ENVIRONMENT COMMITTEE 26 MARCH 2008 ITEM 05 ANNEXE 3 KITCHEN WASTE, CARDBOARD AND PLASTIC BOTTLE RECYCLING: MITIGATION OF RISK Risk Uncertain capacity requirements Mitigation Strategy The number of vehicles and staff required to deliver any waste collection configuration is a function of: Vehicle capacity; Material tonnages; Travel time between pickups; Pickup cycle times; Tipping time. Some of these variables can be assessed in advance. For example vehicle capacity (although capacity in tonnes will vary with the density of material); tipping time (assuming the tipping place is known) and travel time between pickups. The pickup cycle is performed many times per day. This means that minor changes in process can impact significantly on the overall time required to complete a round and the potential impact of such changes requires careful thought. Forecasting collection tonnages becomes progressively more demanding as the number of materials collected separately for recycling increases. A higher tonnage can mean more trips to tip and ultimately more vehicles and staff. A trip to tip is triggered by the first compartment to fill There is also a feedback to crew morale since a well motivated crew will get more done. Several strategies are being used to manage the uncertainties: Using loaned demonstrator vehicles to measure capacity in the local operating environment; Building in a margin of spare capacity by way of vehicles and staff although because of the expense this option is used sparingly; Isolating and measuring some risks upfront for example trade waste and flat collections; Page 1 of 4 ENVIRONMENT COMMITTEE 26 MARCH 2008 Risk ITEM 05 ANNEXE 3 Mitigation Strategy Undertaking what if calculations to measure the impact on vehicle needs of various levels of participation; Developing contingency plans to bring on board additional capacity quickly if necessary. Residents could react against the new service configuration in particular the need to sort more materials and to accommodate additional containers. Resident dissatisfaction The following approach is being taken to minimise this risk: Minimise change by keeping to current collection days, garden waste and dry recycling arrangements; Using the residents’ panel to test perceptions; Using an exhibition to communicate the need for change, the advantages and disadvantages of different service configurations and container choices Communicating during the roll out Maintaining a weekly collection of kitchen waste and nappies; Providing choices where it is practical so to do Non availability of vehicles The major risk areas are: No acceptable tenders are received No one is able to supply a vehicle of the required specification; The vehicles are not available by start up date. The contract has been advertised and a list of potential suppliers drawn up. If the Council is not satisfied with the tender returns the choices would include: Retender on the current or an amended basis (with an almost inevitable delay to the service start); Negotiation with the current supplier of the service; The kerbside collection of kitchen waste is in its infancy although rapid growth is inevitable if national recycling and composting targets are to be met. Vehicle manufacturers are developing Page 2 of 4 ENVIRONMENT COMMITTEE 26 MARCH 2008 Risk ITEM 05 ANNEXE 3 Mitigation Strategy new vehicle types to meet the emerging needs but these not yet widely available. The vehicles that we have had on loan have struggled in a real operating environment to accommodate tonnages that match their advertised capacity. If this remains the case there is a risk that sufficient capacity will not be available from the proposed vehicles. The Council will need to be satisfied that the vehicles proposed by the suppliers offer sufficient capacity. However the provision for a spare vehicle offers some protection against this uncertainty. The vehicle supply industry builds specialist vehicles to order. There is therefore a risk that they will not be available for start up. Non availability of containers The officers have sought to manage this risk by including: A six month build time between the award and start of contract (30 April ‘08 to 31 Oct ‘08); A 4 month float between the projected date of delivery and service launch day (1 Nov ‘08 to 28 Feb ‘09). The containers cannot be ordered until the conclusion of the exhibitions (31 October ‘08). This allows 2.5 months for manufacture before delivery is due to commence. Discussion with suppliers suggests this is an adequate period but unforeseen events could place it at risk. In practice only part of the container order needs to be available by mid Jan ‘08. Half the order does not need to be supplied until mid March and some of the containers needed for phase one will not be required on the first delivery date. Insufficient management capacity The delivery of the project will fall primarily on operational services with customer services and communications also having key roles. The various work streams and the deployment of resources need to be properly planned and resourced. A strategic project team will be established and there is provision within the set up costs for additional staff resources for implementation. Page 3 of 4 ENVIRONMENT COMMITTEE 26 MARCH 2008 ITEM 05 ANNEXE 3 Risk Loss of income from paper Mitigation Strategy Contingency plans to deal with the unforeseen absence of critical team members will be put in place. Currently the Council receives £39 per tonne as a gate fee for paper. By 2009-10 it is estimated that income from paper could exceed £140,000 per annum. However this income could be at risk if residents were to mix paper with cardboard on a significant scale. This would mean that paper would enter the mixed cardboard/plastic bottles collection, to which attaches a cost of £30 per tonne. To mitigate this risk the communications plan will include clear messages as to the importance of a clean paper stream to service costs. The development of bulking facilities to enable the Council to command higher gate fees for dry recyclables by selling materials in larger quantities could also offset this risk. It is estimated that additional gate fees of up to £200,000 pa could be achievable although there would be capital and handling costs. It is intended to investigate these opportunities in more detail. Page 4 of 4