Our ref: Your ref: PCS/118269 The Scottish Government Energy and Climate Change Directorate If telephoning ask for: By email only to: EconsentsAdmin@scotland.gsi.gov.uk 01 March 2012 Lorna Maclean Dear Sir/Madam The Electricity Act 1989 The Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2000 Addendum to Section 36 application to construct and operate Kilgallioch Windfarm (Arecleoch Phase 2) Thank you for your consultation letter dated 26 January 2012. We have previously provided responses to the proposal in letters dated 14 May 2010 and 15 October 2010 in which we made a number of recommendations and asked for planning conditions to be attached to any consent granted. A number of the conditions asked for and recommendations made remain relevant to the revised proposal and are outlined in section 1 below. A summary of these and any other additional recommendations/conditions is presented in Annex 1. Additionally, we provided specific comments on a draft Peat Management Plan in a letter dated 5 September 2011 and on the Construction Environment Management Plan (CEMP) in a letter dated 7 October 2011, a copy of these responses is included as Annex 2. As these were comments on draft plans any advice on these sections of the addendum are included in section 2 of this letter. 1. Previously issued consultation recommendations/conditions to be carried forward Wetland Ecology 1.1 We made the following comments regards wetland ecology in our letter of 15 October 2010. 1. The revised Phase 1 and NVC maps are a significant improvement to that provided in the ES. The presentation of the data can now be used to determine potential impacts on wetland habitats. The maps show that the majority of the infrastructure is located within the forest area which will be felled for the development. The majority of wind farm infrastructure outside the forest area is located on M25, M23 and some M15 vegetation. The maps show that good quality vegetation and blanket bog mesotopes have mostly been avoided. 2. A number of turbines (T52, T56, T64, T110) are located in the forest area that also includes good quality bog vegetation (M17 and M18). We would suggest micrositing in these areas to avoid impacts on good quality vegetation. 3. T127 is located on good quality bog vegetation that is not within a forest area. We would suggest micrositing this turbine to avoid direct or indirect impacts on the good quality vegetation. 4. The revised maps showing peat depths across the site are a significant improvement to that provided in the ES. The maps show that a large proportion of wind farm infrastructure is located on peat deeper than 1m although areas of deeper peat have mostly been avoided. T64, T110, and T74 are located on peat with recorded depths of 3.7m, 3.8m, and 4m. We would suggest micro-siting these turbines (and crane pads and access tracks) to avoid deep peat. 5. T9 is located on peat with a recorded depth of 6m. Due to the limited length of the peat probe (6m) used for the peat depth survey the peat could be deeper in this area. We would recommend moving this turbine to avoid deep peat or using piling for the turbine foundation to minimise the volume of excavated peat. 1.2 In relation to comment 3 above, T127 is still located on an area of good quality blanket bog. It is still advised that impacts on the best quality bog vegetation are avoided as much as possible through micro-siting the turbine, crane hardstanding and access track. 1.3 In relation to comments 4 and 5 above, a further peat survey has been completed at the proposed locations of T64, T110, T74 and T9 (see Table 1, TA11.2). Although the peat depth has reduced (T64 – from 3.7m to 3.3m, T110 – from 3.8m to 2.9m, T74 – from 4m to 2.9m, and T9 – from 6m to 2.2m) all four turbines are still located on deep peat. Further recorded peat depth data is available for the access tracks leading to T64 and T65, T110, T75, and T76, T77 and T79. Peat depths for the access tracks to T75, and T76, T77 and T79 are noted to be between 2 and 2.5m. Peat depths for the access track to T64 and T65 is noted to be between 4 and 4.5m. Peat depths for the access track to T110 are noted to be 3.8m. 1.4 Since the turbine location and the access tracks are located in areas with variable deep peat it is recommended that the location of T65 and T110 (both turbines are on spur tracks from main access tracks) are reconsidered or alternative construction methods for turbine foundations are considered (e.g. piling). Also, T64 is located on a non-forested good quality blanket bog area and T110 is located in an area of more open forest noted to have good quality bog vegetation (see comment 2 above in italics). Relocating (or deleting) this infrastructure would reduce the estimated volume of excavated peat for the development and reduce impacts on biodiversity interests. 2. Advice on new Addendum Peat Management Plan 2.1 It was noted that the plan proposes filling borrow pits with excavated peat. There is no discussion of how the hydrology of this peat in-fill will be maintained to stop it drying out and resulting in habitat loss and the release of carbon. An additional concern here is that if peat slurry without turves is utilized in this way, the borrow pits would become unsafe areas. Proposals must be presented of how the borrow pits will be restored so that SEPA can determine if it is an environmentally and ecologically acceptable use for the excavated 2.2 peat. Operational staff must also be consulted to ensure that current waste regulations regarding the use of peat are being followed. In section 5.2 of the Peat Management Plan general proposals for using excavated peat to restore blanket bog are outlined. It is noted in this paragraph that ‘the ecological benefit is therefore demonstrated’. It is important to highlight to the developer that SEPA will require more detailed proposals for the use of peat in proposed restoration areas to determine if there will be an ecological benefit. This cannot be determined based on the limited information provided at this stage. 2.3 Proposals to restore areas of currently forested peat bog are briefly outlined in the Peat Management Plan. One of the areas highlighted in Figure 2 (mire restoration areas) has a turbine (T52) proposed to be located within it. It is recommended that an alternative area for mire restoration is selected where there will be no direct or indirect impacts from wind farm infrastructure. 2.4 The excavated peat (up to 1.2m) that will be used to cover cable trenches (which will then be overlaid with peat turves) will raise the peat mound too high above the water table and that the peat will then dry out. It needs to be ascertained why this amount of peat needs to be used in this way. 2.5 The use of peat to dress the edge of floating roads (described as 0.7m of peat tapering to 0m at a distance of 2m from track) sounds reasonable, although possibly not justifiable across the entire site. Furthermore it is important that peat turves are used on the surface and not loose deep peat in these locations. Ecology comments on the Construction Environment Management Plan (CEMP) 2.6 We previously raised concerns in our letter commenting on the Construction Environment Management Plan (CEMP) dated 7 October 2011 regarding the acidification of watercourses at this site and the possible impact on the Bladnoch SAC. SNH should be consulted regards any potential impact on the SAC. 2.7 In our response of 7 October 2011 we also raised the issue of macro-invertebrate monitoring to assess the baseline against which potential pollution impacts of the vulnerable watercourses could be monitored. Technical Appendix A4.3 Indicative Water Management Plan refers to surface water monitoring including the requirement for baseline monitoring prior to construction. Although chemical monitoring including pH will be included, there is no discussion regarding macro-invertebrate ecological monitoring (to species/mixed taxon level of identification). No watercourse macro-invertebrate ecological monitoring is discussed in the Ecology Chapter 9 either. Macro-invertebrate survey work has been required at other wind farm development sites and in this case, due to the watershed location of the site and the vast scale of the development, the importance of this requirement increases. 2.8 Chapter 12 refers to watercourse crossings and it was noted that on Figure 12.3 there are numerous new watercourse crossings as well as many existing watercourse crossings that require upgrading. It is suggested that at the very least Cross Luce at Miltonise downstream of the Pilwhirn Burn; Polbae Burn at Derry/Drummakibben and Tarf Water downstream of the Loch Strand burn confluence should have this survey work completed prior to construction and then repeated in spring and autumn during the construction phase. Water Management Plan 2.9 The Water Management Plan should make reference to The Forest and Water Guidelines 5th Edition and The Water Environment (Controlled Activities) (Scotland) Regulations 2011, A Practical Guide, and any works should align with these guides. 2.10 Section 2.1 of the Water Management Plan states that silt traps will be installed in drainage ditches downstream of felling areas. It is not clear whether these drainage ditches are directly connected to other watercourses. Silt traps should be constructed off-line from watercourses. SEPA should be consulted regards the details of the silt traps. 2.11 Although it indicates that all settlement lagoons will discharge to vegetated ground if this changes and the lagoons discharge to a watercourse then this will require to be authorised under The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (CAR). Construction of access tracks should ensure that drainage does not discharge direct to watercourses and should be discussed with SEPA. Any new culverting of watercourses or upgrading of culverts on watercourses on 1:50000 scale map will require to be authorised under CAR. If the bed of the burn is rock then a bottomless arch culvert or clear span bridge should be used instead of a closed culvert to ensure free passage of fish is not affected in watercourses that have a fishery interest. Regulatory advice Regulatory requirements Details of regulatory requirements and good practice advice for the applicant can be found on our website at www.sepa.org.uk/planning.aspx. If you are unable to find the advice you need for a specific regulatory matter, please contact a member of the operations team in your local SEPA office at: SEPA Rivers House Lochside Industrial Estate Irongray Road Dumfries DG2 0JE If you have any queries relating to this letter, please contact me by telephone on 01355 574 200 or e-mail at planning.ek@sepa.org.uk. Yours faithfully Lorna Maclean Senior Planning Officer Planning Service Copy to: Arcus Renewables 2F Swinegate Court East 3 Swinegate York, YO1 8AJ Appendix 1 – Recommendations and Conditions Recommendations Wetland Ecology Micro-siting of T127 to avoid impacts on good quality blanket bog The location of T65 and T110 are reconsidered or alternative construction methods for turbine foundations are considered Relocation or removal of T64 Peat Management Plan Find an alternative area for mire restoration to the area which has turbine T52 located within it where there will be no direct or indirect impacts from wind farm infrastructure. Water Management Plan The Water Management Plan should make reference to The Forest and Water Guidelines 5th Edition and The Water Environment (Controlled Activities) (Scotland) Regulations 2011, A Practical Guide, and any works should align with these guides. Bottomless arch culverts or clear span bridges should be used instead of closed culverts Conditions Peat Management Plan As stated in section 5.1 of the Peat Management Plan a condition should be attached to any consent granted requiring borrow pit restoration plans to be produced and issued to SEPA for review prior to each borrow pit being opened up. A planning condition should be attached to any planning consent granted requiring details of proposals for the use of peat in proposed restoration areas to determine if there will be an ecological benefit. Before excavated peat is used to cover cable trenches, information should be submitted to ascertain why this amount of peat needs to be used in this way. Water Management Plan Wind farm infrastructure should not have a direct or indirect impact on wetland habitats. Settlement lagoons and silt traps should be located away from sensitive wetlands and constructed off-line from watercourses. SEPA should be consulted regards the details of the silt traps. Construction Environment Management Plan (CEMP) Prior to construction macro-invertebrate survey work should be undertaken, this should be repeated in spring and autumn during the construction phase. As stated in section 2 of the CEMP the final locations of proposed borrow pits should be agreed with local operations staff prior to work commencing. Wash out water from concrete delivery vehicles should be removed from site by an appropriately licensed contractor. As stated, in the CEMP the final design of the replacement bridge should be agreed in advance with SEPA. Appendix 2 Peat Management Plan Dr Paul Phillips Arcus Renewable Energy Consulting Ltd. Suite 2F Swinegate Court East 3 Swinegate York YO1 8AJ Our ref: PCS 115559 Your ref: If telephoning ask for: Lorna Maclean 5 September 2011 By email only to: paulp@arcusrenewables.co.uk Dear Sir/Madam Town and Country Planning (Scotland) Acts Kilgallioch Peat Management Plan Thank you for your consultation email of 18 August 2011. We would offer the following comments on the draft Peat Management Plan. Advice for the planning authority 1. Waste Management 1.1 The waste management proposals appear to be in line with current best practice and SEPA’s guidance on developments on peat, however the developer may wish to take cognisance of the following points. Restoration of borrow pits (Section 6.2) 1.2 It is noted that the developer wishes to utilise some of the waste peat for the restoration of borrow pits associated with the proposed development. While waste peat may be suitable for this, the developer must demonstrate that the use of waste peat will have an ecological benefit e.g. that the aim is to create or restore a habitat without causing a risk of harm to human health or pose a risk to animals. Such use of waste peat may require the registration of an exemption from the Waste Management Licensing (Scotland) Regulations 2011, under Schedule 1, Paragraph 9. SEPA should be consulted in detail before any restoration of borrow pits takes place. Enhancement of peat bog (Section 5) 1.3 The proposal to enhance sections of peat bog by the blocking of ditches from forestry operations and the placement of turves must be undertaken with advice from Scottish Natural Heritage. SEPA would require the registration of an exemption from the Waste Management Licensing (Scotland) Regulations 2011, under Schedule 1, Paragraph 9 for such an activity. The developer must demonstrate that the use of waste peat in such a project would provide a definite ecological improvement. 2. Ecology 2.1 We welcome the detailed maps showing peat profiles in relation to windfarm infrastructure. We also welcome the efforts that have been made to micro-site access tracks and turbines; with the total removal of some deep-peat located turbines from the lay-out and the relocation of some tracks to shallower peat. However there remain some concerns as follows: The excavated peat (up to 1.2m) that will be used to cover cable trenches (which will then be overlaid with peat turves) will raise the peat mound too high above the water table and that the peat will then dry out. It needs to be ascertained why this amount of peat needs to be used in this way. It was noted that the plan proposes filling borrow pits with excavated peat. There is no discussion of how the hydrology of this peat in-fill will be maintained to stop it drying out and resulting in habitat loss and the release of carbon. An additional concern here is that if peat slurry without turves is utilized in this way, the borrow pits would become unsafe areas. Proposals must be presented of how the borrow pits will be restored so that SEPA can determine if it is an environmentally and ecologically acceptable use for the excavated peat. Operational staff must also be consulted that current waste regulations regarding the use of peat are being followed. The plan mentions the use of peat for habitat restoration, but further details of this proposal will be required by SEPA to determine if the restoration proposals are acceptable. The use of peat to dress the edge of floating roads (described as 0.5m of peat tapering to 0m at a distance of 2m from track) sounds reasonable, although possibly not justifiable across the entire site. Furthermore it is important that peat turves are used on the surface and not loose deep peat in these locations. Turbine 9 on deep peat (>4m) remains in place. Could this be relocated slightly to adjacent, less deep peat area? Regulatory advice 3. Regulatory requirements 3.1 Details of regulatory requirements and good practice advice for the applicant can be found on our website at www.sepa.org.uk/planning.aspx. If you are unable to find the advice you need for a specific regulatory matter, please contact a member of the operations team in your local SEPA office at: SEPA Rivers House Lochside Industrial Estate Irongray Road Dumfries DG2 0JE Construction Environment Management Plan (CEMP) Our ref: Your ref: Dr Paul Phillips Arcus Renewable Energy Consulting Ltd. Suite 2F Swinegate Court East 3 Swinegate York YO1 8AJ PCS 115559 If telephoning ask for: Lorna Maclean 7 October 2011 By email only to: paulp@arcusrenewables.co.uk Dear Sir Electricity Act 1989 Kilgallioch wind farm, South of Barrhill We would offer the following comments on the Construction Environment Management Plan (CEMP) for Kilgallioch windfarm. 1. General 1.1 It should be noted that some of the catchment shown on figure one drain to Cross Water of Luce and not Tarf Water catchment as stated. 2. Section 1 Silt Trap Design 2.1 SEPA would recommend discharge from these facilities are to ground in the first instance. It appears from the CEMP that the intention is to discharge to vegetated ground, we would welcome this. 2.2 A combination of silt traps and settlement lagoons for any existing road drainage and road drainage during track construction may be required. Experience from other sites recently has shown that rock filled silt traps do not always remove enough sediment. Combination of measures may also be required for road drainage in close proximity to watercourses. The Agency would recommend that areas such as this are monitored by the ecological clerk of works and discussed with us prior to installation. 3. Section 2 Borrow Pits 3.1 3.2 Final locations of proposed borrow pits should be agreed with local operations staff prior to work commencing. As stated in section 2 of the CEMP. Local operations team should be contacted to ascertain if any dewatering licences are required for borrow pits. 4. Section 3 Accidental spillage within construction compounds 4.1 This section mentions straw bales as a measure used to close off the drainage network in the event of a spillage. We would not view this as an effective measure and would recommend a penstock instead. Wash out of empty concrete delivery vehicles 4.2 Under no circumstances would wash out water from concrete delivery vehicles be allowed to be discharged to vegetated land to soak away. All wash out water must be removed from site by an appropriately licensed contractor. 5. Section 4 Tarf Bridge Upgrade 5.1 The agency has no objections to this proposal however local office should be contacted to agree design of the structure, method statements for the work and required authorisations under CAR. As stated in the CEMP section 4 b) the final design of the replacement bridge should be agreed in advance with SEPA. 6. Ecology 6.1 The CEMP states that the only construction work within 50m of watercourses within the Bladnoch SAC is the upgrading of the Tarf Bridge at 222320E 571700N but that the Polbae and Tarf catchments will regularly have track construction and track upgrading works and new crossing points constructed within 50m of the watercourses. The CEMP discusses the prevention of sediment release into the wider hydrological system through the use of settlement lagoons; however there are no details about what happens to the water from the settlement lagoons. The windfarm is located in some of the most acidified catchments in Scotland and the input of further low pH water could worsen the current situation and impact on the Bladnoch SAC. 6.2 The CEMP provided does not discuss environmental monitoring such as macroinvertebrate monitoring to assess the baseline against which potential pollution impacts of the vulnerable watercourses could be monitored. Further details of the on-site monitoring regime including the monitoring of pH and turbidity should be provided. 6.3 Section 3 discusses the management and movement of liquid concrete and suggests that sump water could be discharged to surrounding vegetated surfaces. Such high alkalinity water would damage acid dependant habitats and vegetation and must not be undertaken as the primary mode of disposal without assessment of the habitat quality of the area of ground to be used. 6.4 The Tarf Bridge to be constructed must enable the passage of migratory fish. The Galloway Fisheries Trust must be consulted on the exact design of the new bridge so that it is acceptable. As stated in CEMP section 4B. 6.5 The CEMP provides no information of a tree felling pollution prevention plan. Significant areas of plantation will be required to be clear felled which could lead to pollution impacts on adjacent watercourses through sedimentation and low pH runoff effects. Regulatory advice 7. Regulatory requirements 7.1 Details of regulatory requirements and good practice advice for the applicant can be found on our website at www.sepa.org.uk/planning.aspx. If you are unable to find the advice you need for a specific regulatory matter, please contact a member of the operations team in your local SEPA office at: SEPA Penkiln Bridge Court Minnigaff Newton Stewart DG8 6AA If you have any queries relating to this letter, please contact me by telephone on 01355 574 200 or e-mail at planning.ek@sepa.org.uk. Yours faithfully Lorna Maclean Senior Planning Officer Planning Service