Ground TDMA calibration Calibration by _______________ on (date) ___________ Set up: 1. Turn on TDMA computer and run ground tdma.vi. 2. Start and stop program to shut off power relay. 3. Select “Calibration” from the folder list at the top of the front panel. 4. Record the previous defaults from the front panel. Offset Slope Plumbing time = + /Qs Smearing time = + /Qs Up Down HV zero: 5. Change RH Equilibration time (located in the “0” frame of the main sequence) to 1000000 seconds. 6. Open “Corrected single scan G.vi” (adj. AI icon), “RH control G.vi” (RH cont icon), and “Flow rates PID G.vi” (flows PID icon). 7. Record previous defaults from each of these files: Flow rates G.vi Qs upper limit Qs lower limit Qsh_up lower limit Qsh_dn lower limit RH and T control G.vi Upper limit upstream Lower limit downstream Corrected single scan G.vi Channel Offset 0 (Qs) Multiplier 1 (Qsh up) 2 (Qsh dn) 3 (HV up) 4 (vol T) 5 (RH 2) 6 (RH 3) 7 (RH 1) 8. Set all of the offsets in Corrected single scan G.vi to 0.0 and multipliers to 1.0. 9. Turn all power switches on. 10. Start the program. Relative humidity probe calibration: 1. If probes are not already labeled, attach numbered labels to each. 2. Place all 3 probes in swagelok fittings in calibration system. 3. If available, place an HMP45A probe in the calibration system. 4. Calibrate the probes using each of the saturated salt solutions: Magnesium chloride (33.0%) Sodium chloride (75.6%) Potassium chloride (84.5%) Potassium sulfate (97.5%) RH 1 In between nafion tubes RH 2 (Just upstream 2nd DMA) RH 3 (Downstream of 2nd DMA) HMP45A 5. Plot calibration data in Excel (actual values = Y, expected values = X). 6. Add linear trendlines to each set of points, and have equation and R2 value printed on plot. 7. Enter best fit values and R2 below and in Corrected single scan.vi Multiplier (equal to slope in best fit) Offset (include sign from best fit) R2 Ch 7: RH 1 In between nafion tubes Ch 5: RH 2 (Just upstream 2nd DMA) Ch 6: RH 3 (Downstream of 2nd DMA) HMP45A 8. Print out the graphs and tape in the space below. 9. Connect the Gilibrator to the “Humidty inlet” swagelok fitting. 10. Set the “upper limit RH” and “lower limit RH” voltages on the front panel of RH control G.vi to 0.0 and measure the purge flow rate with the Gilibrator. 11. Incrementally increase these two limits (always equal) until finding the voltage that causes a slight increase in the purge flow rate. Enter that lower limit voltage below. Lower limit upstream (V) 12. Continue slowly increasing the two limits until no further increase in the purge flow rate is observed. Enter that upper limit voltage below Upper limit upstream (V) 13. Record several (~10) voltage and corresponding flow rate pairs in the table below. Voltage applied to valve Flow rate measured with Gilibrator (L/min) 1 2 3 4 5 6 7 8 9 10 14. Plot these data, print out the graph, and tape in the space below. 15. Enter the new limits in RH control G.vi. Tape RH 1 graph here TapeRH 2 graph here Tape RH 3 graph here Tape saturator flow rate graph here Flow rate calibration: 1. Start and stop program to shut off power relay. 2. Turn the regenerative blowers and the Qs / CNC pump off. 3. Start the program. 4. After the relay has been turned on (after a few seconds) zero each of the flow meters. 5. Start and stop program to shut off the power relay. 6. Turn the regenerative blowers and Qs / CNC pump on. 7. Attach Gilibrator tubes in line immediately before sample flow meter. 8. Start the program. 9. Change the Qs lower limit and Qs upper limit voltages on the front panel of flow rates PID G.vi to 0.0. 10. Enter the voltage measured by the flow meter and the flow rate measured by the Gilibrator in the “flow calibration data Table”. 11. Incrementally increase these two limits (always equal) until finding the voltage that causes a slight decrease in the sample flow rate. Enter this lower limit voltage below. Qs lower limit (V) 12. Adjust these limits such that flow rates of approximately 2.0 and 1.0 L/min are measured. Enter the voltages measured by the flow meter and the flow rates measured by the Gilibrator in the “flow calibration data Table”. 13. Continue to increase these limits until no further change in the sample flow rate is observed. Enter this upper limit voltage below. Qs lower limit (V) 14. Enter the voltage measured by the flow meter and the flow rate measured by the Gilibrator in the “flow calibration data Table”. 15. Connect the Gilibrator to the sample inlet. 16. Change the Qs lower limit and Qs upper limit voltages on the front panel of flow rates PID G.vi to 0.0. 17. Enter the flow rate measured by the Gilibrator and by the Qs flow meter below. Qa flow rate (Gilibrator) Qs flow rate (V) 18. Differences between these flow rates (after the Qs flow is corrected) could indicate that there is a leak in one of the sheath flow lines upstream of the filter. 19. Stop the program. 20. Attach Gilibrator tubes in line with the upstream sheath / excess flow loop either downstream of the filter or upstream of the regenerative blower. 21. Change the Qsh_up upper limit and Qsh_up lower limit on the front panel of flow rates PID G.vi to 0.5. 22. Start the program. 23. Slowly (0.3 V at a time) increase both of these limits until reaching 2.2 V. 24. Enter the voltage measured by the flow meter and the flow rate measured by the Gilibrator divided by 20.0 (to relate to the expected flow meter voltage) in the “flow calibration data Table”. 25. Slowly adjust these two limits down such that flow rates of approximately 20.0 and 10.0 L/min are measured. Enter the voltages measured by the flow meter and the flow rates measured by the Gilibrator divided by 20.0 in the “flow calibration data Table”. 26. Continue slowly decreasing these values until blowers stop and no further change in the flow rate is observed. Enter this lower limit voltage below. Qsh up lower limit (V) 27. Enter the voltage measured by the flow meter and the flow rate measured by the Gilibrator divided by 20.0 (hopefully 0.0) in the “flow calibration data Table”. 28. Repeat steps 19 through 27 for the downstream sheath / excess loop Qsh down lower limit (V) 29. Enter the new defaults in flow rates PID.vi. 30. For each of the three flows, plot the calibration data in Excel (for Qs, flow meter voltage = Y, Gilibrator flow rate = X; for Qsh, flow meter voltage = Y, Gilibrator flow rate / 20.0 = X). 31. Add linear trendlines to each set of points, and have equation and R2 value printed on plot. 32. Enter best fit values and R2 below and enter the new multipliers and slopes in Corrected single scan.vi 33. Print out the graphs and tape in the space below. Flow calibration data Table Qs Qsh_up Gilibrator Flow meter [Gilibrator Flow meter flow rate voltage flow rate voltage (L/min) (L/min)]/20.0 Qsh_dn [Gilibrator Flow flow rate meter (L/min)]/20.0 voltage Multiplier (equal to slope in best fit) Offset (include sign from best fit) R2 Ch 0: Qs Ch 1: Qsh_up Ch 2: Qsh_dn 34. Stop the ground tdma.vi, but do not re-start. 35. Within corrected single scan G.vi, flow rates PID.vi, and RH control G.vi, select Operate<<Make current values default, and then save each of the files. Tape Qs calibration graph here Tape Qsh up calibration graph here Tape Qsh dn calibration graph here High voltage supply calibration: 1. Turn both high voltage on/off switches off (the pumps should still be on after finishing the flow calibration). 2. Wait a few seconds to ensure high voltage is discharged, then disconnect the upstream high voltage BNC connector from DMA. 3. Insert extension wire (single strand wire, stripped on both ends, with one end usually folded over) into center of gold colored receptor inside of high voltage connector. 4. Plug high voltage probe leads into multimeter and ground clip onto HV supply. 5. Inexpensive multimeters often have a lower impedence than is necessary for the HV probe, and should not be used to calibrate the supplies. 6. In some manner (aluminum tape, cable ties, …), fix the high voltage connector and (preferably) the high voltage probe such that the probe tip remains in contact with the stripped portion of the extension wire. 7. Open the analog output test panel (not data neighborhood) and select the channel number corresponding to the upstream high voltage output (probably Ch 3). 8. Enter 0.0 and press “update channel”. 9. Turn the on/off switch for the upstream HV power supply on. 10. Slowly vary the control voltage (could be up or down) until the zero is found. It is possible that the voltage measured by the probe will not be zero, but it should not change when the control voltage is decreased slightly, but should when the control voltage is increased slightly. 11. To ensure the true zero was found, vary the control voltage above and below the zero and enter the results below (It’s probably wise to use pencil first in case the zero has to be changed. Control V Zero – 0.0010 = Probe Control V Zero – 0.0010 = Zero – 0.0008 = Zero – 0.0008 = Zero – 0.0006 = Zero – 0.0006 = Zero – 0.0004 = Zero – 0.0004 = Zero – 0.0002 = Zero – 0.0002 = Zero Zero = Probe = Zero + 0.0002 = Zero + 0.0002 = Zero + 0.0004 = Zero + 0.0004 = Zero + 0.0006 = Zero + 0.0006 = Zero + 0.0008 = Zero + 0.0008 = Zero + 0.0010 = Zero + 0.0010 = 12. Plot the values in the table above with the control V along the x-axis and the probe V along the y-axis. The kink in the curve should be located at the HV zero. Print out the graph and tape in the space below. Tape HV up zero determination graph here Tape HV down zero determination graph here 13. Enter the upstream HV zero on the front panel of ground tdma.vi, and in the table below. 14. Sequentially change the input voltage to 0.1 V, 1.0 V, and 3.0 V and record the probe voltage measured by the multimeter below (just the voltage, don’t multiply by 1000). 15. Repeat steps 1 through 14 for the downstream high voltage supply. Input (zero =) Upstream HV Probe Input (zero =) 0.1 V 0.1 V 1.0 V 1.0 V 3.0 V 3.0 V Downstream HV Probe Plumbing time calibration: 1. Add 1 drop of 60 nm PSL to 750 mL of water (D.I. or better) in the atomizer. 2. Fully open the atomizer flow valve, fully close the dilution flow valve, and adjust the compressed air pressure to 25 psi. 3. On the ground tdma.vi front panel, set the Qsh maximum to 25 L/min, Qsh/Qa to 10.0, the plumbing time slope to 0.0, the diameter range to 0.01 to 0.4 m, and the scan time to 60 s. 4. Change the RH equilibration time to 60 seconds and begin the ground tdma.vi program. 5. Wait until the DMA scan is complete, then stop the program and adjust the plumbing time offset to improve up and down scan agreement (increasing the value pushes the upscan distribution to the left and downscan distribution to the right). 6. Once the PSL peaks within the up and down scans are at the same location, enter the plumbing time offset used in the table below. 7. Change the Qsh maximum to 10.0, and repeat steps 4 and 5. 8. Note: It is very important that the sample flow be controlled during this calibration. If the sample flow is not controlling well, it may be necessary to alter the PID parameters or increase the RH equilibration time. Qsh 25.0 Plumbing time offset (s) 10.0 9. Calculate the plumbing time slope and offset: slope offsetQsh 10 L / min offsetQsh 25 L / min 0.6 offset offsetQsh 10 L / min slope Plumbing time slope (s / L/min) Plumbing time offset (s) 10. After entering the new plumbing time slope and offset, select Operate<<Make current values default, and then save the file. Hygroscopic growth calibration: 1. Turn the compressed air flow to the atomizer off. 2. Rinse out the atomizer solution bottle and add 0.75 g of NaCl to 750 mL of D.I. water. 3. Fully open the dilution flow valve on the atomizer cart and close the atomizer valve ~ ¾ of the way. 4. Increase the number of TDMA bins by a factor of 5 (but not the scan time), change the upper limit of the RH range to 85.0%, and change the RH Equilibration time to 1800 seconds. 5. Change the DMA scan time to 20 seconds, and enter 0.03, 0.08, and 0.2 m in the Dp_up for TDMA array. 6. Run the program and wait until all of the TDMA measurements are finished. 7. Once the scans are complete and the distributions plotted, open loop_1.txt from the for_plot folder in which the data the saved using Excel. 8. Plot the data and identify the peak in the growth factor distributions for each of the dry sizes considered. Locate the corresponding peaks in the concentration column and enter the growth factors corresponding to each of these peaks below: Dp_up (m) 0.03 Measured Growth factor Expected Growth factor 2.047 0.08 2.110 0.2 2.136