Argumentos Engineering Jurisdiction – Were the preconditions to arbitration as provided in clause 18 of the contract properly fulfilled? 1.1. ACICA OK. Article 24 just states about the kompetenz-kompetenz principle. 1.2. UNCITRAL Conciliation Rules. 1.2.1. The parties participated actively in the conciliation proceedings. Article 6 states that the parties may be represented or assisted by persons of their choice. Besides that, CEO é um órgão corporativo – pouco importa a pessoa - Mr. Holzer was in charge of operations. He exercised such other duties as were delegated to him by the CEO. Oxford Business English Dictionary says that deputy is: “a person who is immediately below the head of an organization, a department, etc. in rank and who is officialy in charge when that person is not there [the CEO’s daughter was getting married on 29 May 2009]”. Thus, Mr. Holzer’s name with his title was in the list of participants at the conference. 1.2.2. Role of the conciliator. Article 7 was fulfilled, the conciliator assisted the parties in their attempt to reach an amicable settlement of their dispute. 1.2.3. Termination of conciliation proceedings. Article 15 was fulfilled because there was a written declaration of the conciliator, after consultation with the parties, to the effect that further efforts at conciliation are no longer justified (Danubia Arbitration Center has a copy of this declaration, which is dated 4 June 2009). Argumento subsidiário: Ainda que a presence do CEO não tivesse sido regular. 1.3. Princípio de que não há nulidade sem prejuízo; “pas de nullité sans grief”. Não houve qualquer prejuízo ao eventual sucesso da conciliação pelo fato de nela haver figurado o Deputy CEO, pois inexistia qualquer disposição de ambas as partes para a conciliação. Seu resultado teria sido o mesmo qualquer que fosse a pessoa. Breach of good faith duty: The week following the Conciliation Mr. Wilson (Super Pumps) noticed that Mr. Holzer (Engineering) was the Deputy CEO and not the CEO. Why Super Pumps is arguing this just now? Why Super Pumps did not say before that the Conciliation proceedings was not conducted properly? - art. 8º (3) CISG: “in determining the intent of a party or the understanding a reasonable person would have had, due consideration is to be given to all relevant circumstances of the case including the negotiations, any practices which the parties have established between themselves, usages and any subsequent conduct of the parties”. 1.4. Princípio da boa-fé. - art. 7º (1) CISG: “In the interpretation of this Convention, regard is to be had to its international character and to the need to promote uniformity in its application and the observance of good faith in international trade”. The Guide to Enactment and Use of the UNCITRAL Model Law on International Commercial Conciliation (2002) states that art. 2 of the Model Law provides guidance for the interpretation of the Model Law by Courts and was inspired by art. 7 of the CISG; - art. 2 (1) of UNCITRAL Model Law on Conciliation: “in the interpretation of this Law, regard is to be had to its international origin and to the need to promote uniformity in its application and the observance of good faith” - Art. 13 of UNCITRAL Model Law on Conciliation: ver se a regra se encaixa (é o Tribunal Arbitral que deve examinar a aplicabilidade da exceção à eficácia do undertaking to conciliate entered into by the parties). Ultimo argumento (talvez somente oral): De qualquer modo, as partes podem exercer a faculdade de conciliar em qualquer etapa do procedimento arbitral. 1.4. Doctrine. - Gary Born says: “in general, national courts and arbitral tribunals have been reluctant to conclude that compliance with contractual procedural requirements is a jurisdictional condition for commencing an arbitration. A substantial body of arbitral authority from investor-state disputes concludes that compliance with procedural mechanisms in an arbitration agreement (or bilateral investment treaty) is not ordinarily a jurisdictional prerequisite”. Similar arbitral authority exists in other contexts1”. He also states that: “where a party attempts to delay arbitration by insisting on enforcement of a negotiation requirement, courts may decline to assist that party in its delay efforts. Thus, even where the contract at issue included ‘a term requiring mediation ... as a condition precedent to arbitration,’ a court held that ‘surely a party may not be allowed to prolong resolution of a dispute by insisting on a term of the agreement that, reasonably construed, can only lead to further delay.” 2 1 See Interim Award in ICC Case Nº 10256, in Figuera, Multi-Tiered Dispute Resolution Clauses in ICC Arbitration, 14(1) ICC Ct. Bull. 82,87 (2003); Final Award in ICC Case No. 8445, XXVI Y.B. Comm. Arb. 167 (2001): clause requiring efforts to reach amicable settlement, before commencing arbitration, “are primarily expression of intention” and “should not be applied to oblige the parties to engage in fruitless negotiations or to delay an orderly resolution of the dispute”. 2 See Interim award in SCC of 17 July 1992, XXII Y.B. Comm. Arb. 197 (1997) (language of consultation clause is optional in nature); Cumberland and York Distrib. V. Coors Brewing Co., 2002 WL 193323, at *4 (D. Me. 2002) (citing Southland Corp. v. Keating, 465 U.S. 1 (US. S.Ct 1984)):”Courts seek to ensure that contractual dispute resolution mechanisms are not abused or used for improper purposes”. Merits 1) Fundamental breach (Isadora / João Vicente / Larissa) Super Pumps had an obligation to provide pumps that were in conformity with the regulations adopted after the date of the contract SP has always known that the pumps were to be employed in a particular irrigation project in Oceania. The contract wording was in line with this. Acknowledgement of this obligation: when the first change in Oceania regulation came about, to exclude berilyum from the pumps, SP complied with the change without resistance. It only charged Engineering for the extra costs involved with the change. Even with the second change in Oceania regulation, SP would have complied with its contractual obligations if it had delivered the pumps in a timely manner, according to the contract. The (second) new regulation relates to pumps manufactured in Oceania or imported into Oceania, allowing for the use of non-conformity pumps manufactured or imported before 1st of January, 2009. Were SP in breach of its obligation to deliver the pumps by the delivery date in the contract of 15 December, 2008, or, as extended to 22 December, 2008? Super Pumps breached the contract. The seller was under the obligation to deliver the pumps to Engineering in Capital City, Mediterraneo, by 22 December, 2008, and only did so in 6 January , 2009. Delivery date was amended according to a new agreement by the parties (aditamento). This is an implied term in the sense that SP and Engineering would agree to new contractual terms and conditions whenever Oceania enacted new regulations concerning the pumps. (Parties conduct – good faith – see articles 7 and 9 CISG). The contract breach was fundamental (art. 25) because: a) time was of the essence of the contract (problem, page 18) b) delivery of the pumps in breach of the contract date resulted in a detriment to Engineering: because of the late delivery, Engineering contract with Oceania Water SVC was cancelled under the new regime regulation c) this detriment was substantial enough to deprive Engineering of what it was entitled to expect under the contract: Engineering was entitled to use the pumps on the irrigation project in Oceania, according to its contract passed with Oceania Water SVC. d) SP could foresee that the late delivery of the pumps would result in the cancellation of Engineering contract with Oceania Water SVC (remete ao primeiro ponto – time was of the essence of the contract - Problem, p. 18). This is not a case involving force majeure. Accident at the canal. DES Incoterm clause. Pouco mais de um parágrafo. De todo modo, ver advisory opinion n. 7 Did Engineering fail to mitigate the consequences of the cancellation of irrigation contract? Obrigação de meios – dever de envidar esforços – Engineering (aparentemente) não a cumpriu. p. 38 do problema: Trading Co. Mediterraneo era conhecida de Engineering e possuía algumas bombas adequadas para entrega. CISG, art. 77 – reasonable Our date is December, 28 (the latest date regarding the breach) On Dec. 28, three days before the entry into force of new restrictions to pumps enacted by Oceania, it was not reasonable to expect from Engineering to find the only person on Earth that had some of the pumps that fitted the contract specifications. Digest p. 241, parágrafo 11 – CLOUT 166 (ótima decisão) Calculation of damages Gotanda Ver advisory opinion n. 8 Under article 74 – ver advisory opinion 6 Juros Custos de arbitragem