Connection Engineering Study Report for AUC Application Project Title File No. XXX Revision: 0 Revision Date: 2/12/2016 Name Prepared by: Engineer, P. Eng. Reviewed by: Engineer, P. Eng. Approved by: Engineer, P. Eng. Date Signature Connection Engineering Study Report for AUC Application Connection Engineering Study Report for AUC Application: Project Title Executive Summary (Note: The Executive Summary is a high-level summary of the report. Be brief. Make sure the information in the Executive Summary and the information in the Summary and Conclusion are consistent.) Project Overview • Organization proposing the project • Project content • Project location • Project purpose • In-Service date Existing System • Overview of existing system • Relevant constraints Study Summary • Reasons for study • Study scope • Study area definition • Studies carried out (system conditions, such as summer peak considering Category A and Category B conditions) Alternative Selected • Reasons for selection • Post connection constraint(s) and constraint management (if any) Recommendation • Action recommended R[x] Transmission Project Delivery 1 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Contents Executive Summary ................................................................................................................................... 1 1. Introduction ......................................................................................................................................... 5 1.1. Project............................................................................................................................................ 5 1.1.1. Project Overview.................................................................................................................... 5 1.1.2. Load Component ................................................................................................................... 5 1.1.3. Generation Component ......................................................................................................... 5 1.2. Study Scope .................................................................................................................................. 6 1.2.1. Study Objectives .................................................................................................................... 6 1.2.2. Study Area ............................................................................................................................. 6 1.2.3. Studies Performed ................................................................................................................. 7 1.3. Report Overview ............................................................................................................................ 7 2. Criteria, System Data, and Study Assumptions ............................................................................... 8 2.1. Criteria, Standards, and Requirements ......................................................................................... 8 2.1.1. AESO Transmission Reliability Criteria ................................................................................. 8 2.1.2. AESO Operating Policies and Procedures (OPPs) and Authoritative Documents (ADs) ..... 8 2.1.3. Other Requirements (Use a heading for each) ..................................................................... 8 2.2. Load and Generation Assumptions ............................................................................................... 8 2.2.1. Load Assumptions ................................................................................................................. 8 2.2.2. Generation Assumptions ....................................................................................................... 9 2.2.3. Intertie Flow Assumptions ..................................................................................................... 9 2.3. System Projects ........................................................................................................................... 10 2.4. Customer Connection Projects .................................................................................................... 10 2.5. Facility Ratings and Shunt Elements ........................................................................................... 10 2.6. Dynamic Data and Assumptions ................................................................................................. 11 2.7. Protection Fault Clearing Times .................................................................................................. 13 2.8. Voltage Profile Assumptions ....................................................................................................... 13 3. Study Methodology ........................................................................................................................... 14 3.1. Study Objectives .......................................................................................................................... 14 3.2. Study Scenarios .......................................................................................................................... 14 3.3. Connection Studies Carried Out .................................................................................................. 15 3.4. Power Flow Analysis ................................................................................................................... 15 3.4.1. Contingencies Studied ......................................................................................................... 15 3.5. Voltage Stability (PV) Analysis .................................................................................................... 16 3.5.1. Contingencies Studied ......................................................................................................... 16 3.6. Short-Circuit Analysis .................................................................................................................. 17 3.7. Transient Stability Analysis ......................................................................................................... 17 3.7.1. Contingencies Studied ......................................................................................................... 17 3.8. Sensitivity Studies ....................................................................................................................... 17 3.9. Other Studies (Use a heading for each study type) .................................................................... 18 4. Pre-Connection System Assessment ............................................................................................. 18 4.1. Pre-Connection Power Flow Analysis ......................................................................................... 18 4.2. Pre-Connection Voltage Stability Analysis .................................................................................. 18 4.3. Pre-Connection Transient Stability Analysis ............................................................................... 18 5. Connection Alternatives ................................................................................................................... 18 R[x] Transmission Project Delivery 2 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title 6. 7. 8. 9. 5.1. Overview ...................................................................................................................................... 18 5.2. Connection Alternatives Evaluated ............................................................................................. 19 5.2.1. Connection Alternatives Selected for Further Studies ......................................................... 19 5.2.2. Connection Alternatives Not Selected for Further Studies .................................................. 19 Technical Analysis of the Connection Alternatives ...................................................................... 19 6.1. Alternative 1 ................................................................................................................................. 19 6.1.1. Power Flow Analysis (Alternative 1) .................................................................................... 19 6.1.2. Voltage Stability Analysis (Alternative 1) ............................................................................. 20 6.1.3. Transient Stability Analysis (Alternative 1) .......................................................................... 21 6.1.4. Sensitivity Studies (Alternative 1) ........................................................................................ 23 6.1.5. Mitigation Measures for Identified Issues (Alternative 1)..................................................... 23 6.2. Alternatives 2, 3, etc. (Use headings appropriate for each alternative) ...................................... 24 6.3. Conclusions and Recommendations ........................................................................................... 24 Short-Circuit Analysis ....................................................................................................................... 24 7.1. Pre-Connection ............................................................................................................................ 24 7.2. Post-Connection .......................................................................................................................... 25 Project Interdependencies ............................................................................................................... 26 Summary and Conclusion ................................................................................................................ 26 Attachments Attachment A Dynamic Data of all Equipment Proposed for Connection Attachment B Pre-Connection Power Flow Analysis Results (Scenarios 1 to XX) Attachment C Pre-Connection Voltage Stability Analysis Results (Scenarios 1 to XX) Attachment D Pre-Connection Transient Stability Analysis Results (Scenarios 1 to XX) Attachment E Connection Alternatives – Connection Diagrams and Proposed Facility SLD Attachment F Alternative 1: Power Flow Analysis Results (Scenarios 1 to XX) Attachment G Alternative XX: Power Flow Analysis Results (Scenarios 1 to XX) Attachment H Alternative 1: Voltage Stability Analysis Results (Scenarios 1 to XX) Attachment I Alternative XX: Voltage Stability Analysis Results (Scenarios 1 to XX) Attachment J Alternative 1: Transient Stability Analysis Results (Scenarios 1 to XX) Attachment K Alternative XX: Transient Stability Analysis Results (Scenarios 1 to XX) Figures Figure 1: Overview of Critical Voltage Stability Outages (Example) ............................................................................. 21 Figure 2: Three-Phase Fault near Example 1S Substation on 1001L (Example) ......................................................... 22 Figure 3: Transient System Response following Loss of Example Generator (Example) ............................................ 23 Tables Table 1: Summary of System Projects ...........................................................................................................................7 Table 2: Forecast Area Load ..........................................................................................................................................8 Table 3: Load Forecast at the Affected Substations before Connection Project ............................................................9 Table 4: Load Forecast at the Affected Substations after Connection Project - New PoD Included ..............................9 Table 5: Local Generators in the Study Cases ...............................................................................................................9 R[x] Transmission Project Delivery 3 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 6: Summary of System Projects Included in the Study Cases............................................................................ 10 Table 7: Summary of Customer Connection Assumptions ........................................................................................... 10 Table 8: Summary of Transmission Line Ratings ......................................................................................................... 11 Table 9: Summary of Transformer Ratings .................................................................................................................. 11 Table 10: Summary of Shunt Elements in the Study Area ........................................................................................... 11 Table 11: Generator Dynamic (Example) (This could be in Attachment A) .................................................................. 12 Table 12: Exciter Dynamic Data (Example) (This could be in Attachment A) ............................................................... 12 Table 13: Stabilizer Dynamic Data (Example) (This could be in Attachment A) ........................................................... 12 Table 14: Governor Dynamic Data (Example) (This could be in Attachment A) ........................................................... 12 Table 15: Summary of Protection Fault Clearing Times ............................................................................................... 13 Table 16: Summary of Voltage at Key Nodes in the Study Region .............................................................................. 13 Table 17: Study Scenarios (example data based on the example scenarios above) ................................................... 15 Table 18: Contingency List – Transmission Lines ........................................................................................................ 16 Table 19: Contingency List – Generator/Transformer/SVC/etc. ................................................................................... 16 Table 20: Contingency List – Transmission Elements.................................................................................................. 16 Table 21: Contingency List – Generators/Transformers/SVCs/Etc. ............................................................................. 17 Table 22: Contingency List ........................................................................................................................................... 17 Table 23: Summary of System Performance (Element Loading) ................................................................................. 20 Table 24: Summary of System Performance (Voltage) ................................................................................................ 20 Table 25: Summary of Critical Voltage Stability Outages; Initial Load Level for Area XX is YY MW ............................ 21 Table 26: Summary of Transient Stability .................................................................................................................... 22 Table 27: Summary of Short-Circuit Current Levels – Pre-Connection (Year 20XX) ................................................... 24 Table 28: Summary of Short-Circuit Current Levels – Pre-Connection (Year 20XX [Year of Proposed Connection + 10 Years]) ......................................................................................................................................................................... 25 Table 29: Summary of Short-Circuit Current Levels – Post-Connection (Year 20XX) .................................................. 25 Table 30: Summary of Short-Circuit Current Levels – Post-Connection (Year 20XX [Year of Proposed Connection + 10 Years]) .................................................................................................................................................................... 25 R[x] Transmission Project Delivery 4 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Introduction 1. This Customer Connection Engineering Study Report presents the results of the study conducted to analyze the proposed connection of the XXXX Project to the AIES. Present a brief overview of the project using the headings provided. (Note: If a subsection heading is not relevant to the project write "Not Applicable" under the heading in the first draft of the report submitted for AESO review. Such headings must be removed before submission of the final report.) 1.1. 1.1.1. Project Project Overview • Organization proposing the project • Project content • Project location • Project purpose • In-Service date 1.1.2. Load Component Describe the load component of the project. Include the following: • Estimated maximum amount of load to be connected (peak load); both active and reactive power demands to be specified. If any motor loads, specify the number of motors and the size of each motor load. • Expected power factor. • Type of load. • Potential Demand Transmission Service (DTS) the customer intends to apply for. • Possible future expansion plans and anticipated timing for any expansion. 1.1.3. Generation Component Describe the generation component of the project. Include the following: • Size and number of the new generator(s), and the maximum amount of generation that has been studied • Type of generator(s) R[x] Transmission Project Delivery 5 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title • Estimated reactive power capability of the generator(s) when producing maximum gross active power • Maximum and minimum continuous reactive power capability of the generator(s) • Potential Supply Transmission Service (STS) the customer intends to apply for and operate at when the project is connected to the grid • Possible future expansion plans and anticipated timing for any expansion Study Scope 1.2. Study Objectives 1.2.1. The objectives of the study were the following: • XXXX • XXXX 1.2.2. 1.2.2.1. Study Area Study Area Description Define and describe the study area. Include a diagram of the study area that clearly shows salient features such as transmission lines, substations, generating assets, and reactive elements in the area. In a diagram (the study area diagram or a separate diagram) show how the study area is connected to the rest of the Alberta Interconnected Electric System (AIES). 1.2.2.2. Existing Constraints Describe any known constraint(s) in the study area and its vicinity. Explain how the constraint(s) are managed. Discuss any Operating Policies and Procedures (OPPs) and Information Documents (IDs)/Authoritative Documents (ADs) presently applied in the area. Outline all existing manual or automatic Remedial Action Schemes (RASs) in the area. 1.2.2.3. AESO Long-Term Plans Describe the relevant AESO long-term transmission development plans for the study area and its vicinity. List the anticipated in-service dates of those plans. Use a table. Discuss the known impact(s) of any delays in the AESO long-term plans for the area on the project. R[x] Transmission Project Delivery 6 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 1: Summary of System Projects Project Name 1.2.3. In-Service Date Studies Performed Provide a high-level summary of the system conditions and the studies performed, such as analysis of the existing system before the connection and analysis of the system performance after the connection. Include the contingency categories applicable to the project. Use the format of the following example: Example (replace with non-italicized material appropriate to the project): The following studies were performed for the pre-connection analysis considering Category A, B, and selected C contingencies: • Power flow analysis • Voltage stability analysis • Transient stability analysis • Short-Circuit fault studies The following studies were performed for the post-connection analysis considering Category A, B, and selected C contingencies: • Power flow analysis • Voltage stability analysis • Transient stability analysis • Short-Circuit fault studies 1.3. Report Overview The Executive Summary provides a high-level summary of the report and its conclusions. Section 1 provides an Introduction. Section 2 describes the Criteria, System Data, and Study Assumptions. Section 3 presents the Study Methodology. Section 4 discusses the PreConnection System Assessment. Section 5 presents the Connection Alternatives. Section 6 provides a Technical Analysis of the Connection Alternatives. Section 7 provides a Short-Circuit Analysis. Section 8 discusses Project Interdependencies. Section 9 presents a Summary and Conclusion. R[x] Transmission Project Delivery 7 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title 2. 2.1. 2.1.1. Criteria, System Data, and Study Assumptions Criteria, Standards, and Requirements AESO Transmission Reliability Criteria Describe in detail the application of the AESO Transmission Reliability Criteria when the system studies were carried out. 2.1.2. AESO Operating Policies and Procedures (OPPs) and Authoritative Documents (ADs) List the OPPs and ADs taken into consideration when the connection proposals were evaluated and explain how they were applied when the connection studies were performed. 2.1.3. Other Requirements (Use a heading for each) Describe in detail the application of any other AESO requirements, criteria, standards, rules, practices, and guidelines (market or otherwise) when the connection studies were carried out. Use subsection headings that clearly identify the requirement being discussed. 2.2. 2.2.1. Load and Generation Assumptions Load Assumptions Describe the load assumptions and the AESO load forecast applied: peak or light season conditions, year(s), specific regional characteristics, and any other data relevant to the load assumptions and the load forecast. Present the load forecast in table format. Table 2: Forecast Area Load Area Name and Number Season Year Forecast Peak Load (MW) Summer Winter For load connection projects, provide a load forecast for any new point of delivery (PoD) substation proposed for connection. If the connection project involves changes to the loading levels at the existing PoDs, provide load forecast tables to show the load changes before the connection project and after the connection project. R[x] Transmission Project Delivery 8 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 3: Load Forecast at the Affected Substations before Connection Project Substation Name and Number Forecast Peak Load (MW) Season 20XX 20XX 20XX 20XX 20XX 20XX 20XX 20XX 20XX 20XX Summer Winter Table 4: Load Forecast at the Affected Substations after Connection Project - New PoD Included Substation Name and Number Forecast Peak Load (MW) Season 20XX 20XX 20XX 20XX 20XX 20XX 20XX 20XX 20XX 20XX Summer Winter 2.2.2. Generation Assumptions Present the generation forecast information used for this project. List the local generators in the study area and the dispatch level of each. Use a table. Describe the notable features of the local generators, as required. Indicate the range of the generation level considered for the existing generators and the maximum generation level studied for any new unit(s) to be connected. Include the reactive power capability of the generator(s) at maximum output. Table 5: Local Generators in the Study Cases Name Units Facility A (existing) #1 Facility B (proposed) #1 Symbol Max Qmax Capacity (MVAr) (MW) Qmin (MVAr) Generation Level Modelled in the Study Case (MW) #2 #2 Total 2.2.3. Intertie Flow Assumptions Indicate the assumptions regarding the intertie flow between Alberta and neighbouring jurisdictions. R[x] Transmission Project Delivery 9 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title 2.3. System Projects List the relevant transmission facilities that are not in service but were included in the study cases. Use a table. Table 6: Summary of System Projects Included in the Study Cases System Facility Name Projected In-Service Date Study Case (In Service/Not in Service) Briefly discuss any relevant information regarding system projects, such as developments proposed for each project. 2.4. Customer Connection Projects List the relevant customer connection facilities that are not in the existing system but were included in the study cases. Use a table. Include relevant information such as size of the load and/or generation for each project. Table 7: Summary of Customer Connection Assumptions Customer Facility Name Projected In-Service Date Project Status (NID Filed?) Load (MW) Generation (MW) Total Provide any other relevant information for each project, such as whether it has already been approved by the Alberta Utilities Commission (AUC). 2.5. Facility Ratings and Shunt Elements Include tables that show the facility ratings for key existing and proposed equipment rated XX kV and above and any other relevant equipment ratings. Show only the most important equipment. R[x] Transmission Project Delivery 10 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 8: Summary of Transmission Line Ratings Transmission Lines Line Number Summer Rating (MVA) Winter Rating (MVA) Table 9: Summary of Transformer Ratings Transformers Substation Name and Number Transformer Voltages (kV) Transformer ID MVA Rating List the shunt elements in the study area, including shunt element size and status. Use a table. Present all assumptions made regarding the shunt elements, such as whether they were switched on or off in the studies. Table 10: Summary of Shunt Elements in the Study Area Substation Name and Number 2.6. Nominal Number of Bus Voltage Switched Shunt (kV) Blocks Capacitors Total at Nominal Voltage (MVAr) Reactors Status in Study Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Status in Study (on or off) Dynamic Data and Assumptions In Attachment A, list the dynamic data of all equipment proposed for connection to the grid, such as generators, excitation systems and their limiters, power system stabilizers (PSSs), turbine governors, wind turbines, static VAR compensators (SVCs), large motors, as well as all other relevant dynamic representations of the proposed facilities. Use a table. If it is not possible to present the information in a table, attach the detailed dynamic data in a comprehensive format or attach it directly as a dyr file. R[x] Transmission Project Delivery 11 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 11: Generator Dynamic (Example) (This could be in Attachment A) Generator Dynamic Data (GENROU model) T’do T"do S(1.0) S(1.2) T’qo T"qo H D Xd X’d Xq X’q X"d Xl KL Table 12: Exciter Dynamic Data (Example) (This could be in Attachment A) Exciter Dynamic Data (EXAC2 model) TR TB TC KA TA VAMAX VAMIN KB VRMAX VRMIN TE KH KF TF KC KD KE VLR E1 SE(E1) E2 SE(E2) Table 13: Stabilizer Dynamic Data (Example) (This could be in Attachment A) Stabilizer Dynamic Data (PSS2B model) Tw1 Tw2 T6 Tw3 Tw4 T7 KS2 KS3 T8 T9 KS1 T1 T2 T3 T4 T10 T11 VSI1MAX VSI2MIN VSI1MAX VSI2MIN VSTMAX VSTMIN ICS1 M N REMBUS1 ICS2 REMBUS2 Table 14: Governor Dynamic Data (Example) (This could be in Attachment A) Governor Dynamic Data (GGOV1 model) R Tpelec Maxerr Minerr Kpgov Kigov Kdgov Tdgov Vmax Vmin Tact Kturb Wfnl Tb Tc Teng Tfload Kpload kiload Ldref Dm Ropen Rclose Kimw Aact Ka Ta Trate db Tsa Tsb Rup Rdown Rselect Flag R[x] Transmission Project Delivery 12 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Provide a high-level summary of the modelling assumptions made for all other generators, such as the dynamic data provided by AESO used, the generator test reports used (where such test reports were available), and/or the standard generator data used (where such test reports were not available). 2.7. Protection Fault Clearing Times List the fault clearing times used for the transient stability analysis. Use a table. When providing near-end and far-end fault clearing times, include different directions with the clearing times only when the clearing times are not the same for faults at each end. Indicate if the fault clearing time assumptions have been verified by the Transmission Facility Owner (TFO). Table 15: Summary of Protection Fault Clearing Times Transmission Line 2.8. Fault Clearing Times (Cycles) Near-End Far-End Assumed or Verified Voltage Profile Assumptions State the voltage at the key buses (nodes) in the study area. Use a table. Provide a comparison with the minimum voltages given in AESO OPP-702 or the applicable Information Document (ID), if possible. Table 16: Summary of Voltage at Key Nodes in the Study Region Bus No. and Name Minimum Voltage (kV) - OPP-702 Nominal Voltage (kV) Voltage in the Study Case (kV) If there are any SVCs in the area, indicate the typical operational practices for them, and indicate the assumptions made regarding the SVCs in the connection studies. R[x] Transmission Project Delivery 13 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Study Methodology 3. 3.1. Study Objectives The objectives of the study discussed in this report were the following (same text as in the Introduction): • XXXXX • XXXXX 3.2. Study Scenarios Outline the scenarios (system conditions) studied and the study years. These scenarios should represent a range of potential system conditions, assumed loading conditions, and assumed generation dispatches sufficient to allow an analysis of the transmission system performance in the study area. The scenarios may include the following: • Low and high loading levels • Low and high generation levels • Interchange conditions (for example, high, medium, or low export from Alberta to British Columbia or high, medium, or low import from British Columbia to Alberta) • Transmission flow, such as South of Keephills/Ellerslie/Genesee (SOK), Fort McMurray transfer in and out, and other relevant area transfers Provide the rationale for each assumption, for example, selection of the study years, seasonal conditions, and cut-plane flows. Use the format of the two example scenarios below. Example (replace with non-italicized material appropriate to the project): Scenario 1: • 2099 summer peak (SP) load conditions • 780 MW import from BC • All wind generation is offline • All local gas generators in the study area are offline • Economic dispatch of all other generators in the AIES Scenario 2: • 2099 summer peak (SP) load conditions • 0 MW interchange between Alberta and BC • All wind generation dispatched at full power • All local gas generators are offline R[x] Transmission Project Delivery 14 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title • Economic dispatch of all other generators in the AIES Provide a summary of all the study cases based on the given scenarios. Use a table. Table 17: Study Scenarios (example data based on the example scenarios above) 3.3. Load Condition Scenario Year 1 2099 Summer Peak (SP) 2 2099 SP Import from BC (MW) Wind Local Gas Generation Generation Dispatch (MW) (MW) 780 0 0 0 0 5000 Connection Studies Carried Out Outline the studies carried out to assess the connection proposal. Example (replace with non-italicized material appropriate to the project): • Power flow (Category A, B, or C from the AESO Reliability Criteria and the Alberta Reliability Standards) • Voltage stability (Category A, B, or C) • Short-Circuit analysis • Transient stability analysis (Category A, B, or C) Include any studies required to assess transmission system performance, for example, motor starting studies (if the customer facility has motor load). 3.4. Power Flow Analysis Describe the methodology used for the power flow analysis. For example, whether the studies were performed for pre-connection conditions and post-connection conditions, whether all scenarios from Section 3.2 were studied, the purpose of the power flow analysis (for example, to check thermal overload or voltage deviation), how the studies were run (for example, for 10% voltage deviation the transformer taps were locked), the assumed power factor. Include all relevant elements of the power flow study methodology. Include the monitoring quantities, such as thermal loading. Indicate the study tool utilized. 3.4.1. Contingencies Studied List the contingencies studied for each scenario. Use a table. If the contingency list is long, the list of contingencies can be summarized in sentence form. (For example: Outage of each transmission element at XX kV and above in the study area was tested for Category B contingency analysis.) R[x] Transmission Project Delivery 15 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 18: Contingency List – Transmission Lines Scenario System Condition Outage From Substation To Substation 1 All transmission elements in service (N-0) 1001L A B 2 Line 2001L out of service (N-1) 1001L A B Table 19: Contingency List – Generator/Transformer/SVC/etc. 3.5. Scenario System Condition Outage Substation 1 All transmission elements in service (N-0) 240/138 kV T1 transformer (Bus 10000 to Bus 10001) SubA 1000S 2 Line 2001L out of service (N-1) Generator X SubB 2000S Voltage Stability (PV) Analysis Describe the methodology used for the PV analysis. Indicate which scenarios from Section 3.2 were studied. Explain the purpose of the PV analysis and how the studies were run (for example, whether the capacitor banks were locked or moving at each step of the PV analysis). Include any other relevant discussions regarding the PV analysis methodology. Explain the assumptions made regarding source and sink and the rationales for these assumptions. Indicate the study tool utilized. 3.5.1. Contingencies Studied List the contingencies studied for the PV analysis. Use a table. If the contingency list is long, the list of contingencies can be summarized in sentence form. (For example: Outage of each transmission element at XX kV and above in the study area was tested for Category B contingency analysis.) Table 20: Contingency List – Transmission Elements Scenario System Condition Outage R[x] Transmission Project Delivery 16 From Substation To Substation Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 21: Contingency List – Generators/Transformers/SVCs/Etc. Scenario 3.6. System Condition Outage Substation Short-Circuit Analysis Describe the methodology used for the short-circuit analysis. For example, the studies performed for pre-connection conditions, the studies performed for post–connection conditions, the system conditions used for the short-circuit analysis, and the fault types and locations. Include all relevant discussions on the short-circuit analysis methodology. Indicate the study tool utilized. 3.7. Transient Stability Analysis Describe the methodology used for the transient stability analysis. Indicate which scenarios from Section 3.2 were studied. Explain the purpose of the transient stability analysis and how the studies were run, for example, XX amount of load was converted into motor load. Include all relevant discussions regarding the transient stability analysis methodology. Include the monitoring quantities such as relative machine angle (specify the reference generator). Indicate the study tool utilized. 3.7.1. Contingencies Studied List the contingencies studied for the transient stability analysis. Use a table. If the contingency list is long, the list of contingencies can be summarized in sentence form. (For example: Outage of each transmission element at XX kV and above in the study area was tested for Category B contingency analysis.) Table 22: Contingency List Scenario 3.8. System Condition Contingency Fault Description Sensitivity Studies Describe the sensitivity studies performed and the intent of the studies. Include the assumptions. Outline all modifications to the initial set of assumptions. Use a table. R[x] Transmission Project Delivery 17 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title 3.9. Other Studies (Use a heading for each study type) Describe the methodology used for any other studies carried out. Use a separate heading for each study. The headings should match the headings used in Section 3.3.1. Include the intent, the assumptions, and any relevant discussions regarding the study methodology. Use a table. 4. 4.1. Pre-Connection System Assessment Pre-Connection Power Flow Analysis For each scenario, report and discuss the power flow analysis results. Include tables that summarize the results with respect to thermal overloads and voltage dip/rise. See Section 6.1.1 for table format examples. In the appropriate attachments, include power flow diagrams that provide a general representation of the overall study area. Describe the results of the contingency categories that were analyzed. Present the results for each scenario separately. 4.2. Pre-Connection Voltage Stability Analysis Use Power Voltage (PV) curves and tables to show the critical steady state voltage stability analysis results. For each scenario, provide complete information regarding any Category A, Category B, and Category C analyses carried out and the outcomes of each. All figures must be easy to read and have labels for the x axis and the y axis. See Section 6.1.2 for table and figure format examples. Present the results for each scenario separately. 4.3. Pre-Connection Transient Stability Analysis Discuss the main study outcomes of the transient stability analysis. The complete study results can be included in an attachment. Use tables and figures to show results of all Category A, Category B and Category C contingencies examined. See Section 6.1.3 for table and figure format examples. Other figures that may be included are, for example, line flows, machine active and reactive power, and system frequency. 5. 5.1. Connection Alternatives Overview List all the conceptual connection alternatives considered. R[x] Transmission Project Delivery 18 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Connection Alternatives Evaluated 5.2. Describe each connection alternative separately. For each alternative, include a connection diagram that shows the main transmission network in the study area post-connection. Provide single-line diagrams (SLDs) for the proposed facilities. The connection diagrams and proposed facilities SLDs can be presented in the appropriate attachment. Connection Alternatives Selected for Further Studies 5.2.1. Indicate the connection alternatives that were selected for further studies and explain why each was selected. For all alternatives selected include single-line diagrams (SLDs) of any proposed substations. Connection Alternatives Not Selected for Further Studies 5.2.2. Note the connection alternatives that were not selected for the connection studies and explain why each was not selected. 6. Technical Analysis of the Connection Alternatives Using the structure below, detail the results of the studies carried out for each connection alternative. Exclude any subsection that does not apply to the connection studies. 6.1. Alternative 1 For Alternative 1, describe the results of the studies carried out to evaluate it. 6.1.1. Power Flow Analysis (Alternative 1) Present the study results for the power flow analysis of Alternative 1. Use tables and figures where possible. Present the power flow analysis results for each scenario separately. Evaluate the results for the scenarios considered. Place the complete study results in the appropriate attachment. 6.1.1.1. Scenario 1 Provide the results for all system conditions and contingencies considered, as outlined in Section 3 (Category A, Category B, and Category C analysis). Summarize the thermal overload results based on a 100% seasonal static thermal rating (specify the season). Use a table. In the appropriate attachment sections, include power flow diagrams that encompass a general representation of the overall study area. R[x] Transmission Project Delivery 19 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title For each scenario, include a diagram that shows generator output, the switched shunts, and the SVCs, as appropriate, in the attachment to this section. Table 23: Summary of System Performance (Element Loading) Contingency Branch Pre-Connection Post-Connection Power Flow (MVA) % Loading Power Flow (MVA) 600 80 800 1001L 240 kV Line (Substation A to Substation B) No Contingency (N-0) % Loading % DifferLoading ence 107 27 Show the steady state voltage deviation results following different outages. Show the high-side bus voltage, and show the point of delivery (PoD) bus voltage for all main substations in the study region. Use a table. Table 24: Summary of System Performance (Voltage) Contingency Substation Name and Number 1001L (Substation A to Substation B) XXXX 1000S 6.1.1.2. 6.1.2. Initial Bus No. Base kV Voltage (kV) Post Transient (kV) % Change Post Auto (kV) % Change 10000 138 138 130 6 137 1 10001 25 25 23.5 6 25 0 Scenario 2, 3, etc. (use headings appropriate for each scenario) Voltage Stability Analysis (Alternative 1) Present the critical voltage stability results using PV curves and tables. Provide the complete study results regarding the Category A, Category B, and Category C events studied. Present the voltage stability analysis results for each scenario separately. Discuss the main study results in this section and include the details in the appropriate attachment. 6.1.2.1. Scenario 1 All figures must be easy to read and have proper labels for both the x axis and the y axis. See Figure 1 for an example. The table headings must identify the initial amount of static load in the study region or the initial transfer level, whichever is applicable. See Table 25 for an example of a table that shows the stability margin for different system conditions. R[x] Transmission Project Delivery 20 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Figure 1: Overview of Critical Voltage Stability Outages (Example) System Condition: N-FNG, Area Capacitor banks utilized to prepare for next outage, RB Area Load = ~140 MW including losses, Examined: N-FNG-RL1 Rainbow Lake 791S 144kV Bus 155 Voltage (kV) t 150 145 140 Example 135 130 135 140 145 150 155 160 165 Rainbow Area Total Load (MW) N-FNG N-FNG-RL1+LS1 N-FNG-RL1+LS2 N-FNG-RL1+LS3 N-FNG-RL1+LS4 Table 25: Summary of Critical Voltage Stability Outages; Initial Load Level for Area XX is YY MW System Condition Worst Case Outage Incremental Area Load Increase before Collapse Point (MW) Available Voltage Stability Margin (%) Provide additional explanation to clarify the study results and conclusions, as appropriate. Include any var support devices required to alleviate voltage instability or voltage collapse. 6.1.2.2. 6.1.3. Scenario 2, 3, etc. (use headings appropriate for each scenario) Transient Stability Analysis (Alternative 1) Present the transient stability analysis results for each scenario separately. Use tables and figures. R[x] Transmission Project Delivery 21 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title 6.1.3.1. Scenario 1 Provide results for all system conditions and contingencies considered, as outlined in Section 3 (Category A, Category B, and Category C analysis). Discuss the main study outcomes. Place the complete study results in the appropriate attachment. Evaluate the transient stability analysis results for the scenarios considered. Table 26: Summary of Transient Stability System Condition Typical operating condition with all elements in service (N-0) Contingency Results Figure # (Stable/Unstable) Fault Description and Clearing Times 3ph fault at sub A line 1001L to sub B, 1001L (sub A to sub B) 5 cycles: trip sub A CB on 1001L to sub B Stable 7 cycles: trip sub B CB on 1001L to sub A Use figures to illustrate the system dynamic responses following Category A, Category B, and Category C contingencies. The figures must be easy to read and properly labelled. The figure numbers should be noted in the Summary of Transient Stability table and in the attachment. Include figures for system voltages at key nodes in the study area, relevant generator angles with respect to the reference generator, the power output of the relevant generators in the area, and any other relevant information. Figure 2 and Figure 3 are examples of figures that show system response. Figure 2: Three-Phase Fault near Example 1S Substation on 1001L (Example) Bus Voltage (kV) 160 155 150 145 140 Example 135 130 125 120 0 5 Blumenort 10 Ft.Nelson 15 20 High Level R[x] Transmission Project Delivery 22 Hotchkiss 25 Keg River 30 35 Rainbow Lake Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Figure 3: Transient System Response following Loss of Example Generator (Example) NW generators angle: N-FNG 0 Example -10 -20 -30 -40 -50 -60 0 5 RB2 6.1.3.2. 6.1.4. 10 RL1 15 RB5 20 Bear Creek (Gas) 25 Bear Creek (Steam) 30 35 H.R.Milner Scenario 2, 3, etc. (Use headings appropriate for each scenario) Sensitivity Studies (Alternative 1) Discuss the results obtained from all sensitivity tests carried out to determine the robustness of the study conclusions. 6.1.5. Mitigation Measures for Identified Issues (Alternative 1) If system performance issues were discovered based on the study results for Alternative 1, describe the mitigation method(s) proposed to alleviate or manage the condition(s). System performance issues may include, for example, the following Reliability Criteria violations: • Thermal overload based on 100% static seasonal thermal rating • Voltage deviation beyond the allowed levels indicated in the AESO Transmission Reliability Criteria • Unacceptable voltage stability margin Demonstrate the effectiveness of the proposed mitigation methods using the study results. Use tables and figures where possible. Include any explanations required to clarify the study outcome and conclusions. R[x] Transmission Project Delivery 23 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Alternatives 2, 3, etc. (Use headings appropriate for each alternative) 6.2. Using the structure utilized for Alternative 1, detail the results of the studies carried out for each of the other connection alternatives studied. Delete any subsection that is not applicable to that alternative. Conclusions and Recommendations 6.3. List the connection alternatives studied and compare the study results of each from a technical perspective. Recommend the preferred alternative based on the technical assessment presented in Section 6. If all alternatives produce very similar system performance, state that all alternatives are equivalent based on the study results. Note: If there are a number of feasible alternatives and, based on the technical studies, all the feasible alternatives generate similar results, the preferred alternative should be selected based on a matrix that compares the alternatives by their LIA, PIP, economics, and other relevant merits. This comparison is to be carried out in a separate short report that will be an appendix to the Needs Identification Document. 7. Short-Circuit Analysis 7.1. Pre-Connection For load connections, include only the analysis after the preferred connection alternative is in service and explain that the short-circuit current levels would not be changed materially unless the preferred alternative has a large system addition that will impact short-circuit currents. For generator connection proposals, include the short-circuit analysis results for before and after connection of the preferred alternative. Table 27: Summary of Short-Circuit Current Levels – Pre-Connection (Year 20XX) Substation Name and Number Base PreVoltage Fault (kV) Voltage Positive Zero Positive Zero Sequence Sequence PreSequence Sequence 3-Φ Thevenin 1-Φ Thevenin Fault Thevenin Thevenin Fault Source Fault Source Voltage Source Source (kA) Impedance (kA) Impedance (pu) Impedance Impedance (R1+jX1) (R0+jX0) (R1+jX1) (R0+jX0) (pu) (pu) R[x] Transmission Project Delivery 24 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Table 28: Summary of Short-Circuit Current Levels – Pre-Connection (Year 20XX [Year of Proposed Connection + 10 Years]) Substation Name and Number 7.2. Base Voltage (kV) PreFault Voltage PreFault Voltage (pu) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Post-Connection Provide post-connection short-circuit current levels for the preferred alternative. Use a table. Table 29: Summary of Short-Circuit Current Levels – Post-Connection (Year 20XX) Substation Name and Number Base Voltage (kV) PreFault Voltage PreFault Voltage (pu) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Table 30: Summary of Short-Circuit Current Levels – Post-Connection (Year 20XX [Year of Proposed Connection + 10 Years]) Substation Name and Number Base Voltage (kV) PreFault Voltage PreFault Voltage (pu) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) R[x] Transmission Project Delivery 25 Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Project Interdependencies 8. Discuss if there are any interdependencies between this project and other system projects and customer connection projects. Indicate the impact of such interdependencies between the projects. Summary and Conclusion 9. Provide a brief summary of the studies performed and the conclusions reached. Include any mitigation measures needed to facilitate the preferred customer connection while ensuring system reliability and respect for all AESO requirements, criteria, standards, and rules. (Note: Make sure the information in the Summary and Conclusion and the information in the Executive Summary are consistent.) Include the following: • Organization proposing the project • Project content • Project location • Project purpose • In-Service date • Overview of connection alternatives studied • An overview of the technical assessment of the alternative(s) • Mitigation measures required, if any • Conclusions reached as a result of the connection studies R[x] Transmission Project Delivery 26 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment A Dynamic Data of all Equipment Proposed for Connection R[x] Transmission Project Delivery 27 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 28 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment B Pre-Connection Power Flow Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 29 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 30 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment C Pre-Connection Voltage Stability Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 31 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 32 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment D Pre-Connection Transient Stability Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 33 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 34 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment E Connection Alternatives – Connection Diagrams and Proposed Facility SLD R[x] Transmission Project Delivery 35 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 36 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment F Alternative 1: Power Flow Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 37 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 38 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment G Alternative XX: Power Flow Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 39 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 40 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment H Alternative 1: Voltage Stability Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 41 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 42 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment I Alternative XX: Voltage Stability Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 43 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 44 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment J Alternative 1: Transient Stability Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 45 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 46 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title Attachment K Alternative XX: Transient Stability Analysis Results (Scenarios 1 to XX) R[x] Transmission Project Delivery 47 Public R2-2012-03-21 Connection Engineering Study Report for AUC Application: Project Title R[x] Transmission Project Delivery 48 Public R2-2012-03-21