CONTINUING PROFESSIONAL DEVELOPMENT Maximum Period 3 Hours RECENT ADJUDICATION CASES – PART 11 By Roger Knowles INDEX 1.0 Breach of Natural Justice 1.1 Ardmore Construction Ltd v Taylor Woodrow Ltd (2006) 1.2 Keir Regional Ltd (trading as Wallis) v City and General (Holborn) Ltd (2006) 2.0 Enforcement of Post Adjudication Agreement Baris Ltd v Kajima Construction Europe (UK) Ltd (2006) 3.0 Side Agreement L Brown and Sons v Crosby North West Homes (2005) 4.0 Adjudicator Uses His Own Expertise Ramkor and Perco v Igoe (2006) 5.0 When Does a Dispute Arise Orange EBS Ltd v ABV Ltd (2003) 6.0 Dealing With a Successful Party’s Likely Inability to Repay Ajudicator’s Decision in Subsequent Proceedings Wimbledon Construction Company Ltd v Derek Vargo (2005) 7.0 Enforcement of Adjudicator’s Decision Harlow and Milner Ltd v Teasdale (2006) 8.0 Contracts in Writing Trustees of the Stratfield Saye Estates v AHL Construction Ltd (2004) 9.0 Introducing a New Claim Into The Adjudication Process William Verry (Glazing Systems Ltd v Furlough Homes Ltd (2005) 10.0 Adjudicator’s Decision and Set Off 10.1Balfour Beatty Construction v Serco Ltd (2005) 10.2 Geris v Handelsgesellschaft GmbH v Les Constructions Industrielles de Mediterrannee SA (2005) ADJUDICATION CASES PART 11 1.0 Breach of Natural Justice 1.1 Ardmore Construction Ltd v Taylor Woodrow Ltd (2006) A fairly well developed strategy for avoiding an unwelcome adjudicator’s decision is to allege that there has been a breach of natural justice. Basically natural justice is served if it is clear as to the case each party has to answer and an opportunity has been provided for them to be heard. A number of challenges have been made to decisions of adjudicators on the grounds that the manner in which the adjudicator has conducted the proceedings resulted in a breach of the rules of natural justice. The present case involved work at Glasgow Harbour. Ardmore entered into a subcontract with Taylor Woodrow to carry out groundworks, concrete works and drainage works. Ardmore submitted an interim application for payment which among other matters included a claim for overtime working. A dispute arose and the matter was referred to an adjudicator who found in favour of Ardmore including the overtime working. This decision was based upon the fact that there had been verbal instructions given by Taylor Woodrow or acquiescence on their part. Taylor Woodrow refused to comply with the adjudicator’s decision on the grounds that there had been a breach of natural justice and as a result enforcement proceedings were commenced by Ardmore. The claim for overtime working was based upon the interpretation of a letter dated 2 nd July 2003. Nothing in the written material put before the adjudicator gave notice of an argument that there had been verbal instructions given or acquiescence. It was alleged by Ardmore that whilst there was no reference in the written submissions representations had been made concerning these matters at the hearing. This was disputed by Taylor Woodrow who argued that the adjudicator’s decision had been based upon arguments which had not been raised or discussed before him and for which they had received no notice. It was held by the Outer House of the Court of Sessions in Scotland that the adjudicator had failed to observe the basic rules of natural justice and had behaved in a manner which on an objective basis involved a disregard of fair play. That part of the decision relating to the overtime working was not enforced but Taylor Woodrow were obliged to pay the remainder. 1.2 Kier Regional Ltd (trading as Wallis) v City and General (Holborn) Ltd (2006) This is another case where the court had to decide whether an adjudicator’s decision had been arrived at involving a breach of the rules of natural justice. The question to be answered by the court was whether new information could be introduced by one of the parties after the adjudication proceedings had commenced. Wallis entered into a contract for the refurbishment and rebuilding of premises which formerly were the Patent Office Library. Disputes arose between the parties some of which were referred to adjudication. One referral involved a claim for an extension of time. An extension of time had been granted under the contract for 28 weeks and the adjudicator in his decision awarded a further 30 weeks. Wallis then evaluated the loss and expense associated with the delay which totalled £1,330,012 and made an application for certification and payment. A sum of £527,192 was certified by the contract administrator which did not meet with the approval of Wallis who instigated a further referral to adjudication. Two expert’s reports were submitted as part of the City and General’s defence. However as these reports had not been seen prior to the referral by Wallis it was argued that the adjudicator had no jurisdiction to take them into account. The adjudicator decided that as the experts reports were new evidence not available to the parties at the time the dispute crystallised they were not to be taken into account. Further due to the short time scale involved in adjudication there was insufficient time available for Wallis to properly consider the reports which is sometimes referred to as defence by ambush. His decision was that Wallis was entitled to an additional payment of £719,295. City and General refused to pay and enforcement proceedings were commenced. City and General argued that the adjudicator’s refusal to consider the expert’s reports was manifestly unfair and amounted to one of the plainest cases of a breach of natural justice. The court was not fully convinced but concluded that it was not necessary to make a decision on the point as if the adjudicator was wrong it amounted to an error in law which was not sufficient to invalidate the adjudicator’s decision. This type of case makes it difficult to differentiate between a breach of natural justice which invalidates an adjudicator’s decision and an error of law which does not. 2.0 Enforcement of Post Adjudication Agreement Baris Ltd v Kajima Construction Europe (UK) Ltd (2006) It is unusual for the parties where a dispute has been the subject of an adjudicator’s decision, which has been resisted by one of the parties, to arrive at a compromise agreement. However this was what happened in this case. Baris was a subcontractor to Kajima to construct dry wall partitioning on a Health and Safety Executive building in Bootle. A dispute arose which was referred to adjudication where a decision was made on 1st December 2005 that Kajima should pay Baris the sum of £181,895 plus interest. This decision was not to the liking of Kajima who refused to make payment. On the 13th December 2005 Baris made a pre-action offer to settle by fax headed “without prejudice save as to costs” in accordance with CPR 36. The wording of the offer was: “Baris Ltd hereby offer to fully and finally settle their rights given by the adjudicator if Kajima Construction Europe (UK) Ltd pay the total sum in the decision namely £181,893.65 only within 21 days of this letter i.e. 3rd January 2006 plus the costs to be taxed if not agreed on a simple basis incurred by Baris Ltd in issuing and serving proceedings in the High Court.” The difference between the adjudicator’s decision and the compromise agreement seems to be limited to the matter of interest only. However Kajima replied on 14 December 2005 “We acknowledge receipt of your letter dated 13th December 2005 and confirm that funds will be in your account on or before 3 rd January 2006” Rather strangely on 19th December 2005 after the exchange of letters but before payment, Baris commenced proceedings in Court to enforce the adjudicator’s decision including interest and costs. No reference was made by Baris to the compromise agreement. Kajima must have been more than a little non plussed and submitted a defence to the effect that a compromise agreement was in existence which stood in the place of the adjudicator’s decision. Baris argued that as the compromise did not constitute a binding agreement and in any event as it was headed without prejudice it could not be used in evidence. The court held that normally a document headed without prejudice cannot be used in evidence. However if an offer embodied in a without prejudice letter has been accepted, so that there is a binding compromise between the parties, then the without prejudice tag falls away and the letter can be used. It was considered that to deny the court a sight of the offer letter would be absurd and would effectively deprive Kajima of the opportunity of raising the compromise point as a defence to the claim. On the matter of whether or not the exchange of correspondence constituted a binding agreement it was argued by Baris that there was no binding agreement because Kajima had not agreed or paid any interest and had not agreed upon any liability as to their costs. This was dismissed by the court as there was a binding compromise between the parties as a result of the exchange of faxes. 3.0 Side Agreement L Brown and Sons v Crosby North West Homes (2005) A contract was entered into between the parties using JCT 1998 With Contractor’s Design. Clause 39A was amended to provide for any dispute “arsing under out of or in connection with the contract “ to be referred to adjudication. There was also a side agreement to the effect that the claimant was entitled to claim payment of a bonus which would not be reduced by any entitlement the respondent might have to deduct liquidated damages. Despite the side agreement the respondent sought to deduct liquidated damages. The matter was referred to adjudication but it was argued by the respondent that the side agreement was not governed by the adjudication provisions in clause 39A as the dispute did not arise under the contract. The side agreement did not contain a separate right of adjudication. It was held that it is not uncommon for parties to a construction contract to enter into side agreements which varied the terms of the contract without themselves having their own dispute resolution clause. The parties under the circumstances must have intended that the original contract dispute resolution provisions would apply. The adjudication provisions therefore applied to the side agreement. 4.0 Adjudicator Uses His Own Expertise Dr Rankillor and Perco v Igoe (2006) There have been a few cases which have dealt with an adjudicator using his own expertise when arriving at a decision. In the Balfour Beatty v London Borough of Lambeth case the judge said that where an adjudicator intends to use his own expertise he should put his initial thoughts to the parties for comment before employing them in the final decision making process. If the adjudicator failed to follow this procedure then it would amount to him or her making out the case on behalf of one of the parties and hence a breach of natural justice. In the present case a dispute arose between a contractor and subcontractor in relation to augur boring work. In the final analysis it came down to an interpretation of laboratory test results concerning the condition of the soil. The subcontractor Perco who undertook the augur work claimed that additional cost had been incurred as a result of unforeseen difficult ground conditions. Both parties submitted their interpretation of the laboratory test results to the adjudicator. He seemed to disagree with the relative interpretations and substituted his own experience and expertise. His conclusion was that the machine chosen was not capable of undertaking the work and had there been a proper site investigation undertaken the conditions which were encountered could have been foreseen. The adjudicator in his decision concluded that Perco were entitled to be paid extra. The adjudication rules were those of the ICE which expressly allowed the adjudicator to use his own expertise and experience when making a decision. In arriving at his decision the adjudicator did not give any advance warning of the findings he intended to make which did not allow Igoe an opportunity of responding to the adjudicator’s views about the soil conditions. It was argued by Igoe that this amounted to a breach of natural justice. It has been held in the case Carillion v Devonport Dockyard (2005) that the adjudicator was not required to put his provisional views to the parties in every case. It all comes down to what the court decides is fair. It is not unreasonable however when the adjudicator rules state that the adjudicator can use his own experience and expertise if he or she does just that. 5.0 When Does a Dispute Arise? Orange EBS Ltd v ABV Ltd (2003) Reference to adjudication cannot commence until there is a dispute between the parties. It is not uncommon once a referral has been made for one of the parties to argue that the adjudicator has no jurisdiction on the basis that no dispute has crystalllised. What constitutes a dispute has been the subject of a number of cases and judges have been eloquent in providing definitions. Examples are Fastrack Contractors v Morrison Construction (2000) In this case judge Thornton made the following observation: “A dispute can only arise once the subject matter of a claim issue or other matter has been brought to the attention of the opposing party and that party has had an opportunity of considering and admitting modifying or rejecting the claim or assertion” Sindall v Solland (2001) Judge Humphrey Lloyd provided the following definition in this case: “For there to be a dispute for the purposes of exercising the statutory right of adjudication it must be clear that a point has emerged from the process of discussion or negotiation … and that there is something that must be decided” Edmund Nuttall v RG Carter (2002) Judge Seymour’s view expressed in this case is: “For there to be a dispute there must have been an opportunity for the protagonists each to consider the position adopted by the other and to formulate arguments of a reasoned kind” The present case again involved the question as to whether a dispute had arisen which could be referred to adjudication. Orange was a subcontractor to ABB for M and E work at John Radcliffe Hospital Oxford employing a DOM/1 form of contract. Orange submitted a penultimate application for payment in the sum of £81,339 when 75% of work had been completed. ABB responded stating that Orange had failed to complete the work and refused them further access to the site. On 6th July 2002 ABB wrote to Orange informing them that the employer would not readmit them to the site as they had abandoned the works. ABB advised Orange that some of their work was defective and requested the submission of a final account. Orange denied that they had abandoned the works or that any of their work was defective. A comprehensive final account was delivered by Orange to ABB on or about 2 nd December 2002. ABB advised Orange that they would need until 20 th January 2003 to review the final account. On 6th January 2003 ABB served a notice of adjudication. ABB claimed that there was no dispute as they needed until 20 th January 2003 to review the final account. An adjudicator was appointed and found in favour of Orange in the sum of £90,283 which ABB refused to pay on the grounds that as there was no dispute the adjudicator had no jurisdiction. The court considered from early December 2002 until 6 th January 2003 gave ABB sufficient time for the evaluation and negotiation of the final account, despite the holiday period. It was unfair that a company should be denied substantial sums of money because of the intervention of a holiday period. By the 6th January 2003 the process of negotiation and discussion should have come to an end and therefore a dispute had arisen. 6.0 Dealing With a Successful Party’s Likely Inability to Repay Adjudicator’s Decision in Subsequent Proceedings Wimbledon Construction Company Ltd v Derek Vargo (2005) The likelihood of a successful party to an adjudicator’s decision being unable to repay a sum awarded in subsequent proceedings has arisen in a few enforcement proceedings. In the case of Bouygues v Dahl Jenson the court refused to enforce an adjudicator’s decision on the grounds that Dahl Jenson was in liquidation. A similar decision was given in the case of Rainford House v Cadogan due to there being a strong prima facie case that the claimant was insolvent. There are however examples of the court enforcing the decision of an adjudicator even though the party seeking to enforce the decision was in a financially weak position and there was a likelihood that in the event of a reversal of the decision in subsequent proceedings the money would not be forthcoming. Examples of this type of case are: Absolute Rentals v Glencor Henshall Engineering v Breen Properties Total M and E Services v ABB All-in-One Building v Makers UK In the present case Wimbledon had carried out construction work to Vago’s house in south west London and disputes arose concerning the value of the works. An adjudication took place and the adjudicator in his decision ordered Vago to pay Wimbledon the sum of circa £120,000. About the same time Vago commenced arbitration proceedings against Wimbledon. Enforcement proceedings were instigated by Wimbledon for the payment of the adjudicator’s decision. Due to Wimbledon’s uncertain financial position Vago offered to pay the £120,000 into court pending the outcome of the arbitration. In considering the above cases the judge considered that each case must be judged on its own facts. He then set out the following principles which should be used as a guide to deciding whether or not an adjudicator’s decision ought to be enforced. 1. Adjudication is a quick and inexpensive method of arriving at a temporary result 2. Adjudicator’s decisions are intended to be enforced summarily and the successful party should not be kept out of his money 3. The probable inability of the successful party to repay the sum awarded may constitute “special circumstances” rendering it appropriate to stay the enforcement proceedings 4. If there is no dispute that the successful party is insolvent then the decision will not be enforced 5. Even if the successful party’s financial position suggests that it is probable that it would be unable to repay the amount of the judgement, payment will none the less be enforced if: o The financial position is similar to what it was at the time the contract was made o The financial position is due to the losing party’s failure to pay money awarded by the adjudicator The judge decided to enforce the adjudicator’s decision even though it unlikely that any repayment could be made for the following reasons: 1. The judge was impressed that the directors of Wimbledon had made loans to the company demonstrating a high degree of practical faith in the future of the business 2. Wimbledon’s financial position was no different than it had been when the contract had been entered into 3. Wimbledon’s financial position appeared to be a direct result of Vago’s failure to pay the amount of the adjudicator’s decision. 7.0 Enforcement of Adjudicator’s Decision Harlow and Milner Ltd v Teasdale (2006) It has been well established since statutory adjudication came into force in 1998, with such decisions as Macob Civil Engineering Ltd v Morrison Construction (1999), that the most appropriate method of enforcing an adjudicator’s decision is by way of an application to the court for summary judgement. In the present case Harlow and Milner undertook work for Linda Teasdale on property in Leeds employing a JCT Minor Works form of contract. A dispute arose and the matter was referred to adjudication where the adjudicator found in favour of Harlow and Milner in the sum of £90,194 including interest. Mrs Teasdale refused to pay up and Harlow and Milner were left to enforce the decision. Instead of applying to the court for summary judgement they chose to serve a statutory notice on Mrs Teasdale and pursue bankruptcy proceedings. Harlow and Milner or their advisers realised they had made an error and applied to have the statutory demand set aside. They then set in motion the normal method of enforcement. Mrs Teasdale argued that the adjudication was unfair because it was quick and that in any event the work was defective. She also expressed a concern that if she won a subsequent court case which overturned the adjudicator’s decision Harlow and Milner would be unable to repay her. The court dismissed all Mrs Teasdale’s arguments. The procedure was in accordance with the Construction Act and meant to be quick. If the work was defective the matter should have been raised in the adjudication proceedings. Finally the risk of the successful party being unable to repay the sum included in an adjudicator’s decision is not a good defence to an application for enforcement. The court ordered that she should pay the amount of the adjudicator’s decision plus additional interest. With regard to the costs of the bankruptcy proceedings the court held that each party should bear its own costs. This seemed a little unfair on Mrs Teasdale as Harlow and Milner had wrongly commenced the proceedings and then abandoned them. However Mrs Teasdale had not helped herself in being rather tardy in her response to the bankruptcy proceedings and this is why the court decided that each party should bear its own costs. 8.0 Contracts in Writing Trustees of the Stratfield Saye Estate v AHL Construction Ltd (2004) For statutory adjudication to be applicable The Construction Act requires construction contracts to be in writing, or evidenced in writing. There have been a number of cases which deal with this matter, the most publicised being RJT Consulting Engineers v DM Engineering (NI) (2002). In the present case, which dealt with the same subject matter, the works comprised the restoration of a derelict house. Phase I of the works, as shown on drawings, involved making the building wind and watertight. Discussions took place between representatives of the two parties at which agreement was reached concerning relevant matters relating to the contract, but no formal contract was entered into. However a representative of Stratfield wrote to AHL confirming their appointment and stating that payment for the work was to be on a cost plus basis at rates which had been agreed for various trades people. One week after work had commenced Stratfield cancelled the project. Two adjudications were commenced the first of which did not proceed because the dispute had not crystallise. A second dispute concerned the value of work carried out prior to the cancellation for which an adjudicator’s decision was given and paid by Stratfield. Finally adjudication was commenced relating to compensation for the cancellation in respect of which AHL claimed a sum of £132,000. The adjudicator found in favour of AHL in the sum of £75,413 but Stratfield refused to make payment. Stratfield applied to the court for a declaration that there was no construction contract in writing. It was held by the court that there was a contract in writing for the following reasons: 1. The scope of the works could be found on the drawings and in the minutes of site meetings. 2. The express terms of the contract were recorded in writing on the drawings, the minutes and correspondence, these being the works, the price, the basis for payment and the rates. Hence the agreement was evidenced in writing 3. Whilst there was no programme and agreed date for completion of the works neither was necessary for the contract to come into being. It must have been implied that the work was to be completed in a reasonable time. 4. In making submissions in the first two adjudications Stratfield had accepted that the contract was governed by the Construction Act. In arriving at a decision that there was a contract in existence the court took into account the following principles established in the RJT Consulting Engineers case: 1. An agreement is only evidenced in writing for the purposes of the Construction Act if all the express terms are recorded in writing 2. It is not sufficient to show that all the terms which are material to the issues which form the dispute have been recorded in writing. 9.0 Introducing A New Claim Into the Adjudication Process William Verry (Glazing Systems Ltd v Furlough Homes Ltd (2005) The question as to whether a party to adjudication is entitled to introduce into the proceedings a new claim which falls outside the disputed matters included in the referral has been a hot topic for some time. In the case of Edmund Nuttall Ltd v R G Carter Ltd (2002) Nuttall a subcontractor submitted to the main contractor Carter a claim for prolongation, delay and disruption in the sum of £1,979,752 in May 2001 which was rejected by Carter. The claim was unresolved and a notice of referral to adjudication dated 14th December 2001 was submitted by Nuttall. The referral notice was accompanied by a report prepared by Anthony Caletka which set out a claim for an extension of time of 235days. Prior to the referral Carter had not seem this report. The adjudicator found in favour of Nuttall in the sum of £834,468 which Carter refused to pay. Nuttall sought enforcement of the sum by the court which was resisted by Carter. It was argued that the dispute which had been referred to adjudication related to the claim submitted by Nuttall in May 2001 and as the report prepared by Anthony Caletka was first submitted with the referral notice it was not the subject of the dispute. The court agreed with this reasoning and refused to enforce the adjudicator’s decision. In the present case Verry was employed by Furlough to undertake curtain walling, cladding and associated works. Delays occurred and Furlough granted extensions of time until 2nd February 2004. On 2nd July 2004 Verry submitted a claim for an extension of time until 24th June 2004 together with its final account. The accompanying letter specifically indicated that it did not take into account any delays relating to ongoing work. Furlough disputed that an entitlement to more money existed and argued that Verry had in fact been overpaid. Furlough referred the dispute to adjudication including the entirety of the dispute concerning the final account which included issues about variations, extensions of time, loss and expense and liquidated damages. The referral was in broad terms asking the adjudicator to decide whether or not the extension of time granted by Furlough was correct. Verry in its response sought an extension of time to 31st July 2004 which was well beyond the 24th June 2004 the date in the earlier request. This involved Furlough in putting in a response to a claim which they had not previously seen. However the adjudicator found in favour of Verry which was resisted by Furlough. The court also found in favour of Verry. It was held that the response submitted by Verry was not a new claim and contained material to which the adjudicator was entitled to have regard in any event. Even if a new claim was involved the referral notice was framed in such broad terms as to include the late extension of time claim. When these two cases are read together it is difficult to conclude that both courts were adopting the same principles. It seems to come down to a lack of consistency as to the definition of what is meant by dispute. Whether a submission made at the time of the referral notice or later is classed as a new claim and not admissible will depend upon the openness of the wording in the notice. In the Verry case the judge referred to an open adjudication where the matters to be referred to adjudication are provided in broad terms. This is to be compared with a closed adjudication where the mattes to be referred are written in a very restrictive way. 10.0 Adjudicator’s Decision and Se Off 10.1 Balfour Beatty Construction v Serco Ltd (2005) It has been well established that once an adjudicator has made a decision relating to a dispute submitted in a referral notice there is no facility for the losing party to reduce the effect of the decision by setting off money owed by the successful party. There have been a number of attempts to overcome the difficulties this presents to the losing party and the present case is an example. Balfour Beatty was engaged by Serco to provide variable message signs on motorways. A dispute arose relating to an entitlement to an extension of time and financial entitlement. The matter was referred to adjudication and the adjudicator found in favour of Balfour Beatty whereby an entitlement to an extension of time to 7th June 2004 and a payment of £620,664 became due. The adjudicator was not asked to decide whether there was an entitlement to any extension of time beyond this date although claims had been submitted in this respect for the periods of time after this date. Serco declined to pay the amount of the adjudicator’s decision arguing that it had a setoff for liquidated damages for delay in respect of the period of time after 7th June 2004 when work was still ongoing. It was also argued that Serco’s entitlement to liquidated damages arose as a matter of course from the adjudicator’s decision. It was held by the court that the entitlement to any extension of time after 7th June had still to be determined and therefore there could be no entitlement at this stage to the deduction of liquidated damages. The matter of an entitlement to liquidated damages had not been included in the referral and therefore was not a part of the adjudicator’s decision. 10.2 Geris Handelsgesellschaft GmbH Industrielles de Mediterrannee SA (2005) v Les Constructions In this case the matter of set off also became a key factor on which the court had to give a decision. In doing so the court arrived at a different conclusion from what had been decided in the Balfour Beatty case. The claimant Geris was a subcontractor to CNIM the subcontract being the I.Chem.E. Model Form for Process Plant. Prior to completion CNIM terminated the subcontract on the grounds that Geris had failed to proceed regularly and diligently with the works. By way of response Geris argued the CNIM had repudiated the contract and claimed for payment in respect of the work they had undertaken, loss and damage together with an extension of time. The matter was referred to adjudication but unfortunately the adjudicator’s decision was far from being a model of clarity. The decision provided for the following: The gross value of Geris’ work was £334,889 The termination by CNIM was lawful CNIM has an entitlement to back charges which were allowed provisionally pending the receipt of more details Geris’ claim was reduced from £ 154,540 to £8,100 No decision was made concerning the extension of time entitlement as the dispute had not crystallised The decision listed the rights of the parties but did not indicate that a sum of money should be paid. Geris applied to the court to enforce payment of £341,176 being roughly the value of work and claim as evaluated by the adjudicator. The judge in making up his mind had to decide what the adjudicator meant. He considered that CNIM had an immediate right to set off the amount of its back charges from money otherwise due. This could take effect even though the adjudicator had not included in his decision a sum in respect of these back charges. It was unfortunate that the decision was unclear but in the circumstances the court decided that the question of set off depends upon what is included in the decision. As the decision did not indicate that any sum should be paid, the court refused to order enforcement of a part only of the decision without taking into account other parts. In this case the court refused to enforce payment of the sum of £341,176 to Geris. QUESTIONS 1.0 Is an adjudicator empowered to take into account matters which are relevant to the dispute which is the subject of the referral, but which have not been included in the submissions by either of the parties or raised at any time during the proceedings? Yes or No 2.0 What is the position if parties enter into a standard form of contract which includes an adjudication clause for undertaking construction work but also enter into a side agreement which has been specifically drafted but does not include an adjudication clause. Will the adjudication clause in the standard contract be applicable to the side agreement? Yes or No 3.0 An adjudicator issued a decision that A is to pay B the sum of £100,000. Both parties felt that if the case were referred to arbitration the award would be much less than £100,000. The parties then entered into a compromise agreement under which A is to pay B the sum of £80,000. Would A be entitled to ignore the compromise agreement and enforce the adjudicator’s decision. Yes or No 4.0 If an adjudicator in a decision orders A to make a substantial payment to B can A successfully refuse to make payment on the grounds that B whilst not in liquidation is unlikely to be able to repay A if the matter is subsequently referred to arbitration and B is successful. A’s financial position had not changed since the contract was entered into. Yes or No 5.0 If an adjudicator in a decision orders A to make a substantial payment to B can A successfully refuse to make payment on the grounds that B is in liquidation and that Bs liquidator will in all probability be unable to repay the money if A is successful in a subsequent arbitration. Yes or No 6.0 A contractor enters into a contract for construction work with a sole trader. A dispute arises which is referred to adjudication. The decision goes in favour of the contractor and a sum of money becomes payable. The sole trader refuses to make payment. Which of the following legal procedures is the most appropriate to enforce payment. Summary Judgement or Bankruptcy proceedings 7.0 A dispute is referred to adjudication whereby a contractor submits a request for and extension of time and payment of loss and expense. An extension of time is included in the decision together with a payment in respect of loss and expense. There is however still a shortfall between the extended completion date and actual completion leaving the contractor exposed to a claim for liquidated damages. The employer did not include in his submissions to the adjudicator a claim for liquidated damages. Is the employer entitled to deduct the liquidated damages from the amount of the adjudicator’s decision. Yes or No ANSWERS 1.0 No 2.0 Yes 3.0 No 4.0 No 5.0 Yes 6.0 Summary Judgement 7.0 No