figure 3 Integrated 6-tower model of the Miyun Feed support demonstrator 6.Measurement and control system 6.1 Technological study This mainly includes: design of the fiducial network and global positioning system (GPS) experiment; experiment of the orientation measurement of the feed support unit; experiment of the cabin cable damping; API (automated precision incorporation) experiments; global network control of the Miyun demonstrator; measurement of the reflector element shape; dynamic measurement of the reflector. 6.2 Domestic and International Cooperation October 22.2009, cooperation framework agreement between NAOC and Automated Precision Incorporation (API) was signed. July 22, 2009, collaboration agreement with USTC (university of science and technology of China) was successfully completed. 7. Receiver and back-end system 7.1 Study of the L-band multi-beam receiver front-end The Sino-England-Australia cooperation continues in 2009—a tripartite tele-conference was held in April 2009. A plan for studying the wide band feed array was initiated, and a related research contract was being prepared. This contract was finally signed in October 2009. 7.2 Manufacture of low frequency feed 7.3 Vacuum cryogenic system 7.4 Low frequency digital transmission by optical fibers 4 7.5 Time and frequency system 7.6 Design of the digital back-end IV. Research team and personnel training The total number of staffs The number of senior staff The number of intermediate staff The number of junior staff Others Graduated Masters postgraduate student Postdoc 68 36 10 12 10 5 15 3 V.International cooperation 1. Actively seeking the support from the government. Working hard to attract foreign talents. In year 2009, FAST project invited a total of 9 foreign experts for research visits through the talent recruitment project of CAS. Six seminars were given by foreign guests. On July 1st, 2009, a three-members delegation from South Africa visited NAOC and discussed the key technologies of large radio telescopes with related FAST staff. On November 24-26, 2009, “FAST structural design and experiment discussion and advisory conference” was held at NAOC. The Experts made many valuable suggestions, which provide good reference for the follow-up optimization study of FAST. 2. Using the strategy of “going out and invite in”, extensive contacts have been established, and substantial exchange and cooperation have been promoted. There were two international joint research programs in 2009: (1) the cooperative framework arrangement between FAST and the US company API on measurement solution and related instrument development. The two sides will cooperate in the design of real time dynamic measurement solutions as well as in the development of corresponding instruments for the FAST telescope; (2) In October, 2009, cooperation agreement between FAST and Australia’s Commonwealth Scientific and Industrial Research Organization (CSIRO) on the design of feed array/polarizer was signed, in which the two sides will cooperate in the design of low frequency feeds. Both of these two agreements are now on –going. 3. Actively participating in international cooperation and promoting publicity The chief engineer of FAST project Nan Ren-Dong chaired the radio astronomy division of international astronomical union (IAU) in 2006-2009. This is the first time for a Chinese astronomer to take position at this level. Dr. Peng Bo worked as a member of the executive committee of square kilometer array (SKA) for the term 1999-2011. In 2009, FAST staff visited abroad for a total of 13 person-times, in which 2 person-times were for cooperative researches, 7 person-times were for international conferences, and 4 person-times were for study visits. Through these cooperation activities in various channels, the influence of FAST project was promoted. On July 19, 2009, the American Journal “Science” once again reported 5 the progress of NAOC’s FAST project. VI. Events 2009.3.13 Acceptance review meeting of the national natural science foundation key project; 2009.8.19 First work meeting of the Office of FAST Project Management; 2009.10.22 Cooperation framework agreement between NAOC and automated precision incorporation (API) was signed; 2009.11.24 Discussion and advisory meeting on FAST structure design; 2009.12.8 On-site acceptance review meeting of the detailed survey of FAST telescope site. VII. Contact National astronomical observatories, Chinese academy of sciences 500-meter aperture spherical radio telescope (FAST) Mailing address: Da Tun road A 20, Chao Yang district, Beijing Zip code: 100012 Homepage: http://www.bao.ac.cn/bao/LT/ Contact: Liu Na, nliu@bao.ac.cn VIII. Editorial board and editors in charge Editors in charge: Liu Na, Zhang Haiyan, Zhu Ming Editorial Board: Zhang Shuxin 6