APPLICATION NOTE Category: Construction management Keywords: Variations, Neural Networks, Modelling, Contingency allocation, Project control. University: University of Wolverhampton, U.K. Department: School of Engineering & the Built Environment Contact Email: me6049@wlv.ac.uk APPLICATION SUMMARY 1. Problem Description The construction industry has been consistently criticised for poor performance in attaining its clients requirements. Time and cost overruns were predominately common and were well documented (NEDO, 1975; RICS, 1979). The incidence and magnitude of variations was identified as a major cause and a focus of much of the criticism (Bromilow, 1969, 1970; Hibberd, 1980, 1986; Latham, 1994). Variation issued during the construction period are time consuming and costly. Thus accepted as an inevitable part of construction, variations are a major cause of disruption, delay and disputes and generate significant cost impact. Yet no empirical method or tool, quantitative or otherwise, is available for managing or controlling them. The conventional approach is to include a percentage of the project cost as contingency in the pre-contract budget for their occurrences. The allocated contingency based on this method is largely judgmental and arbitrarily allocated. However, construction projects are unique; as they may have distinctive set of objectives, require the application of new technology or technical approaches to achieve the required result, or even duplicate a given set of results in an entirely different environment (Hamburger, 1992). This uniqueness makes the conventional method based wholly on the project manager/supervisors' experience and intuition in danger of overly simplistic and unrealistic (Yeo, 1990). The objectives of the contingency allocation are to ensure that the budget set aside for the project is realistic and sufficient enough to contain the risk of unforeseen cost increases. Therefore any realistic contingency must serves as a basis for decision making concerning financial viability of the variations, and a baseline for their control. After all to manage variations means being able to anticipate their occurrences and to control or monitor their associated cost (Ashley et al, 1986). This paper therefore, describes The development a model to predict the total contingency cost allowance for variations on a construction project is described. 2. Investigator Akinsola, A.O., Researcher in construction management, School of Engineering and Built Environment, University of Wolverhampton, Wulfruna Street, Wolverhampton, WV1 1SB. 3. NN Application Structure Considering the nature of our problem a simple three-layer MLP neural network structure is chosen for the ANN model of total cost of variations on construction projects. The first layer, an input layer, consist of 14 PEs. The number of the PE in the input layer is determined by the number of factors which has been found to influences the magnitude of variations on building projects (Akinsola et al, 1995, 1996). The second layer is the hidden layer, consisting of 5PEs. Finally, the output layer consist of a single PE which produce the total cost of variations. Data Collection and Analysis The data used in the study was collected through a structured questionnaire from 45 building projects completed within the last five years in UK. The projects covered wide spectrum of building types and complexity, from simple residential buildings to very complex office and industrial buildings. Variations were measured in terms of the actual total cost of variations (TCV) ordered per project. TCV is based on the total cost of variations contained as variation order sheets. A variation order sheet may contain a number of works to be done, each of which is a separate variation, summed to derive the total cost of variation per project. Detail description of the data collection instrument and the analysis results has been reported in our earlier papers (Akinsola et al, 1995, 1996). Of the twenty-two factors identified fourteen were found to have significant influence on the magnitude of the incidence of variations observed on building projects. These factors were used as the input variables of the neural network. The fourteen factors are presented in Table 1 below. Training The supervised training method is used to trained the network. The trained model was tested in stages. In the first stage, the same data set used for training was used as the test data. The data as described above consists of 35 projects. In final stage the model was tested using the independent data set aside for testing. The data consists of 2 office, 1 industrial, 3 education, 2 residential, and 2 other buildings projects. 4. The Results To assess the model prediction performances, two quantitative prediction accuracy measurements were calculated and examined; the mean absolute percentage error (MAPE), and the coefficient of variation (CV). The MAPE measure the average percentage of the model prediction error and is calculated by: n MAPE ( AE ) i i 1 N AEi (Y y ) 2 / N Where N is the number of sample of projects. AE represent the absolute error. The Y and y denote the actual and the network predicted total cost of variations respectively. Finally, the coefficient of variations (CV) is calculated by: CV SDr MTCV *100 where SDr is the standard deviation of the error and the MTCV is the mean of the actual total cost of variations. The model predictions were compared with the actual total cost of variations. The percentage error ranges between 0% and 2.5% with a percentage mean of only 0.21% and a coefficient of variation of only 0.22%. These results show that the model predictions are more accurate than expected thus the data set are known to the model. The second test used independent (i.e. unseen by the model) data set. This test is a simulation of the use of the model in practice and assesses how the model will perform if presented with unknown data set. The percentage errors ranges between 0.5% and 15% with a percentage mean of only 3.28% and coefficient of variation of only 1.2%. These results validate the study hypothesis that the cost magnitude of variations can be realistically predicted as demonstrated. Using the first test results as a baseline, the results shows the model predictions are well within the accuracy limit. In the industry forecasting accuracy of 10-15% at the stage are considered adequate Considering that the model is proposed to be used at budget estimate stage of the project the model's accuracy are within the industry standard limit of 15% (McCaffer, 1975; Blok, 1982; Ashworth, 1988; Yeo, 1990). 5. How the results applied Paper published: Title: A NEURAL NETWORK MODEL FOR PREDICTING BUILDING PROJECTS' CONTINGENCY ALLOWANCE. Conference: Proceeding of Association of Researchers in Construction Management, ARCOM 96, Sheffield Hallam University, England, 11-13 Sept. 1996, pp 507-516