AutoEdge EHP4 for SAP ERP 6.0 March 2011 English Scheduling Agreement with Summarized JIT Call (A67) Business Process Documentation SPARTA A KPIT Cummins Company Corporate Headquarters 111 Woodmere Road Suite 200 Folsom, CA 95630 888-985-0301 916-985-0300 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Contents 1 Purpose ......................................................................................................................................... 3 2 Prerequisites.................................................................................................................................. 4 2.1 Master Data and Organizational Data .................................................................................... 4 2.2 Business Conditions ............................................................................................................... 5 2.3 Roles ...................................................................................................................................... 5 3 Process Overview Table ............................................................................................................... 6 4 Process Steps ............................................................................................................................... 8 5 4.1 OEM Processes: Planned Independent Requirements Processing ...................................... 8 4.2 OEM Processes: Material Requirements Planning ................................................................ 9 4.3 OEM Processes: Displaying the Schedule Lines in the Scheduling Agreements ............... 11 4.4 OEM Process: Creating Scheduling Agreement Release ................................................... 11 4.5 OEM Process: Displaying the Releases from the Scheduling Agreements ........................ 13 4.6 OEM Process: Message Outputting: Delivery Schedules .................................................... 14 4.7 OEM Process: EDI Outbound Processing, Forecast Delivery Schedule ............................. 15 4.8 Supplier Process: EDI Inbound Processing, Forecast Delivery Schedule ........................... 16 4.9 Supplier Process: Processing Forecast Delivery Schedule for Scheduling Agreement ...... 17 4.10 OEM Process: Material Staging – Summarized JIT Call .................................................. 18 4.11 OEM Process: Changing/Displaying the Summarized JIT Call........................................ 19 4.12 OEM Process: Sending an Outbound Summarized JIT Call............................................ 20 4.13 Supplier Process: SD Determination of the Incoming Summarized JIT Call ................... 21 4.14 Supplier Process: Calling Monitoring for the Inbound Summarized JIT Calls .................. 22 4.15 Supplier Process: Delivery the Summarized JIT Call ....................................................... 23 4.16 Supplier Process: Posting Good Issue ............................................................................. 24 4.17 Supplier Process: Billing the Outbound Delivery / Summarized JIT Call ......................... 25 4.18 OEM Process: Posting GR for outbound JIT call ............................................................. 26 4.19 OEM Process: Completing / Deleting the Outbound JIT Call........................................... 27 Close Action ................................................................................................................................ 28 5.1 OEM Process: Reverse Stock.............................................................................................. 28 5.2 OEM Process: Reverse Independent Requirements Processing ........................................ 29 5.3 OEM Process: Material Requirements Planning.................................................................. 30 ©2011 Sparta Consulting Page 2 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Scheduling Agreement with Summarized JIT Call 1 Purpose General Information and Target User This documentation gives an instruction on how the scenario: (A67 – Scheduling Agreement with Summarized JIT Call) is processed from business point of view, Also, it gives a step by step operation guide, which the users can follow to finish the process of this scenario. The target user of this documentation will possibly be: Partners Customers Overview The incoming summarized JIT call inbound receives calls whose items comprise a date and quantity pair. The items are not linked to the finished product and are not delivered in a predefined sequence. The call reference number controls downstream processes, such as the delivery creation or the transport creation. This type of processing can be employed when the manufacturer transfers calls for non-vehicle related materials. Call components (= materials ordered via releases) are often pre-produced and the summarized JIT calls can be delivered immediately after the goods have been received. The call components are documented in the delivery Comment and in the subsequent invoice. The R/3 System contains a material master for each call component. In general, the following scenarios are supported: Calls for individual materials: In a summarized JIT call, the manufacturer sends one or more quantities and dates for a call component. The system stores the summarized JIT call reference number as an external call number in the call header (the external reference number is stored in the summarized JIT call at header level). This scenario can be used for mapping PSA / NISSAN / RENAULT KANBAN calls. Calls for multiple materials: In a summarized JIT call, the manufacturer sends multiple materials for a summarized JIT call number and date. The system stores each material as a call component and stores the reference number as an external call number (the external reference number is stored in the summarized JIT call at item level). This scenario can be used for mapping the OPEL MAIS pick up sheet. Note This form of sales order processing is essentially different from mapping the summarized JIT calls as JIT calls (that is, importing a summarized JIT call as a JIT call) in two ways: The manufacturer does not transfer any cumulative quantities or a “final delivery number”. In the same way various information about the summarized JIT call is sent, such as a KANBAN number (in variant 2 this is the outbound summarized JIT call number), point of consumption, and so on. This information must be stored in the JIT call at schedule line level (no fields are available for this in the JIT call). This process description focuses on the “calls for individual materials” scenario. ©2011 Sparta Consulting Page 3 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Creating an outbound summarized JIT call Creating a summarized JIT call in inbound processing Delivering the summarized JIT call Billing the summarized JIT call delivery The manufacturer uses forecast delivery schedules to transfer a rough estimate of the quantities required. The summarized JIT call transfers a refined outbound forecast and a delivery release. This occurs when the manufacturer: 2 Sends a manually created outbound summarized JIT call to the supplier via EDI. The supplier supplies the data from the summarized JIT call accordingly and bills the services he has performed. Prerequisites 2.1 Master Data and Organizational Data Default Values Essential master and organizational data was created in your ERP system during the implementation phase, such as the data that reflects the organizational structure of your company and master data that suits its operational focus, for example, master data for materials, vendors, and customers. The business process is enabled with this organization-specific master data, examples of which are provided in the next section. Use the following master data in the process steps described in this document: Master / Org. Data Value Master / Org. Data Details Material A-67-2000_OEM Air Condition Type A Plant 1000 Vendor A-V6701 A production plant Vendor A-V6701 OEM Client Master data: MM Scheduling Agreement 560006701 Supplier Client Master data: Material A-67-2000_SUP Air Condition Type A Sold-to party: A-6701 Customer A-6701 Customer A-6701 Customer A-6701 Sales organization: 1000 Dom. Sales Org Distribution Channel 10 Direct Sales Division 10 Product Division 10 Plant 1000 Storage Location 1040 A production plant Shipment w / o LWM ©2011 Sparta Consulting Page 4 of 31 Comments AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 2.2 Business Conditions The business process described in this Business Process Documentation is part of a bigger chain of integrated business processes or scenarios. As a consequence, you must have completed the following processes and fulfilled the following business conditions before you can start going through this scenario: Business Condition Scenario You have completed all relevant steps described in the Business Process Documentation Prereq. Process Steps (154). Prereq. Process Steps (154) 2.3 Roles Use The following roles must have been installed to test this scenario in the SAP NetWeaver Business Client (NWBC).You only need these roles if you are using the NWBC interface. You do not need these roles if you are using the standard SAP GUI Prerequisites The business roles have been assigned to the user who is testing this scenario for OEM Client. Business Role Technical Name Process Step Employee (Professional User) SAP_NBPR_EMPLOYEE-S Assignment of this role is necessary for basic functionality. Strategic Planner SAP_NBPR_STRATPLANNERS OEM Processes: Planned Independent Requirements Processing Production Planner SAP_NBPR_PRODPLANNER-S OEM Processes: Material Requirements Planning Purchaser SAP_NBPR_PURCHASER-S OEM Processes: Displaying the Schedule Lines in the Scheduling Agreements OEM Process: Creating Scheduling Agreement Release OEM Process: Message Outputting: Delivery Schedules IT Administrator (Professional User) SAP_NBPR_IT_ADMIN-S OEM Process: EDI Outbound Processing, Forecast Delivery Schedule Production Planner (AUTO) SAP_NBPR_PRODPLANNER_ AUTO-S OEM Process: Material Staging – Summarized JIT Logistics Execution JIT (AUTO) SAP_NBPR_JIT_AUTO-S OEM Process: Changing/Displaying the Summarized JIT Call OEM Process: Sending an Outbound Summarized JIT Call OEM Process: Posting GR for ©2011 Sparta Consulting Page 5 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Business Role Technical Name Process Step outbound JIT call OEM Process: Completing / Deleting the Outbound JIT call The business roles have been assigned to the user who is testing this scenario for Supplier Client. Business Role Technical Name Process Step Employee (Professional User) SAP_NBPR_EMPLOYEE-S Assignment of this role is necessary for basic functionality. IT Administrator (Professional User) SAP_NBPR_IT_ADMIN-S Supplier Process: EDI Inbound Processing, Forecast Delivery Schedule Sales Administrator SAP_NBPR_SALESPERSON-S Supplier Process: Processing Forecast Delivery Schedule for Scheduling Agreement Logistics Execution JIT (AUTO) SAP_NBPR_JIT_AUTO-S Supplier Process: SD Determination of the Incoming Summarized JIT Call Supplier Process: Calling Monitoring for the Inbound Summarized JIT Calls Supplier Process: Delivery the Summarized JIT Call Warehouse Clerk SAP_NBPR_WAREHOUSECLE RK-S Billing Administrator SAP_NBPR_BILLING-S 3 Supplier Process: Posting Good Issue Supplier Process: Billing the Outbound Delivery / Summarized JIT Call Process Overview Table Process Step Business role Transaction Code Expected Results OEM Processes: Planned Independent Requirements Processing Strategic Planner MD61 OEM Side: Planned Independent Requirements Created OEM Processes: Material Requirements Planning Production Planner MD02 MRP run OEM Processes: Displaying the Schedule Lines in the Scheduling Agreements Purchaser ME39 Displaying the Schedule Lines ©2011 Sparta Consulting External Process Reference Business Condition Page 6 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Process Step Business role Transaction Code Expected Results OEM Process: Creating Scheduling Agreement Release Purchaser ME84 Created Scheduling Agreement Release OEM Processes: Displaying the Schedule Lines in the Scheduling Agreements Purchaser ME39 Displaying the Schedule Lines OEM Process: Message Outputting: Delivery Schedules Purchaser ME9E Delivery Schedules Message is Output OEM Process: EDI Outbound Processing, Forecast Delivery Schedule IT Administrator (Professional User) WE05 EDI Outbound display Supplier Process: EDI Inbound Processing, Forecast Delivery Schedule IT Administrator (Professional User) WE05 EDI Iutbound display Supplier Process: Processing Forecast Delivery Schedule for Scheduling Agreement Sales Administrator VA33 Display the forecast delivery schedule OEM Process: Material Staging – Summarized JIT Production Planner (AUTO) PK23 summarized JIT call has been generated OEM Process: Changing/Displaying the Summarized JIT Call Logistics Execution JIT (AUTO) PJ03 Displaying the Summarized JIT Call OEM Process: Sending an Outbound Summarized JIT Call Logistics Execution JIT (AUTO) JITOM an outbound summarized JIT call is send to the supplier Supplier Process: SD Determination of the Incoming Summarized JIT Call Logistics Execution JIT (AUTO) EMJIT check the IDOC received from customer Supplier Process: Calling Monitoring for the Inbound Summarized JIT Logistics Execution JIT (AUTO) JIT3 summarized JIT call with the external ©2011 Sparta Consulting External Process Reference Business Condition Page 7 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Process Step External Process Reference Business Condition Business role Transaction Code Calls Expected Results number display Supplier Process: Delivery the Summarized JIT Call Logistics Execution JIT (AUTO) JITK a delivery is created for the summarized JIT call Supplier Process: Posting Good Issue Warehouse Clerk VL02N a delivery is posted for the summarized JIT call Supplier Process: Billing the Outbound Delivery / Summarized JIT Call Billing Administrator VF04 billing is carried out OEM Process: Posting GR for outbound JIT call Logistics Execution JIT (AUTO) JITOM OEM post goods receipt for outbound JIT call. OEM Process: Completing / Deleting the Outbound JIT call Logistics Execution JIT (AUTO) JITOM OEM finishes the processing of outbound JIT call 4 Process Steps 4.1 OEM Processes: Planned Independent Requirements Processing Use PIRs (Planned Independent Requirements) is created in this step. This step will reflect on MRP run and generate schedule lines. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Production Production Planning Demand Management Planned Independent Requirements Create Transaction code MD61 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role ©2011 Sparta Consulting Strategic Planner Page 8 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD (SAP_NBPR_STRATPLANNER-S) Business role menu Production Production Planning Demand Management Create Planned Indep. Requirements 2. On the Create Planned Independent Requirements: Initial Screen, make the following entries: Field name Description User action and values Comment Material A-67-2000_OEM Change the planned independent requirements for each material Plant 1000 Version 00 Planning period M 3. Choose User Parameters, 4. On the Settings: User Parameters pop-up screen, make the following entry: Field name Description User action and values Comment VSF Requirements type 5. Choose Enter to confirm your entries. 6. Choose Continue (Enter) in the Information dialog box to confirm the save of user parameters. 7. On the Create Planned Independent Requirements: Initial Screen, choose Enter. 8. Choose Sched.lines tab page. 9. On the Plnd ind.reqmts Create: Schedule Lines screen, make the following entry: Field name Description User action and values Comment ReqmtDate. Next month For example, 12.2010 Planned qty 200 10. Choose Save. 11. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.2 OEM Processes: Material Requirements Planning Use In this step, we run MRP to generate schedule line. Prerequisites ©2011 Sparta Consulting Page 9 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD The vendor A-V6701 is stored in the source list as a fixed vendor for materials A-67-2000_OEM and therefore, material requirements planning generate schedule lines automatically. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Production MRP Planning Multilevel Single-Item Planning Transaction code MD02 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Production Planner (SAP_NBPR_PRODPLANNER-S) Business role menu Production MRP Planning MRP - Single-Item, Multi-Level 2. On the Single Item Multi Level screen, make the following entries: Field name Description User action and values Material A-67-2000_OEM Plant 1000 Comment MRP control parameters Processing key NETCH Create purchase req. 2 (Purchase requisitions in opening period) Delivery Schedules 3 (Schedule lines) Create MRP list 1 (MRP list) Planning mode 1 (Adapt planning data (normal mode)) Scheduling 1 (Basic dates will be determined for planned orders) 3. Confirm your entries by choosing Enter twice. Note The system displays an overview of the statistics generated and informs you that planning has been carried out. 4. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). ©2011 Sparta Consulting Page 10 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 4.3 OEM Processes: Displaying the Schedule Lines in the Scheduling Agreements Use In this step, we check whether the schedule line is generated automatically after MRP run. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Purchasing Outline Agreement Scheduling Agreement Delivery Schedule Display Transaction code ME39 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Purchaser (SAP_NBPR_PURCHASER-S) Business role menu Purchasing Outline Agreement Scheduling Agreement Display Sched. Agmt Schedule 2. On the Display Sch. Agmt. Schedule: Initial Screen, make the following entries: Field name Agreement Description User action and values Comment 5600006701 3. Choose Enter. 4. On the Display Sch. Agmt. Schedule: Item Overview screen, select Item 10, and choose from menu (NWBC: More…) Item Delivery schedule. Note Here, you can see the schedule lines in the individual outline agreements that were generated by the MRP planning run. 5. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.4 OEM Process: Creating Scheduling Agreement Release Use ©2011 Sparta Consulting Page 11 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD In this step, delivery schedules are created based on the scheduling agreement delivery schedule lines and released to the supplier. Note The scheduling agreement is assigned a release profile YA02, which sends forecast delivery schedules to the vendor every week for the next 6 months. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Purchasing Outline Agreement Scheduling Agreement Create SA Release Transaction code ME84 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Purchaser (SAP_NBPR_PURCHASER-S) Business role menu Purchasing Outline Agreement Scheduling Agreement Generation of Sched. Agmt. Releases 2. On the Create Releases screen, make the following entries: Field name Description User action and values Comment FRC scheds only Choose release type Select scheduling agreements 1000 Plant MRP area MRP controller A-67-2000_OEM Material Vendor Scheduling agreement 5600006701 Scope of select. Choose: Changed or next date Optional- (on) Optional- W/o checking strategy in profile Created on Acc. to strat. in profile W/o checking strategy in profile ©2011 Sparta Consulting Page 12 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Additional functions remove Test run 3. Choose Execute (F8). 4. On the Create Releases screen, the system then displays the messages together with the forecast delivery schedule numbers. 5. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.5 OEM Process: Displaying the Releases from the Scheduling Agreements Use In this step, we check whether the schedule lines are released. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Purchasing Outline Agreement Scheduling Agreement Delivery Schedule Display Transaction code ME39 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Purchaser (SAP_NBPR_PURCHASER-S) Business role menu Purchasing Outline Agreement Scheduling Agreement Display Sched. Agreement Schedule 2. On the Display Sch. Agmt. Schedule: Initial Screen, make the following entries: Field name Agreement Description User action and values Comment 5600006701 3. Confirm you inputs with Enter, and choose the first scheduling agreement item. 4. Select the item 10, and choose from menu (NWBC: More…) Item SA release docu. Note Here, you can see the individual outputs that were generated. 5. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). ©2011 Sparta Consulting Page 13 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.6 OEM Process: Message Outputting: Delivery Schedules Use After the messages (delivery schedules) have been generated (see previous step), the created IDocs need to be sent to the EDI subsystem. In this scenario, the messages are sent to supplier Side. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Purchasing Outline Agreement Scheduling Agreement Delivery Schedule Print/Transmit Transaction code ME9E Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Purchaser (SAP_NBPR_PURCHASER-S) Business role menu Purchasing Outline Agreement Scheduling Agreement Message Output: Sch. Agmt. Schedules 2. On the Message Output screen, make the following entries: Field name Description User action and values Comment Purch. doc. data Document number 5600006701 Vendor A-V6701 Only in case of messages for SA releases Plant 1000 Only messages for SA release (choose) Message data Application EL Message type ©2011 Sparta Consulting Page 14 of 31 . AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Processing status 0 Creation date Today's date Time created 3. Choose Execute (F8). 4. The system displays a list containing a number of documents. Select the desired documents with at the start of the line. 5. Choose Output message, the forecast delivery schedules are then sent to the vendor via EDI. 6. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.7 OEM Process: EDI Outbound Processing, Forecast Delivery Schedule Use In this step, we check whether EDI Outbound processing has been carried out successfully. If the SAP System transfers the IDocs to the EDI subsystem, you can find out the status of the IDocs by means of a list. Note If it is carried out successfully, the IDoc is assigned the status 03. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Product Catalog Environment IDoc Overview Transaction code WE05 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role IT Administrator (Professional User) (SAP_NBPR_IT_ADMIN-S) Business role menu IT Administration Administration IDocs IDoc Lists 2. On the IDoc List screen, make the following entries: Field name Description User action and values Default Created at ©2011 Sparta Consulting Page 15 of 31 Comment AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Created on Today Last changed at Last changed on DELFOR Logical message Message variant Message function Partner port Partner number Partner type Partner role 3. , you see an IDoc with the status 03 (Data Passed to port OK) 4. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.8 Supplier Process: EDI Inbound Processing, Forecast Delivery Schedule Use In this step, we check whether EDI inbound processing has been carried out successfully. If the EDI subsystem transfers the IDocs to the R/3 System, you can find out the status of the IDocs by means of a list. Note If scheduling is carried out successfully, the IDoc is assigned the status 53. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Product Catalog Environment IDoc Overview Transaction code WE05 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role IT Administrator (Professional User) (SAP_NBPR_IT_ADMIN-S) Business role menu ©2011 Sparta Consulting IT Administration Administration IDocs IDoc Lists Page 16 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 2. On the IDoc List screen, make the following entries: Field name Description User action and values Comment Default Created at Created on Last changed at Last changed on Logical message DELFOR Message variant Message function Partner port Partner number Partner type Partner role 3. If posting has been carried out successfully, you see an IDoc with the current status 53 (application document posted). 4. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.9 Supplier Process: Processing Forecast Delivery Schedule for Scheduling Agreement Use In this step, the supplier receives the forecast delivery schedules via EDI, that is, the scheduling agreement schedule lines are entered in the SD scheduling agreement. Note The vendor receives the delivery schedules via EDI. The cumulative quantities are updated automatically. When a new delivery schedule is received, the variance tolerances are checked. When a new delivery schedule is received, a planned delivery schedule is created automatically. You can change this planned delivery schedule manually in the scheduling agreement so that smoothed requirements can be passed on to materials planning. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) ©2011 Sparta Consulting Page 17 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD SAP ECC menu Logistics Sales and Distribution Sales Scheduling Agreement Display Transaction code VA33 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Sales Administrator (SAP_NBPR_SALESPERSON-S) Business role menu Sales Scheduling Agreements Display Scheduling Agreement 2. On the Display Scheduling Agreement: Initial Screen, make the following entries. Field name Description Scheduling Agreement User action and values Comment 35006701 Determine the forecast delivery schedule number with a match code using the customer's PO number (for example, 5600006701 for EXT). 3. Choose Enter to confirm your entries. 4. On the Display SchedAgrt w/Dly Ord. 35006701: Overview screen, the system displays the scheduling agreement header and item data. 5. Select the item 10 and from the menu choose the menu: (NWBC: More…) Goto Item Forecast dlv. sched. 6. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.10 OEM Process: Material Staging – Summarized JIT Call Use In this step, delivery-relevant calls are sent to the vendor. A summarized JIT call can be delivered at a specific time (partial-day) or several times a day. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Production KANBAN Control Kanban Signal Event-Driven Kanban Transaction code PK23 ©2011 Sparta Consulting Page 18 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Production Planner (AUTO) (SAP_NBPR_PRODPLANNER_AUTO-S) Production Kanban Control Manual Kanban Creation Business role menu 2. On the Create: Kanban screen, make the following entries: Field name Description User action and values Comment Material Activate line indicator ()) A-67-2000_OEM Plant 1000 Supply area YA0004 3. Confirm your entries by choosing Enter. The system proposes data from the control cycle for a new summarized JIT call. 4. Choose Save. Record the Summarized JIT call number __________________. 5. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.11 OEM Process: Changing/Displaying the Summarized JIT Call Use In this step, you can display the summarized JIT call. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Production KANBAN JIT Call Display Transaction code PJ03 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Logistics Execution JIT (AUTO) (SAP_NBPR_JIT_AUTO-S) Business role menu Logistics Execution JIT Outbound Display Summarized JIT Call 2. Enter the JIT call number. 3. Choose Enter to confirm your entry. ©2011 Sparta Consulting Page 19 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 4. On the Summarized JIT Call XXXXXXXXXX screen, you can see the scheduling agreement in the Purchasing Doc. field. 5. The summarized JIT call has generated an output. To view this output, choose Message F6. 6. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.12 OEM Process: Sending an Outbound Summarized JIT Call Use In this step, an outbound summarized JIT call is send to the supplier. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Logistics Execution JIT Outbound Control Data Monitoring JIT Outbound Transaction code JITOM Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Logistics Execution JIT (AUTO) (SAP_NBPR_JIT_AUTO-S) Business role menu Logistics Execution JIT Outbound Monitoring JIT Outbound 2. On the Monitor for Outgoing Calls screen, make the following entries: Field name Description User action and values Comment D Summarized JIT call Header Data for Independent calls Call type 3. Choose Components Group tab page, make the following entries: Field name Description User action and values Components Groups Data Vendor A-V6701 4. Choose Execute (F8). 5. Select the call at header level that you want to send. 6. Choose Actions. The possible actions are displayed. ©2011 Sparta Consulting Page 20 of 31 Comment AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 7. Choose Action OSDD /Send Outbound Call: Process Message 8. Choose Execute Action & Back (F9). 9. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.13 Supplier Process: SD Determination of the Incoming Summarized JIT Call Use In this step, you check the IDOC received from customer. Note The JIT call, triggered by a summarized JIT call outbound, receives an internally assigned number. The vendor uses this number as an external summarized JIT call number (for identification purposes). No other internal summarized JIT call numbers are assigned. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Logistics Execution JIT Inbound Environment IDoc IDoc Monitor for JIT Calls Transaction code EMJIT Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Logistics Execution JIT (AUTO) (SAP_NBPR_JIT_AUTO-S) Business role menu Logistics Execution JIT Inbound IDoc Monitor for JIT Calls 2. On the IDoc Monitor for Incoming JIT Calls screen, confirm the following values: Field name Description User action and values Created at Created on Today's date SummJIT call (choose) Application do.posted (status 53) (choose) 3. Choose Execute. ©2011 Sparta Consulting Page 21 of 31 Comment AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 4. If the time is not specific enough, several IDocs may appear. Choose the most recent IDoc (Time created), and choose IDoc Display to display the IDoc. 5. Expand the Data Records folder. 6. Double-click the IDoc segment E1KSJCL. 7. The external call number is stored in the PRODN field. Make a note of this number (including leading zeros). External call number ___________________ 8. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.14 Supplier Process: Calling Monitoring for the Inbound Summarized JIT Calls Use In this step, the IDOC can be displayed. Note The inbound IDoc has created a summarized JIT call with the external number (from the E1KSJCL-PRODN IDoc field). Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Logistics Execution JIT Inbound JIT Call Display Transaction code JIT3 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Logistics Execution JIT (AUTO) (SAP_NBPR_JIT_AUTO-S) Business role menu Logistics Execution JIT Inbound Display JIT Call 2. On the Display JIT Call screen, make the following value and choose Enter. Field name Description User action and values Comment Sold-to party A-6701 Partner Desc. 1000 It is case sensitive. Ext. JIT call No. As noted above Can also be searched via matchcode – sold-to party. ©2011 Sparta Consulting Page 22 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Maintenance Mode 3. You can find the JIT call details. 4. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.15 Supplier Process: Delivery the Summarized JIT Call Use In this step, a delivery is created for the summarized JIT call. This is only possible with transaction JITK (summarized JIT calls due for shipment). Prerequisites Note Check the stock using transaction code MMBE. If sufficient stock is not available for creating the delivery in the following process, you can post additional stock using the movement type 561. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Logistics Execution JIT Inbound Follow-on Functions Delivery Summarized JIT Calls Due for Delivery Transaction code JITK Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Logistics Execution JIT (AUTO) (SAP_NBPR_JIT_AUTO-S) Business role menu Logistics Execution JIT Inbound Summarized JIT Calls Due for Dely 2. On the Summarized JIT Call ( JIT Call View) screen, confirm the following values: Field name Description User action and values Shipping point/Receiving Pt 1000 Deliv. Creation Date Today’s date or select a date in the future. Ship-to party A-6701 ©2011 Sparta Consulting Page 23 of 31 Comment AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Role JIT2 must be stored as the role – with summarized JIT calls. In User Role tab page Customer JITCall no. External call number recorded above (for example: 0000000002) In Summarized JIT Call tab page 3. Choose Execute (F8). 4. On the Activities Due for Shipping Summarized JIT calls (JIT call view) screen, choose the summarized JIT call due for deliver which contains sold-to party A-6701 and material A-672000_SUP. 5. Choose the Create Delivery in Background to create the delivery in the background. Note You cannot create the delivery with the “Create single delivery in dialog” pushbutton. 6. Choose menu (NWBC: More…) Goto Create Delivery Log to check the log details 7. On the Delivery Creation Log screen, choose Documents. You can find the delivery number. Record the Delivery number ____________________. 8. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.16 Supplier Process: Posting Good Issue Use In this step, a delivery is posted for the summarized JIT call. Procedure Option 1: SAP Graphical User Interface (SAP GUI) 1. Access the activity using one of the following navigation options: SAP ECC menu Logistics Sales and Distribution Shipping and Transportation Outbound Delivery Change Single Document Transaction code VL02N 2. Enter in Outbound Delivery number you recorded and choose Enter. 3. On the Change Outbound Delivery screen, select the item and choose Post goods issue to finish processing the delivery. 4. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role 1. Access the transaction choosing one of the following navigation options: ©2011 Sparta Consulting Page 24 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Business role Warehouse Clerk (SAP_NBPR_WAREHOUSECLERK-S)) Warehouse Management Shipping Outbound Delivery Business role menu 2. Select the Due for Post Goods Issue tab page, expand Show Quick Criteria Maintenance. 3. Enter the Shipping Point / Receiving Pt: and choose Apply (refresh the current query if necessary). 4. Select your Delivery. 5. Choose Goods issue. 6. Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 4.17 Supplier Process: Billing the Outbound Delivery / Summarized JIT Call Use In this step, billing is carried out. Procedure Option 1: SAP Graphical User Interface (SAP GUI) 1. Access the activity using one of the following navigation options: SAP ECC menu Logistics Sales and Distribution Billing Billing Document Process Billing Due List Transaction code VF04 2. On the Maintain Billing Due List screen, confirm the following values: Field name Description User action and values Billing date to Today’s date or select a date in the future. Sold-to party A-6701 Documents to be selected Delivery-related Comment select 3. Choose DisplayBillList. The deliveries to be billed are displayed. 4. Select the delivery and choose Individual billing document. Then the Invoice (F2) create: Overview of Billing Items screen appears. 5. Choose Save to create the billing document. 6. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role ©2011 Sparta Consulting Page 25 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 1. Access the transaction choosing one of the following navigation options: Business role Billing Administrator (SAP_NBPR_BILLING-S) Business role menu Sales Billing 2. On the Billing screen choose Billing Due List tab page (refresh the current query if necessary). 3. Expand Show Quick Criteria Maintenance, enter the relevant search criteria; (for example: soldto – party: A-6701) select the Delivery-Related flag. Choose Apply 4. Mark the lines with the sales documents you want to bill then choose Billing in Background. 5. The system provides you with a list of the created billing documents. 6. Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). Result Financial postings: Posting Key Account Description Amount (example) Currency 01 A-6701 Customer A-6701 4,410,000 JPY 50 81110000 Revenue - domestic 4,200,000- JPY 50 42210000 Receipt - cons tax 210,000- JPY 4.18 OEM Process: Posting GR for outbound JIT call Use OEM post goods receipt for outbound JIT call. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Logistics Execution JIT Outbound Control Data Monitoring JIT Outbound Transaction code JITOM Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Logistics Execution JIT (AUTO) (SAP_NBPR_JIT_AUTO-S) Business role menu Logistics Execution JIT Outbound Monitoring JIT Outbound 2. On the Monitor for Outgoing Calls screen, make the following entries: ©2011 Sparta Consulting Page 26 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Field name Description User action and values Comment D Summarized JIT call Header Data for Independent calls Call type 3. Choose Components Group tab page, make the following entries: Field name Description User action and values Comment Components Groups Data Vendor A-V6701 4. Choose Execute (F8). 5. Select the call at header level that you want to send. 6. Choose Actions. The possible actions are displayed. 7. Choose Action OGRE /Post Goods Receipt for JIT Outbound. 8. Choose Execute Action & Back (F9). Note You can check the GR material document through menu (NWBC: More... ) Goto Components Group Material Documents. If you can not find the material document, you can exit the transaction JITOM and access it again. 9. Choose Back. You go to the screen List of Selected Outbound Calls. Note Do not leave the transaction for further processing. 4.19 OEM Process: Completing / Deleting the Outbound JIT Call Use OEM finishes the processing of outbound JIT call. Procedure 1. Without leaving previous screen, on the List of Selected Outbound Calls screen, choose Actions. The possible actions are displayed. 2. Choose Action OFIN / Complete Outbound Components Group. 3. Choose Execute Action & Back (F9). 4. Confirm the appearing message “Action OFIN Complete Outbound Components Group was executed successfully 1 times”. 5. Choose Actions again. 6. Choose Action OREO / Delete JIT Outbound Calls. ©2011 Sparta Consulting Page 27 of 31 AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD 7. Choose Execute Action & Back (F9). 8. Choose Yes to confirm Data deletion 9. Confirm the appearing message. 10. Choose Refresh. 11. The outbound JIT call is deleted and no longer displayed. 12. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 5 Close Action You have finished all the activities that are part of the business process described in this document. To repeat this business process, carry out the process steps described in the followings: 5.1 OEM Process: Reverse Stock Use The purpose of this activity is to reverse stock. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Materials Management Inventory Management Goods Movement Goods Movement (MIGO) Transaction code MIGO Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Warehouse Clerk (SAP_NBPR_WAREHOUSECLERK-S) Business role menu Warehouse Management Consumption and Transfers Other Goods Movement 2. On the Goods Receipt Other screen, choose A01 Goods Receipt R10 other, then choose Enter. 3. Enter following entries: Field name Description User action and values Material A-67-2000_OEM Qutantity For example:10 ©2011 Sparta Consulting Page 28 of 31 Comment Use MMBE review the stock, reverse all AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD unrestricted stocks Movement Type 562 Plant 1000 Storage Location 1040 4. Choose Enter. 5. Choose Save. 6. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 5.2 OEM Process: Reverse Independent Requirements Processing Use This business process step is used to delete planned independent requirements of a purchased part at the customer side. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Production Production Planning Demand Management Planned Independent Requirements Change Transaction code MD62 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Strategic Planner (SAP_NBPR_STRATPLANNER-S) Business role menu Production Production Planning Demand Management Change Planned Indep. Requirements 2. On the Change Planned Independent Requirements: Initial Screen, maintain in accordance with the following table: Field name Description User action and values A-67-2000_OEM Material MRP area 1000 Plant Selection parameters ©2011 Sparta Consulting Page 29 of 31 Comment AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD Version Activate all active versions - or Selected version (00) (on) - or all active/inactive versions Planning horizon From If necessary, change value defaulted by system To If necessary, change value defaulted by system Planning period M Monthly 3. Confirm your entries and the message output by the system. 4. On the Plnd ind. reqmts Create: Planning Table screen, delete all the independent requirements. 5. Choose Save. 6. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). 5.3 OEM Process: Material Requirements Planning Use This business process step is used to re-execute material requirements planning at the customer side. Procedure 1. Access the activity using one of the following navigation options: Option 1: SAP Graphical User Interface (SAP GUI) SAP ECC menu Logistics Production MRP Planning Multilevel SingleItem Planning Transaction code MD02 Option 2: SAP NetWeaver Business Client (SAP NWBC) via Business Role Business role Production Planner (SAP_NBPR_PRODPLANNER-S) Business role menu Production MRP Planning MRP - Single-Item, Multi-Level 2. On the Single-Item, Multi-Level screen, maintain in accordance with the following table: Field name Description ©2011 Sparta Consulting User action and values Page 30 of 31 Comment AutoEdge Scheduling Agreement With Summarize JIT Call (127): BPD A-67-2000_OEM Material MRP area 1000 Plant Scope of planning Product group MRP control parameters Processing Keys NETCH Create purhase. req. 2 (Purchase requisitions in opening period) Delivery schedules 3 (Schedule lines) Create MRP list 1 (MRP list) Planning mode 3 (Delete and recreate planning data) Scheduling 1 (Basic dates will be determined for planned orders) 3. Confirm your entries and the following system messages. The system displays an overview of the statistics generated and tells you that planning has been carried out. 4. Go back to the Single-Item, Multi-Level screen. 5. Choose Back (F3) to return to the SAP Easy Access screen (SAP GUI). Or Choose Exit (Shift+F3) and confirm the Business client message with Yes to return to SAP Home (SAP NetWeaver Business Client). ©2011 Sparta Consulting Page 31 of 31