Land Acquisition Policy Framework

advertisement
LAND ACQUISITION POLICY FRAMEWORK
FOR THE BULGARIA: MUNICIPAL INFRASTRUCTURE DEVELOPMENT - P099895
1.
The purpose of the Land Acquisition Policy Framework (PF) is to clarify land acquisition
principles, together with organizational arrangements under the Bulgaria Municipal
Infrastructure Development Project (MIDP). The proposed project objective is to improve the
provision of water and wastewater supply.
2.
This objective will be met through the following components:
Component 1: Project Implementation Support
Component 2: Technical Services to prepare Master Plans in [48] water and wastewater
utilities
Component 3: Completion of three water supply dams – Luda Yana, Neikovtsi, and
Plovdivtsi – and rehabilitation of the Studena dam that is currently operational which
supplies water to the town of Pernik
3.
Component 1 will provide support to project implementation and management.
Component 3 will support investment, which may require acquisition of land for the dam
construction, reservoir and/or sanitary belts surrounding the reservoir. Because the nature and
design of the rehabilitation works of Component 3 are not known before appraisal, the zone of
impact of the constructions or the precise sitting alignments and areas to be included within the
reservoirs and sanitary belts cannot be determined either. Therefore, the Government of Bulgaria
hereby submits a Land Acquisition Policy Framework [LAPF] consistent with the World Bank
O.P 4.12 on Involuntary Resettlement, as a condition of appraisal. For the successive
investments to be carried out and financed by the Bank, specific land acquisition plans consistent
with the principles included in this LAPF will be submitted to the Bank for approval when
detailed investment planning information and the scope of the civil works becomes available.
4.
Component 2 will support Technical Services to help identify investment priorities for
water supply and waste water management for Municipal Water Companies. The outputs of TA
under Component 2 are expected to be only at a pre-feasibility level of detail, with feasibility
studies, detailed designs and investment to follow later and be financed separately, possibly with
assistance from EU. However, the TA provided under Component 2 involves preparation of site
assessments including specific recommendations for siting of facilities which if implemented
could involve expropriation of land. The TA will therefore provide all information needed to
apply the processes outlined in this Policy Framework to the acquisition of any such land. The
World Bank has reviewed the Terms of Reference for TA under Component 2 to ensure that this
aspect is appropriately addressed. Based on this understanding, the LAPF applies to Component
2.
5.
The Policy Framework covers the following elements, consistent with the provisions
described in the World Bank Policy, OP 4.12 on Involuntary Resettlement:
(i) Activities for which land acquisition is required
1
(a) Expropriation of land
6.
As indicated before, the design, siting, scope of the works and other details for the
investments are not known in advance. The design for the specific investment will be determined
during implementation. Land that has been or may in future need to be expropriated includes the
site of the dams, their respective reservoir areas, and the area of the sanitary zones of Belt 1 (see
below) where land use restrictions are sufficiently stringent that it has been determined these
areas should become state property. The bulk of the land required for the main dam wall, dam
lakes and corresponding submerged area, ancillary structures and adjacent infrastructure has
previously been acquired by the Government of Bulgaria in the years 1978-1982, 1986, and
1998-2000.
At the previous stage of construction designs for sanitary zones were prepared for Neikovtzi and
Plovdivtzi dams and the lands within Belt I have also been expropriated. As the design for the
sanitary zones at Luda Yana dam is yet to be prepared, at this stage it is not clear if additional
lands should be expropriated. Considering, however, that the land expropriated for Luda Yana
currently exceeds the projected size of the dam cup, and the fact that the reservoir is likely to be
smaller than originally planned as the new design will no longer include provision for irrigation
of 6,300 hectares, it is unlikely that additional expropriation will be needed. However, in the
unlikely event that additional land is needed, expropriation will be done in accordance with the
LAPF. The additional land acquisition supported under the Project is expected to be relatively
minor, such as construction of ancillary structures including a water purification plant at Luda
Yana dam,. Based on the available data it is not expected that any additional expropriation of
land for will be required for Neikovtzi dam.
7.
Any expropriation of land required for or directly linked to the dams will be carried out
following well-established procedures specified in Bulgarian laws and procedures relating to
land purchase and expropriation and World Bank Operational Policy (OP) 4.12 and Bank
Procedures (BP) 4.12 on Involuntary Resettlement. Wherever Bulgarian Laws and World Bank
policies are not in agreement, the principles agreed upon in the LAPF will be followed (as
further specified in the following sections). However, the total value of compensation provided
for any expropriation in any case should not be less than the amount which the individual or
household would receive under the Government’s legal framework for land restitution and
expropriation. It should be noted that no displacement of population is expected at any of the
three sites.
8. According to the Agricultural land Ownership and Use Act 1991, and the Act Restoring
Ownership on Forests and Forest Stock Land Tracts form the Forestry Fund, 1997, the last
date for people to initiate claims for restitution of agricultural or forest land was May 14,
2007. Therefore, this LAPF does not include provisions for addressing new claims of
ownership of land required for construction or operation of the three dams or is otherwise
linked with the project. However, the LAPF does cover any cases in which the initial claim
was made prior to this deadline and in accordance with the law, but which have not yet been
resolved. This may include one known case in the vicinity of Plovdivtzi dam, concerning
land which was claimed by the heirs of a Mr. Sinapov. There is one known case in which
some land parcels were restituted to claimants under a court judgment and an expropriation
process was initiated in 1998, but because the State failed to provide the details of the dam
2
project to be added to the map of restored properties, it was not possible to determine
whether the land fell within the area required for the dam. If the detailed design indicates
that any of this land falls within the reservoir or within SSA belts any expropriation that is
required will be carried out in accordance with this LAPF. (see next section),
(b) Restriction of land use or access
9.
Under OP 4.12, restrictions on access to land or on use of land are regarded as a form of
land acquisition. Bulgarian law provides for some restrictions of the activities within the
sanitary zones, depending on their proximity to the dam site. The design and setting up of the
sanitary zones shall be performed in accordance with the relevant Bulgarian law (Water Act,
Public Health Act and Ordinance N 3 of 16.10.2000 on the Conditions and Procedures for
studying, planning, approving and exploiting Sanitary and Protection Zones neighbouring water
sources and drinking and household water supply facilities and mineral water sources used for
treatment, prevention, drinking and hygiene purposes). As noted above, the strongest restrictions
are imposed on the activities in the sanitary zones of belt I which should become public state
property (expropriation). Land use and access restrictions in Belts II and III are more limited
and are not considered equivalent to expropriation. Under this LAPF, such restrictions will be
treated as loss of assets and income in the context of OP 4.12: i.e., the corresponding
compensation amount at replacement cost will be determined based on a process of negotiation
with the affected people and will be of a size sufficient to restore their livelihoods that are
adversely affected.
(ii) Principles and objectives governing land acquisition
10.
For civil works associated with MIDP, it is likely that there is need for limited acquisition
and this may result in the loss of land and perhaps the loss of sources of income. Loss of shelter
is highly unlikely as people are not expected to lose their residences or other structures.
11.
The premise governing the LAPF is that land acquisition may cause hardship and
impoverishment, and therefore where it is not feasible to avoid land acquisition, project affected
persons (PAPs) will consulted and compensated and assisted in their efforts to improve or restore
their livelihoods and standards of living to levels prevailing prior to the beginning of project
implementation. To support this objective, the following principles will apply:

During the sub-project preparation process, consideration of technical options shall
involve a concurrent assessment of potential associated land acquisition impacts, so that,
where feasible, design alternatives to minimize such impacts can be identified as early as
possible.

Consultation arrangements during the project sub-component preparation process shall be
transparent and inclusive to ensure that all persons affected by involuntary land
acquisition are consulted on the mitigation measures.

Compensation for lost assets shall be provided before land and other assets are taken into
possession.
(iii) Legal framework reviewing the fit between Bulgarian laws and regulations and World
Bank OP 4.12 requirements, and measures proposed to bridge any gaps between them,
and description of entitlements
3
12.
Bulgaria does not have a single expropriation law. Rather there are several legislative acts
governing the expropriation process. These laws and ordinances include the Law on Ownership,
State Property Act, Municipal Property Act, Spatial Development Act, Code of Civil Procedure
and Ordinance for the order of establishing prices of agricultural lands. These together define the
procedures for expropriation of immovable property in Bulgaria. The expropriation of private
properties is done only for a public interest and with fair compensation.
13.
Prior to land acquisition, the investor submits proposals to the Committee on Agricultural
Lands at the Ministry of Agriculture and Forests for approval of the design and likely change in
land use. Simultaneously, licensed assessors begin the process of property evaluation to assess
compensation amounts. The expropriation proposal is then submitted to the Minister of Finance
and the Minister of Regional Development and Public Works, who jointly submit the proposal to
the Council of Ministers (CoM). Simultaneously with the submission of the proposal for
expropriation to the Council of Ministers, the copies of the expropriation proposal are mailed to
the concerned Municipalities who announce it immediately. The Mayor of the respective
Municipality also informs the potentially affected persons the proposal for expropriation. After
the Council of Ministers decrees a decision on the proposal, appeals by interested owners are
allowed to be submitted at the Supreme Administrative Court within 14 days after the
publication of the information in the State Gazette. The investor of the project makes the
payment of the compensation amounts into accounts of affected individuals at a commercial
bank. The investor also announces the action in two national and one local newspaper. The
Bulgarian procedures provide for information to the local governments and the people likely to
be affected by a particular project.
14.
Under the Project, in addition to the mailing of the expropriation proposal to the Mayor
by the investor, the PIU will take supplemental measures to ensure that all affected people are
notified in a timely way regarding their lands that are expected to be expropriated. In addition,
under the Project, the Government of Bulgaria will allow appeals by interested owners to be
submitted to the Supreme Administrative Court within 30 days after the Council of Ministers
decrees a decision on the proposal.
15.
The amount of compensation is determined with the help of qualified property
assessment experts for urban and rural lands. For rural areas, where there is no active land
market, the offer price for land is calculated based on a situation-specific formula that takes into
account the market value of the affected property (as published by the MoA), and includes
coefficients to improve the market price depending on the size and quality of the estate;
existence of irrigation systems; distance from basic markets; distance from the coastal line of the
Black sea or from the end of the beach strip; and the distance urban zones and bordering roads
with permanent cover. The market value of the asset determined in conjunction with the State
Property Act (STA) and paid as compensation to affected persons. The World Bank policy
requires compensation for land to be at “replacement value,” enabling the affected person to
purchase land of equivalent area and quality in the vicinity. Under the project, the Government
of Bulgaria will appoint an independent valuator to review the Government’s valuation method
and the resulting proposed offer prices for the first 15 expropriation cases to determine whether
they correspond to this principle of “replacement value.” If this review indicates they do not, the
valuation methodology applied to expropriation associated with the project will be revised to
correct the discrepancy.
4
16.
Loss of Income: It should also be noted that less than 10-20% of an individual’s land
holding is expected to be adversely affected by the land acquisition process for the project –
therefore, no significant loss of income is expected and impacts can be generally considered to
be minor. However, if PAPs suffer loss of income through loss of more than 20% of their land
holding, income restoration assistance will be provided if required, despite the fact that
Bulgarian law does not call for this. This will take the form of “Rehabilitation Assistance”
meaning assistance comprising job placement, job training, cash compensation, transition
support or other forms of support to enable displaced persons, who have lost their source of
livelihood as a result of the displacement, to improve or at least restore their income levels and
standard of living to pre-project levels.
17.
Loss of Structures: It is not expected that there will be any residential or other structures
that will need to be acquired in the project site. However, in the event that there are structures
(barns, kiosks, small commercial buildings etc.,) that will need to be demolished, “depreciation”
will not be considered in calculating the compensation payable for affected structures. Although
this differs from the provisions of Bulgarian law, the affected people will be compensated at a
level enabling them to replace their structures."
18.
Bans and Restrictions on Sanitary Zones: Under the legislation currently in force, belt І
of Sanitary and Security Area around the dams comprises “the aquatic area from the dam wall up
to a distance of 1000 m. from the water collecting facility against the stream, as well as a 50 m
large strip from the boundary of the water site”. As mentioned elsewhere, these lands for belt I
may need to be expropriated for the Luda Yana though it is not very likely, but not for Plovdivtzi
or Neykovtzi sites as they have already been expropriated. The lands falling under belt ІІ and
belt ІІІ are not subject to expropriation; however, some bans and restrictions on carrying out
certain activities that are likely to have negative impacts on the water source, have been
established. These include in the case of Neykovtzi, the managing of private animal farm, falling
within the SSA belt ІІ; the managing of three chalets, falling within SSA belt ІІІ, creating new
cemeteries etc,. According to data provided by the Municipality of Rudozem and Plovdivtzi
county, the establishment of belt ІІ and belt ІІІ of Plovdivtzi Dam SSA will not result in bans or
restrictions on activities. The restrictions in Luda Yana belts II and III are not yet known. The
compensation for the expropriation of the lands in the innermost belt, Belt I, will be carried out
as per the details set out in the Policy Framework .In Bulgaria, people adversely affected by land
use restrictions in Belts II and III shall be compensated for loss of profits according to the
procedures laid down by the Minister of the Regional Development and Public Works and the
Minister of Environment and Waters; people who have restrictions imposed on farming and
related activities shall be compensated according to a methodology for the evaluation of the
compensation for lost profits deriving from restricted application of agrochemicals in the SSA,
which shall be established by the Minister of Agriculture and Food Supply. Under this project,
these restrictions on land use on Belts II and III on all dam sites will be treated as loss of assets
and income triggering the Bank’s Policy on Involuntary Resettlement and the corresponding
compensation amount at replacement cost will be determined based on a process of negotiation
with the affected people and will be of a size sufficient to restore their livelihoods that are
adversely affected.
5
19.
Informal Land Use: During the field survey carried on 24, 25 and 26 October 2007 the
following forms of informal use of the land in the dam sites have been identified:

Luda Yana dam: during the whole year, except for the winter season, the dam site is used
for grazing of approximately 50 cows, each of them owned by a separate household from
the residential neighborhood of an individual in the Municipality of Panagiurishte. All
the owners of the cattle have assigned the grazing to a single shepherd. The same
households also use the dam site as a year-round pasture for their goats and sheep. The
number of goats and sheep varies but during the period of most intense grazing it reaches
60 sheep (a single flock) and 60 goats distributed into 2 herds (one comprising 20 goats
and the other – 40). The dam site is used by the cattle as a direct road to the municipal
common designated for grazing and located in the area of Tarnov dol, which is not
affected by the project. After the dam site is submerged, the cattle could be grazed at the
above mentioned common but the road to it will be extended by approximately 500
meters. Approximately 46 000 000 m2 of pastures and commons are located at the
territory of Panagiurishte Municipality, representing 18% of its entire agriculture fund.
After the dam site is submerged, the cattle owners will have at their disposal other
pastures and commons to meet the grazing needs. The Office of the Mayor of the
Panagiurishte Municipality has confirmed that that after the dam site is submerged, the
cattle owners will have at their disposal other pastures and commons to meet the grazing
needs. See Attachment 1.

Neikovtzi dam: the dam site is covered with construction materials and normally it is not
used for agriculture purposes. As an exception, one of the local people uses the site for
incidental grazing of his 4 sheep. Another local resident is grazing his 3 cows at a
location approximately 1 km above the dam site. The relevant municipality has agreed
that alternative land for grazing will be provided. See Attachment 2.

Plovdivtzi dam: the dam site is used for grazing of 12 cows, 14 goats and 4 sheep, owned
by a total of 10 households. The cows are normally immobilized in a barn and the hay
mowed from the dam site is being brought to them. The mowing season covers the
period from June to September-October. Normally the goats and sheep graze every day
or every other day. Some of the interviewees said that a great part of the grass at the site
is being mowed to restrict the risk of fire rather than for breeding purposes. Most of the
cattle owners are not worried by the future submerging as they have enough land to
support the grazing needs. One of the informal users, however, explicitly stated that he
cannot continue to support his livestock (1 cow, 2 goats and 3 sheep) once the dam site is
submerged. However, no information was provided as to why the alternative land that
will be provided by the municipality cannot be used for the livestock. The relevant
municipality has agreed that alternative land for grazing will be provided. See
Attachment 3.
20. The informal use of land in the 3 dam site is limited to grazing. The involved households
are using the cattle breeding as a support to their main source of income, but it is not their main
form of livelihood. The shepherds of the herds and flocks at Luda Yana dam, for whom the
grazing of cattle is their main profession, will have the opportunity to continue their activity
even after the land is submerged as Panagiurishte Municipality have enough grazing zones.
6
21.
While the World Bank OP 4.12 embodies the principle that a lack of legal land title does
not disqualify people from resettlement assistance, under relevant Bulgarian legislation,
discrepancies with this principle arise. However, as mentioned above, within the scope of this
project, informal users of land without title or lease who use the land for temporary or seasonal
purposes such as grazing will be entitled to alternative spaces for grazing. All informal users of
land in the Sanitary Belts will also be entitled under the Project to rehabilitation assistance or
some form of support to enable affected persons, who have lost their source of livelihood, to
restore their income levels to pre-project levels.
22.
However, the government wants to prevent false claims for assistance appearing after
disclosure of project plans. Therefore, October 26, 2007 [the last date of the survey] has been
chosen as a cut-off date after which any person carrying out illegal/ informal activities in the area
is not eligible to receive any assistance as a result of project activities. This cut-off date is the
date the consultants carried out the land-use survey to examine public lands allocated for the
project for evidence of private use. Additionally, the Government has also a photographic file
showing the current conditions in all three dams.
(iv) Eligibility and entitlements
23.
The following entitlement matrix describes the eligibility for compensation and/or
assistance for impacts/losses for different types of assets and categories of project affected
persons, applicable to the dam area and sanitary zones.
Table 1: ENTITLEMENT MATRIX
ASSET
ACQUIRED
ENTITLE
TYPE OF IMPACT D
PERSON


AGRICULTU
RAL LAND/
MEADOW
LAND

Less than 70%
of land holding
affected,
The remaining
land remains
economically
viable
More than 70%
of land holding
affected and
remaining land
is not viable
COMPENSATION ENTITLEMENT

Cash compensation for affected land
determined in conjunction with SPA such
that it is equal to the replacement cost of
the lost asset

Rehabilitation assistance such as job
placement, skills training and/or use of
alternative land/property to re-establish use
such as grazing

Cash compensation for the assets at their
replacement value plus Assistance
comprising costs of shifting, allowance
until first harvest, cash compensation, job
placement, or job training, transition
allowance etc,.
Owner/title
holder
User of
land
without
title
Owner/title
holder
7
ASSET
ACQUIRED
ENTITLE
TYPE OF IMPACT D
PERSON
COMPENSATION ENTITLEMENT

Rehabilitation assistance such as job
placement, skills training and/or use of of
alternative land/property to re-establish use
such as grazing

Cash compensation for entire structure and
other fixed assets without depreciation
Right to salvage materials without
deduction from compensation
Rehabilitation assistance if required
(assistance with job placement, skills
training)
User of
land
without
title
BUILDINGS

Entire structure
affected

STANDING
CROPS
Crops affected by
land acquisition or
temporary
acquisition or
easement
Owner
TREES
Trees lost
Owner
TEMPORAR
Y
ACQUISITIO
N
Temporary
acquisition

Cash compensation equivalent to the
market value for the affected crops

Cash compensation based on type, age and
productive value of affected trees
Cash compensation for any assets affected
(e.g. boundary wall demolished, trees
removed)

Owner

LAND
Bans and
restrictions on
activities in
Sanitary Zones II
and III
Owner
User of
land
without
title


Compensation for loss of assets at
replacement cost
Cash compensation for loss of income
Rehabilitation assistance such as job
placement, skills training and/or use of
alternative land/property to re-establish use
such as grazing
(v) Mechanisms for consultations
24. In addition to documenting the expropriation procedures indicated above, once the scope of the
civil works is identified, the concerned Municipality and other institutions will hold public
consultations to discuss the expropriation and its implications, to which all land users whose lands
will be affected by the expropriation will be invited. The PIU will also take the lead in ensuring that
consultations are held with affected people and not entirely transfer the responsibility to the
concerned Municipalities. The content and results of the consultation will be recorded in Minutes
that are maintained in the sub-project files and made available to the Project Implementation Unit
8
PIU) and the Bank team. The Government of Bulgaria under the Project will supplement the
expropriation notification procedure by extending the period of appeals regarding the compensation
amount by affected people from 14 days to 30 days.
(vi) Description of the implementation process and Arrangements for funding land acquisition
25.
For civil works activity that requires land acquisition, a specific Resettlement/ Land
Acquisition Action Plan will be prepared and submitted to the Bank for approval. The
implementation of land acquisition activities will be linked to the implementation of the civil works
to ensure that acquisition of land or other assets does not occur before the payment of compensation
is made or other activities have been carried out. To repeat, land and related assets will be taken only
after compensation has been paid.
26.
The overall responsibility for expropriation for the Project is under the Bulgarian
government represented by the Council of Ministers as well as the financial responsibility for
expropriation. Allocation of relevant funds will be envisaged during budget preparation. The
Minister of Finance and the Minister of Regional Development and Public Works are responsible for
submitting of the expropriation documentation required by Bulgarian Law on expropriation.
Following the budget preparation procedure, the MoF should envisage the necessary funds in the
budget of Ministry of Regional Development and Public Works for expropriation procedure.
27.
The decision for expropriation is taken by the Council of Ministers and the procedure is
as follows:

The proposal for expropriation is prepared by the Ministry of Regional Development and
Public Works (MRDPW);

The Minister of Finance and the Minister of Regional Development submit the proposal
to the Council of Ministers, which decree a decision;

The Decision Decree is published in the State Gazette. After that it can be appealed in the
court. In case the decision decreed is not appealed in the court within the statutory time, it
enters into force and can be implemented;

Otherwise after the court passes judgment on the lodged complaint, the respective court
order should be implemented.
28.
The Minister of Regional Development and Public Works is responsible for following up
and concluding of the expropriation procedures which include payment of compensation as well.
The Minister of Finance in accordance to the Law follows up whether the request for expropriation
is financially secured. The decision will also specify the authority that will bear the cost of the
expropriation expenditures. MRDPW is responsible for the legal aspect of the expropriation request.
The land acquisition transfer must be fully completed, and payment made, before any work can
begin on the expropriated or acquired property. According to the Bulgarian legislation no civil works
can start unless expropriation and compensation procedures have been completed. The land can be
considered as expropriated from the moment of transfer of the compensation that is due to the
affected parties.
(vii) Responsible Institutions and/or Agencies
9
29.
The key activities and responsible actors in the planning and implementation of the
specific Land Acquisition Plan are outlined in the table below:
LAND ACQUISITION ACTIVITY
RESPONSIBLE AUTHORITY
Assessment of Impacts & Inventory of Ministry of Regional Development
Losses, including consultations
and Public Works (MRDPW) and PIU
Census of PAPs (socio-eco info), MRDPW and PIU
including consultations
Drafting the Land Acquisition Plan
MRDPW and PIU
Valuation of Assets
MRDPW assigns to Licensed
Independent valuation experts
Consultations with PAPs
MRDPW and the Mayor of the
respective municipality and PIU
Payment of Compensation and MRDPW
Relocation Assistance
(as
cash
transferred to Bank Accounts or in a
public setting)
Expropriation of land and assets
Council of Ministers
Monitoring and Evaluation
MRDPW and PIU
(viii) Grievance Redressal Mechanisms
30.
The Expropriation Laws provide for an appeals process against the proposed award for
compensation. The PIU staff also play an advisory and facilitating role in resolving grievances.
Grievances related to land acquisition impacts should be pursued at the municipality/ community
level with facilitation by PIU staff together with design consultants in order to find technical
solutions that avoid or further minimize the need for land acquisition. Solutions to grievances
related to compensation amounts, delays in compensation payments should be pursued directly
by the designated authorities in liaison with the PIU staff who will inform PAPs about the
avenues for grievance redress, and will maintain a record of grievances received, and the result
of attempts to resolve them (Annex 1). This information will be entered into the Management
Information System (MIS) and be included in the regular progress reporting.
(ix) Process for preparing and approving Land Acquisition Plan and arrangements for
monitoring
31.
The PIU on the basis of completed and approved design including the Parcel Layout Plan
for Land Acquisition will prepare a site-specific Land Acquisition Plan for all the expropriation
required for the ancillary works in all 3 dams and/ or other activities and submit it for Bank
review at least 6 months prior to commencing physical works. The Plan will include details
about any prior steps taken, such as notification or consultation with owners, and description of
the land acquisition process and mitigation measures. The Resettlement / Land Acquisition Plan
will cover the following:
10

A census of persons affected by involuntary land acquisition including an inventory of
lost assets and valuation of these, and socio-economic data.

Description of the compensation to be provided

Minutes of the public consultations with affected/persons

Institutional responsibility for implementation and procedures for grievance redress

Arrangements for monitoring and implementation

A time-bound implementation plan and budget.
32.
This will be submitted to the Bank for review and approval. The implementation of the
Land Acquisition Plan will monitored by PIU as well as Bank supervision missions. The
sources of funding for the different activities in the Land Acquisition Plan shall be clearly
specified in the budget. The time-bound implementation plan will specify the delivery of land
acquisition compensation and entitlements in relation to the timing of physical construction
activities.
11
Annex 1
Reporting Format
for
Grievance Redress
Name of
Complainant
Type of Grievance
Affected, but
not informed
about impacts
and options
Compensation Compensation
awarded is
not paid
inadequate1
before asset
acquisition
Grievance resolution
Other
Date of
complaint
Date
resolved
Pending
Case
referred
to the
Court
Complainant A
Complainant B
Complainant C
Complainant D
Complainant E
TOTAL
1
The column must be filled in as a result of effective decision of a court at law.
12
Annex 2
Reporting Format for Land Acquisition (Socio-Economic Data)
Project name and location: _______________________________________________
ID #
Name of PAP
Gender Age
Education
Date: ________________________
Source of
income
(occupation /
employment)
Estimated total
annual income
(average of last
3 years)
Estimated
income 6
months after
relocation
Annex 3
Reporting Format for Land Acquisition (Inventory of Assets Lost, & Delivery of Compensation)
13
Project name and location: __________________________________
Date: __________________
Name of PAPs
Inventory of Assets acquired through land acquisition and
Compensation
value of compensation awarded
Agricultural Land
<#%
>#%
CV
5
Buildings
(Residences,
Shops)
Part
ly
Full
y
CV
Other Assets
Tree
s
Tem
p.
CV
Total
value
of
Date
Of
Com3
Date
of
Poss4
Comp2
/crop
s
2
Total value of Com(pensation) = The total monetary value of compensation for different types of lost assets.
3
Date of Com(pensation) = The date on which the compensation payment was made to the PAP.
Date of Poss(ession) = The date on which the assets acquired were physically taken into possession for the community project.
CV = Compensation Value at replacement costs assessed in Levs.
4
5
14
Download