Transmission Costs v.2 CPUC GHG Modeling 10/31/07 CPUC Greenhouse Gas Modeling Transmission Cost Assumptions Transmission Costs in the GHG Model Transmission upgrades can be a significant contributor to the cost of new generation, especially for resources that are in remote or transmission-constrained locations. The GHG model includes two different components of transmission upgrade cost: (1) The costs of generation interconnection or “collector systems” – transmission that is radial to the main transmission grid and that collects energy produced by generators and transmits it to a higher voltage, backbone facility (2) The costs of main grid upgrades or “trunk lines” – the higher voltage facilities necessary for transmitting large amounts of power over long distances. The GHG model assumes that generation interconnection facilities are financed by the generation owner, while main grid upgrades are network upgrades that use investorowned utility financing. New studies of potential transmission upgrades to facilitate the development of lowcarbon generation resources are outside the scope of the GHG modeling project, so transmission costs for both trunk lines and collector systems were developed on the basis of previous studies and accepted engineering-economic rules of thumb. However, the methodology for estimating the cost of transmission upgrades is currently under review to ensure that consistency with other costing methodologies used in the GHG model, and particularly to ensure that transmission costs reflect the recent, dramatic inflation in the cost of steel and other raw materials. For transmission within California, assumptions about costs and potential routes and capacities are discussed in the next section. For interstate transmission WECC regions, including California, the assumptions are discussed in the subsequent section. Transmission within California for Renewable Resources In the GHG model reference cases, it is assumed that renewable resources will be obtained within California (and closely bordering areas such as northern Baja California (CFE) and the Reno, Nevada area) only, and that trunk lines to obtain renewable resources from distant regions are not built. The main assumptions regarding the transmission routes, line capacities, and costs necessary to provide access to the resources in different renewable resource zones within the state are shown in Table 1 below. (The development of zonal resource supply curves for new generation within these zones is discussed in the section on “Resource Ranking and Selection.”) 1 Transmission Costs v.2 CPUC GHG Modeling 10/31/07 The basis for cost estimation is shown in the “Cost Notes” column of Table 1. In many cases, costs are based on existing transmission studies, adjusted for inflation. In a few cases, costs are based on measured distances between resource zones and load centers, to which rule of thumb estimates were applied. These rules of thumb are shown in Table 2 and Table 3. Table 1. California Transmission in the Reference Case Interconnection Point Geothermal and Wind Sites in Shasta, Lassen, Modoc, and Siskiyou Counties Cluster Name Northeast CA Counties Siskiyou, Shasta, Modoc, Lassen Geysers/Lake Lake, Colusa, Sonoma Geothermal and Wind sites in Lake & Colusa Counties (and on Sonoma Border with Lake County) Vaca-Dixon Substation $58 Bay Delta Solano, Alameda, Contra Costa, Marin Kern Solano and Alameda Wind Sites Vaca-Dixon Substation & Altamont Substation $218 Source: CRS, p.66 (adjusted to 2008$). Tehachapi Wind Sites Pardee/Vincent $2,282 Source CRS, p.65 (adjusted to 2008$). San Bernardino San Bernardin o Mountain Pass & 2 new substations along the way Lugo $1,718 Mono/Inyo Mono, Inyo Lundy/Mono/Lee Vining Lugo $432 Assumed two 500 kV AC transmission lines with a length of 200 miles. Cost = (200 miles X $2.15 million per mile X 2 circuits) + (4 line terminations, series capacitor banks and svc x (26M+10M+30M) Plus 3 collection subs x 4 spokes per sub of 230 kV line, CPUC 2003 Transmission Study for picking up 580 MW of Solar Thermal, Wind, Geothermal from Mono/San Bernardino total (removed costs for lines & substation going west to El Dorado) San Diego San Diego East San Diego wind sites San Diego (SWPL Substation) $191 Tehachapi Delivery Point Round Mountain & Cottonwood Substations in Shasta County Total Cost ($MM 2008) $263 2 Cost Notes Source: CRS, p.66, for 295 MW geothermal for geothermal (adjusted to 2008$). Added (3 x $1.1M/mile for 230 kV x 50 miles) + (3 x 2 x 10M each for line terminations) for interconnection of wind ~700 MW. Assumed Upgrade of Geysers to Vaca-Dixon, per North Geysers transmission upgrade environmental study. Distance: 30 mi. Cost = ($1,600/MW-mi X 400 MW X 30 mi). Added ($1,600/MW-mi X 300 MW X 50 mi) for wind interconnection. Source: CPUC Transmission Study 2003, p.90 (Adjusted to 2008$). Value has been doubled to account for doubling the capacity. Transmission Costs v.2 CPUC GHG Modeling 10/31/07 Imperial Imperial Imperial San Diego $1,269 Source CRS, p.65 (adjusted to 2008). Plus $44.2MM for Path 42 upgarde -- Source: SDG&E 10/30/2006 IV Bank 82 Addition Presentation, recommended option. CA Distributed Entire State Biomass/Biogas sites Local regions throughout CA $61 Assumed interconnection for 36 x 25 MW biomass units in urban area with 10 miles average gen tie. Cost = ($1,600/MW-mi X 25 MW X 3 miles X 36 units) + ($1.5 million substation upgrade X 36 units). CFE Northern Baja Rumorosa/Mexicali Around Miguel Substation $1,269 Assumed same cost as Sunrise line Reno Area/Dixie Valley All NV Geo sites Various Reno & Dixie Corridor Sites (a) Bordertown, NV up to Malin Sub then down to Tracy Sub [1200 MW] plus (b) Donner Pass to Truckee [500 MW]& (b) PDCI tap near Gerlach, NV [400MW] $1,169 Source: CRS, p.66 (adjusted to 2008$). Assume the existing DC line can accommodate with a new DC Substation and some upgrades; Assumes both new AC and PDCI tap in. Added costs from Geothermex report for collector to each of the sites. Notes: CRS = Center for Resource Solutions, Achieving a 33% Renewable Energy Target, prepared for CPUC, November 2005 CPUC Transmission Study 2003 = CPUC Energy Division, Electric Transmission Plan for Renewable Resources in California, December 2003 Table 2. Rules of Thumb for Transmission Capacity Estimates – California-Only Case Approximate Power Carrying Capability of Uncompensated AC Transmission Lines (MW) Nominal Voltage (kV) 138 161 230 345 500 765 Line Length (Miles) 145 195 390 1260 3040 6820 50 100 130 265 860 2080 4660 100 60 85 170 545 1320 2950 200 50 65 130 420 1010 2270 300 NA NA 105 335 810 1820 400 NA NA NA 280 680 1520 500 NA NA NA 250 600 1340 600 Source: Russell and Craft, The Wheeling and Transmission Manual, 3rd Edition, Spectrum Books, 1999. Table 3. Rules of Thumb for Transmission Cost Estimates – California-Only Case 3 Transmission Costs v.2 CPUC GHG Modeling 10/31/07 Source: CEC, Scenario Analysis for 2007 IEPR, Table 4-3. Trunk Line Transmission Costs between WECC Regions The methodology for estimating trunk line transmission costs from other WECC regions to California is still under development. Generation Interconnection Costs The GHG model contains six types of conventional resources and five types of renewable resources. Costs for generation interconnection – transmission facilities that connect the generator radially to the high-voltage, “backbone” grid – are estimated separately for each type of resource. Each resource is assigned a distance from the backbone grid, and is assessed the cost of building transmission over that distance. Interconnection costs are assumed to be linear with the size of the generation resource, and a simple rule of $1600/MW-mile is applied. Interconnection costs are also subject to the regional capital cost multiplier. Assumptions about distance to the backbone grid vary by resource type. For renewable resources outside of California, the methodology for assigning transmission distances is integral to the methodology for assessing resource availability, about which more details can be found in the separate “Resource and Cost Assumptions” report for each technology. Conventional 4 Transmission Costs v.2 CPUC GHG Modeling 10/31/07 The model assumes the following distances to the backbone transmission system for conventional resources: Nuclear and coal resources: 25 miles CCGT and SCGT resources: 10 miles Levelized interconnection costs for conventional resources range from $0.22 to $0.77/MWh. Wind For wind resources, the GHG model uses the NREL transmission assignment method to estimate collection costs for wind generation. This method estimates the total MW capacity of all existing 69kV to 345 kV lines in each WECC zone based on the line’s length and voltage, and assumes that 10% of the total capacity of each line is available for transmission of new wind resources.1 Starting with the lowest cost wind resources, the NREL optimization assigns wind resources of each wind class from individual grid squares to the nearest transmission line until no available transmission capacity remains, then moves to next nearest line. In the GHG model, the distances from the resource grid squares to transmission were backed out from the NREL data, and used to estimate the interconnection cost. In a few situations in which wind resources of Class 5 or higher were not assigned to a transmission line through the NREL methodology, E3 manually assigned the resource the highest transmission distance for any wind of the same region and class that did connect to available existing transmission. Concentrating Solar Power The GHG model uses NREL zonal data for solar thermal resources to estimate transmission interconnection costs for CSP. E3 used a web-based map from Idaho National Laboratory to measure the distance from the center of the greatest resource concentration within each NREL zone to the nearest transmission line with a voltage of 230 kV or higher. Geothermal In the GHG model, geothermal resources are identified on a site-specific basis. E3 used the INL map to locate transmission lines and measure the distance from the site location to the nearest transmission line with a voltage of 115 kV or higher. Per NREL WinDS model description (http://www.nrel.gov/analysis/winds/transmission_cost.html), “The transmission line capacity as a function of kV rating and length is drawn from Weiss, Larry and S. Spiewak, 1998, The Wheeling and Transmission Manual, The Fairmont Press Inc., Lilburn GA.” 1 5 Transmission Costs v.2 CPUC GHG Modeling 10/31/07 Small Hydro In the GHG model, small hydro resources are identified on a site-specific basis. E3 used the INL database and map to estimate the distance from potential hydro sites to transmission, then used this to determine the average distance from the site location to the nearest transmission line for all potential sites within each zone. Sites without specified distances were assigned the maximum value of 25 miles when calculating the zonal averages. Biomass Biomass was treated as distributed resource, with average interconnection distance of 25 miles. 6