Our ref: Your ref: Karen Gallager Scottish Government Energy and Climate Change Directora Glasgow PCS/120950 None If telephoning ask for: Pat Haynes 25 July 2012 By email only to: EconsentsAdmin@scotland.gsi.gov.uk Dear Ms Gallager Section 36 Addendum on the Glenmorie Wind Farm Wind Farm Addendum (including revised carbon assessment) Glenmorie 10km South West of Bonar Bridge Thank you for your consultation which SEPA received by way of email on 19 July 2012. We were also consulted directly by the applicant by way of letter dated 20 June 2012 For the avoidance of doubt we have reiterated our previous comments where relevant and updated our requirements for further information and conditions as appropriate in relation to any subsequent information that has been provided by the applicant in response to our initial consultation response. We object to this planning application on the grounds of lack of information. We will remove this objection if the issues detailed in Section 2 below are adequately addressed. We also ask that the planning conditions in Section 1.4, 3.1, 5.1, 6.2 be attached to the consent. If any of these will not be applied, then please consider this representation as an objection. Please also note the advice provided below. This advice is given without prejudice to any decision made on elements of the proposal regulated by us, which may take into account factors not considered at the planning stage. Advice for the Scottish Government carried forward and updated from response dated 19 December 2011 (our reference PCS117100) 1. 1.1 Re-use and disposal of excavated peat In our response of 19 December 2011 we stated that we understood that peat covers the majority of the site and that we noted from the spreadsheet calculations submitted to us in support of the Carbon Assessment that around 304 258m3 of peat is expected to be lost through the creation of borrow pits, foundations, hard-standing and access tracks. We therefore objected to the proposed development on the grounds of a lack of information on the re-use and disposal of excavated peat. We stated that we would consider withdrawing our objection if additional information is submitted which demonstrates that the proposal is in accordance with the above Regulatory Position Statement and thus capable of consent under our regulatory regimes. 1.2 In our response of 14 June 2012 (PCS 120577) we were pleased to be able to advise that the draft peat management plan which was submitted to us on 30 May 2012 takes into account the reduction in the number of turbines to 34 and generally addresses most of our concerns in relation to the impacts of the development on peatlands as outlined in our letter to the applicant of 16 May 2012. The reduced total of peat to be extracted was calculated to be 213,409m 3 which, with a bulking factor of 25% increased to 266,761m3. However we still consider that there are further steps which could be taken to reduce the surplus peat generated by this scheme and these are outlined below and in the advice to the applicant. 1.3 We therefore request that a condition is attached to any consent requiring the submission to the determining authority in consultation with SEPA and other appropriate consultees a full and detailed peat management plan to be submitted and approved in writing at least two months prior to the start of the project. This document should form part of the Construction Environmental Management Plan for the project and address all of issues detailed above. To assist, the following wording is suggested: 2. At least two months prior to the commencement of any works, a site specific Peat Management Plan which includes detail of how disruption to peat lands have been minimised must be submitted for the written approval of the Planning Authority (in consultation with SEPA) and all work shall be carried out in accordance with the approved plan. Access route options 2.1 In our letter to the applicant of 16 May 2012 we clearly explained our reasoning for the applicant to undertake an environmental assessment of the various access route options. We do not consider that neither the Environmental Statement nor the explanatory letter of 30 May 2012 provided appropriate and detailed justification for the selection of the Midfearn route. We therefore maintain our objection to this aspect of the proposals until this is done in accordance with Section 2 of Schedule 4 of The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011 in relation to of The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011. 2.2 Whilst we acknowledge that a transportation study was undertaken as part of the original Environmental Assessment the study only considered the impacts on existing public roads and did not assess the environmental impacts of any new access track construction. We do not consider that neither the Environmental Statement nor the explanatory letter of 30 May 2012 provides appropriate and detailed justification for the selection of the Midfearn access route 2.3 Given that nine turbines have been removed from the proposed project which were located closest to the new Mid Fearn access route, no new information or revised access route option assessment has been provided as part of the Addendum to justify the construction of approximately 16 kilometres of new access track on the Midfearn route which would appear to generate 29,041m3 of peat. This could be avoided if the single track road up to Kildermorie (route 5) were to be used for access. This would also reduce the requirement for borrow pits required to provide aggregate to construct that section of new track and also therefore potentially further reduce the quantities of surplus peat generated. There is also a part of section 7 of the proposed access which could be avoided and this would decrease further the amount of peat generated. 2.4 The Transportation Study originally submitted has only addressed the direct impacts on public roads and the adjacent receptor communities and has not taken account of the impacts on the wider environment of any new construction works that might be required to facilitate the selection of route. 2.5 In section 2.4 of the Addendum it is stated that 44 metre turbines blades will be utilised. Based on the information in the Transportation study Route choice 5 would appear to be suitable for this size of turbine as section 4.3 states that this route appears to be feasible for transportation of a 44 m blade. As the utilisation of route 5 would significantly reduce the amount of peat which could potentially be disturbed if the Mid Fearn access route were to be selected and would also reduce the potential for pollution from construction and operational activities entering the Wester Fearn burn, we consider that this route should be given further consideration. 3. Flood risk 3.1 In our response of 19 December 2011, we objected to the proposed development on the grounds that it may place buildings and persons at flood risk contrary to Scottish Planning Policy (SPP). However as outlined in our response to the applicant of 16 May 2012 (PCS120031) which was copied to the Scottish Government, the additional watercourse crossing information submitted by the applicant on 30 April 2012 demonstrated that all new or upgraded watercourse crossings are likely to be designed to an appropriate standard. In order to ensure this, we object to the development on flood risk grounds unless a condition is applied requiring the culverts and bridges to be designed to accommodate the 1 in 200 year flood 3.2 We have requested this condition because of the need to deal with potential flood risk through planning as it has recently been determined that it cannot be controlled through The Water Environment (Controlled Activities) (Scotland) Regulations 2011. 3.3 Where possible we would advise the use of existing tracks and crossing points. Any approaches to and the designs of new crossings should be designed to minimise the impact on the functional floodplain this includes ensuring that ground levels remain at existing levels. 3.4 Please note that we are reliant on the accuracy and completeness of any information supplied by the applicant in undertaking our review, and can take no responsibility for incorrect data or interpretation made by the authors. 3.5 The advice contained in this letter is supplied to you by SEPA in terms of Section 72 (1) of the Flood Risk Management (Scotland) Act 2009 on the basis of information held by SEPA as at the date hereof. It is intended as advice solely to The Highland Council as Planning Authority in terms of the said Section 72 (1). Our briefing note entitled: “Flood Risk Management (Scotland) Act 2009: Flood risk advice to planning authorities” outlines the transitional changes to the basis of our advice inline with the phases of this legislation and can be downloaded from www.sepa.org.uk/flooding/flood_risk/planning__flooding.aspxPollution prevention and environmental management 4. 4.1 5. 5.1 The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (CAR We can advise that the watercourse crossings specified in the Watercourse Crossing Assessment as submitted to us on 30 April 2012 are likely to be consentable under CAR. Construction Environmental Management Plan In our response of to the applicant of 16 May 2012 (PCS 120031) we were pleased to note that an outline Construction Environmental Management Plan (CEMP) had been submitted as part of the ES (Appendix 4) and we welcome the general mitigation principles and pollution prevention measures which have been set out within the document. In line with this, we would request that a condition is attached to any approved consent requiring the submission of a full, site specific CEMP, prior to works commencing. To assist, the following wording is suggested: 5.2 6. At least two months prior to the commencement of any works, a site specific Construction Environmental Management Plan (CEMP) which includes details of any proposals for micro-siting must be submitted for the written approval of the Planning Authority (in consultation with SEPA) and all work shall be carried out in accordance with the approved plan. Adopting this approach will provide a useful link between the principles of development which need to be outlined in the early stages of the project and the method statements which are usually produced following the award of contracts. Further advice on what issues we would expect to see covered under the EMP is detailed under section 13 below. Decommissioning and site restoration 6.1 We note from section 2.86 of the ES that detailed decommissioning proposals will be established and agreed with the relevant authorities prior to commencement of any activity. 6.2 We would request that a planning condition is attached to any approved consent seeking a formal Decommissioning and Restoration Plan. The plan should be submitted at least two years prior to the end of the design life of the development and based on best practice guidelines which are applicable at the time of submission. To assist, the following wording is suggested: 7. 7.1 At least two months prior to the commencement of any works, a site specific Decommissioning and site restoration plan which includes details of any proposals for micro-siting must be submitted for the written approval of the Planning Authority (in consultation with SEPA) and all work shall be carried out in accordance with the approved plan. Disruption to wetlands including peat We are pleased to note that a National Vegetation Classification (NVC) survey (drawing number A5 Rev 3) has been undertaken within 100m of turbine infrastructure. We note from drawing number A2 Rev 3 that the ecological survey area includes the proposed access track, however, as far as we understand this has not been reflected in the NVC survey as there is no mapping of vegetation along the access route. 7.2 The NVC survey has identified a number of vegetation communities which are considered Groundwater Dependant Terrestrial Ecosystems (GWDTEs) and are therefore specifically protected under the Water Framework Directive. These include classifications M23b, M6 and U6. Drawing number A5 Rev 3 indicates the following: There is an area of vegetation classification U6 adjacent to the track between turbine 33 and turbine 34. We note that turbine 36 has been removed from the proposals and therefore our previous comments in relation to an area of vegetation classification M23b located adjacent to the track immediately south east of turbine 36 no longer applies. There are small patches of vegetation classification M6 throughout the site, some of which are affected by access tracks. 7.3 In our previous response we commented that it was stated throughout the ES that development components have been located away from deep and wet peat areas as far as possible and that micro-siting will be used to avoid the deepest areas of peat. However, turbines T4, T22, T31, T37 and T40 appear to be on peat 2.01 – 4.00 metres deep and a number of other turbines appear to be located on 1.51 – 2.00 metre deep peat, where shallower areas of peat are located adjacent. We note that turbines 37 and 40 have been removed from the proposals and therefore the previous comments no longer apply in relation to these turbines. 7.4 We note from section 2.38 of the ES that during construction, site infrastructure will be micro-sited to mitigate adverse impacts on watercourses and groundwater. We welcome this approach and would request that areas of M6 wetland and the areas of deep peat discussed above are specifically avoided where possible. As detailed in section 11 below, we would therefore request that as part of the requested CEMP, full details of any proposed micro-siting are discussed with SEPA prior to any works commencing on site. This should include vegetation mapping along the proposed access route which appears to have been omitted from the ES. 8. 8.1 9. 9.1 Existing groundwater abstractions No significant hydrogeological issues have been identified as a result of the proposed development. In addition, the site is located in an upland area remote from settlements and therefore it is very unlikely that the development would impact on private water supplies (PWS). The PWS identified through the ES are located well in excess of the 250 m buffer zone required by SEPA for major excavations, cabling and tracks. We therefore have no further concerns in this regard. Requirement for dewatering Due to the very low productivity of the bedrock aquifer it is not anticipated that dewatering would be required. However, any dewatering during excavations should be in compliance with General Binding Rule 2 and General Binding Rule 15 of the CAR Practical Guide. Abstraction of groundwater in quantities greater that 10m3/day will require formal authorisation under CAR depending on the scope and duration of the works. In this case, details should be provided to our local operations team regarding how any dewatering will be managed, the amount of groundwater proposed to be abstracted and the anticipated timescales. 10. Requirements under the Water Framework Directive 10.1 Section 4.7 of SEPA’s Land Use Planning System – Guidance Note 4 outlines procedures for the provision of an indication of the ‘consentability’ of a Section 36 windfarm proposal under Water Framework Directive requirements. In line with this, on the basis of the information available and without prejudice to any future applications for authorisation under CAR, we would expect the proposal to fall into a ‘Category 1 – Capable of being authorised’. 11. Carbon balance assessment 11.1 We have been in consultation directly with the applicant in this respect who has subsequently provided us with additional information in relation to the assessment. We advise that we are not currently satisfied with the justification for the data that has been submitted Please see Appendix 2 for a detailed validation of the Carbon Balance Assessment. Please note we are reliant on the accuracy and completeness of any information supplied by the applicant in undertaking our review and can take no responsibility for incorrect data or interpretation made by authors. Detailed advice for the applicant 12. Peat management plan 12.1 We are pleased to note the Draft Peat Management Plan that has been previously submitted and are generally satisfied with the measures proposed. For the avoidance of doubt we re-iterate our previous comments to ensure that the issues of concern are addressed in the final submission 12.2 We are pleased to note the considerable efforts undertaken to minimise the generation of surplus peat. If the peat cannot be utilised in the restoration on site then this would need a Waste management licence for disposal on site or would need to be taken off site for disposal. Any proposal to use peat to block up drainage ditches for ecological benefit will require an exemption from waste management licensing. 12.3 The access road up to section 6 appears to generate 29,041m3 of peat. This could be avoided if the single track road up to Kildermorie were to be used for access. There is also a part of section 7 of the proposed access which could be avoided and this would decrease further the amount of peat generated. 12.4 The T31 crane pad stands out as having a particularly large contribution to the peat extraction quantity. We suggest that consideration is given to whether it is possible to micro site this turbine in order to further reduce the volume of peat generated. 12.5 There is mention of the use of piling for a number of turbines, but the total peat quantity figure includes excavation for all turbines bases and it would be helpful to have clarification of whether it is still proposed to utilise piling for any of the turbines. 12.6 A peat bulking factor of between 25 -45% is has been referred to and whilst we consider that it is sensible to adopt this approach we note that this bulking factor accounts for the majority of the calculated excess of peat. It is also stated (section 2.3.2) that mitigation of factors leading to bulking will reduce the volume to nominal levels. This seems to be contradictory to what was previously stated. It would be helpful to clarify this apparent anomaly in the finals version of the peat management plan 13. Construction Environmental Management Plan 13.1 Please note that we have requested that a planning condition is attached to any consent requiring a detailed Construction Environmental Management Plan (CEMP) to be submitted at least two months prior to the proposed commencement of development. The CEMP should incorporate detailed pollution prevention and mitigation measures for all construction elements potentially capable of giving rise to pollution during all phases of construction, reinstatement after construction and final site decommissioning. In addition, full details of any proposed micro-siting should be included and discussed with SEPA throughout the development of the plan and prior to submission. 13.2 We welcome the commitment in section 4.2 of the submitted Outline Construction Environmental Management Plan to consider waste, pollution, surface water, peat management, maintenance, refuelling and emergency response. Full details of what should be included in the CEMP can be found on the pollution prevention section of our website and in The Highland Councils own guidance note Construction Environmental Management Process for Large Scale Projects, which is available from www.highland.gov.uk/NR/rdonlyres/485C70FB-98A7-4F77-8D6BED5ACC7409C0/0/construction_environmental_management_22122010.pdf 13.3 It is also stated in the ES that all drainage design will be developed in consultation with SEPA. We welcome early engagement in this regard to ensure an appropriate drainage plan is agreed. The drainage plan should include details of appropriate and sufficient cross drains for cut tracks to ensure hydrological continuity and the overall minimisation of hydrological impacts. As proposed in the ES, the use of impervious dams should also be established in order to prevent cableways becoming drainage channels. 13.4 It should be noted that there is an existing fish hatchery which abstracts water on the Wester Fearn Burn at NGR NH 6263 8755. There is high potential for sediment run off to have a serious impact on the hatchery and although the mitigation measures proposed are acceptable, the developer should be aware of the importance of ensuring sediment run off does not affect the Wester Fearn Burn. 14. Engineering activities in the water environment 14.1 We are satisfied that the proposed watercourse engineering works will be capable of consent under CAR. For your information however, any subsequent CAR application will require details on individual watercourse crossings. SEPA would expect culvert crossings to be avoided and bridging solutions used where practicable. A systematic table detailing the justification for the activity and how any adverse impact will be mitigated should also be included. The table should be accompanied by a photograph of each affected water body along with its dimensions. 14.2 Further guidance on the design and implementation of crossings can be found in our Construction of River Crossings Good Practice Guide. Other best practice guidance is also available within the water engineering section of our website. Regulatory advice 15. Regulatory requirements 15.1 Details of regulatory requirements and good practice advice for the applicant can be found on our website at www.sepa.org.uk/planning.aspx. If you are unable to find the advice you need for a specific regulatory matter, please contact a member of the operations team in your local SEPA office at: Graesser House, Fodderty Way, Dingwall Business Park, Dingwall IV15 9XB Tel:01349 862 021 If you have any queries relating to this letter, please contact me by telephone on 01349 860447 or e-mail at planning.dingwall@sepa.org.uk. Yours sincerely Pat Haynes Senior Planning Officer Planning Service ECopy to: natasha.lawrence@aes.com Kellyw@naturalpower.com Ken.mccorquodale@highland.gov Liz.maclaughlin@snh.gov.uk Disclaimer This advice is given without prejudice to any decision made on elements of the proposal regulated by us, as such a decision may take into account factors not considered at the planning stage. We prefer all the technical information required for any SEPA consents to be submitted at the same time as the planning application. However, we consider it to be at the applicant's commercial risk if any significant changes required during the regulatory stage necessitate a further planning application and/or neighbour notification or advertising. We have relied on the accuracy and completeness of the information supplied to us in providing the above advice and can take no responsibility for incorrect data or interpretation, or omissions, in such information. If we have not referred to a particular issue in our response, it should not be assumed that there is no impact associated with that issue. If you did not specifically request advice on flood risk, then advice will not have been provided on this issue. Further information on our consultation arrangements generally can be found in How and when to consult SEPA, and on flood risk specifically in the SEPAPlanning Authority Protocol Appendix 1- Summary of objections and conditions 1. Access Route Options In our letter to the applicant of 16 May 2012 we clearly explained our reasoning for the applicant to undertake an environmental assessment of the various access route options. We do not consider that neither the Environmental Statement nor the explanatory letter of 30 May 2012 provided appropriate and detailed justification for the selection of the Midfearn route. We therefore maintain our objection to this aspect of the proposals until this is done in accordance with Section 2 of Schedule 4 of The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011 in relation to of The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011. 2. Re-use and disposal of excavated peat We request that a condition is attached to any consent requiring the submission to the determining authority in consultation with SEPA and other appropriate consultees a full and detailed peat management plan to be submitted and approved in writing at least two months prior to the start of the project. This document should form part of the Construction Environmental Management Plan for the project and address all of issues detailed above. To assist, the following wording is suggested: At least two months prior to the commencement of any works, a site specific Peat Management Plan which includes detail of how disruption to peat lands have been minimised must be submitted for the written approval of the Planning Authority (in consultation with SEPA) and all work shall be carried out in accordance with the approved plan. 3. Flood risk We object to the development on flood risk grounds unless a condition is applied requiring the culverts and bridges to be designed to accommodate the 1 in 200 year flood We have requested this condition because of the need to deal with potential flood risk through planning as it has recently been determined that it cannot be controlled through The Water Environment (Controlled Activities) (Scotland) Regulations 2011. 4. Pollution prevention and environmental management We request that a condition is attached to any approved consent requiring the submission of a full, site specific CEMP, prior to works commencing. To assist, the following wording is suggested: At least two months prior to the commencement of any works, a site specific Construction Environmental Management Plan (CEMP) which includes details of any proposals for micro-siting must be submitted for the written approval of the Planning Authority (in consultation with SEPA) and all work shall be carried out in accordance with the approved plan. 5. Decommissioning and site restoration We request that a planning condition is attached to any approved consent seeking a formal Decommissioning and Restoration Plan. The plan should be submitted at least two years prior to the end of the design life of the development and based on best practice guidelines which are applicable at the time of submission. To assist, the following wording is suggested: . At least two months prior to the commencement of any works, a site specific Decommissioning and site restoration plan which includes details of any proposals for micro-siting must be submitted for the written approval of the Planning Authority (in consultation with SEPA) and all work shall be carried out in accordance with the approved plan. Appendix 2 Carbon Assessment of Section 36 Wind Farms: SEPA Validation Response Template Carbon Assessment of Section 36 Wind Farms: SEPA Validation Response Template Name of proposal: Glenmorie Wind Farm Date received: 17.07.2012 Scottish Government Reference: none Deadline for response: 20.07.2012 SEPA PCS Reference: PCS/120950 Owning planning officer (SEPA): Pat Haynes Previous advice on carbon assessment and/or previous PCS Reference: PCS117100; email sent to Natasha Lawrence detailing issues with PCS120950 on 05.07.12. SECTION 1: SUMMARY OF REPONSE Issue Yes / No If no, is any deficiency significant enough to affect substantially the carbon payback period? Is there sufficient confidence in the carbon payback figure for it to be used by Scottish Ministers as a material consideration in their decision making? No The 'payback' period is sensitive to some of the parameters for which there are still concerns. These are noted in Section 2 below. Comments Further requirements to enable positive validation (where applicable) Clarifications made in the letter from Stuart McGowan (Golder Associates) to Natasha Lawrence (Wind Energy / AES) regarding the values entered into the carbon calculator for air temperature, dry soil bulk density, maximum and minimum peat depths, drainage depth for floating roads and time required for the hydrology of the borrow pits to return to their previous state. Further information is required as detailed in Section 2 below. The use of the correct counterfactual factors is also necessary. We would recommend that this is submitted in version 2.6 of the carbon calculator, although version 2.4 is still acceptable. It should take no more than a few minutes to transfer values from the previous version of the tool to the current one. However, further justification is still required for the capacity factor used, and concerns about the access route remain. SECTION 2: DETAILED RESPONSE Issue Yes If no, is any / No deficiency significant enough to affect substantially the carbon payback period? Are all relevant data input as required in the tool? No As noted in our email of the 5th of July, 2012, the carbon calculator is sensitive to capacity factor. As noted in our email of the 5th of July, 2012, the carbon calculator is sensitive to the length of access track planned. Comments Further requirements to enable positive validation (where applicable) Windfarm characteristics: Capacity factor: your letter of 17.07.2012 explains that your expected capacity factor of 33.3% is based on 'is based on Wind Energy’s long term average projections for the site.' The methodology and data for these projections are necessary in order to evaluate the carbon balance for Glenmorie Wind Farm, as stated in our email to Natasha Lawrence (05.07.2012). Counterfactual emissions factors: Please ensure the latest counterfactual factors are used, as required by section 10 of the technical note on the Scottish Government website: http://www.scotland.gov.uk/Topics/BusinessIndustry/Energy/Energy-sources/19185/17852-1/CSavings. Access tracks: Neither the letter from AES to the Highland Council, dated the 2nd of March nor the traffic access study adequately answer the question in our email as to why the alternative routes suggested are not feasible, or why the Midfearn Route is 'justifiably preferred'. More specifically: Route 5 appears to be viable and according to your letter has been rejected on the basis of public concern. However, your letter does not make clear the level of this concern. Based on the traffic access study, it is unclear why Route 8 has been rejected. The route via Beinn Tharsuinn wind farm does not appear to have been considered at all. Details of how the expected capacity factor entered into the C calculator are required in order for this carbon balance to be validated. Use of the latest counterfactual factors is required. From a C-balance point of view, Route 5 is the most preferable route (minimising construction of additional access tracks), Clear explanation and justification should be provided for the selection of access route. Do the data correspond with the information provided in the Environmental Statement? Yes Is there sufficient evidence that peat/soil depth measurements have been probed to full depth? Yes Do the data (including peat depth) correspond with the information in the Halcrow peat slide assessment? Yes Are the data credible? Yes followed by a route via Beinn Tharsuinn, then the Midfearn Route. Route 8 also remains worth considering. This last option also uses few new access tracks although the road travel distance is much longer than for any of the other routes, which would impact on C emissions in the construction phase. The data largely correspond with the ES. SECTION 3: GOOD PRACTICE Issue No – proposal adheres to good practice Is there potential to reduce the carbon payback through improved adherence to the SEPA/SNH Good practice during wind farm construction guidance and/or SEPA’s Regulatory Position Statement for Development on Peat? Yes – improved adherence would improve the carbon payback Yes Where applicable specify areas of good practice that could be introduced to improve the carbon payback of the proposal An access route that minimizes the disturbance of the soil and ecology would improve the carbon balance of this development. Based on the Soil Indicators for Scottish Soils tool, it appears that the route preferred by the developers (the Midfearn route) would be mostly over undamaged peat over half a metre deep, whereas the route via Beinn Tharsuinn appears to be mostly over damaged peat and peaty mineral soil, with a much smaller part of it over undamaged peat. The letter from Golder Associates to Natasha Lawrence (17.07.2012) does not address our recommendation to develop a habitat management plan. There may be some confusion between 'habitat management' and 'peat restoration'. In terms of habitat management, we are specifically referring to the improvement of other degraded bog (see rows 77 - 81 of version 2.4 of the carbon calculator or rows 76- 80 of version 2.6). A good habitat management plan is likely to improve the carbon balance of the development. Validator: Alan Cundill, Claudia Erber, Ishani Erasmus. Date of validation: 20.07.2012