CONFERENCE NOTES - Access Disputes Committee

advertisement
Territory Engineering Conference (Scotland) for 2007 RotR – 3rd November 2005, Consort House, Glasgow, 9am to 4pm.
Map 11 – Central Scotland, Grangemouth and Perth
Summary
Duration
Collessie (Rev)
Weeks 37-38 (2x29hrs)
Bonnymuir (Dn)
Weeks 42-45 (4x29hrs)
Notes – valid at time of Engineering Conference
Operator Comments / Responses / Actions
Work piggybacking at – Greenhill Lower Jn (12hrs)
Now Weeks 44-47 in Evo2 – due to Grangemouth
in week 43 for Annual Maintenance Tamp.
S&C re-dating (Greenhill Lower Jn in wk 46).
Grangemouth S&C
Weeks 46-48 (2x54hrs;
Work piggybacking at – Dunning (Up) and
EWS – 54hrs will be problematic at any time.
renewal and follow-up
1x29hrs)
Carmuirs East/West (Up)(both 29hrs) in week 46.
FSR – request re-date Carmuirs East-West outwith
tamp.
Week 52 (16hrs)
Grangemouth works. Also re-date Grangemouth to
avoid Rugby Internationals. Now Weeks 41-43 & 48
in Evo2.
Problems persist - particularly packaging Carmuirs
East/West and Bonnymuir.
Newburgh (Rev)
Weeks 1-3 (3x29hrs)
Now Weeks 3-5 in Evo2 – due to Duke St re-dating
/ resourcing considerations.
Abernethy (Rev)
Weeks 4-5 (2x29hrs)
Now 1x54hrs in Week 7 in Evo2 (piggybacking
Hilton Jn S&C works) – due to Duke St re-dating.
Ninewells (Dn)
Week 5 (29hrs)
FSR – best undertaken with Hilton Jn S&C renewal.
Now Week 6 in Evo2.
Hilton Jn S&C
Weeks 6-9 (1x78hrs,
Works piggybacking as follows :-
Following the S-A-K presentation the Operator
Renewal
3x54hrs – final week on
Week 6 – UB 110/025 & 026 Abernethy (78hrs on
consensus was that Stirling Middle S&C renewal
Ladybank Branch only)
Ladybank Branch); Kippenross Tunnel (Dn) (78hrs);
should be brought forward to coincide with the final
Week 15 (1x16hrs)
Stirling Plat. 6 (29hrs).
phase of re-opening works, to avoid significant
Week 7 - UB 110/29 Carey Farm (54hrs on
disruption in 2008/09.
Ladybank Branch);
NR – there may be problems undertaking the S&C
Jeanfield (Up) (54hrs); Ashfield (Dn) (29hrs); Stirling
design in time to meet these timescales.
V1 – 11/11/05
Page 1
Territory Engineering Conference (Scotland) for 2007 RotR – 3rd November 2005, Consort House, Glasgow, 9am to 4pm.
Middle S&C Maintenance Tamp (18hrs).
Action – NR to review options for bringing Stirling
Week 8 - UB 110/032 Clayton, Bridge of Earn & UB
Middle S&C renewal forward and deferring Hilton
110/033 Patersons, Bridge of Earn (54hrs on
Jn to 08/09 (MB / NW / AR - RSPG).
Ladybank Branch); Auchterarder (Up) (29hrs);
Stirling Plat. 9 (29hrs);
Week 9 – Collessie (Civils, 54hrs on Ladybank
Branch)
Week 15 – Follow-up tamp (ALB).
S-A-K Re-opening – presentation from Marc Hamilton – distributed on CD with minutes
–
21km or line, single with 3 passing loops.
–
Wk9 of 2007 – 54hrs commissioning possession at Stirling (wheels free duration yet to be confirmed) SN83 – SM47, and LG28 – agreed
position of temporary buffer.
–
Looking to piggyback Larbert S&C disruptives in weeks 25-28 of 2006 for preparatory works.
–
SC121 route number to be retained.
–
Question to Martin Batty - are block joints to be renewed in Platforms 6&9? Action – MB to advise
–
Question from Audrey McArthur – when are timetabled services due to start? FSR replied – hopefully from June 2007, but the timeline for
driver training is very tight (2 weeks), so Project Team / TIE / EWS / FSR need to review – so a September date may be more realistic..
–
Draft timetable needed by NR asap as there are Network Change aspects that need to be progressed.
–
Martin Batty – all to note that Stirling Middle Renewal may need to be undertaken in 2008. All Operators requested that this work be
brought forward to coincide with SAK works. NR – this will be considered but is likely to be very challenging, particularly re. design
timescales and compatibility with SAK works.
V1 – 11/11/05
Page 2
Territory Engineering Conference (Scotland) for 2007 RotR – 3rd November 2005, Consort House, Glasgow, 9am to 4pm.
Map 12 – Dundee to Aberdeen
Summary
Duration
Notes – valid at time of Engineering Conference
Mossend – Elgin Re-
Weeks 39-40, 48-52
Programme of bridgeworks, track slews etc. to enable higher
gauging Scheme
(2x54hrs; 1x29hrs;
gauge freight to run via this route between Mossend and
4x54hrs)
Elgin. The majority of worksites requiring disruptive access are
Operator Comments / Resulting Actions
understood to be between Dundee and Aberdeen.
Works piggybacking in same weeks - Earthworks in the
Stonehaven area.
Kinnaber (Dn)
Week 48 (29hrs)
Montrose S&C
Weeks 49-51 (1x 78hrs;
May involve re-modelling of layout – disruptive access
EWS – may be some issues with the 78hr
renewal
2x54hrs)
requirements to be refined during design phase. Includes
duration disruptive.
reinstatement of 3 a/b at the North end of the station.
NR – design not finalised yet – options
Possible bi-di working through the main platform.
to go through RSPG and RURIG reviews.
Action – NR to review design options in
order to finalise disruptive access
requirements (MB / NW / AR - RSPG).
Arbroath (Up & Dn)
Week 49 (78hr)
Piggybacking Montrose S&C renewal.
Balcathie (Up)
Weeks 50-51 (54hrs)
Piggybacking Montrose S&C renewal.
Dock St Tunnel (Up)
Week 52 (54hrs)
PL track renewal within Tunnel - lighting and ventilation
requirements make it uneconomic to undertake as a series of
29hr disruptives.
V1 – 11/11/05
Page 3