Proposal for Storm Drains for Courthouse

advertisement
KELLEY/WISE ENGINEERING, INC.
Civil Engineering, Surveying, Land Planning
February 9, 2012
Mr. Bill Otwell
Otwell Associates Architects
121 E. Goodwin Street
Prescott, AZ 86303
bill@otwell-architects.net
SUBJECT: Proposal for Civil Engineering and Surveying Services for
Yavapai County Courthouse Roof Drain Connections
Dear Mr. Otwell:
Kelley-Wise Engineering, Inc. (KWE) is please to provide this proposal for civil engineering services
for the subject project. We understand our work scope would include: 1) conceptual layout; 2)
topographic survey; 3) construction plans and specifications; 4) design report; 5) construction
stalking; and 6) construction inspections. County personnel have discovered that the roof drains may
connect into the sanitary sewer system based on their recent camera work for the sanitary sewer
system. The City of Prescott does not allow storm water runoff to be connected into their sanitary
sewer system. Four roof drains exist – one at each corner of the courthouse building.
Last week we surveyed the flowline elevation of Montezuma Street on the west side of the
courthouse. West of the courthouse building the flowline elevation varies from about 5353.5 sloping
north to about 5351.0. The bathroom floor on the west side of the courthouse is 5358.4. Gravity flow
of the roof drain should be achieved if you can re-plumb these connections within the basement to
exit the building at about elevation 5355.5 (south side) and 5353.0 (north side) or higher. This would
provide about two feet of fall to the gutter flowline in Montezuma Street. Based on this scenario, we
offer the following work scope:
TASK 1: CONCEPTUAL LAYOUT – KWE will develop a conceptual layout for the new roof drain
connections. We anticipate two gravity storm drain connections from the west side of the courthouse
- one connection near each of the northwest and southwest corners of the building. These two pipe
routes would then extend westerly and discharge at the face of curb on the east side of Montezuma
Street.
TASK 2: TOPOGRAPHIC SURVEYING AND MAPPING - KWE will collect field topographic data of
the proposed storm drain alignment route, including mapping the existing land contours at 1-foot
interval, locating existing improvements; i.e., trees, service alignment, paving, and found aboveground utilities that exist at the time of survey. KWE will utilize the city’s vertical datum system.
The topographic limits will include the area of the proposed storm drain improvements.
TASK 3: CONSTRUCTION PLANS AND SPECIFICATIONS – KWE will prepare construction documents
for the new roof drain connections. The construction plans will include necessary call-outs for
hardscape repair and removals as necessary. The construction plans for the new storm roof drain
146 Grove Avenue • Prescott, AZ 86301
(928) 771-1730 • Fax: (928) 778-2220
Mr. Bill Otwell
February 9, 2012
Page 2 of 3
will include: 1) existing [per owner records] and proposed size of pipe; 2) construction key
description for design of the new building roof drain service with appropriate standard detail
callouts; and, 3) standard details and notes for construction. KWE will coordinate with the
architect to establish the building roof service size, location and pipe material. The location and
size will be based on the architect’s (or plumbing subconsultant’s) recommendation.
TASK 4: DESIGN REPORT – KWE will prepare a brief design report to support the design size of
storm drain pipe lateral. The private storm drain pipe will be maintained by Yavapai County.
TASK 5: CONSTRUCTION STAKING – Construction staking to include the following:
survey
calculations, clearing and match lines, and layout of the new storm drain pipe with offset and cut stakes
for the design invert.
TASK 6: CONSTRUCTION INSPECTIONS – KWE will assist the design team with contractors’ RFI’s,
COR’s and related matters to our work scope. During construction we will provide part-time
construction observation services and as-built trench alignment survey and subsequent as-built
plans. The final as-built plans will be furnished electronically to the architect for review and
submission to the Owner.
Project Schedule: KWE will coordinate this work with your project schedule. We can proceed
after our receipt of this signed contract, notice to proceed, and the client-furnished information
referenced herein.
PAYMENT AGREEMENT
We propose providing Tasks 1 through 6, described above, on a lump sum basis for an estimated
fee of $7,250 with a task breakdown as follows:
Task 1:
Task 2:
Task 3:
Task 4:
Task 5:
Task 6:
Conceptual Layout .................................................................... $ 1,500
Topographic Survey and Mapping .............................................. 1,500
Construction Plans & Specifications ........................................... 2,000
Design Report ............................................................................. 500
Construction Staking ................................................................... 750
Construction Inspections .............................................................. 1000
Total ............................................................................................ $7,250
Direct expenses associated with the project, including plan copies, shall be reimbursed at cost
plus 15 percent. Fees are payable with monthly billing based upon the percent complete amount
accomplished within that billing period. Additional services authorized by the client will be
itemized separately on the monthly invoice. All billings are due and payable within 30 days of
dated invoice.
CONDITIONS
The following items are not included in this proposal. Should any of the following items become
necessary, services can be provided by separate agreement:
Mr. Bill Otwell
February 9, 2012
Page 3 of 3
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Boundary surveying or mapping.
Agency review fees, permits and recording fees are to be paid by the owner.
Printing of plans and other direct expenses will be itemized separately as additional
charges.
Flood Insurance Program (FEMA) involvement.
Design of public utilities or rerouting existing utility conflicts.
Development budgets.
Right-of-way and easement dedication or abandonment map(s).
Section 404, NPDES, or AZDES Permit Applications.
Contract specifications.
Legal descriptions.
Utility relocation study or design.
Private utility locate services or related Blue Stake fees.
Items not identified in the Scope of Services.
Authorization to Proceed: If you are in agreement with the Scope of Work, the lump sum fee of
$7,250 for Tasks 1 through 6, and the conditions as stated in the Standard Provisions, please sign
both copies of this Agreement and return the original to indicate your understanding of and
concurrence with the conditions set forth herein.
Sincerely,
KELLEY/WISE ENGINEERING, INC.
Gary R. Kelley, P.E.
Principal
Enclosure: Standard Provisions
c: P12-017
ACCEPTED AND APPROVED
Signature _____________________________________ Date ________________________________
Printed Name _________________________________ Title ________________________________