21 July 2015 Response to National Grid route decision on 17/06/15 1. Introduction Power Without Pylons recognises the need for more power generation. However, we firmly believe that new 50m pylons – twice the height and more than twice the width of existing pylons - would have an enormous negative impact on the landscape south of Moorside, and there is an alternative. It is our conviction that the Offshore route is the only rational solution to connecting Moorside to the electricity grid. Building a new line of huge pylons in this area would be a retrograde step and a disaster for the Cumbrian landscape. The countryside in the UK is blighted by poles and wires in many places. This cannot be corrected overnight, but the long-term objective should be to remove as many pylons, poles and overhead wires as possible, and not to install more. We do not believe that our objection is a NIMBY (“Not in My Back Yard”) reaction. A more relevant acronym would be LAYBY – “Looking After Your Back Yard.” We are trying to look after this landscape for all of the future generations of visitors. Many of the millions of people who have to live in cities only find that tolerable if they can regularly escape to the wonderful landscapes in the National Parks. 1.1. Existing pylons National Grid believes that people will not object to replacement pylons that are twice as high and more than twice as wide. It describes the existing line as an “opportunity corridor.” We believe that the existing pylons are an eyesore and should never have been built in this wonderful landscape. The existing OHL was constructed around 1950 just before the National Park was created. There is therefore no precedent for Lake District National Park Authority (LDNPA) to have given permission for an OHL within the Park. LDNPA would not have allowed this construction if it had existed at the time. The existing pylons have been there for 65 years, and it is likely that the new ones would be there for at least another 65 years. This is not acceptable. NG_PWP_response_post_150617.doc 1.2. Ofgem VIP project Ofgem has recently provided £500m funding to National Grid “Visual Impact Provision” project to remove OHLs from National Parks. It would be senseless for National Grid to be funded by Ofgem to remove OHLs in other National Parks, while putting up a new one in the Lake District National Park. This route would contravene Ofgem’s own rules: “When installing this equipment companies must take into account the environmental impacts of new investment, including the visual impact of infrastructure. Action to conserve natural beauty might include finding alternative routes, undergrounding cables, alternative pylon design, tree screening and camouflage.” We do not accept that “alternative pylon design, tree screening or camouflage” would lessen the impact of 50m-high 400kV pylons. 2. Negative effects of Onshore with Tunnel option 2.1. Landscapes 2.1.1 Adopting the Onshore South with Tunnel option would have a major negative impact on the internationally and nationally important landscape and environment of the Lake District National Park and adjacent areas. It would contravene legislation designed to protect important areas of scenic beauty from damaging developments and flout national policy guidelines. 2.1.2 The National Parks and Access to the Countryside Act 1949, amended by the Environment Act 1995, states that the statutory purposes of National Parks are: “To conserve and enhance the natural beauty, wildlife and cultural heritage of the National Park; and To promote opportunities for the understanding and enjoyment of the special qualities of the National Park by the public.” 2.1.3 The 1995 Act also states that when exercising or performing any functions which affect land in a National Park any relevant authority (of which National Grid is one) shall have regard to National Park purposes. If it appears that there is a conflict between those purposes, greater weight should be attached to the purpose of conserving and enhancing the natural beauty, wildlife and cultural heritage of the National Park. By pursuing an onshore route, National Grid is not meeting its obligation as a Statutory Undertaker with a Duty under S62 of the Environment Act 1995 to have due regard to National Park purposes. 2.1.4 The National Planning Policy Framework states that great weight should be given to conserving landscape and scenic beauty in National Parks. Planning permission should be refused for major developments in these designated areas except in exceptional circumstances and where it can be demonstrated that there are no alternative options. Where applications are submitted they are required to include an assessment of any detrimental effect on the environment, the landscape and the extent to which that could be moderated. 2.1.5 The Holford Rules govern decisions on routeing overhead power lines today. They were first set out in 1959 – several years after the existing 132kV cabling was permitted. Rule 1 states that the major areas of highest amenity - which include National Parks; Areas of Outstanding Natural Beauty; Heritage Coasts and World Heritage Sites - should be avoided altogether if possible. It is possible to avoid these areas in this case. National Grid is ignoring the Holford Rules. 2.1.6 Section 31 of the English National Parks and the Broads UK Government Vision and Circular 2010 states that major development in or adjacent to the boundary of a Park can have a significant impact on the qualities for which they were designated. This needs to be considered in respect of all sections of the proposed corridor. 2.1.7 Whilst a significant proportion of the proposed overhead power lines lie within the Lake District National Park, a further longer stretch of lines lie within 2km of the National Park boundary where they are likely to have a significant adverse impact on the setting of and views from the National Park. 2.1.8 Outside the National Park, the proposed route includes two Special Areas of Conservation (Duddon Mosses and Drigg Coast at the Ravenglass Estuary) and a designated Heritage Coast section (St Bees Head.) In addition it impacts on other sensitive landscapes and seascapes. 2.1.9 PWP is concerned that National Grid has inaccurately assessed the landscape value and sensitivity to electricity infrastructure of the coastal plain through which the proposed route runs. The coastal plain on the Moorside to Silecroft section has open views between high fells to the coast. These views are greatly valued as part of the Lake District’s landscape character and 50m-high pylons would be a considerable detractor both when looking inland to the mountains from the coast, and towards the coast from the fells – for example from Corney Fell and Black Combe. 2.1.10 PWP has particular concerns about the area at the head of the Duddon Estuary, which falls within a Site of Special Scientific Interest (SSSI), Special Protection Area and Ramsar site. We consider neither route E2.1 nor E2.2 to be acceptable. We strongly object to the northern route (E2.2) for the following reasons: it is longer and would therefore disfigure more landscape; it runs closer to a centre of population; it would have a much greater visual impact on head of the Duddon Estuary. 2.2. Health 2.2.1 The government document, “National Policy Statement for Electricity Networks Infrastructure”, includes a section (2.10) on Electric and Magnetic Fields (EMFs) which states: “EMFs can have both direct and indirect effects on human health. The direct effects occur in terms of impacts on the central nervous system resulting in its normal functioning being affected.” 2.2.2 The document also gives guidelines for siting 400kV lines where houses and schools are nearby. Current proposals may contravene these guidelines where the planned route would pass close to schools. 2.2.3 Kirkby-in-Furness is of particular concern. If a new 400kV OHL were to follow the line of the existing 132kV OHL, as planned, it would be very close to the school and the site of a proposed housing estate behind the school. The corridor here is a very narrow, with little scope for rerouting. Not only would the much larger pylons needed for a 400kV line be an eyesore, but the higher voltage lines would also bring greater potential health risks from electric and magnetic fields. 2.2.4 There has also been discussion in the past relating to leukaemia clusters close to power lines. This has not been proved, yet equally it has not been disproved. 2.3. Cultural heritage 2.3.1 The Lake District plays an important national and international role in the development of the landscape conservation movement. Such is the significance of the Lake District National Park’s cultural landscape that the UK government backed an application for the National Park to be designated by UNESCO as a World Heritage Site. A proposal to site pylons through and close to the National Park is wholly incompatible with World Heritage status and may jeopardise the bid. 2.3.2 Ravenglass Roman Fort and bath house is part of the ‘Frontiers of the Roman Empire’ trans-national World Heritage Site. The impact of an electricity infrastructure on the landscape will have implications not only for the proposed Lake District World Heritage Site but also for the ‘Frontiers of the Roman Empire’ World Heritage Site and their settings. PWP is concerned that the effects of the planned route on valuable physical assets have not been fully assessed. 2.4. Ecology 2.4.1 Cumbria County Council has produced an assessment of the ecological implications of National Grid’s preferred option. Whilst it has assessed the effects of pylons above ground, it has not considered the ecological implications of mitigation such as undergrounding. If the onshore option is to be pursued, a comprehensive ecological assessment will be required. 2.5. Tourism 2.5.1 National Grid acknowledges that there is the potential for overhead pylon development to have an effect on tourism in the area. Tourism is a vital part of the local economy: farmers and landowners have been encouraged to diversify by providing holiday accommodation and many local businesses that provide products and services to visitors rely fully or partly on tourism. 2.5.2 Since the economy is therefore highly sensitive to landscape damage, it is necessary to have a clear understanding of the potential effects of an onshore route and the likely costs to the economy. 3. The case for mitigation 3.1. National Grid consultation 2014, stage 2 3.1.1. All the impacts referred to in Section 2. above were previously raised by many respondents in consultation stages 1 and 2. 3.1.2. Most public responses were in favour of the Offshore route. Stakeholder responses were more mixed, but many said or implied that if an onshore route were taken adequate mitigation would be needed in several places. They were not referring to the mitigation already on offer, i.e. the Morecambe Bay tunnel. 3.1.3. By adequate mitigation, we refer mainly to undergrounding. Tree screens do not work with 50m pylons. 3.1.4. Important locations requiring mitigation include: Lake District National Park: Ravenglass /River Irt /River Mite /River Esk /Roman remains Lake District National Park: coastal stretch Whicham valley in or just outside the Lake District National Park Duddon Estuary Lindal 3.2. Inconsistency There appears to be an inconsistency in National Grid’s attitude to mitigation. The Hinkley Point C grid connection plan shows an underground section, designed to mitigate the impact on the Mendip Hills AONB. Given that National Parks have a higher level of protection than AONBs, the implication is that this sort of mitigation would be offered as a matter of course in the Lake District National Park. 3.3. Justification National Grid has stated that “justification will be needed for more mitigation.” The justifiable case for effective mitigation has already been clearly made by many respondents to the consultation, to whom justification was obvious. Rather than requiring consultees to justify mitigation, we believe the onus should be on National Grid to justify the disfigurement of the landscape. Nothing we have heard so far justifies the destruction of the Lake District landscape, particularly when there is an alternative. 4. Offshore south sub-sea HVDC route PWP recognises the enormous problems associated with doing any effective mitigation on the National Grid-preferred Onshore route. There are potentially major problems associated with undergrounding and crossing river estuaries, including archaeology and ground conditions. It will be noted that the locations listed in Section 3.1.4 as requiring proper mitigation reflect most of the preferred overland route. For this reason PWP continues to insist that the Offshore sub-sea HVDC route is by far the best option. Nothing we have heard so far in any meetings or read in documentation convinces us that this route is impossible or impractical. National Grid has not said that it is impossible to construct. If it were not a feasible option, National Grid would not have proposed it. 4.1. Sub-sea element Despite what has appeared in the media, it has been stated in National Grid workshops that it is not impossible to bury the cables in the sea-bed. A number of potential sub-sea difficulties have been cited – including the risk of unexploded shells - but National Grid does not appear to view these as the main problem. The White Young Green report states that the offshore route “diverts away from the coast to avoid the Eskmeals firing range.” Furthermore, we believe that most Eskmeals test firing is not done with live shells. 4.2. HVDC/nuclear power station connection – technical difficulties We have requested, from National Grid and NUGEN, a technical description of the difficulties involved in connecting HVDC to a nuclear power station. We are still waiting. 4.2.1. “Nuclear Safety” We believe this term may be being used to justify rejection of the offshore option when this may not in fact be a safety issue at all. If this relates to the capability to import electricity in a disaster-type scenario, there must be alternative ways of handling this. 4.2.2. Technology approvals NUGEN is concerned about schedule delays due to having to gain approval for nonstandard technical options. This is not an adequate justification for rejecting the HVDC option. There would appear to be plenty of time to gain any necessary approvals. National Grid and NUGEN should be applying for these approvals now, and continuing to design this option, so that if the Infrastructure Planning Commission (IPC) rejects their preferred route, the schedule can still be maintained. We have requested from the Office of Nuclear Regulation details of any new approvals that might be required. 4.2.3. Security of supply We believe this term refers to the ability to export the generated electricity. This would appear to be a commercial issue, not a safety one. HVDC technology is described as slightly less reliable, but in this situation the northern AC OHL route would secure an adequate supply. It has been stated that the entire output of the power station can be carried on just one of the two northern AC circuits. There would therefore appear to be sufficient redundancy in a design which included an HVDC element. 4.2.4. White Young Green (WYG) consultancy technical report This report states: 1. “A simultaneous outage of two converter units or cable sections in the HVDC system would still permit security requirements to be maintained and generation from the plant could continue, rather than suddenly being reduced.” 2. “However, there are other potential issues with a DC link operating within the AC system. For example, power oscillations and frequency control could cause disturbance particularly if there is an unplanned outage of one of the converter units and where the other units have reached their maximum output. Issues such as these can be resolved by careful design and implementation of latest technology.” This would appear to indicate that there are some potential problems, but that they can be resolved. 4.3. Cost 4.3.1. The extra cost of an offshore HVDC route over and above the National Gridpreferred route is approximately 40%, or £400m (National Grid figure). However, this National Grid connection should be considered as part of the whole Moorside power station project. The extra cost of the Offshore route would be a very small proportion of the total cost (perhaps 3%). 4.3.2. The extra cost of an offshore HVDC route over and above the National Gridpreferred route is approximately 40%, or £400m (National Grid figure). However, this National Grid connection should be considered as part of the whole Moorside power station project. The extra cost of the Offshore route would be a very small proportion of the total cost (perhaps 3%). 4.3.3. £1bn of capital expenditure equates to £1 on annual electricity bills (National Grid figure). The extra cost to the consumer of the offshore HVDC option compared with National Grid-preferred onshore route is therefore 40p per annum. Locally, this tiny increase in electricity bills would be greatly outweighed by, for example, lost tourist revenue and traffic delays during the construction phase. 4.3.4. We understand that that the costs involved in providing an Offshore South route may conflict with National Grid’s “statutory duty to maintain an economic and efficient transmission system.” However, this duty needs to be balanced with National Grid’s statutory duty to have regard for the purposes for which the National Park was designated and also its duty to biodiversity under the NERC Act 2006. 5. Onshore route mitigation 5.1. PWP believes that the Offshore HVDC route is by far the best option. However, for the sake of completeness, we have listed below alternative technologies and routes that we are aware of. If adequate mitigation were to be done in all of the necessary locations on the onshore route, the onshore route option would almost certainly become much more expensive and difficult than the offshore one. 5.2 Alternative technologies 5.2.1 Gas-Insulated Line (GIL) The cable runs inside a gas-filled tube. The tubes can be installed in several different ways: for example buried in a trench, or cut-and-cover tunnel. One of the main advantages is that they can be installed much closer to each other than a standard underground cable. GIL advantages: Has far less visual impact on the landscape Takes far less space (corridor width) Removes Electrical Fields and reduces Magnetic Fields dramatically Considerably reduces transmission losses (paid for by tax payer on their electricity bill) Is safe to be close to Is safe in a failure state Causes minimal damage to the environment Has no impact on tourism, property values, or socio‐economic issues Can be virtually invisible when completed Reduces CO2 emissions Can be accessed 24 hours a day for maintenance Can readily accept additional capacity Is not affected by adverse weather Is less vulnerable to acts of terrorism Is easily monitored remotely 24/7 Allows installation inspections to be carried out remotely 24/7 Reduces time and cost of maintenance Reduces downtime Provides an available duct to run other services such as media/broadband cables Causes less disruption to local residents and visitors in the construction phase. 5.2.2 Horizontal Directional Drilling (HDD) The technology is derived from the oil industry and involves drilling down at an angle to pass under the river bed and then up the other side. The cable can then be dragged through the borehole. National Grid has stated that the distance limit in this situation is about 500m due to the required size of cable. (Longer distances can be achieved with HDD with smaller cable sizes.) 5.2.3 Undergrounding Compared with OHL construction and GIL, the standard undergrounding technique has a number of disadvantages. These include the opposite of most of the GIL advantages listed above. In addition it is expensive and requires a huge width of corridor for a double 400kV circuit (in construction the working width is approx 40m – 65m.) 5.3 Areas requiring mitigation 5.3.1 Lake District National Park Ravenglass/River Irt /River Mite /River Esk /Roman remains This area includes the historic village of Ravenglass, three separate estuaries, Muncaster Castle, and Roman remains including bath house. Adequate mitigation could mean HDD across the estuaries plus undergrounding. Another alternative method of crossing the estuaries could be by using the railway bridges. GIL could be of use in this area in order to restrict the necessary corridor width, and to mitigate the impact on archaeology. Note: This option was considered by National Grid (see “Route Corridors and Search Areas Considered and Not Taken Forward.”) 5.3.2 Lake District National Park coastal stretch Adequate mitigation can only mean undergrounding. This could be standard undergrounding, or perhaps GIL, in a trench or even in a tunnel (buried or surface) alongside the railway. 5.3.3 Whicham Valley The proposed OHL in the beautiful Whicham valley, with its ancient woodland sites, lies partly in and partly outside the Lake District National Park. Again, adequate mitigation can only mean undergrounding. 5.3.4 Duddon Estuary area – possible solutions 5.3.4.1 HDD in the lower estuary (Millom - Askam area) This would appear to be the best solution for the Duddon Estuary area, if it is technically feasible. If the maximum borehole length in this situation is 500m, this could be solved by building islands in the estuary to allow more than one stretch of HDD. The nature of the estuary here – shallow with deeper channels in the middle – would make this possible. Pros: Avoids a long section of pylons around the estuary. Cons: Ecological impact in estuary. PWP believes that any negative impacts of this option would be fewer than the visual, ecological and other impacts of pylons, together with their individual construction tracks, all around the estuary. Cost: The cost of this solution would need to be assessed but it could be less than installing the long stretch of pylons that it would replace. 5.3.4.2 Tunnel in the lower estuary (Millom - Askam area) This would be similar to the proposed Morecambe Bay tunnel, using AC cables. Pros: Avoids a long section of pylons around the estuary; technically feasible. Cons: None identified Cost: As a rough estimate, this could cost around £150m (offset by the cost of pylons around the estuary – perhaps around £50m.) 5.3.4.3 Undergrounding all the way around the estuary This could be standard undergrounding. Alternatively GIL could be used, in a trench or a tunnel (buried or surface), perhaps alongside the railway. Pros: Cons: regard. Cost: Avoids a long section of pylons around the estuary. Standard undergrounding needs a wide corridor. GIL is much better in that 5.3.4.4 Trenched cables in the lower estuary (Millom - Askam area) This would be an expensive solution There is an existing (lower voltage) cable already in this location that supplies electricity to Millom. There are believed to be problems with river bed scouring and shifting channels, that make this option less than ideal. Pros: Avoids a long section of pylons around the estuary. Cons: River bed scouring, shifting channels; ecological impacts. Cost: This is likely to be inexpensive 5.3.4.5 Trench further out to sea, in a loop just outside the estuary - variation on the previous option To avoid the problems with river bed scouring and shifting channels mentioned above, a trenched method could be used, going offshore from the Millom area, or maybe Silecroft, as far out as is necessary to avoid those problems, and coming back onshore - maybe in the Barrow area. This method would use AC cable. Pros: Cons: Cost: 5.3.4.6 Avoids a long section of pylons around the estuary. None identified This is likely to be inexpensive Extending the Morecambe Bay tunnel to cross the Duddon Estuary This would make the tunnel much longer, but might avoid the fixed upfront costs if, for example, the same tunnelling machines could be used. Pros: Cons: Cost: Avoids a long section of pylons around the estuary. None identified This could be expensive 5.3.4.7 Duddon crossing in the lower estuary (Millom - Askam area) This idea would make use of a proposed new road bridge or barrage to carry transmission cables across the estuary. Pros: Avoids a long section of pylons around the estuary. Cons: The time schedule for the grid connection may not permit waiting for the bridge to gain funding and permission. Ecological impact due to necessary piers in the estuary bed. PWP believes that the negative impacts of this option would be fewer than those of pylons (with their individual construction tracks) all around the estuary. Cost: For the grid connection this would be a low-cost solution. 5.3.4.8 Dedicated cable bridge in the lower estuary (Millom - Askam area) A bridge built just to carry transmission cables across the estuary. Pros: Avoids a long section of pylons around the estuary. Cons: Not visually attractive, though better than pylons all around the estuary, and better than a pylon crossing; ecological impact due to necessary piers in the estuary bed. PWP believes that the negative impacts of this option would be fewer than those of pylons (with their individual construction tracks) all around the estuary. Cost: Possibly less than the long stretch of pylons that it would replace 5.3.4.9 Pylon Duddon crossing in the lower estuary (Millom - Askam area) Pylons to carry transmission cables across the estuary. Some pylons would be necessary in the estuary itself. Pros: Avoids a long section of pylons around the estuary. Cons: Visual impact. Ecological impact due to necessary piers in the estuary bed. PWP believes that the negative impacts of this option would be fewer than those of pylons (with their individual construction tracks) all around the estuary. Cost: Possibly less than the long stretch of pylons around the estuary that it would replace. Note: This option was considered by National Grid (see “Route Corridors and Search Areas Considered and Not Taken Forward.”) 5.3.4.10 HDD at the head of the estuary, near the railway bridge This technique will be used for a new water main in this area, currently being constructed. Pros: Technically feasible. Cons: Avoids only one small section of pylons across the river at the head of the estuary. Cost: An inexpensive solution 5.3.5 Lindal The Lindal area, including the Lindal tee grid junction, is an existing eyesore, with lines of pylons going in four directions. This situation can only be made far worse by 400kV pylons. There is an existing pylon very close to Lindal school. Again, adequate mitigation can only mean undergrounding. 6. Conclusion There remains widespread support for the Offshore option. Many individuals and organisations that expressed support for the Onshore with Tunnel option did so with the caveat that adequate mitigation would be required in many areas. On closer analysis, areas requiring mitigation make up the greater part of the proposed land-based route. A number of mitigation measures are possible, yet the entire topic of mitigation is fraught with difficulties. Major difficulties include irreconcilably conflicting issues surrounding biodiversity, ecology and landscape preservation, and cost. To provide the mitigation likely to be required to meet National Grid’s various statutory obligations with regard to environmental protection would in all probability outweigh the cost of the Offshore option. Many, if not all, of the negative impacts stated in Section 2. above were recognised by National Grid in relation to the Onshore route without tunnel which would take pylons around Morecambe Bay. As a result, this option has now been ruled out. These same negative impacts apply to the overland parts of the Onshore with Tunnel route – and perhaps in greater measure due to the particular sensitivities of many areas. It is illogical and difficult to understand that National Grid now appears to disregard these factors. We intend to challenge National Grid’s plans at the Infrastructure Planning Commission enquiry. We assume that National Grid will be progressing the design for an offshore HVDC route in parallel with its preferred route, to allow for the possibility of the onshore route being rejected by the Planning Inspectorate. It is totally unacceptable to construct a new line of giant pylons in and around the Lake District National Park. PWP’s conviction is that the Offshore route is the only rational solution to connecting Moorside to the electricity grid.