DRAFT n.10 CMS Pixel Extraction Procedure CERN, March 2009 Authors: M. Alidra, A. Ball, G. Bolla, S. Buontempo, J. Conway, S. Di Vincenzo, A. Dominguez, G. Faber, M. Gastal, R. Goudard, R. Hall-Wilton, P. Lepeule, J.D. Maillefaud, P. Petagna, T. Rodrigo, C. Schaefer, N. Smiljkovic, D. Stickland, R. Vasquez-Sierra, W. Zeuner The present document describes the official sequence of operations needed to extract CMS Pixel detector (Forward only or Forward + Barrel) in safe mode both for operators and equipments. For each step of the sequence we define the starting conditions, the action to be done, the closing conditions, the duration and the name of reference person (coordinating the activities in Vac tank during that step). Maf and Sandro are the site managers linking all the different steps in the procedure. They will take care also of the coherency vs other cavern activities in terms of unexpected possible interferences, safety, tooling and integrity of equipments. Before starting its step the reference person must check if the starting conditions in the area are fulfilled. He will release the control of the area to next step coordinator when the closing conditions are fulfilled. For each step few pictures of relevant actions are shown, with glossary and indications on the relevant parts involved in that action. The procedure will be upgraded including ALARA concept in a future version of present document. 1 DRAFT n.10 Glossary To add 2 drawings with table of names and arrows, numbers. 2 DRAFT n.10 Official sequence of operations 0. General Starting conditions (Gerard, Boki, Patrik) 0.1 Additional BP support with column @ 10.7m and spiders @6m MUST be there. The configuration of BP support @10.7m can be adapted with column displaced by 80 cm and additional horizontal extension (nose) if ES activity is planned to go on in parallel. A specific additional operation is needed in this case in step 3. Fig. a Fig. b 0.2 Main Installation Platform (Yellow platform). We can have 3 configurations: 0.2.1 Heavy weight platform (20 t) for EE, ES and Pixel activities (fig. a and link a) 0.2.2 Light weight platform (10 t) for Forward pixel activities only (fig b and link b) possible on both + and – Z sides. Fig. c 0.2.3 Light weight platform (10 t) for Forward and Barrel Pixel activities only (fig c and link c), possible on – Z side only. 0.3 Standard BP mechanical protections (fig d and ref [1 ]) must be ALWAYS there, except during Pixel activities. Fig. d 3 DRAFT n.10 1 Installation of support beams for Pixel platform (Paolo) Starting conditions: availability of yellow platform or something equivalent at nominal position. Action: screw on the magnet solenoid structure 4 support beams to hold Pixel platform. Completion: the beams are placed and some wood panels are on them. The nominal position is respected at metrology level. Duration: ½ day. NOTE: Present Beam design allows their installation with or without the Surkov frame rails being placed. If rails are not there a small piece for additional thickness is needed. At the end of present activities we will evaluate possible modifications of the Surkov frame rails in order to allow either their installation after Pixel beam supports are there (not possible at present) or their folding on the magnet to maximize the accessibility in the VacTank having them placed. 4 DRAFT n.10 2 Installation of Pixel platform (Paolo). Starting conditions: support beams are placed. Action: place and screw the 3 parts of Pixel platform. No survey needed. They are placed by metrology on the nominal position. Completion: platform in nominal position, check the presence of barriers and need of formal validation from CERN safety personnel (VIC). Duration: ½ day. 5 DRAFT n.10 3 Installation of Pixel scissor table (Paolo) Starting conditions: VIC done on Pixel platform. NOTE: if the additional BP support @10.5m is not with column placed at its nominal position (meaning horizontal extension nose is installed for ES activity going on in parallel) it needs to be TEMPORARY (max 1h) removed to let Pixel scissor table come in. A new design of the support base with rotating base is being evaluated. Action: place the Pixel scissor table on the platform and stop its vertical range with mechanical references in high. Table position on its rails defined according to the use (3 different official positions for BCM, FPix or BPix). Completion: the operation is over when table base with rails is screwed on the Pixel platform floor against the reference pieces available there and scissor table left in the garage position (centered, lowest, back away form IP, hydraulic system disconnected). Duration: ½ day. 6 DRAFT n.10 4 Alignment ring temporary support and Bosch guiding rails (Paolo, Teresa) Starting condition: blue frame (alignment ring garage) provided by ES group (Wolfgang reference person) MUST be on the main platform. Pixel scissor table installed. Action: Install the alignment ring temporary support on blue frame. Screw on Pixel scissor table the so called Bosch rails needed to displace the alignment ring. Completion: Rails placed on table up to the ES support at metrology nominal position. Duration: 2h. 7 DRAFT n.10 5 Electrical Disconnection of the alignment ring (Teresa). NOTE: this can be done any moment and usually this is done well before. Duration: 1 hour. 8 DRAFT n.10 6 Moving Alignment ring to higher Z using a temporary support (Bosch profile) (Teresa Rodrigo and Paolo Petagna). Starting conditions: Garage support and guiding rails (Bosch profile) must be there aligned. Alignment ring MUST be disconnected. Action: unscrew the alignment ring and displace it on the garage. Completion: when alignment ring is locked (by 3 screws on the garage support) and protected with macrolon foil we remove the guiding rails (Bosch profiles) from the scissor table and leave them on the Pixel platform floor. Duration: 15 minutes NOTE1: during this operation you need to temporary remove the 2 spider wires (additional BP support @ 6m) and immediately reinstall them after the alignment ring has been displaced. The spider wires must be in cross position (near top going to far bottom and far top going to near bottom) in order to leave the max clearance for the Pixel extraction. The mechanical pieces have to stay at max distance from BP in order to avoid interference with FPix extraction NOTE2: we plan to extend vertically the macrolon protection to protect also the bottom part of the alignment ring. 9 DRAFT n.10 7 Removal of nose shell (called also thermal screen) (Paolo). Starting conditions: alignment ring displaced in its garage position. Action: un-taping, unscrewing, disconnecting the wires, dismount the 2 pieces. The 2 half of the nose shell must be placed in a safe place not to risk to damage them during further activities on pixel platform. Completion: 2 nose shells must be dismounted and stored in a safe place. Duration : ½ hour. 10 DRAFT n.10 8 Visual inspection Survey of BP (Patrick, Raphael) Starting conditions: Nose shell removed. Access to Main installation platform is secured ONLY to Survey people. Action: Inspect visually the integrity of the equipments visible after nose shell removal (Fig 1). Check the strength of the horizontal wires. Remove frontal carbon fiber panels (see fig 2) from the carbon fiber rings to allow the visual access close to BP in IP zone through the holes there . Start the survey of BP. Completion: Visual inspection done and BP position recorded Duration: 2 hours. Fig 1 NOTE 1: Installation of needed infrastructures for survey can be started in parallel with the removal of nose shell (step 7). NOTE 2: NO operator can stay on the Main installation platform a part of Survey people. NOTE 3: in the same day a draft written report is circulated to the present document author list. A complete formal survey written report will be distributed in at most one week. Fig 2. 11 DRAFT n.10 9 Modification of BP support for BCM extraction (remove the carbon fiber lateral support @3.5m and half of it @3.2m ) (Patrick and Paolo). Starting condition: BP Survey done. Action: remove half bottom carbon fiber reinforcement ring support @3.2m and. Remove all carbon fiber support ring @3.5m and put there the Al stiffener support. Then remove the inner bulk head. NOTE: we do this operation only now in order to keep the fibers protected till this time. Completion: bulk head panels are folded in place. Duration: 2 h. 12 DRAFT n.10 10 Disconnection and removal of BCM (Beam Condition Monitor) (Richard Hall-Wiltom and David Stickland). Starting conditions: visual inspection and BP survey done. Pixel scissor table in right position (push it forward in IP and lower in Y). Action: disconnection and extraction of the BCM two half (near and far part) and temporary place it on the Scissor table. Then 2 half BCMs are transported (inside transport boxes) by hand out of Pixel and main installation platforms,. Fiber connections are secured. Completion : 2 half BCMs are out of main installation platform and all BCM optical fibers are secured. Duration: ½ day for both near and far sides. 13 DRAFT n.10 11 Release the horizontal wires @3.2m (Patrick and Paolo). Starting condition: survey and visual inspections is over. BCM is out. Action: check length of horizontal wire protruding the screws, unscrew the wires, and tape them on the bellow protection. Retract the 2 horizontal pulley supports Completion: wires unscrewed and secured with tape on the Al frame, supports retracted. Duration: ½ hour. 14 DRAFT n.10 12 Modification of BP support for Pixel extraction (remove the carbon fiber lateral support and inner bulk head) (Patrick and Paolo). Starting condition: horizontal wired unscrewed. Action: remove top part of carbon fiber reinforcement ring support @3.2m and put there the Al stiffener support. Put Pixel scissor table at right Y and Z for F Pix extraction. Y= 875 mm and Z=970 mm (Z = distance of table face to docking pin of inner rails) . Completion: bulk head panels are folded in place both carbon fiber supports are replaced by Al stiffener supports. Duration: 2 h. 15 DRAFT n.10 13 Optional BP survey (central collars) (Patrick and Raphael). Starting condition: Carbon fiber lateral support MUST be removed. Halogen lamp MUST be installed in the vac tank zone. Action: Access to Main installation platform is secured ONLY to Survey people. Survey of central BP (collars).Theodolite can pe placed close to Alignment ring garage support (see fig). Completion: position data recorded by survey people. Duration: 2 h. NOTE1: NO operator can stay on the Main installation platform a part of Survey people. NOTE2: in the same day a draft written report is circulated to the present document author list. A complete formal survey written report will be distributed in at most one week. 16 DRAFT n.10 14 Extraction of Pixel Forward (-/+ Z) (Gino) Starting conditions: modifications of BP support done. Pixel scissor table at 875 mm Y and 970 mm in Z (Z = distance of table face to docking pin of inner rails) Action: Disconnection of electrical, optical and cooling connections. Crane the CTU (Cylinder Transport Units) in the cavern. Prepare the infrastructures needed on the Pixel scissor table. Extract the F Pixel Put it in the CTU on Pixel platform. Crane the CTU + Pixel on the cavern floor. Then crane it out of cavern using big crane. Completion: the FPixel is in the CTU out of cavern. Duration: 1 day. NOTE: first part of the activity (disconnections) can be done even before step 11 if there is some time slot available (evening or w.e.) in order to save time. 17 DRAFT n.10 15 Place back the nose shells and Secure the Vac tank access zone (Maf and Sandro) Starting conditions: F Pixel and tooling are out. Action: Nose shells are placed back to protect that area. We secure the Pixel platform access zone in order to avoid any unplanned activity there. Put red/white tape in there and place a panel with reference person to call (Maf and Sandro). Only activities formally approved in the TCM (and present in the official planning) are possible in that zone. Completion: zone is secured Duration: 30 min. 18 DRAFT n.10 16 Extraction of Pixel Barrel (only possible on the –Z) (Gino) TO BE COMPLETED. Starting conditions: F Pixel and tooling are out. Pixel scissor table at 875 mm Y and back at most in Z (opposite to IP) Action: Disconnection of electrical, optical and cooling connections. Crane the CTU (Cylinder Transport Units) in the cavern. Prepare the infrastructures needed on the Pixel scissor table. Extract the B Pixel Put it in the CTU on Pixel platform. Crane the CTU + Pixel on the cavern floor. Then crane it out of cavern using big crane. Completion: the BPixel is in the CTU out of cavern. Duration: 2 days 19 DRAFT n.10 17 Installation of the column or special support bars @3.5m BP (Patrick, Paolo). Starting condition: F Pix (B Pix if step 14 is done) extraction is over. Action: reinstall the support column @3.5m. This operation is needed only if no other operation is planned before one day (max time we accept for BP without this support). Completion: BP support @3.5m placed(two options being evaluated now: column support or special bars) Duration: column option 1h, special support bars option ??h 20 DRAFT n.10 18 Bake out of BP (Patrick). Starting condition: B Pix extraction is over. BP additional support @3.5 m MUST be there . YE+1 and YE-1 MUST be in intermediate opening position @3740mm (YE1 to YB2 distance face to face). Action: BP additional supports for bake out are installed on both sides /+Z. Installation of all the heating jackets and elements all around the BP on -/+Z. Installation of heating racks. Start the BP heating cycle. After there is a vacuum analysis. Injection of pure gas back to atmospheric pressure. Removal of all the BP bake out equipments Completion: BP vacuum analysis and removal of all BP bake out equipments Duration: 3 weeks 21 DRAFT n.10 19 Survey of BP after bake out (Patrick, Raphael). Starting condition: BP bake out is over. Action: Completion: Duration: ?? 22 DRAFT n.10 20 Put back standard BP protection (Patrick, Paolo). Starting conditions: installation of additional support @ 3.5m Action: Place all the mechanical pieces as described in the standard BP support manual (Ref [1]).. Completion: BP protection placed Duration: 2h NOTE: In case the Surkov frame is still there (this is not the standard BP protection configuration) we have to place a “not standard BP protection” hanging it to the Surkof frame (see fig). 23 DRAFT n.10 Reference documents: [1] CMS-Beampipe-Support-Manual-Rev8 (Farchild, Boki, Oriunno) [2] All the survey reports concerning the Beam pipe are puplished on EDMS. You can find them on the following web page https://edms.cern.ch/cedar/plsql/navigation.tree?cookie=8174289&p_top_id=1945124478&p_top_type=P&p_open_id=1193614997&p_open_type=P [3] All the survey reports concerning the Tracker and the Pixel are puplished on EDMS. You can find them on the following web page https://edms.cern.ch/cedar/plsql/navigation.tree?cookie=8174289&p_top_id=1945124478&p_top_type=P&p_open_id=1306659041&p_open_type=P . 24